CN218577971U - Monitoring buoy - Google Patents

Monitoring buoy Download PDF

Info

Publication number
CN218577971U
CN218577971U CN202222995268.6U CN202222995268U CN218577971U CN 218577971 U CN218577971 U CN 218577971U CN 202222995268 U CN202222995268 U CN 202222995268U CN 218577971 U CN218577971 U CN 218577971U
Authority
CN
China
Prior art keywords
buoy
reel
monitoring
groove
main shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222995268.6U
Other languages
Chinese (zh)
Inventor
王竹
张丹薇
彭文韬
王志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222995268.6U priority Critical patent/CN218577971U/en
Application granted granted Critical
Publication of CN218577971U publication Critical patent/CN218577971U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The utility model discloses a monitoring buoy, including detection assembly, detection assembly includes buoy and detector, anchoring mechanism is installed to the bottom of buoy, anchoring mechanism includes fixing anchor and thread, automatic line subassembly is received to the inboard of buoy, automatic line subassembly includes reel and main shaft, drive assembly is installed to one side of main shaft, drive assembly includes clockwork spring and branch, install broken string alarm assembly on the branch, this monitoring buoy can adjust the length of thread automatically according to the depth of water, avoids the thread overlength to lead to buoy to float everywhere, and then avoids the thread winding on the object in the water, the work of retrieving of monitoring buoy of being convenient for can utilize the auxiliary line to fix after the thread disconnection, avoids buoy to be washed away by rivers, sends the police dispatch newspaper through wireless alarm simultaneously, and personnel can carry out reconnection work to the thread in time, ensures monitoring buoy's safety, and the quality testing who is applicable to the water environment uses.

Description

Monitoring buoy
Technical Field
The utility model relates to a monitoring buoy equipment technical field specifically is a monitoring buoy.
Background
The utility model discloses a utility model patent with patent application number CN202020772049.X, discloses a monitoring buoy for water area operation, which is provided with an anchor chain furling adjusting component on the basis of the existing monitoring buoy structure, can conveniently carry out the lowering and furling of an anchor chain and a fixed anchor, solves the problem that the traditional manual throwing and drawing back of the fixed anchor are labor-consuming and inconvenient, and solves the problems that the length of the traditional anchor chain is fixed, and the anchor chain with different lengths is required to be installed on the buoy in water areas with different water depths, wherein the camera lens cleans the setting of subassembly, can realize the cleanness of camera and light mirror surface, do benefit to better going on such as waters operation environmental monitoring, see according to its disclosed technical scheme, current monitoring buoy equipment is when using, on the one hand, can not carry out rolling work to the hawser according to the difference of the degree of depth of water automatically, cause the hawser overlength easily, make the buoy flutter all around, produce the winding with the internal object of water easily, be unfavorable for the recovery work of monitoring buoy, on the other hand, when the disconnection appears in the hawser, make the buoy washed away by rivers, be unfavorable for the work safety of guarantee monitoring kickboard.
Therefore, how to design a monitoring buoy becomes a problem to be solved currently.
SUMMERY OF THE UTILITY MODEL
Not enough to prior art exists, the utility model aims at providing a monitoring buoy to solve the problem that proposes in the above-mentioned background art, the utility model relates to a rationally, it is comparatively convenient during the use, be applicable to the quality testing of water environment and use.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a monitoring buoy, includes the monitoring buoy body, the monitoring buoy body includes determine module, determine module includes buoy and detector, anchoring mechanism is installed to the bottom of buoy, anchoring mechanism includes anchorages and thread, the automatic line subassembly of receiving is installed to the inboard of buoy, the automatic line subassembly of receiving includes reel and main shaft, drive assembly is installed to one side of main shaft, drive assembly includes clockwork spring and branch, install broken string alarm component on the branch, broken string alarm component includes spring and push switch.
Further, the detector is installed at the bottom of the buoy through a bolt, an inner cavity is formed in the inner side of the buoy, the reel is clamped on the inner side of the inner cavity, one end of the main line is bound on the reel, and the other end of the main line is wound on the outer side of the reel, penetrates through the bottom of the buoy and is bound at the top of the fixed anchor.
Further, the bottom end of the main shaft is welded at the center of the bottom of the reel, and the top of the main shaft penetrates through the inner cavity and is installed on the inner side of the buoy through a bearing.
Furthermore, a clamping groove is formed in the inner side of the buoy and located at the top of the inner cavity, the top end of the support rod is clamped in the inner side of the clamping groove, the bottom end of the support rod penetrates through the clamping groove and is welded at the center of the clockwork spring, the clockwork spring is mounted on the inner side of the inner cavity, and the clockwork spring is located at the top of the inner side of the reel.
Furthermore, a first gear is welded on the outer side of the main shaft, a second gear is welded on the outer side of the spring, and the second gear is meshed with the first gear.
Furthermore, an inner groove is formed in the inner side of the buoy, a reel is installed in the center of the inner groove, the top end of the reel penetrates through the inner groove and extends to the top of the buoy, an auxiliary line is connected to the reel, and one end of the auxiliary line is wound on the outer side of the reel, penetrates through the bottom of the buoy and then is bound to the top of the fixed anchor.
Furthermore, the one end integrated into one piece of branch has a piece, one side of a piece is connected with one side of draw-in groove through the spring, press the switch card on the inner wall of the opposite side of draw-in groove, a piece card is on press the switch, the wireless alarm is installed through the bolt in the top of buoy.
Further, the battery is installed to the inboard of detector, the battery passes through the electric wire and is connected with detector and press the switch, press the switch and pass through the electric wire and be connected with wireless alarm.
Has the beneficial effects that: 1. this monitoring buoy can be according to the length of the depth of water automatically regulated thread of water, avoids the thread overlength to lead to the buoy to wave everywhere, and then avoids the thread winding on the object in the water, is convenient for monitor buoy recovery work.
2. This monitoring buoy can appear breaking off the back at the thread, utilizes the auxiliary line effectively to fix the buoy, avoids the buoy to be washed away by rivers, simultaneously sends out the police dispatch newspaper through wireless alarm automatically for personnel can carry out reconnection work to the thread in time, ensure monitoring buoy's work safety.
3. The monitoring buoy has reasonable design and high efficiency and is convenient to use, and is suitable for the quality detection of water environment.
Drawings
Fig. 1 is a schematic structural view of a monitoring buoy of the present invention;
fig. 2 is a cross-sectional view of a monitoring buoy of the present invention;
fig. 3 is a sectional view of a spring of a monitoring buoy according to the present invention;
fig. 4 is a top cross-sectional view of a strut of a monitoring buoy of the present invention;
in the figure: 1. a float; 2. a detector; 3. fixing an anchor; 4. a main line; 5. an auxiliary line; 6. a reel; 7. an inner cavity; 8. coiling; 9. a main shaft; 10. a clockwork spring; 11. a first gear; 12. a second gear; 13. a strut; 14. a card slot; 15. a spring; 16. a push switch; 17. provided is a wireless alarm.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution: a monitoring buoy comprises a monitoring buoy body, the monitoring buoy body comprises a detection assembly, the detection assembly comprises a buoy 1 and a detector 2, an anchoring mechanism is installed at the bottom of the buoy 1 and comprises a fixed anchor 3 and a main line 4, an automatic wire collecting assembly is installed on the inner side of the buoy 1 and comprises a reel 8 and a main shaft 9, a driving assembly is installed on one side of the main shaft 9 and comprises a clockwork spring 10 and a supporting rod 13, a wire breaking alarm assembly is installed on the supporting rod 13 and comprises a spring 15 and a press switch 16, the detector 2 is installed at the bottom of the buoy 1 through bolts, an inner cavity 7 is formed in the inner side of the buoy 1, the reel 8 is clamped in the inner side of the inner cavity 7, one end of the main line 4 is bound on the reel 8, the other end of the main line 4 is wound on the outer side of the reel 8 and penetrates through the bottom of the buoy 1 to be bound to the top of the fixed anchor 3, the bottom end of the main shaft 9 is welded at the center of the bottom of the reel 8, the top of the main shaft 9 penetrates through the inner cavity 7 and is mounted on the inner side of the buoy 1 through a bearing, the inner side of the buoy 1 is provided with a clamping groove 14, the clamping groove 14 is located at the top of the inner cavity 7, the top end of the supporting rod 13 is clamped on the inner side of the clamping groove 14, the bottom end of the supporting rod 13 penetrates through the clamping groove 14 and is welded at the center of the spiral spring 10, the spiral spring 10 is mounted on the inner side of the inner cavity 7, the spiral spring 10 is located at the top of the inner side of the reel 8, the outer side of the main shaft 9 is welded with a first gear 11, the outer side of the spiral spring 10 is welded with a second gear 12, the second gear 12 is meshed with the first gear 11, when the fixed anchor 3 is put into the water, the fixed anchor 3 automatically pulls the main line 4 and the auxiliary line 5, the main line 4 drives the reel 8 to rotate, the reel 8 drives the main shaft 9 to rotate, the main shaft 9 drives the clockwork spring 10 to rotate through the meshing of the first gear 11 and the second gear 12, the center of the clockwork spring 10 is fixedly supported by the supporting rod 13, the reel 8 is always tensioned by the elasticity of the clockwork spring 10, and therefore the situation that the buoy floats around due to the fact that the main line 4 is too long due to looseness is effectively avoided, the main line 4 is prevented from being wound on an object in the water body, and buoy recycling work is convenient to monitor.
In the embodiment, an inner groove is formed in the inner side of the buoy 1, a reel 6 is installed at the center of the inner groove, the top end of the reel 6 penetrates through the inner groove and extends to the top of the buoy 1, an auxiliary wire 5 is connected to the reel 6, one end of the auxiliary wire 5 is wound on the outer side of the reel 6 and penetrates through the bottom of the buoy 1 to be bound to the top of the fixed anchor 3, a support block is integrally formed at one end of a support rod 13, one side of the support block is connected with one side of a clamping groove 14 through a spring 15, a press switch 16 is clamped on the inner wall of the other side of the clamping groove 14, the support block is clamped on the press switch 16, a wireless alarm 17 is installed at the top of the buoy 1 through a bolt, a storage battery is installed on the inner side of the detector 2 and is connected with the detector 2 and the press switch 16 through electric wires, the push switch 16 is connected with the wireless alarm 17 through an electric wire, when the work is carried out, the clockwork spring 10 generates anticlockwise torsion in the direction of the attached drawing 4 in the process that the main line 4 is released outwards, the supporting rod 13 drives the supporting block compression spring 15 and is far away from the push switch 16, when the main line 4 is broken, the clockwork spring 10 drives the rotary disc 8 to withdraw the main line 4 to the outer side of the reel through the torsion of the clockwork spring 10, meanwhile, the spring 15 pushes the supporting block to extrude the push switch 16, the wireless alarm 17 is further opened, the wireless alarm work is carried out, the auxiliary line 5 keeps the connection work with the fixed anchor 3, the auxiliary line 5 is effectively used for fixing the buoy, the buoy is prevented from being washed away by water flow, meanwhile, the alarm is automatically sent out through the wireless alarm 7, so that personnel can reconnect the main line in time, and the work safety of monitoring the buoy is guaranteed.
The monitoring buoy provides electric energy for used electric equipment through the storage battery, when the monitoring buoy is used, the fixing anchor 3 is thrown into the water bottom, the fixing anchor 3 automatically pulls the main line 4 and the auxiliary line 5, so that the main line 4 drives the reel 8 to rotate, the reel 8 drives the main shaft 9 to rotate, the main shaft 9 drives the clockwork spring 10 to rotate through the meshing of the first gear 11 and the second gear 12, the center of the clockwork spring 10 is fixedly supported by the supporting rod 13, the elasticity of the clockwork spring 10 is utilized to ensure that the reel 8 always tensions the main line 4, further, the buoy is effectively prevented from floating around due to the overlong and long loosened main line 4, further, the main line 4 is prevented from being wound on an object in the water body, the recovery work of the monitoring buoy is facilitated, and in the working process, the clockwork spring 10 is loosened outwards from the main line 4, the anticlockwise torsion in the direction of the attached drawing 4 is generated, the supporting rod 13 drives the supporting block compression spring 15 and is far away from the press switch 16, when the main line 4 is broken, the clockwork spring 10 drives the rotary disc 8 to withdraw the main line 4 to the outer side of the reel by utilizing the torsion of the clockwork spring 10, meanwhile, the torsion of the clockwork spring 10 disappears, the spring 15 pushes the supporting block to extrude the press switch 16, then the wireless alarm 17 is opened, the wireless alarm work is carried out, the auxiliary line 5 is kept connected with the fixed anchor 3, the auxiliary line 5 is effectively used for fixing the buoy, the buoy is prevented from being washed away by water flow, meanwhile, the alarm is automatically sent out through the wireless alarm 7, the personnel can reconnect the main line in time, and the work safety of monitoring the buoy is guaranteed.
Furthermore, it should be understood that although the present specification describes embodiments, not every embodiment includes only a single embodiment, and such description is for clarity purposes only, and it is to be understood that all embodiments may be combined as appropriate by one of ordinary skill in the art to form other embodiments as will be apparent to those of skill in the art from the description herein.

Claims (8)

1. A monitoring buoy, includes the monitoring buoy body, the monitoring buoy body includes the determine module, the determine module includes buoy (1) and detector (2), anchoring mechanism is installed to the bottom of buoy (1), anchoring mechanism includes anchor (3) and thread (4), its characterized in that: automatic line subassembly is received to the inboard of buoy (1) is installed, automatic line subassembly of receiving includes reel (8) and main shaft (9), drive assembly is installed to one side of main shaft (9), drive assembly includes clockwork spring (10) and branch (13), install broken string warning subassembly on branch (13), broken string warning subassembly includes spring (15) and push switch (16).
2. A monitoring buoy in accordance with claim 1, characterized in that: the detector (2) is installed at the bottom of the buoy (1) through a bolt, an inner cavity (7) is formed in the inner side of the buoy (1), the reel (8) is clamped in the inner side of the inner cavity (7), one end of the main line (4) is bound on the reel (8), and the other end of the main line (4) is wound on the outer side of the reel (8) and penetrates through the bottom of the buoy (1) to be bound at the top of the fixed anchor (3).
3. A monitoring buoy in accordance with claim 2, characterized in that: the bottom end of the main shaft (9) is welded at the center of the bottom of the reel (8), and the top of the main shaft (9) penetrates through the inner cavity (7) and is arranged on the inner side of the buoy (1) through a bearing.
4. A monitoring buoy in accordance with claim 3, characterized in that: draw-in groove (14) have been seted up to the inboard of buoy (1), draw-in groove (14) are located the top of inner chamber (7), the top card of branch (13) is in the inboard of draw-in groove (14), draw-in groove (14) and welding are passed in the center department of clockwork spring (10) in the bottom of branch (13), clockwork spring (10) are installed in the inboard of inner chamber (7), clockwork spring (10) are located the top of the inboard of reel (8).
5. A monitoring buoy in accordance with claim 4, wherein: the outer side of the main shaft (9) is welded with a first gear (11), the outer side of the spring (10) is welded with a second gear (12), and the second gear (12) is meshed with the first gear (11).
6. A monitoring buoy in accordance with claim 5, wherein: an inner groove is formed in the inner side of the buoy (1), a reel (6) is installed at the center of the inner groove, the top end of the reel (6) penetrates through the inner groove and extends to the top of the buoy (1), an auxiliary line (5) is connected onto the reel (6), one end of the auxiliary line (5) is wound on the outer side of the reel (6) and penetrates through the bottom of the buoy (1) to be bound to the top of the fixed anchor (3) again.
7. A monitoring buoy in accordance with claim 6, wherein: one end integrated into one piece of branch (13) has a piece, one side of a piece is passed through spring (15) and is connected with one side of draw-in groove (14), press switch (16) card is on the inner wall of the opposite side of draw-in groove (14), a piece card is on press switch (16), wireless alarm (17) are installed through the bolt in the top of buoy (1).
8. A monitoring buoy in accordance with claim 7, characterized in that: the battery is installed to the inboard of detector (2), the battery passes through the electric wire and is connected with detector (2) and press switch (16), press switch (16) pass through the electric wire and are connected with wireless alarm (17).
CN202222995268.6U 2022-11-10 2022-11-10 Monitoring buoy Active CN218577971U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222995268.6U CN218577971U (en) 2022-11-10 2022-11-10 Monitoring buoy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222995268.6U CN218577971U (en) 2022-11-10 2022-11-10 Monitoring buoy

Publications (1)

Publication Number Publication Date
CN218577971U true CN218577971U (en) 2023-03-07

Family

ID=85376727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222995268.6U Active CN218577971U (en) 2022-11-10 2022-11-10 Monitoring buoy

Country Status (1)

Country Link
CN (1) CN218577971U (en)

Similar Documents

Publication Publication Date Title
CN113566796B (en) Thing networking water monitoring environmental protection floats station
CN218594514U (en) Simple platform for water quality monitoring buoy
CN218577971U (en) Monitoring buoy
CN114155998A (en) Floating type overwater photovoltaic cable structure and using method thereof
CN115367052A (en) Maintenance-free water sample collecting buoy for marine environment shore-based monitoring system
CN111547191A (en) Stable form coastal waters floating observation device who conveniently retrieves
CN212074343U (en) Water area operation monitoring buoy
CN111551686B (en) Water quality monitoring intelligence reel
CN116022288A (en) Auxiliary device for marine hydrological meteorological monitoring
CN213387294U (en) Automatic winding and unwinding device for navigation mark mooring rope
CN212529979U (en) Cable winding device for ship
CN111896040B (en) Underwater detection device convenient to fold and unfold
CN210150527U (en) Boats and ships bank is cable winding and unwinding devices for electricity
CN211717512U (en) River course velocity of flow, water level automatic monitoring device
CN115556874A (en) Anti-collision safety buoy
CN212432621U (en) Sewage sampling device
CN219806937U (en) Buoy device for marine environment monitoring
CN216232842U (en) Marine ecology automatic monitoring buoy device
CN220500945U (en) Buoy capable of automatically monitoring
CN215245368U (en) Double-drum quick anchor windlass
CN219838680U (en) Environment monitoring device for ocean engineering
CN113846896B (en) High-strength composite material telegraph pole
CN217034903U (en) Monitoring device for ocean disaster early warning
CN219790459U (en) Buoy for monitoring water environment
CN216746096U (en) Hydrological reflecting buoy used at night