CN218509172U - Electric power tower convenient to personnel install fast - Google Patents

Electric power tower convenient to personnel install fast Download PDF

Info

Publication number
CN218509172U
CN218509172U CN202222759044.5U CN202222759044U CN218509172U CN 218509172 U CN218509172 U CN 218509172U CN 202222759044 U CN202222759044 U CN 202222759044U CN 218509172 U CN218509172 U CN 218509172U
Authority
CN
China
Prior art keywords
base
electric power
bracing piece
personnel
power tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222759044.5U
Other languages
Chinese (zh)
Inventor
潘成磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Guita Tower Co ltd
Original Assignee
Guangxi Guita Tower Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Guita Tower Co ltd filed Critical Guangxi Guita Tower Co ltd
Priority to CN202222759044.5U priority Critical patent/CN218509172U/en
Application granted granted Critical
Publication of CN218509172U publication Critical patent/CN218509172U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Housings And Mounting Of Transformers (AREA)

Abstract

The utility model relates to an electric power tower technical field especially relates to an electric power tower convenient to personnel install fast, has solved among the prior art when carrying out electric power tower base and concrete foundation's installation, all fixes through a great deal of bolt, though the mode of this kind of installation has certain stability, but this kind of mounting means consumes a large amount of human labor, is not convenient for carry out the problem of the maintenance in later stage simultaneously. The utility model provides an electric power tower convenient to personnel install fast, includes base and four concrete bases, four corners in the bottom of base all are equipped with the bracing piece. The utility model discloses in the mode of proposing, support the installation to the base through the bracing piece, utilize the arc mounting panel to install in the ring channel on the bracing piece simultaneously, can realize the stable installation to the base, then carry on the base electric power shaft tower erect can, avoid adopting a great deal of bolt to fix the time problem of wasting time and energy in the tradition, only need adopt the screw rod with two fixed can of butt joint plate.

Description

Electric power tower convenient to personnel install fast
Technical Field
The utility model relates to an electric power tower technical field especially relates to an electric power tower convenient to personnel install fast.
Background
The tower is a support used for supporting the transmission line in the overhead transmission line, is mostly made of steel or reinforced concrete and is a main supporting structure of the overhead transmission line, and is a rod-shaped or tower-shaped structure which supports the lead and the overhead ground wire of the overhead transmission line and keeps a certain distance between the lead and the overhead ground wire and the ground. The line towers of various countries in the world adopt steel structures, wood structures and reinforced concrete structures. Rod-shaped structures of wood and reinforced concrete are commonly referred to as poles, and steel structures of turriform and reinforced concrete chimney-shaped structures are commonly referred to as towers. Towers without guy wires are called free-standing towers, and towers with guy wires are called guy wire towers.
Wherein when carrying out electric power tower's erection construction, need the construction concrete to beat the ground, after doing the ground, fix electric power tower's base on concrete foundation again, but when carrying out electric power tower base and concrete foundation's installation among the prior art, all fix through a great deal of bolt, though the mode of this kind of installation has certain stability, but this kind of mounting means consumes a large amount of human labor, be not convenient for carry out the maintenance in later stage simultaneously, seem very inconvenient, all need a quick electric power tower who installs of personnel of being convenient for urgently.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an electric power tower convenient to personnel install fast has solved among the prior art when carrying out the installation of electric power tower base and concrete foundation, all fixes through a great deal of bolt, though the mode of this kind of installation has certain stability, but this kind of mounting means consumes a large amount of human labor, is not convenient for carry out the problem of the maintenance in later stage simultaneously.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides an electric power shaft tower convenient to personnel install fast, including base and four concrete bases, four corners in the bottom of base all are equipped with the bracing piece, and the top of four bracing pieces all runs through the base through the slot, one side of four bracing pieces all is equipped with the loading board with the bottom fixed connection of base, and the equal sliding connection in both sides of loading board has the connecting plate, and the equal fixedly connected with arc mounting panel in one side of two connecting plates, wherein the equal fixedly connected with butt joint plate of two arc mounting panel other ends, through screw rod fixed connection between two butt joint plates, the ring channel that cooperation arc mounting panel used all has been seted up on one of four bracing pieces, the bottom of four bracing pieces respectively with four concrete bases's top fixed connection.
Preferably, the equal fixedly connected with roof in top both sides of four bracing pieces, and rotate between two roofs and be connected with the dwang to fixedly connected with fly leaf on the dwang, one side of fly leaf is equipped with the threaded rod, and all sets up the thread groove that the cooperation threaded rod used with the top of base on the fly leaf.
Preferably, the two ends of the four rotating rods are respectively and rotatably connected with all the top plates through rotating shafts.
Preferably, one side of each connecting plate is fixedly connected with a sliding block, and the sliding blocks are connected with one side of the bearing plate in a sliding mode through sliding rails.
Preferably, the four support rods are distributed in an annular array along the center of the base.
Preferably, the upper parts of the four support rods are sleeved with the baffle plates, and the four baffle plates are located at the bottom of the base.
The utility model discloses possess following beneficial effect at least:
the utility model discloses in an electric power shaft tower convenient to quick installation of personnel when carrying out the installation of base, at first peg graft the base with four bracing pieces along the position of four slots, and four bracing pieces all pass through between two of all arc mounting panels, slide about going on corresponding arc mounting panel after that, make the ring channel on arc mounting panel and the bracing piece be located same horizontal direction, utilize the butt-joint plate to draw together two arc mounting panels after that, make two arc mounting panels be in the ring channel, utilize the screw rod at last to fix two butt-joint plates can, for carrying out electric power shaft tower base and concrete foundation's installation among the prior art, all fix through a great deal of bolt, though the mode of this kind of installation has certain stability, but this kind of mounting mode consumes a large amount of human labor, be not convenient for carrying out the problem of maintenance in later stage simultaneously, the utility model discloses in the mode of proposing, support the installation through the base through the bracing piece, utilize the arc mounting panel to install in the ring channel on the bracing piece simultaneously, can realize the stable installation to the base, then carry out the electric power shaft tower on the base can, adopt the bolt to erect a great deal of hard problem when avoiding in the tradition, can only adopt the fixed screw rod to erect two fixed screw rods.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without any creative effort.
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic top view of the present invention;
fig. 3 is a schematic view of the support rod of the present invention and its structure.
In the figure: 1. a base; 2. a support bar; 3. an annular groove; 4. a baffle plate; 5. a top plate; 6. a threaded rod; 7. a movable plate; 8. rotating the rod; 9. a carrier plate; 10. inserting slots; 11. a thread groove; 12. an arc-shaped mounting plate; 13. a butt plate; 14. a screw; 15. a connecting plate; 16. a slider; 17. a slide rail; 18. a concrete foundation.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention will be further described in detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Referring to fig. 1-3, an electric power tower convenient for personnel to install fast includes base 1 and four concrete bases 18, four corners in the bottom of base 1 all are equipped with bracing piece 2, and the top of four bracing pieces 2 all runs through base 1 through slot 10, one side of four bracing pieces 2 all is equipped with the loading board 9 with base 1's bottom fixed connection, and the equal sliding connection in both sides of loading board 9 has connecting plate 15, and the equal fixedly connected with arc mounting panel 12 in one side of two connecting plates 15, wherein two arc mounting panels 12 other end equal fixedly connected with butt-joint plate 13, through screw 14 fixed connection between two butt-joint plates 13, ring channel 3 that cooperation arc mounting panel 12 used all sets up on one end of four bracing pieces 2, the bottom of four bracing pieces 2 respectively with four concrete bases 18's top fixed connection, concretely, support the installation to base 1 through bracing piece 2, utilize arc mounting panel 12 to install in ring channel 3 on bracing piece 2 simultaneously, can realize the stable installation to base 1, then erect can electric power tower on base 1, avoid a great deal of adopting the bolt to fix the problem that a lot of wasting time and energy in the tradition, only need screw 14 can fix two butt-joint plates 13.
The scheme has the following working processes:
at first peg graft base 1 along the position of four slots 10 with four bracing pieces 2, and four bracing pieces 2 all pass through between two of all arc mounting panels 12, slide about going on corresponding arc mounting panel 12 next, make arc mounting panel 12 and the annular groove 3 on the bracing piece 2 be located same horizontal direction, utilize butt joint plate 13 to close together two arc mounting panels 12 next, make two arc mounting panels 12 be in annular groove 3, it can to utilize screw rod 14 to fix two butt joint plates 13 at last.
According to the working process, the following steps are known:
support the installation to base 1 through bracing piece 2, utilize arc mounting panel 12 to install in ring channel 3 on bracing piece 2 simultaneously, can realize the stable installation to base 1, then on base 1 carry out electric power shaft tower erect can, avoid adopting a great deal of bolt to fix in the tradition the time-consuming and energy-consuming problem, only need adopt screw rod 14 with two butt joint plates 13 fixed can.
Further, the equal fixedly connected with roof 5 in top both sides of four bracing pieces 2, and rotate between two roofs 5 and be connected with dwang 8, and fixedly connected with fly leaf 7 on the dwang 8, one side of fly leaf 7 is equipped with threaded rod 6, and all offer the thread groove 11 that cooperation threaded rod 6 used with base 1's top on the fly leaf 7, concretely, utilize fly leaf 7 to be connected through threaded rod 6 and base 1's top, can further strengthen base 1's stability, utilize the rotation effect of fly leaf 7, can not hinder base 1 and place on bracing piece 2.
Furthermore, two ends of the four rotating rods 8 are respectively connected with all the top plates 5 through rotating shafts in a rotating manner.
Further, all the connecting plates 15 are fixedly connected to a sliding block 16 on one side, the sliding block 16 is connected to one side of the bearing plate 9 through a sliding rail 17 in a sliding mode, specifically, the sliding block 16 slides in the sliding rail 17, and therefore the connecting plates 15 can be more stable.
Furthermore, four support rods 2 are distributed along the center of the base 1 in an annular array.
Further, baffle 4 has all been cup jointed on the upper portion of four bracing pieces 2, and four baffles 4 all are located base 1's bottom, and is specific, utilizes baffle 4 to support base 1, prevents that base 1 from transferring excessively.
In summary, the following steps: utilize fly leaf 7 to be connected through threaded rod 6 and base 1's top, can further strengthen base 1's stability, utilize fly leaf 7's rotation effect, can not delay base 1 and place on bracing piece 2, utilize slider 16 to slide in slide rail 17, and then can be so that connecting plate 15 is more stable, utilize baffle 4 to support base 1, prevent that base 1 from transferring excessively.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the principles of the present invention may be applied to any other embodiment without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides an electric power tower convenient to personnel install fast, includes base (1) and four concrete foundation (18), its characterized in that, four corners in bottom of base (1) all are equipped with bracing piece (2), and the top of four bracing pieces (2) all runs through base (1), four one side of bracing piece (2) all is equipped with bottom fixed connection's of base (1) loading board (9), and the equal sliding connection in both sides of loading board (9) has connecting plate (15) to the equal fixedly connected with arc mounting panel (12) in one side of two connecting plates (15), wherein the equal fixedly connected with of two arc mounting panel (12) other ends buttcover plate (13), two through screw rod (14) fixed connection, four between buttcover plate (13) one of bracing piece (2) is served and is all offered ring channel (3) that cooperation arc mounting panel (12) used, four the bottom of bracing piece (2) respectively with the top fixed connection of four concrete foundation (18).
2. The electric tower convenient for quick installation of personnel as claimed in claim 1, characterized in that top end two sides of four support rods (2) are fixedly connected with top plates (5), a rotating rod (8) is rotatably connected between the two top plates (5), a movable plate (7) is fixedly connected to the rotating rod (8), a threaded rod (6) is arranged on one side of the movable plate (7), and threaded grooves (11) matched with the threaded rod (6) are formed in the movable plate (7) and the top of the base (1).
3. An electric tower convenient for personnel to install quickly as claimed in claim 2, wherein both ends of the four rotating rods (8) are respectively and rotatably connected with all the top plates (5) through rotating shafts.
4. The electric tower convenient for people to install quickly as claimed in claim 1, wherein one side of all the connecting plates (15) is fixedly connected with a sliding block (16), and the sliding block (16) is connected with one side of the bearing plate (9) in a sliding manner through a sliding rail (17).
5. An electric tower facilitating quick installation by personnel according to claim 1, characterised in that four of said support rods (2) are distributed in a circular array along the centre of the base (1).
6. The electric tower convenient for personnel to install rapidly as claimed in claim 1, wherein the upper parts of the four support rods (2) are sleeved with baffles (4), and the four baffles (4) are located at the bottom of the base (1).
CN202222759044.5U 2022-10-19 2022-10-19 Electric power tower convenient to personnel install fast Active CN218509172U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222759044.5U CN218509172U (en) 2022-10-19 2022-10-19 Electric power tower convenient to personnel install fast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222759044.5U CN218509172U (en) 2022-10-19 2022-10-19 Electric power tower convenient to personnel install fast

Publications (1)

Publication Number Publication Date
CN218509172U true CN218509172U (en) 2023-02-21

Family

ID=85218249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222759044.5U Active CN218509172U (en) 2022-10-19 2022-10-19 Electric power tower convenient to personnel install fast

Country Status (1)

Country Link
CN (1) CN218509172U (en)

Similar Documents

Publication Publication Date Title
CN211239244U (en) Building engineering power cable erects structure
CN218509172U (en) Electric power tower convenient to personnel install fast
CN217631485U (en) Rail sliding type temporary support for large-span steel structure roof
CN102661077A (en) Method for erecting fulcrum bar
CN207538522U (en) A kind of safety-type platform canopy station
CN116436385A (en) Adjustable flexible photovoltaic bracket and application method thereof
CN110572112A (en) Assembled photovoltaic support and mounting method thereof
CN213476900U (en) Combined splayed support
CN212642131U (en) A building templates fixing device for transformer substation's capital construction
CN214615031U (en) A steel column mounting structure for BIM assembled house
CN2612743Y (en) Combined type steel skeleton system
CN210186407U (en) Support frame structure for ski platforms
CN111877560A (en) Steel-wood mixed cross string arch structure
CN205945605U (en) Distributing type photovoltaic module ground mounting structure
CN215888570U (en) Support system for tree-shaped column structure installation
CN206110349U (en) Basic platform device
CN215803485U (en) Console for construction engineering field construction
CN217267592U (en) Portable bridge pile foundation steel reinforcement cage location making devices
CN211849487U (en) Easy dismouting formula underground structure
CN212113988U (en) 5G communication base station with lightning protection effect
CN218715074U (en) Steel structure support for building
CN212201533U (en) Support system for large-span cable membrane type greenhouse
CN217053964U (en) Conversion structure for connecting roof truss
CN215528191U (en) Lightning protection grounding device for building engineering
CN213038930U (en) Steel structure support convenient to install and carry

Legal Events

Date Code Title Description
GR01 Patent grant