CN218758636U - Core barrel pump pipe overhauling device integrated on integral steel platform die carrier - Google Patents

Core barrel pump pipe overhauling device integrated on integral steel platform die carrier Download PDF

Info

Publication number
CN218758636U
CN218758636U CN202221861429.6U CN202221861429U CN218758636U CN 218758636 U CN218758636 U CN 218758636U CN 202221861429 U CN202221861429 U CN 202221861429U CN 218758636 U CN218758636 U CN 218758636U
Authority
CN
China
Prior art keywords
platform
pump line
steel
personnel
die carrier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221861429.6U
Other languages
Chinese (zh)
Inventor
马静
张秀凤
顾剑斌
扶新立
石健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Equipment Engineering Co ltd
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Equipment Engineering Co ltd
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Equipment Engineering Co ltd, Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Equipment Engineering Co ltd
Priority to CN202221861429.6U priority Critical patent/CN218758636U/en
Application granted granted Critical
Publication of CN218758636U publication Critical patent/CN218758636U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides an integrate in core section of thick bamboo pump line maintenance device of whole steel platform die carrier, the device adopts personnel transportation operation platform and pump line hoist device, personnel transportation operation platform connects in whole steel platform die carrier floorbar and is located its below, personnel transportation operation platform can reciprocate, pump line hoist device installs on whole steel platform die carrier floorbar, through the lift of personnel transportation operation platform, the operation personnel of standing on personnel transportation operation platform, can remove one by one the pump line festival at the jam position of pump line in proper order, and carry out the mediation clearance to core section of thick bamboo floor one by one through pump line hoist device handling, then use through the cooperation of personnel transportation operation platform and pump line hoist device equally, the installation that resets pump line festival after will clearing up from top to bottom in proper order, the high efficiency of super high-rise core section of thick bamboo pump line has been realized, the safety mediation is overhauld, the solution adopts the traditional approach to set up the scaffold to consume a large amount of time and the manpower, the efficiency of construction is low, the poor problem of security.

Description

Core barrel pump pipe overhauling device integrated on integral steel platform die carrier
Technical Field
The utility model belongs to the technical field of the construction, in particular to core section of thick bamboo pump line maintenance device integrated in whole steel platform die carrier.
Background
At present, the super high-rise building mostly adopts a frame-core tube structure. Aiming at the super high-rise building with a core tube of a reinforced concrete structure and an outer frame of a steel structure and a composite floor slab, the construction usually adopts the step-by-step flow construction, the vertical structure of the core tube is firstly constructed, the steel structure of the outer frame is firstly constructed, and the horizontal floor slab of the core tube and the steel structure of the outer frame are constructed after lagging. When the process is adopted for construction, the vertical structure of the core cylinder leads the horizontal structure by 6-10 layers.
When whole steel platform die carrier is adopted in the construction of a core section of thick bamboo, for satisfying the vertical wall body concrete pouring demand of a core section of thick bamboo, generally with cloth machine fixed arrangement on whole steel platform die carrier top girder steel, carry the concrete that the pump pressure came through the pump line of joining in marriage inside the core section of thick bamboo perpendicularly and wait to pour the position.
When the pump pipe vertically arranged in the core barrel is blocked, no floor slab is provided for the operation platform to overhaul the pump pipe in the construction height difference range of the vertical structure and the horizontal structure of the core barrel. The traditional construction method is that an overhanging scaffold is erected along a pump pipe, a constructor searches for a blocking position on the overhanging scaffold, then the overhanging scaffold is dredged and cleaned after being disassembled in sections, and the overhanging scaffold is reinstalled after the cleaning is completed. However, when the traditional method is adopted for pump pipe maintenance, a large amount of time and manpower are consumed for building the cantilever scaffold, and the construction efficiency and the safety are low. For solving above-mentioned problem, make safe, the efficient clearance of dredging after the pump line blocks up, guarantee the construction progress, consider that the integrated pump line of whole steel platform die carrier bottom overhauls the device and satisfy the construction demand.
SUMMERY OF THE UTILITY MODEL
The utility model aims at utility model a core section of thick bamboo pump line maintenance device integrated in whole steel platform die carrier sets up the scaffold that encorbelments when solving and adopting traditional approach to carry out the pump line maintenance and consumes plenty of time and manpower, the efficiency of construction is low, the poor problem of security, has promoted efficiency and security that superelevation layer core section of thick bamboo pump line overhauld the mediation by a wide margin, guarantees the construction progress.
In order to solve the technical problem, the utility model provides a following technical scheme:
the utility model provides an integrate in core section of thick bamboo pump line maintenance device of whole steel platform die carrier, includes: personnel transport operation platform and pump line hoist device, personnel transport operation platform connects in whole steel platform die carrier floorbar and lies in whole steel platform die carrier floorbar below, personnel transport operation platform can reciprocate, personnel transport operation platform is used for operation personnel's transportation and dismantles, the operation platform as when installing at the pump line, the vertical arrangement of pump line is in a core section of thick bamboo, the pump line is fixed with core section of thick bamboo wall, the pump line is connected gradually by a plurality of pump line sections and is constituteed, pump line hoist device installs on whole steel platform die carrier floorbar, pump line hoist device is used for handling the pump line section.
Preferably, in foretell integrated in the core section of thick bamboo pump line maintenance device of whole steel platform die carrier, personnel's transportation operation platform is including hanging girder steel, platform unit, power device and wire rope, it adopts H shaped steel to hang the girder steel, hang on the girder steel is fixed in whole steel platform die carrier floorbar, hang the lower flange of girder steel and set up the hoisting point board, the platform unit hangs on the hoisting point board through wire rope, power device install in on the platform unit, through power device control wire rope's receive and release the upper and lower operation that realizes the platform unit.
Preferably, in the above core barrel pump pipe inspection and repair apparatus integrated in the monolithic steel platform formwork, the apparatus includes: personnel transport operation platform and pump line hoist device, personnel transport operation platform connects in whole steel platform die carrier floorbar and is located whole steel platform die carrier floorbar below, personnel transport operation platform can reciprocate, personnel transport operation platform is used for operation personnel's transportation and dismantles, as operation platform when the installation at the pump line, the vertical arrangement of pump line is in a core section of thick bamboo, the pump line is fixed mutually with core section of thick bamboo wall, the pump line is connected gradually by a plurality of pump line sections and is constituteed, pump line hoist device installs on whole steel platform die carrier floorbar, pump line hoist device is used for the handling pump line section.
Preferably, in foretell integration in the core section of thick bamboo pump line maintenance device of whole steel platform die carrier, personnel's transportation work platform is including hanging girder steel, platform unit, power device and wire rope, it adopts H shaped steel to hang the girder steel, hang on the girder steel is fixed in whole steel platform die carrier floorbar, the lower flange that hangs the girder steel sets up the hoisting point board, the platform unit hangs on the hoisting point board through wire rope, power device install in on the platform unit, the upper and lower operation of platform unit is realized to receive and release through power device control wire rope.
Preferably, in the core barrel pump pipe overhauling device integrated on the integral steel platform die set, the platform unit is a square frame with an open top, the bottom of the square frame is provided with a steel plate, and the periphery of the square frame is provided with a fence.
Preferably, in the core barrel pump pipe overhauling device integrated with the integral steel platform formwork, the hoisting point plate is vertically arranged, the upper end of the hoisting point plate is fixedly connected to the lower surface of the lower flange of the suspended steel beam, and a hoisting hole for the steel wire rope to pass through is formed in the hoisting point plate.
Preferably, in the core cylinder pump pipe overhauling device integrated with the integral steel platform formwork, a plurality of stiffening plates arranged at intervals are arranged on the suspension steel beam at positions corresponding to the hoisting point plates.
Preferably, in foretell integrated in the core section of thick bamboo pump line maintenance device of whole steel platform die carrier, pump line hoist device includes hoisting device, installation girder, connecting plate, fixing base, fender rope device, guider and lifting rope, the installation girder passes through the connecting plate spiro union on whole steel platform die carrier floorbar, hoisting device passes through the fixing base install in the one end of installation girder, fender rope device and guider set up respectively in the other end of installation girder, lifting rope one end is connected with hoisting device, the other end of lifting rope passes through guider truns into vertically and is connected with the shackle by transversely, the below of shackle sets up a clamping device, clamping device is used for centre gripping or pine pump line festival.
Preferably, in the core barrel pump pipe overhauling device integrated with the integral steel platform formwork, the personnel transportation operation platform further comprises a pair of top wall devices for preventing the personnel transportation operation platform from shaking in the lifting process.
Preferably, in the core barrel pump pipe overhauling device integrated on the whole steel platform die carrier, the top wall device comprises a horizontal support rod and an elastic roller, the elastic roller is arranged at one end of the horizontal support rod, and the other end of the horizontal support rod is fixedly connected with the platform unit.
Known by the above disclosed technical scheme, compare with prior art, the beneficial effect of the utility model is as follows:
the utility model provides a pair of integrate in core section of thick bamboo pump line maintenance device of whole steel platform die carrier, the device adopt personnel transportation operation platform and pump line hoist device, and personnel transportation operation platform connects in whole steel platform die carrier floorbar and is located whole steel platform die carrier floorbar below, personnel transportation operation platform can reciprocate, the pump line is connected gradually by a plurality of pump line sections and forms, pump line hoist device installs on whole steel platform die carrier floorbar, through personnel transportation operation platform's lift, stands the operating personnel on personnel transportation operation platform, can carry out section by section in proper order to the pump line section at the jam position of pump line and demolish to core section of thick bamboo floor through pump line hoist device section by section handling, then use through personnel transportation operation platform and pump line hoist device's cooperation, the installation that resets in proper order from top to bottom of pump line section after clearing up, realized the high efficiency of super high-rise core section of thick bamboo pump line, the safe mediation maintenance, solved and set up when adopting traditional approach to overhaul and choose the scaffold hand consumption time and manpower, the problem that the security is low, the construction efficiency is poor.
Drawings
Fig. 1 is a schematic elevation view of a core barrel pump tube inspection device integrated into a monolithic steel platform formwork.
Fig. 2 is a schematic plan view of a core barrel pump tube servicing apparatus integrated into a monolithic steel platform formwork.
Fig. 3 is a schematic structural view of the personnel transportation work platform.
Fig. 4 is a schematic structural view of the top wall device.
Fig. 5 is a schematic elevation view of the pump tube hoist.
Fig. 6 is a schematic plan view of the pump tube hoist.
Fig. 7 is a schematic view of the pump pipe hoisting device in use.
Figure 8 is a schematic view of the construction of the suspension steel beam.
Fig. 9 is a side view of fig. 8.
In the figure: 1-integral steel platform formwork, 11-integral steel platform formwork bottom beam, 12-personnel safety rope hanging point, 2-personnel transportation operation platform, 21-hanging steel beam, 22-platform unit, 23-power device, 24-steel wire rope, 25-top wall device, 251-horizontal support rod, 252-elastic roller, 26-hoisting point plate, 27-stiffening plate, 3-pump pipe hoisting device, 31-hoisting device, 32-mounting main beam, 33-connecting plate, 34-fixing seat, 35-guiding device, 36-rope blocking device, 37-hoisting rope, 38-shackle, 39-clamping device, 4-core barrel, 5-pump pipe and 51-pump pipe joint.
Detailed Description
The present invention will be described in further detail with reference to the following drawings and specific embodiments. The technical contents and features of the present invention will be described in detail below with reference to the accompanying drawings by way of examples. It should be further noted that the drawings are in simplified form and are not to precise scale, and are provided for the purpose of facilitating and clearly explaining the embodiments of the present invention. For convenience of description, the directions of "up" and "down" in the following description are the same as the directions of "up" and "down" in the drawings, but this should not be construed as limiting the technical solution of the present invention.
Referring to fig. 1 to 9, in which the unit of size is millimeter, the embodiment discloses a core barrel pump pipe maintenance device integrated in an integral steel platform mold frame, which includes: personnel transport operation platform 2 and pump line hoist device 3, personnel transport operation platform 2 connects in whole steel platform die carrier floorbar 11 and is located whole steel platform die carrier floorbar 11 below, personnel transport operation platform 2 can reciprocate, personnel transport operation platform 2 is used for the transportation of operation personnel and dismantles, as operation platform when the installation at pump line 5, 5 vertical arrangement of pump line is in core section of thick bamboo 4, pump line 5 is fixed mutually with 4 wall bodies of core section of thick bamboo, pump line 5 connects gradually by a plurality of pump line festival 51 and constitutes, pump line hoist device 3 installs on whole steel platform die carrier floorbar 11, pump line hoist device 3 is used for handling pump line festival 51.
The utility model provides a pair of integrate in core section of thick bamboo pump line maintenance device of whole steel platform die carrier, include: personnel transport operation platform 2 and pump line hoist device 3, personnel transport operation platform 2 connects in whole steel platform die carrier floorbar 11 and is located whole steel platform die carrier floorbar 11 below, personnel transport operation platform 2 can reciprocate, personnel transport operation platform 2 is used for the transportation of operation personnel and dismantles, as operation platform when the installation at pump line 5, 5 vertical arrangement of pump line is in core section of thick bamboo 4, pump line 5 is fixed mutually with 4 wall bodies of core section of thick bamboo, pump line 5 connects gradually by a plurality of pump line festival 51 and constitutes, pump line hoist device 3 installs on whole steel platform die carrier floorbar 11, pump line hoist device 3 is used for handling pump line festival 51. Through the lift of personnel transportation operation platform 2, the operation personnel of standing on personnel transportation operation platform 2, can carry out the festival by festival in proper order to the pump line section 51 at the jam position of pump line 5 and demolish, and through pump line hoist device 3 festival by festival handling to core section of thick bamboo 4 floor mediation clearance, then use through the cooperation of personnel transportation operation platform 2 and pump line hoist device 3, the installation that resets in proper order from top to bottom of pump line section 51 after will clearing up, the high efficiency of super high-rise core section of thick bamboo 4 pump line 5 has been realized, the safe mediation is overhauld, the problem of setting up when adopting traditional approach to overhaul pump line 5 and encorbelmenting the scaffold and consuming a large amount of time and manpower, the efficiency of construction is low, the security is poor is solved.
Preferably, in the above-mentioned core section of thick bamboo pump line maintenance device of integrated in whole steel platform die carrier, personnel's transportation operation platform 2 is including hanging girder steel 21, platform unit 22, power device 23 and wire rope 24, hang girder steel 21 and adopt H shaped steel, hang on girder steel 21 is fixed in whole steel platform die carrier floorbar 11, hang the lower flange of girder steel 21 and set up hoisting point board 26, platform unit 22 hangs on hoisting point board 26 through wire rope 24, power device 23 install in on the platform unit 22, the upper and lower operation of platform unit 22 is realized through the receive and release of power device 23 control wire rope 24. The personnel transportation operation platform 2 with the structure can realize safe lifting of operation personnel and is convenient for the maintenance operation of the pump pipe joint 51, and has the advantages of quick, convenient, safe and reliable lifting.
Preferably, in foretell integrated in core section of thick bamboo pump line maintenance device of whole steel platform die carrier, platform unit 22 is an open-topped square frame, and square frame's bottom sets up the steel sheet, and square frame sets up the rail all around, and the platform unit can hold 1 to 2 operating personnel, makes things convenient for the operating personnel to construct.
Preferably, in the core barrel pump pipe overhaul device integrated in the integral steel platform formwork, the hoisting point plate 26 is vertically arranged, the upper end of the hoisting point plate 26 is fixedly connected to the lower surface of the lower flange of the suspended steel beam, and a hoisting hole for the steel wire rope 24 to pass through is formed in the hoisting point plate 26, so that the platform unit can be stably suspended.
Preferably, in the core cylinder pump pipe overhaul device integrated in the integral steel platform formwork, the plurality of stiffening plates 27 arranged at intervals are arranged on the suspended steel beam 21 at positions corresponding to the hoisting point plates, and three stiffening plates 27 are arranged in the embodiment, so that the stability and strength of the suspended steel beam 21 can be improved, and the lifting safety and stability of the personnel transportation operation platform are further improved.
Preferably, in foretell core section of thick bamboo pump line maintenance device of integrated in whole steel platform die carrier, pump line hoist device 3 includes hoisting device 31, installation girder 32, connecting plate 33, fixing base 34, fender rope device 36, guider 35 and lifting rope 37, installation girder 32 passes through connecting plate 33 spiro union on whole steel platform die carrier floorbar 11, hoisting device 31 passes through fixing base 34 install in the one end of installation girder 32, fender rope device 36 set up respectively with guider 35 in the other end of installation girder 32, lifting rope 37 one end is connected with hoisting device 31, the other end of lifting rope 37 passes through guider 35 is turned into vertically and is connected with shackle 38 by transversely, the below of shackle 38 sets up a clamping device 39, clamping device 39 is used for centre gripping or the pine pump line festival 51. By adopting the pump pipe hoisting device 3 with the structure, the pump pipe joint 51 can be safely and conveniently hoisted.
Preferably, in the core barrel pump pipe overhaul device integrated in the monolithic steel platform formwork, the personnel transportation operation platform 2 further includes a top wall device 25, the top wall device 25 includes a horizontal support bar 251 and an elastic roller 252, the elastic roller 252 is disposed at one end of the horizontal support bar 251, and the other end of the horizontal support bar 251 is fixedly connected to the platform unit 22. Through setting up the headwall device 25, be favorable to the steady lift of personnel transportation operation platform 2, avoid personnel transportation operation platform 2 to rock at the operation in-process, prevent that personnel transportation operation platform 2 from colliding with the pump line.
The above description is only for the purpose of describing the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention, and any changes and modifications made by those skilled in the art according to the above disclosure are all within the scope of the appended claims.

Claims (8)

1. The utility model provides an integrated in core section of thick bamboo pump line maintenance device of whole steel platform die carrier which characterized in that includes: personnel transport operation platform and pump line hoist device, personnel transport operation platform connects in whole steel platform die carrier floorbar and is located whole steel platform die carrier floorbar below, personnel transport operation platform can reciprocate, personnel transport operation platform is used for operation personnel's transportation and dismantles, as operation platform when the installation at the pump line, the vertical arrangement of pump line is in a core section of thick bamboo, the pump line is fixed mutually with core section of thick bamboo wall, the pump line is connected gradually by a plurality of pump line sections and is constituteed, pump line hoist device installs on whole steel platform die carrier floorbar, pump line hoist device is used for the handling pump line section.
2. The core barrel pump pipe overhauling device integrated with the integral steel platform formwork of claim 1, wherein the personnel transportation operation platform comprises a suspension steel beam, a platform unit, a power device and a steel wire rope, the suspension steel beam is made of H-shaped steel, the suspension steel beam is fixed on a bottom beam of the integral steel platform formwork, a hoisting point plate is arranged on a lower flange of the suspension steel beam, the platform unit is suspended on the hoisting point plate through the steel wire rope, the power device is arranged on the platform unit, and the power device controls the winding and unwinding of the steel wire rope to realize the up-and-down operation of the platform unit.
3. The core barrel pump pipe overhauling device integrated with the integral steel platform formwork of claim 2, wherein the platform unit is a square frame with an open top, a steel plate is arranged at the bottom of the square frame, and a fence is arranged around the square frame.
4. The core barrel pump pipe overhauling device integrated with the integral steel platform formwork of claim 2, wherein the hoisting point plate is vertically arranged, the upper end of the hoisting point plate is fixedly connected to the lower surface of the lower flange of the suspension steel beam, and a hoisting hole for a steel wire rope to pass through is formed in the hoisting point plate.
5. The core barrel pump pipe overhauling device integrated with the integral steel platform formwork of claim 2, wherein a plurality of stiffening plates arranged at intervals are arranged on the suspension steel girder at positions corresponding to the lifting point plates.
6. The core cylinder pump pipe overhauling device integrated with the integral steel platform formwork of claim 1, wherein the pump pipe hoisting device comprises a hoisting device, an installation main beam, a connecting plate, a fixing seat, a rope blocking device, a guiding device and a lifting rope, the installation main beam is screwed on a bottom beam of the integral steel platform formwork through the connecting plate, the hoisting device is installed at one end of the installation main beam through the fixing seat, the rope blocking device and the guiding device are respectively arranged at the other end of the installation main beam, one end of the lifting rope is connected with the hoisting device, the other end of the lifting rope is transversely turned into a vertical direction through the guiding device and is connected with a shackle, a clamping device is arranged below the shackle, and the clamping device is used for clamping or loosening a pump pipe section.
7. The core barrel pump tube servicing apparatus integrated with a one-piece steel platform formwork of claim 2, wherein said personnel transportation platform further comprises a pair of top wall means for preventing the personnel transportation platform from rocking during lifting.
8. The core barrel pump pipe overhauling device integrated with the integral steel platform die carrier as recited in claim 7, wherein the top wall device comprises a horizontal supporting rod and an elastic roller, the elastic roller is arranged at one end of the horizontal supporting rod, and the other end of the horizontal supporting rod is fixedly connected with the platform unit.
CN202221861429.6U 2022-07-04 2022-07-04 Core barrel pump pipe overhauling device integrated on integral steel platform die carrier Active CN218758636U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221861429.6U CN218758636U (en) 2022-07-04 2022-07-04 Core barrel pump pipe overhauling device integrated on integral steel platform die carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221861429.6U CN218758636U (en) 2022-07-04 2022-07-04 Core barrel pump pipe overhauling device integrated on integral steel platform die carrier

Publications (1)

Publication Number Publication Date
CN218758636U true CN218758636U (en) 2023-03-28

Family

ID=85690386

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221861429.6U Active CN218758636U (en) 2022-07-04 2022-07-04 Core barrel pump pipe overhauling device integrated on integral steel platform die carrier

Country Status (1)

Country Link
CN (1) CN218758636U (en)

Similar Documents

Publication Publication Date Title
CN102155089B (en) Self-jacking construction platform integrating vertical transportation equipment and mold base
CN202000646U (en) Self-lifting construction platform integrating vertical transportation device and mould frame
CN202467191U (en) Hydraulic slip form device used for construction of circular reinforced concrete chimney wall
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN211286601U (en) Chimney construction device applying hydraulic lifting and rollover technology
CN205367454U (en) Large -size formwork hoisting machine constructs
CN218758636U (en) Core barrel pump pipe overhauling device integrated on integral steel platform die carrier
CN112482317A (en) Door slot second-stage concrete self-climbing slip form pouring system and construction method
CN209740490U (en) Lifting appliance suitable for lowering reinforcement cages with different diameters
CN111058609A (en) Construction and protection integrated portable operation platform and method
CN204983692U (en) Concrete panel's hoist device
CN207312995U (en) One kind self-control bridge-collision-avoidance wall form hanging device
CN214573768U (en) Self-climbing sliding formwork pouring system for second-stage concrete pouring of gate slot
CN215974712U (en) Device for lifting concrete pouring guide pipe of underground continuous wall
CN203050106U (en) Integral hoisting balcony mould
CN115095128B (en) Method for overhauling pump tube of super high-rise core tube
CN209890066U (en) Box girder bottom web reinforcing bar lifting device
CN208934392U (en) Construction mould bases
CN215519871U (en) Combined elevator shaft operating frame
CN217710358U (en) Transverse connection and end beam self-propelled mounting trolley between reinforced concrete composite beam boxes
CN215885996U (en) F-shaped prefabricated T-beam template hoisting device
CN217480795U (en) Combined building formwork structure
CN205077876U (en) Machine and stressing jack linkage are worn to restraint by prestress wire
CN217051331U (en) Anchorage top cover plate installation device
CN219471532U (en) Multifunctional formwork climbing hanger

Legal Events

Date Code Title Description
GR01 Patent grant