CN213085204U - Auxiliary hoisting device for construction site - Google Patents
Auxiliary hoisting device for construction site Download PDFInfo
- Publication number
- CN213085204U CN213085204U CN202021273000.6U CN202021273000U CN213085204U CN 213085204 U CN213085204 U CN 213085204U CN 202021273000 U CN202021273000 U CN 202021273000U CN 213085204 U CN213085204 U CN 213085204U
- Authority
- CN
- China
- Prior art keywords
- blowing case
- fixedly connected
- kelly
- sliding connection
- gag lever
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 8
- 238000007664 blowing Methods 0.000 claims abstract description 31
- 238000009434 installation Methods 0.000 claims abstract description 19
- 238000010586 diagram Methods 0.000 description 4
- 238000007599 discharging Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000012840 feeding operation Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model belongs to the technical field of building site is with supplementary lifting by crane, especially, be a building site is with supplementary hoisting accessory, including the blowing case, terminal surface sliding connection has the gag lever post before the blowing case, gag lever post bottom fixedly connected with holds in the palm the end, blowing case right side fixedly connected with installation piece, the inboard sliding connection of installation piece has the kelly, with the blowing case cover with the gag lever post alignment behind the spacing groove of blowing case behind the material outside and insert, then hold in the palm the end and shovel the material, insert the kelly and hold in the palm the end, thereby the installation piece is spacing to accomplish the spacing fixed of support end to the kelly, accomplishes the installation to holding in the palm the end to accomplish the material loading operation, save the cost of labor, improve device material loading operating efficiency, labour saving and time saving improves the convenience that the device used.
Description
Technical Field
The utility model belongs to the technical field of building site is with supplementary lifting by crane, concretely relates to building site is with supplementary hoisting accessory.
Background
The hoisting refers to a general term of installation and in-place of equipment by a crane or a hoisting mechanism, and in the process of maintenance or repair, various hoisting tools are used for hoisting the equipment, workpieces, appliances, materials and the like to change the positions of the equipment, so that the equipment is usually subjected to the work of installation, transportation, installation and the like, and the construction safety is most important no matter whether the equipment is hoisted by using a derrick mast or is hoisted by a machine.
The prior art has the following problems:
1. the traditional hoisting device for the construction site is inconvenient to carry out feeding operation when in use, and the materials need to be placed in a material box one by one, so that the operation is troublesome, and time and labor are wasted;
2. traditional hoisting accessory for building site is when using, because the blowing case is the cuboid, when blowing incasement side filled up the material, is difficult to the skew in the direction of the broadside of blowing case, but the easy slope that takes place in blowing case long edge direction, and the operation of hoisting is unsafe, uses unstablely.
In order to solve the problem, the application provides an auxiliary hoisting device for a construction site.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a building site is with supplementary hoisting accessory has the convenient characteristics that carry out the material loading operation and conveniently avoid the workbin slope.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building site is with supplementary hoisting accessory, includes the blowing case, terminal surface sliding connection has the gag lever post before the blowing case, gag lever post bottom fixedly connected with holds in the palm the end, blowing case right side fixedly connected with installation piece, the inboard sliding connection of installation piece has the kelly.
As the utility model relates to a building site is with supplementary hoisting accessory is preferred, the spacing groove has all been seted up to terminal surface and rear end face before the blowing case, the quantity of gag lever post is two, two the gag lever post outside respectively with two the spacing groove sliding connection of blowing case, the end of holding in the palm is "L" form setting, hold in the palm the end top with the bottom sliding connection of blowing case, the draw-in groove has been seted up to the end inboard of holding in the palm, the motion trail of kelly is the linearity, the draw-in groove setting at the end of holding in the palm is in on the motion trail of kelly, the kelly runs through the installation piece.
As the utility model relates to a building site is with supplementary hoisting accessory is preferred, blowing case top end fixedly connected with gallows, the inboard fixedly connected with pull rod of gallows, the pull rod outside fixedly connected with connecting block, connecting block top fixedly connected with mounting bracket, two fixedly connected with threaded rod between the mounting bracket, threaded rod outside screwed connection has the threaded sleeve, the threaded sleeve outside is rotated and is connected with the link, link top end fixedly connected with rings, the inboard sliding connection in rings top has the lifting hook.
As the utility model relates to a building site is with supplementary hoisting accessory is preferred, the quantity of pull rod is two, two the symmetry sets up around the pull rod is the gallows is inboard, the quantity of mounting bracket is two, two the mounting bracket is the symmetry and sets up both ends about the threaded rod, the thread bush is "worker" style of calligraphy setting, the turn trough has been seted up to the link inboard, the thread bush outside with the turn trough of link rotates to be connected.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the material placing box sleeve is inserted into the limiting groove of the material placing box after the limiting rod is aligned to the limiting groove of the material placing box outside the material, the material is shoveled at the bottom of the support, the clamping rod is inserted into the bottom of the support, the installation block is used for limiting the clamping rod and fixing the position of the support bottom, and the installation of the support bottom is completed, so that the material loading operation is completed, the labor cost is saved, the material loading operation efficiency of the device is improved, the time and the labor are saved, and the use convenience of the device is improved.
2. When the device hoists, rotate the threaded sleeve on the threaded rod, drive the link side-to-side movement to adjust the position of rings relative to the mounting bracket, avoid the blowing case horizontal tilt that the skew caused about the material focus in the blowing incasement, improve the stability that the device hoisted, conveniently adjust the operation, improve the security that the material hoisted.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic overall structure diagram of the present invention;
fig. 2 is the mounting structure schematic diagram of the middle threaded rod of the present invention.
In the figure: 1. a material placing box; 2. a limiting rod; 3. supporting the bottom; 4. mounting blocks; 5. a clamping rod; 6. a hanger; 7. a pull rod; 8. Connecting blocks; 9. a mounting frame; 10. a threaded rod; 11. a threaded bushing; 12. a connecting frame; 13. a hoisting ring; 14. and (4) a lifting hook.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1;
fig. 1 is an overall schematic configuration diagram.
The utility model provides a building site is with supplementary hoisting accessory, includes blowing case 1, and terminal surface sliding connection has gag lever post 2 before blowing case 1, and 3 at the bottom of the 2 bottom fixedly connected with of gag lever post holds in the palm, 1 right side fixedly connected with installation piece 4 of blowing case, and 4 inboard sliding connection of installation piece have a kelly 5.
In this embodiment: will put workbin 1 cover behind the material outside aim at behind the spacing groove of putting workbin 1 with gag lever post 2 and insert, then hold in the palm end 3 and shovel the material, the material falls on holding in the palm end 3, then insert 3 at the end of the support with kelly 5, thereby installation piece 4 is to 5 spacing completions of kelly to the spacing fixed of 3 at the end of the support, the completion is to the installation at the end of the support 3 to accomplish the material loading operation.
As shown in fig. 1;
fig. 1 is an overall schematic configuration diagram.
In an optional embodiment, the front end face and the rear end face of the material placing box 1 are both provided with limiting grooves, the number of the limiting rods 2 is two, the outer sides of the two limiting rods 2 are respectively in sliding connection with the limiting grooves of the two material placing boxes 1, the bottom support 3 is arranged in an L shape, the top end of the bottom support 3 is in sliding connection with the bottom end of the material placing box 1, the inner side of the bottom support 3 is provided with a clamping groove, the motion track of the clamping rod 5 is linear, the clamping groove of the bottom support 3 is arranged on the motion track of the clamping rod 5, and the clamping rod 5 penetrates through the mounting block 4.
In this embodiment: conveniently carry out the material loading operation, save the cost of labor, improve device material loading operating efficiency, labour saving and time saving improves the convenience that the device used.
As shown in fig. 1 and 2;
FIG. 1 is a schematic overall structure;
fig. 2 is a schematic view of the mounting structure of the threaded rod.
In an optional embodiment, the top end of the emptying box 1 is fixedly connected with a hanging bracket 6, the inner side of the hanging bracket 6 is fixedly connected with a pull rod 7, the outer side of the pull rod 7 is fixedly connected with a connecting block 8, the top end of the connecting block 8 is fixedly connected with mounting frames 9, a threaded rod 10 is fixedly connected between the two mounting frames 9, the outer side of the threaded rod 10 is spirally connected with a threaded sleeve 11, the outer side of the threaded sleeve 11 is rotatably connected with a connecting frame 12, the top end of the connecting frame 12 is fixedly connected with a hanging ring.
In this embodiment: the position of the lifting ring 13 relative to the mounting frame 9 is adjusted, so that the left and right inclination of the material discharging box 1 caused by left and right deviation of the gravity center of materials in the material discharging box 1 is avoided, and the lifting stability of the device is improved.
As shown in fig. 1 and 2;
FIG. 1 is a schematic overall structure;
fig. 2 is a schematic view of the mounting structure of the threaded rod.
In an alternative embodiment, the number of the pull rods 7 is two, the two pull rods 7 are symmetrically arranged on the inner side of the hanger 6 in a front-back manner, the number of the mounting frames 9 is two, the two mounting frames 9 are symmetrically arranged on the left end and the right end of the threaded rod 10, the threaded sleeve 11 is arranged in an I shape, the inner side of the connecting frame 12 is provided with a rotary groove, and the outer side of the threaded sleeve 11 is rotatably connected with the rotary groove of the connecting frame 12.
In this embodiment: avoid the skew about the material focus in the blowing case 1, improve the stability that the device hoisted, conveniently adjust the operation, improve the security that the material hoisted.
The utility model discloses a theory of operation and use flow: when the device is used, the material placing box 1 is sleeved outside a material, the limiting rod 2 is aligned to the limiting groove of the material placing box 1 and inserted, then the material is shoveled by the support bottom 3, the material falls on the support bottom 3, then the clamping rod 5 is inserted into the support bottom 3, the mounting block 4 limits the clamping rod 5 so as to complete the limiting and fixing of the support bottom 3, and the support bottom 3 is mounted, so that the loading operation is completed, the labor cost is saved, the loading operation efficiency of the device is improved, the time and the labor are saved, the use convenience of the device is improved, when the device is hoisted, the threaded sleeve 11 is rotated on the threaded rod 10 to drive the connecting frame 12 to move left and right, thereby the position of the hoisting ring 13 relative to the mounting frame 9 is adjusted, the left and right inclination of the material placing box 1 caused by the left and right deviation of the gravity center of the material in the material placing box 1 is avoided, the hoisting stability of the device is improved, the lifting ring 13 is lifted by the lifting hook 14, so that the threaded rod 10 is pulled by the threaded sleeve 11, the threaded rod 10 pulls the pull rod 7 to move by the mounting frame 9 and the connecting block 8, and the pull rod 7 drives the discharge box 1 to move by the lifting frame 6.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (4)
1. The utility model provides a building site is with supplementary hoisting accessory, includes blowing case (1), its characterized in that: the utility model discloses a blowing case, including blowing case (1), terminal surface sliding connection has gag lever post (2) before blowing case (1), gag lever post (2) bottom fixedly connected with holds in the palm end (3), blowing case (1) right side fixedly connected with installation piece (4), installation piece (4) inboard sliding connection has kelly (5).
2. The auxiliary hoisting device for construction site according to claim 1, wherein: the spacing groove has all been seted up to terminal surface and rear end face before blowing case (1), the quantity of gag lever post (2) is two, two gag lever post (2) outside respectively with two the spacing groove sliding connection of blowing case (1), hold in the palm end (3) and be "L" form setting, hold in the palm end (3) top with the bottom sliding connection of blowing case (1), hold in the palm end (3) inboard and seted up the draw-in groove, the motion orbit of kelly (5) is the linearity, the draw-in groove setting of holding in the palm end (3) is in on the motion orbit of kelly (5), kelly (5) run through installation piece (4).
3. The auxiliary hoisting device for construction site according to claim 1, wherein: blowing case (1) top fixedly connected with gallows (6), gallows (6) inboard fixedly connected with pull rod (7), pull rod (7) outside fixedly connected with connecting block (8), connecting block (8) top fixedly connected with mounting bracket (9), two fixedly connected with threaded rod (10) between mounting bracket (9), threaded rod (10) outside threaded connection has threaded sleeve (11), threaded sleeve (11) outside is rotated and is connected with link (12), link (12) top fixedly connected with rings (13), rings (13) top inboard sliding connection has lifting hook (14).
4. The auxiliary hoisting device for the construction site according to claim 3, wherein: the quantity of pull rod (7) is two, two the symmetry sets up around pull rod (7) is gallows (6) inboard, the quantity of mounting bracket (9) is two, two mounting bracket (9) are the symmetry and set up both ends about threaded rod (10), threaded sleeve (11) are "worker" style of calligraphy setting, the rotary groove has been seted up to link (12) inboard, the threaded sleeve (11) outside with the rotary groove of link (12) rotates and connects.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021273000.6U CN213085204U (en) | 2020-07-01 | 2020-07-01 | Auxiliary hoisting device for construction site |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021273000.6U CN213085204U (en) | 2020-07-01 | 2020-07-01 | Auxiliary hoisting device for construction site |
Publications (1)
Publication Number | Publication Date |
---|---|
CN213085204U true CN213085204U (en) | 2021-04-30 |
Family
ID=75622261
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021273000.6U Expired - Fee Related CN213085204U (en) | 2020-07-01 | 2020-07-01 | Auxiliary hoisting device for construction site |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN213085204U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113479620A (en) * | 2021-06-17 | 2021-10-08 | 地久恒达建设集团有限公司 | Building construction material loading machine based on location transmission formula |
CN116425012A (en) * | 2023-06-14 | 2023-07-14 | 阳信东泰精密金属有限公司 | Material horizontal lifting device with unhooking prevention function |
-
2020
- 2020-07-01 CN CN202021273000.6U patent/CN213085204U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113479620A (en) * | 2021-06-17 | 2021-10-08 | 地久恒达建设集团有限公司 | Building construction material loading machine based on location transmission formula |
CN116425012A (en) * | 2023-06-14 | 2023-07-14 | 阳信东泰精密金属有限公司 | Material horizontal lifting device with unhooking prevention function |
CN116425012B (en) * | 2023-06-14 | 2023-08-25 | 阳信东泰精密金属有限公司 | Material horizontal lifting device with unhooking prevention function |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN213085204U (en) | Auxiliary hoisting device for construction site | |
CN209881225U (en) | Trolley for mounting cable trough box | |
CN211393540U (en) | Steel member hoist and mount auxiliary device | |
CN210972948U (en) | Novel automatic carrying device | |
CN208054796U (en) | A kind of cement block boom hoisting | |
CN211523985U (en) | Bearing frame for building construction | |
CN216141163U (en) | Indoor curtain wall glass installation construction equipment | |
CN214423956U (en) | Multifunctional hanging basket for building construction | |
CN214885496U (en) | Building engineering construction is with hanging mould device | |
CN204545800U (en) | A kind of brake type platform trailer welded limiting frock | |
CN104827219B (en) | A kind of brake type platform trailer welded limiting frock | |
CN211444792U (en) | Can dismantle civil air defense engineering protective apparatus hoist device | |
CN209890101U (en) | Electric hoist convenient to fix | |
CN211055769U (en) | Hopper equipment for electrolytic aluminum | |
CN211971488U (en) | Multi-functional hoist device of architectural equipment | |
CN215047975U (en) | Assembled building is hoisting frame for assembly | |
CN221116703U (en) | Building material hoisting mechanism for building engineering | |
CN212755050U (en) | Building new material show board | |
CN211141360U (en) | Stable hoisting protection frame with stability | |
CN211998530U (en) | Electromechanical device installs with supporting hanger | |
CN218754521U (en) | Photovoltaic module hoist and mount protective equipment | |
CN208963950U (en) | A kind of large size resin tile shipment conveying device | |
CN110654710A (en) | Hopper equipment for electrolytic aluminum | |
CN215442066U (en) | Sand casting excavator accessory | |
CN109018913A (en) | A kind of large size resin tile shipment conveying device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |