CN218201898U CN202222411968.6U CN202222411968U CN218201898U CN 218201898 U CN218201898 U CN 218201898U CN 202222411968 U CN202222411968 U CN 202222411968U CN 218201898 U CN218201898 U CN 218201898U
Authority
CN
China
Prior art keywords
fixedly connected
hoist
construction
shipping box
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222411968.6U
Other languages
Chinese (zh)
Inventor
李兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222411968.6U priority Critical patent/CN218201898U/en
Application granted granted Critical
Publication of CN218201898U publication Critical patent/CN218201898U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a hoist device is used in construction steel structure construction, including the sling cart, firm mechanism is installed at the top of the hoist cart front side, hoist and mount rope is installed to firm mechanism's bottom, fixed establishment is installed to the bottom of hoist and mount rope, fixed establishment includes the mounting bracket, the inner chamber fixedly connected with shipment case of mounting bracket, the equal fixedly connected with L template in front side and the rear side of shipment case right side bottom. The utility model discloses a set up firm mechanism and stably deposit the steel construction, the bottom that drives two baffles through the output of first motor in the fixed establishment simultaneously rotates, makes the baffle close the shipment mouth of shipment case, drives the pressing plate through the linkage subassembly simultaneously and fixes the steel construction, has solved current hoist device for construction steel construction does not possess to stably deposit in the case and to the hook and deposit the problem of going on fixing between the junction of case to the steel construction.

Description

Hoist device is used in construction of building steel construction
Technical Field
The utility model belongs to the technical field of hoist device, especially, relate to a hoist device is used in construction of building steel structure.
Background
The hoisting refers to a general term of installation and positioning of equipment by a crane or a hoisting mechanism, and various hoisting machines are used for hoisting the equipment, workpieces, appliances, materials and the like in the process of maintenance or repair so as to change the positions of the equipment.
For example: the application number is CN202220099421.4, the utility model discloses a hoisting device for construction of a building steel structure, which comprises a vehicle body, a telescopic rod system, a rope system and a hoisting system, wherein the telescopic rod system, the rope system and the hoisting system are fixedly arranged above the vehicle body, a supporting system is fixedly connected around the vehicle body, a rotating base is rotatably arranged at one end of the vehicle body, a driving unit is fixedly arranged above the rotating base, and one end of the rope system and one end of the telescopic rod system are fixedly arranged at one end of the driving unit; the horizontal sensor can sense the weight change of two sides of the hoisting arm, the steel structure positions of two sides of the hoisting arm are adjusted, the balance weight can slide in the balance slide rail and is adjusted by the horizontal sensor, and the control of the real-time small range of the hoisting process is greatly improved in the hoisting operation safety.
Based on the retrieval of above-mentioned patent, and combine the equipment discovery among the prior art, above-mentioned equipment is when using, the problem that traditional hoist device security reduces when hoist and mount operation has been solved, wherein the hoist and mount operation includes a building steel construction, it still has some weak points itself in the in-process that uses, one of them, the steel construction needs to be placed in the case before hoist and mount, if improper operation in-process when operating personnel uses hoist device hoist and mount case, the steel construction drops from hoist device easily, the steel construction smashes the workman on the building site when droing easily, two of it, hoist device usually hooks the case of placing the steel construction through the hook, but this kind of connected mode is unstable, in the in-process of hoist and mount easily because the case of hoist device bottom rocks and leads to depositing in the case breaks away from the inner chamber of hook, lead to depositing the case and smash to ground from the high altitude.
The utility model provides a pair of hoist device is used in construction of building steel structure, make current hoist device for construction of building steel structure deposit the case in hoist and mount, the steel construction of depositing incasement portion can not be because of operating personnel operates improperly and drop, hoist device can fix between the junction of hook and deposit the case when hoist and mount deposit the case simultaneously, the messenger deposits the case and can not rock and break away from hoist device because of self when hoist and mount, thereby avoided operating personnel to operate improperly at the in-process that uses hoist device and lead to depositing the problem that the steel construction of incasement portion drops, and solved hoist device and deposited the case and can not rock and break away from hoist device's the condition because of self when hoist and deposit the case.
SUMMERY OF THE UTILITY MODEL
The problem to prior art exists, the utility model provides a hoist device is used in construction of building steel structure possesses to the steel construction stably leave in deposit the case and to the hook and deposit and go on the advantage fixed between the junction of case, has solved current hoist device is used in construction of building steel structure and has not possessed to the steel construction stably leave in deposit the case and to the hook and deposit the problem of going on fixing between the junction of case.
The utility model is realized in such a way that the hoisting device for the construction of the building steel structure comprises a hoisting vehicle, the top of the front side of the hoisting vehicle is provided with a stabilizing mechanism, the bottom of the stabilizing mechanism is provided with a hoisting rope, the bottom of the hoisting rope is provided with a fixing mechanism, the fixing mechanism comprises a mounting rack, the inner cavity of the mounting rack is fixedly connected with a shipping box, the front side and the rear side of the right bottom of the shipping box are both fixedly connected with L-shaped plates, the right side of each L-shaped plate is fixedly connected with a first motor, the output end of the first motor extends to the left side of the L-shaped plate and is fixedly connected with a baffle plate, the left side of the baffle plate is movably connected with the shipping box through a shaft pin, one side opposite to the two baffle plates is movably connected with the shipping box, the surface of the output end of the first motor is fixedly connected with a driving wheel, the surface of the driving wheel is movably connected with a first driven wheel through a belt, the inner cavity of the first driven wheel is fixedly connected with a rotating rod, two sides of the rotating rod are respectively and movably connected with a positioning plate and a positioning frame, the bottom of the positioning plate is fixedly connected with the shipping box, one side of the two positioning frames opposite to the left side is fixedly connected with the shipping box, the left side of the surface of the rotating rod is fixedly connected with second driven wheels, one opposite side of each of the two second driven wheels is movably connected with a third driven wheel through a belt, the inner cavity of the third driven wheel is fixedly connected with a bidirectional threaded rod, both sides of the bidirectional threaded rod are movably connected with the shipping box, the surface of the bidirectional threaded rod is movably connected with a movable block, the bottom of the movable block is movably connected with an adjusting rod through a shaft pin, a pressing plate is movably connected between the bottoms of the two adjusting rods through the shaft pin, and one side of the pressing plate, which is close to the inner wall of the shipping box, is movably connected with the inner wall of the shipping box.
As the utility model discloses it is preferred, firm mechanism includes the hoist and mount hook, the top and the sling fixed connection of hoist and mount hook, the inner chamber and the hoist and mount rope swing joint of hoist and mount hook, the equal fixedly connected with fixed plate in both sides of hoist and mount hook, the inner chamber fixedly connected with hydraulic stem of fixed plate, the output fixedly connected with inserted bar of hydraulic stem, the inner chamber that two inserted bars are relative all extend to the hoist and mount hook, the surperficial swing joint of inserted bar has the limiting plate, the bottom and the hoist and mount rope fixed connection of the relative one side of two limiting plates.
As the utility model discloses it is preferred, the fixed surface of first motor is connected with solid fixed ring, gu fixed ring's left side all with L template fixed connection.
As the utility model discloses it is preferred, the first fixed block of the equal fixedly connected with in bottom of locating plate both sides, the bottom and the shipment case fixed connection of first fixed block.
As the utility model discloses it is preferred, the equal fixedly connected with second fixed block in one side that the L template is relative, the second fixed block is close to one side and the shipment case fixed connection of shipment case.
As the utility model discloses it is preferred, the equal fixedly connected with fixed strip in both sides of mounting bracket front side and rear side, the fixed strip is close to one side and the shipment case fixed connection of shipment case.
As the utility model discloses it is preferred, the equal fixedly connected with gag lever post of front side and the rear side at shipment case top, the surface and the movable block swing joint of gag lever post.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up firm mechanism and stably deposit the steel construction, the bottom that drives two baffles through the output of first motor in the fixed establishment simultaneously rotates, makes the baffle close the shipment mouth of shipment case, drives the pressing plate through the linkage subassembly simultaneously and fixes the steel construction, has solved current hoist device for construction steel construction does not possess to stably deposit in the case and to the hook and deposit the problem of going on fixing between the junction of case to the steel construction.
2. The utility model discloses a workman places the hoist and mount rope in the inner chamber of hoist and mount hook, start two hydraulic stems afterwards, the output of two hydraulic stems drives two inserted bars respectively and removes to relative one side, the inserted bar injects in the inner chamber of limiting plate at the in-process that removes, inject again afterwards in the inner chamber of hoist and mount hook, because be fixed connection between limiting plate and the hoist and mount rope, make the hoist and mount rope can not drop the inner chamber of hoist and mount hook, thereby the purpose of fixing between the junction of going on to the hook and depositing the case has been played, through setting up solid fixed ring, fixed effect has been played to first motor, make first motor can not lead to droing because of the unexpected condition, through setting up first fixed block, make have stronger fixity between the junction of locating plate and shipment case, the fixed effect of enhancement has been played.
3. The utility model discloses a set up the second fixed block, played fixed effect to the L template, make the L template can not separate with the shipment case because of unexpected collision, through setting up the fixed strip, make to have stronger fixity between the junction of mounting bracket and shipment case, played and strengthened fixed effect, through setting up the gag lever post, played spacing effect to the movable block, make the movable block can not lead to self to rotate because of being thread movement.
Drawings
Fig. 1 is a schematic structural diagram provided in an embodiment of the present invention;
fig. 2 is a top side view of a partial structure provided by an embodiment of the present invention;
fig. 3 is a front side view of a partial structure provided by an embodiment of the present invention;
fig. 4 is an enlarged view of a part of the structure at a in fig. 2 according to an embodiment of the present invention.
In the figure: 1. a sling cart; 2. a stabilizing mechanism; 201. hoisting hooks; 202. a fixing plate; 203. a hydraulic lever; 204. a rod is inserted; 205. a limiting plate; 3. hoisting a rope; 4. a fixing mechanism; 401. a mounting frame; 402. a shipping box; 403. an L-shaped plate; 404. a first motor; 405. a baffle plate; 406. a driving wheel; 407. a first driven wheel; 408. rotating the rod; 409. positioning a plate; 410. a positioning frame; 411. a second driven wheel; 412. a third driven wheel; 413. a bidirectional threaded rod; 414. a movable block; 415. adjusting a rod; 416. a pressing plate; 417. a fixing ring; 418. a first fixed block; 419. a second fixed block; 420. a fixing strip; 421. a limiting rod.
Detailed Description
In order to further understand the contents, features and effects of the present invention, the following embodiments are illustrated and described in detail with reference to the accompanying drawings.
The structure of the present invention will be described in detail with reference to the accompanying drawings.
As shown in fig. 1 to 4, a hoisting device for construction of a building steel structure provided by the embodiment of the invention comprises a sling cart 1, a stabilizing mechanism 2 is installed at the top of the front side of the sling cart 1, a hoisting rope 3 is installed at the bottom of the stabilizing mechanism 2, a fixing mechanism 4 is installed at the bottom of the hoisting rope 3, the fixing mechanism 4 comprises an installation frame 401, an inner cavity of the installation frame 401 is fixedly connected with a shipping box 402, the front side and the rear side of the bottom of the right side of the shipping box 402 are fixedly connected with an L-shaped plate 403, the right side of the L-shaped plate 403 is fixedly connected with a first motor 404, the output end of the first motor 404 extends to the left side of the L-shaped plate 403 and is fixedly connected with a baffle 405, the left side of the baffle 405 is movably connected with the shipping box 402 through a shaft pin, one side of the two baffles 405 opposite is movably connected with the shipping box 402, the surface of the output end of the first motor 404 is fixedly connected with a driving wheel 406, the surface of the driving wheel 406 is movably connected with a first driven wheel 407 through a belt, the inner cavity of the first driven wheel 407 is fixedly connected with a rotating rod 408, two sides of the rotating rod 408 are respectively movably connected with a positioning plate 409 and a positioning frame 410, the bottom of the positioning plate 409 is fixedly connected with the shipping box 402, the opposite sides of the left sides of the two positioning frames 410 are respectively fixedly connected with the shipping box 402, the left side of the surface of the rotating rod 408 is fixedly connected with a second driven wheel 411, the opposite sides of the two second driven wheels 411 are respectively movably connected with a third driven wheel 412 through a belt, the inner cavity of the third driven wheel 412 is fixedly connected with a bidirectional threaded rod 413, two sides of the bidirectional threaded rod 413 are respectively movably connected with the shipping box 402, the surface of the bidirectional threaded rod 413 is movably connected with a movable block 414, the bottom of the movable block 414 is movably connected with an adjusting rod 415 through a shaft pin, and a pressing plate 416 is movably connected between the bottoms of the two adjusting rods 415 through a shaft pin, the side of the pressing plate 416 adjacent to the inner wall of the shipping container 402 is movably attached to the inner wall of the shipping container 402.
Referring to fig. 1, fig. 2, fig. 3 and fig. 4, stabilizing mechanism 2 includes hoisting hook 201, the top of hoisting hook 201 and sling 1 fixed connection, hoisting hook 201's inner chamber and hoisting rope 3 swing joint, the equal fixedly connected with fixed plate 202 in hoisting hook 201's both sides, the inner chamber fixedly connected with hydraulic stem 203 of fixed plate 202, the output fixedly connected with inserted bar 204 of hydraulic stem 203, the inner chamber of hoisting hook 201 is all extended to two opposite sides of inserted bar 204, the surperficial swing joint of inserted bar 204 has limiting plate 205, the bottom and hoisting rope 3 fixed connection of two opposite sides of limiting plate 205, the fixed surface of first motor 404 is connected with solid fixed ring 417, gu fixed ring 417's the left side all with L template 403 fixed connection, the equal fixedly connected with first fixed block 418 in the bottom of locating plate 409 both sides, the bottom and the shipment case 402 fixed connection of first fixed block 418.
The scheme is adopted: the hoisting rope 3 is placed in the inner cavity of the hoisting hook 201 through workers, then the two hydraulic rods 203 are started, the output ends of the two hydraulic rods 203 respectively drive the two inserting rods 204 to move towards the opposite side, the inserting rods 204 are inserted into the inner cavity of the limiting plate 205 in the moving process, and then the inner cavity of the hoisting hook 201 is inserted again, as the limiting plate 205 and the hoisting rope 3 are fixedly connected, the hoisting rope 3 cannot fall off the inner cavity of the hoisting hook 201, so that the purpose of fixing the connection part of the hook and the storage box is achieved, through the arrangement of the fixing ring 417, the first motor 404 is fixed, the first motor 404 cannot fall off due to an accident condition, through the arrangement of the first fixing block 418, the connection part of the positioning plate 409 and the loading and transporting box 402 has stronger fixity, and the fixing strengthening effect is achieved.
Referring to fig. 1, 2 and 4, a second fixing block 419 is fixedly connected to each of opposite sides of the l-shaped plate 403, one side of the second fixing block 419 close to the shipping box 402 is fixedly connected to the shipping box 402, fixing strips 420 are fixedly connected to both sides of the front side and the rear side of the mounting frame 401, one side of the fixing strips 420 close to the shipping box 402 is fixedly connected to the shipping box 402, a limit rod 421 is fixedly connected to both the front side and the rear side of the top of the shipping box 402, and the surface of the limit rod 421 is movably connected to the movable block 414.
Adopt above-mentioned scheme: through setting up second fixed block 419, played fixed effect to L template 403, make L template 403 can not separate with shipment case 402 because of unexpected collision, through setting up fixed strip 420, make to have stronger fixity between the junction of mounting bracket 401 and shipment case 402, played and strengthened fixed effect, through setting up gag lever post 421, played spacing effect to movable block 414, make movable block 414 can not lead to self to rotate because of being the screw thread removal.
The utility model discloses a theory of operation:
when the hoisting device is used, when the storage box is hoisted by the hoisting device and needs to stably store a steel structure, a worker carries the construction steel structure into the shipping box 402, then the output ends of the two first motors 404 respectively drive the bottoms of the two baffles 405 to rotate, the bottoms of the two baffles 405 close the shipping port of the shipping box 402 at the opposite side in the rotating process, the output end of the first motor 404 also drives the driving wheel 406 to rotate in the rotating process, the driving wheel 406 drives the first driven wheel 407 to rotate through a belt, the first driven wheel 407 drives the rotating rod 408 to rotate, the rotating rod 408 drives the second driven wheel 411 to rotate, the second driven wheel 411 drives the third driven wheel 412 to rotate through the belt, the third driven wheel 412 drives the bidirectional threaded rod 413 to rotate, the bidirectional threaded rod 413 drives the two movable blocks 414 to move to the opposite side in the rotating process, the movable block 414 drives the top of the adjusting rod 415 to move through the shaft pin at the bottom in the moving process, and simultaneously, the bottom of the adjusting rod 415 moves downwards, the pressing plate 416 is driven to move downwards through the shaft pin when the bottoms of the two adjusting rods 415 move downwards, when the pressing plate 416 moves downwards to a specified position, the building steel structure can be fixed, so that the building steel structure cannot fall off in the hoisting process, and the purpose of stably storing the steel structure is achieved, meanwhile, when the hoisting device needs to fix the joints in the hoisting and storing process, a worker places the hoisting rope 3 in the inner cavity of the hoisting hook 201, then the two hydraulic rods 203 are started, the output ends of the two hydraulic rods 203 respectively drive the two inserting rods 204 to move to the opposite sides, and the inserting rods 204 are inserted into the inner cavity of the limiting plate 205 in the moving process, then, the lifting hook 201 is inserted into the inner cavity of the lifting hook again, and the limiting plate 205 and the lifting rope 3 are fixedly connected, so that the lifting rope 3 cannot fall off from the inner cavity of the lifting hook 201, and the purpose of fixing the hook and the connecting part of the storage box is achieved.
In conclusion: this hoist device is used in construction of architectural steel structure, through setting up sling cart 1, stabilizing mean 2, hoist and mount rope 3, fixed establishment 4, mounting bracket 401, shipment case 402, L template 403, first motor 404, baffle 405, action wheel 406, first from driving wheel 407, rotary rod 408, locating plate 409, locating rack 410, the second is from driving wheel 411, the third is from driving wheel 412, two-way threaded rod 413, movable block 414, adjust pole 415 and pressing plate 416's cooperation and use, the problem of current hoist device for construction of architectural steel structure does not possess to stabilize to store in the case and carry out the fixing between the hook and the junction of depositing the case to the steel structure is solved.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a hoist device is used in construction of building steel construction, includes sling cart (1), its characterized in that: the top of the front side of the sling cart (1) is provided with a stabilizing mechanism (2), the bottom of the stabilizing mechanism (2) is provided with a hoisting rope (3), the bottom of the hoisting rope (3) is provided with a fixing mechanism (4), the fixing mechanism (4) comprises a mounting frame (401), an inner cavity of the mounting frame (401) is fixedly connected with a shipping box (402), the front side and the rear side of the right bottom of the shipping box (402) are both fixedly connected with an L-shaped plate (403), the right side of the L-shaped plate (403) is fixedly connected with a first motor (404), the output end of the first motor (404) extends to the left side of the L-shaped plate (403) and is fixedly connected with a baffle (405), the left side of the baffle (405) is movably connected with the shipping box (402) through a shaft pin, the two opposite sides of the baffle (405) are movably connected with the shipping box (402), the surface of the output end of the first motor (404) is fixedly connected with a driving wheel (406), the surface of the driving wheel (406) is movably connected with a first driven wheel (407) through a belt, the inner cavity of the first driven wheel (407) is fixedly connected with a rotating rod (408), the two sides of the shipping box (408) are respectively connected with a positioning plate (409) and a positioning plate (410), relative one side in two locating rack (410) left sides all with shipment case (402) fixed connection, the left side fixedly connected with on rotary rod (408) surface is followed driving wheel (411) for the second, and two second follow driving wheel (411) relative one side all have the third through belt swing joint from driving wheel (412), the third is followed driving wheel (412) inner chamber fixedly connected with bidirectional threaded rod (413), the both sides of bidirectional threaded rod (413) all with shipment case (402) swing joint, the surface swing joint of bidirectional threaded rod (413) has movable block (414), the bottom of movable block (414) has through pivot swing joint adjusts pole (415), has through pivot swing joint between the bottom of two regulation poles (415) and presses clamp plate (416), press clamp plate (416) near the one side of shipment case (402) inner wall and the inner wall swing joint of shipment case (402).
2. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: stabilizing mean (2) are including hoist and mount hook (201), the top and sling cart (1) fixed connection of hoist and mount hook (201), the inner chamber and the hoist and mount rope (3) swing joint of hoist and mount hook (201), the equal fixedly connected with fixed plate (202) in both sides of hoist and mount hook (201), the inner chamber fixedly connected with hydraulic stem (203) of fixed plate (202), output fixedly connected with inserted bar (204) of hydraulic stem (203), one side that two inserted bars (204) are relative all extends to the inner chamber of hoist and mount hook (201), the surperficial swing joint of inserted bar (204) has limiting plate (205), and the bottom and hoist and mount rope (3) fixed connection of one side relative to two limiting plates (205).
3. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: the surface of the first motor (404) is fixedly connected with a fixing ring (417), and the left side of the fixing ring (417) is fixedly connected with the L-shaped plate (403).
4. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: the bottom of both sides of locating plate (409) all fixedly connected with first fixed block (418), the bottom and the shipment case (402) fixed connection of first fixed block (418).
5. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: and one sides of the two L-shaped plates (403) opposite to each other are fixedly connected with second fixing blocks (419), and one sides of the second fixing blocks (419) close to the shipping box (402) are fixedly connected with the shipping box (402).
6. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: the two sides of the front side and the rear side of the mounting frame (401) are fixedly connected with fixing strips (420), and one side, close to the shipping box (402), of each fixing strip (420) is fixedly connected with the shipping box (402).
7. The hoisting device for construction of the building steel structure as recited in claim 1, wherein: the front side and the rear side of the top of the shipping box (402) are both fixedly connected with a limiting rod (421), and the surface of the limiting rod (421) is movably connected with a movable block (414).
CN202222411968.6U 2022-09-09 2022-09-09 Hoist device is used in construction of building steel construction Active CN218201898U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222411968.6U CN218201898U (en) 2022-09-09 2022-09-09 Hoist device is used in construction of building steel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222411968.6U CN218201898U (en) 2022-09-09 2022-09-09 Hoist device is used in construction of building steel construction

Publications (1)

Publication Number Publication Date
CN218201898U true CN218201898U (en) 2023-01-03

Family

ID=84632461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222411968.6U Active CN218201898U (en) 2022-09-09 2022-09-09 Hoist device is used in construction of building steel construction

Country Status (1)

Country Link
CN (1) CN218201898U (en)

Similar Documents

Publication Publication Date Title
CN106865177A (en) A kind of turning device and suspender
CN110528863B (en) Hanging basket device for outer inclined plane construction and construction method
CN208120594U (en) A kind of section of jurisdiction for subway work vertical transport system automatically grabs handler
CN206705188U (en) A kind of turning device and suspender
CN108249315A (en) Intelligent remote controls full-automatic subway work vertical transport system
CN218201898U (en) Hoist device is used in construction of building steel construction
CN113959405A (en) Real-time online lofting intelligent monitoring device for tunnel section measuring point
CN213085204U (en) Auxiliary hoisting device for construction site
CN107086474B (en) Meter box installation power assisting device
CN216613795U (en) Double-crane arm frame bridge crane
CN216034591U (en) Simple hoisting trolley for constructional engineering
CN214885384U (en) Pulling-up hanging basket for construction of constructional engineering
CN216141132U (en) Telescopic hanger for overhauling shuttle car
CN110040618B (en) Wall-hanging equipment fixing frock
CN208120593U (en) Intelligent remote controls full-automatic subway work vertical conveying device
CN221273929U (en) Novel stainless steel casting collector capable of effectively reducing collision
CN212893566U (en) Anti-swing crane
CN220432081U (en) Building support hoisting device for building construction
CN221093481U (en) Maintenance hanging bracket for electromechanical equipment
CN217812250U (en) Building bearing platform for outdoor building
CN210457295U (en) Accelerate regulation delivery device of concrete block construction
CN216512654U (en) Lifting machine for constructional engineering
CN218809971U (en) Fixed large crane
CN220664772U (en) Auxiliary device for electrical installation of building engineering
CN210620065U (en) Light crane tower for carrying construction machinery materials