CN218149932U - Petrochemical construction is with circular tower rag bolt construction equipment - Google Patents
Petrochemical construction is with circular tower rag bolt construction equipment Download PDFInfo
- Publication number
- CN218149932U CN218149932U CN202222282777.4U CN202222282777U CN218149932U CN 218149932 U CN218149932 U CN 218149932U CN 202222282777 U CN202222282777 U CN 202222282777U CN 218149932 U CN218149932 U CN 218149932U
- Authority
- CN
- China
- Prior art keywords
- horizontal
- plate
- annular
- bolt
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 55
- 238000000034 method Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 5
- 238000007711 solidification Methods 0.000 description 5
- 230000008023 solidification Effects 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 3
- 230000007246 mechanism Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 239000000945 filler Substances 0.000 description 2
- 230000006872 improvement Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000008602 contraction Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 229910052761 rare earth metal Inorganic materials 0.000 description 1
- 150000002910 rare earth metals Chemical class 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model provides a petrochemical construction is with circular tower ware rag bolt construction equipment relates to petrochemical construction equipment field. A petrochemical engineering construction includes with circular tower rag bolt construction equipment: the upper end of the support frame is provided with an annular base; the annular base comprises an annular plate and a telescopic rod, and the annular plate is of a semi-annular plate-shaped structure; the two annular plates are oppositely arranged and connected through a telescopic rod; the telescopic rod is fixedly connected with the support frame; the supporting frame is also provided with a bolt fixing frame, the bolt fixing frame comprises a plurality of symmetrically arranged horizontal plates, and bolt fixing sleeves are arranged at the bottom ends of the horizontal plates; compared with the prior art, the foundation bolt can be quickly and accurately arranged, the setting precision of the foundation bolt is guaranteed, and meanwhile the foundation bolt is convenient to use and high in applicability.
Description
Technical Field
The utility model relates to a petrochemical construction equipment field particularly, relates to a petrochemical construction is with circular tower rag bolt construction equipment.
Background
Along with the gradual increase of the production and living range of people, the improvement and construction technology of people for living environment is mature day by day, in the existing building construction, in order to facilitate the connection firmness of basic building facilities such as a tower crane, a large-span steel structure and the like, foundation bolts are usually poured and fixed on the construction ground, and the definition of the foundation bolts is screw rod pieces used for fastening equipment, the steel structure and the like on a concrete foundation; when the existing foundation bolt is built, a screw rod piece is mostly placed in a pit on the ground, concrete filler is filled in the pit, and after concrete is solidified, a stable foundation bolt connecting piece is formed.
In the solidification process, the concrete is the rare earth state, and rag bolt receives self gravity to influence when placing at concrete filler intermediate position, perhaps external job site's vibrations, makes rag bolt take place the skew in the concrete solidification process gradually easily, leads to solidifying the rag bolt slope after accomplishing, influences the connection accuracy of equipment, steel construction, for this we have proposed a petrochemical engineering construction and have solved above-mentioned problem with circular tower rag bolt construction equipment.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a petrochemical construction is with circular tower rag bolt construction equipment, its can be fast accurate set up rag bolt, guarantee that rag bolt sets up the precision, its convenient to use simultaneously, the suitability is strong.
The embodiment of the utility model is realized like this:
the embodiment of the application provides a construction device for foundation bolts of a circular tower for petrochemical engineering construction, which comprises a support frame, wherein an annular base is arranged at the upper end of the support frame; the annular base comprises an annular plate and a telescopic rod, and the annular plate is of a semi-annular plate-shaped structure; the two annular plates are oppositely arranged and connected through a telescopic rod; the telescopic rod is fixedly connected with the support frame; the support frame is also provided with a bolt fixing frame, the bolt fixing frame comprises a plurality of symmetrical horizontal plates, and the bottom ends of the horizontal plates are provided with bolt fixing sleeves.
In some embodiments of the present invention, a vertical sliding groove is provided on the supporting frame, and the bolt fixing frame is slidably connected to the supporting frame through the vertical sliding groove.
In some embodiments of the present invention, the device further comprises at least two balance rods, wherein the balance rods are retractable and provided with vertical length scales; the horizontal plate is provided with a first horizontal sliding groove, the lower end of the balancing rod is connected with the horizontal plate in a sliding mode through the first horizontal sliding groove, and the upper end of the balancing rod is connected with the annular plate in a clamping mode.
In some embodiments of the present invention, the bolt fastening bracket includes a sliding frame, and the sliding frame is fixedly connected to the horizontal plate; the vertical sliding grooves are provided with a plurality of sliding frames which are connected with the vertical sliding grooves in a sliding mode.
In some embodiments of the present invention, the horizontal plate includes an outer plate and an inner plate, the outer plate is provided with a second horizontal sliding groove, and the inner plate is slidably connected to the second horizontal sliding groove.
In some embodiments of the present invention, a first level is disposed on the carriage.
In some embodiments of the present invention, the telescopic rod comprises a first inner rod, a second inner rod and a sleeve seat; the sleeve seat is provided with two parallel horizontal through grooves, and the first inner rod and the second inner rod are respectively sleeved with the two horizontal through grooves.
In some embodiments of the present invention, the sleeve seat is provided with a gear between the two horizontal through grooves; and one side of the first inner rod and one side of the second inner rod, which are opposite to the gear, are provided with racks, and the gears are meshed with the racks.
In some embodiments of the present invention, the sleeve seat is provided with a second level.
In some embodiments of the present invention, the annular plate is annularly provided with a plurality of circular holes.
Compared with the prior art, the embodiment of the utility model has following advantage or beneficial effect at least:
the embodiment of the application provides a construction device for foundation bolts of a circular tower for petrochemical engineering construction, which comprises a support frame, wherein an annular base is arranged at the upper end of the support frame; the annular base comprises an annular plate and a telescopic rod, and the annular plate is of a semi-annular plate-shaped structure; the two annular plates are oppositely arranged and connected through a telescopic rod; the telescopic rod is fixedly connected with the support frame; the support frame is also provided with a bolt fixing frame, the bolt fixing frame comprises a plurality of symmetrical horizontal plates, and the bottom ends of the horizontal plates are provided with bolt fixing sleeves. The two annular plates connected through the telescopic rod can be adjusted according to different circular towers, and workers can simulate the bottoms of different circular towers after adjusting the annular bases according to actual conditions, so that foundation bolts can be better arranged; simultaneously, be provided with the fixed cover of bolt through the horizontal plate bottom, can fix rag bolt effectively, the condition of rag bolt emergence skew in the concrete solidification process gradually is avoided appearing. And a plurality of horizontal plates which are symmetrically arranged also ensure the arrangement requirements of a plurality of foundation bolts.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are required to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
Fig. 1 is a plan view of embodiment 1 of the present invention;
fig. 2 is a top view of the annular base according to embodiment 1 of the present invention;
fig. 3 is a plan view of embodiment 2 of the present invention;
fig. 4 is a top view of a bolt fastening bracket according to embodiment 3 of the present invention;
fig. 5 is a sectional view of the socket according to embodiment 4 of the present invention;
fig. 6 is a top view of the ring-shaped base according to embodiment 5 of the present invention.
An icon: 1. a support frame; 2. an annular base; 3. an annular plate; 4. a telescopic rod; 5. a bolt fixing frame; 6. a horizontal plate; 7. fixing a sleeve by a bolt; 8. a vertical chute; 9. a balancing pole; 10. a carriage; 11. a first inner bar; 12. a second inner bar; 13. a sleeve seat; 14. a gear; 15. a circular hole.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the accompanying drawings, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures.
In the description of the embodiments of the present invention, it should be noted that, if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and the like indicate the position or positional relationship based on the position or positional relationship shown in the drawings, or the position or positional relationship which is usually placed when the product of the present invention is used, the description is only for convenience of description of the present invention and simplification, but the indication or suggestion that the device or element to be referred must have a specific position, be constructed and operated in a specific position, and therefore, the present invention should not be construed as being limited thereto. Furthermore, the terms "first," "second," "third," and the like are used solely to distinguish one from another and are not to be construed as indicating or implying relative importance.
Furthermore, the terms "horizontal", "vertical", "suspended" and the like do not require that the components be absolutely horizontal or suspended, but may be slightly inclined. For example, "horizontal" merely means that the direction is more horizontal than "vertical" and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
In the description of the embodiments of the present invention, "a plurality" means at least 2.
In the description of the embodiments of the present invention, it should be further noted that unless otherwise explicitly stated or limited, the terms "set", "mounted", "connected" and "connected" should be interpreted broadly, and may be, for example, a fixed connection, a detachable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
Example 1
Referring to fig. 1-2, fig. 1 is a plan view of the present embodiment; fig. 2 is a top view of the annular base 2 of the present embodiment.
The embodiment provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and a telescopic rod 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; two annular plates 3 are arranged, and the two annular plates 3 are oppositely arranged and connected through a telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; the support frame 1 is further provided with a bolt fixing frame 5, the bolt fixing frame 5 comprises a plurality of symmetrical horizontal plates 6, and the bottom ends of the horizontal plates 6 are provided with bolt fixing sleeves 7.
The two annular plates 3 connected through the telescopic rod 4 can be adjusted according to different circular towers, and workers can simulate the bottoms of different circular towers after adjusting the annular base 2 according to actual conditions, so that foundation bolts can be arranged better; simultaneously, be provided with the fixed cover of bolt 7 through 6 bottoms of horizontal plate, can fix rag bolt effectively, avoid appearing the condition appearance that rag bolt takes place the skew in the concrete solidification process gradually. And, a plurality of horizontal plates 6 that the symmetry set up have also guaranteed a plurality of rag bolt's setting needs.
Example 2
Referring to fig. 3, fig. 3 is a plan structure diagram of the present embodiment.
The embodiment provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and an expansion link 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; the two annular plates 3 are oppositely arranged and connected through the telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; the support frame 1 is further provided with a bolt fixing frame 5, the bolt fixing frame 5 comprises a plurality of symmetrical horizontal plates 6, and the bottom ends of the horizontal plates 6 are provided with bolt fixing sleeves 7. This example is substantially the same as example 1, and the main difference is that: the support frame 1 is provided with a vertical sliding chute 8, and the bolt fixing frame 5 is connected with the support frame 1 in a sliding mode through the vertical sliding chute 8. The bolt fixing frame 5 which is connected with the support frame 1 in a sliding mode through the vertical sliding groove 8 enables a worker to adjust the height of the bolt fixing frame 5 according to actual needs, and the applicability of the device is improved.
In some embodiments of the present invention, the utility model further comprises at least two balance bars 9, the balance bars 9 are retractable and provided with vertical length scales; the horizontal plate 6 is provided with a first horizontal sliding groove, the lower end of the balancing rod 9 is connected with the horizontal plate 6 in a sliding mode through the first horizontal sliding groove, and the upper end of the balancing rod is connected with the annular plate 3 in a clamping mode. The balance bar 9 is arranged to measure and fix the horizontal height between the annular plate 3 and the horizontal plate 6 while performing auxiliary fixing on the annular plate and the horizontal plate; the vertical length scales also enable workers to quickly judge the horizontal condition between the two through the vertical length scales to adjust in time. The lower end of the balance rod 9 is connected with the horizontal plate 6 in a sliding mode through the first horizontal sliding groove, so that the position of the balance rod 9 can be adjusted according to actual conditions.
Example 3
Referring to fig. 4, fig. 4 is a top view of the bolt fixing frame 5 of the present embodiment.
The embodiment provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and a telescopic rod 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; the two annular plates 3 are oppositely arranged and connected through the telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; the support frame 1 is also provided with a bolt fixing frame 5, the bolt fixing frame 5 comprises a plurality of symmetrically arranged horizontal plates 6, and the bottom ends of the horizontal plates 6 are provided with bolt fixing sleeves 7; the supporting frame 1 is provided with a vertical chute 8, and the bolt fixing frame 5 is connected with the supporting frame 1 in a sliding way through the vertical chute 8; the balance bar mechanism further comprises at least two balance bars 9, wherein the balance bars 9 are telescopic and are provided with vertical length scales; the horizontal plate 6 is provided with a first horizontal sliding groove, the lower end of the balancing rod 9 is connected with the horizontal plate 6 in a sliding mode through the first horizontal sliding groove, and the upper end of the balancing rod is connected with the annular plate 3 in a clamping mode. This example is substantially the same as example 1, and the main difference is that: the bolt fixing frame 5 comprises a sliding frame 10, and the sliding frame 10 is fixedly connected with the horizontal plate 6; the vertical sliding chutes 8 are provided in plurality, and the sliding frame 10 is slidably connected with the vertical sliding chutes 8. The plurality of vertical runners 8 ensures the stability of the carriage 10 and avoids skewing.
In some embodiments of the present invention, the horizontal plate 6 includes an outer plate and an inner plate, the outer plate is provided with a second horizontal sliding groove, and the inner plate is slidably connected to the second horizontal sliding groove. The inner plate is slidably connected with the second horizontal sliding groove to enable the horizontal plate 6 to be telescopic, and the fixing position of the foundation bolt sleeve is adjusted.
In some embodiments of the present invention, a first level is provided on the carriage 10. The first level is provided to allow the operator to observe the level of the carriage 10.
Example 4
Referring to fig. 5, fig. 5 is a cross-sectional view of the socket 13 of the present embodiment.
The embodiment provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and a telescopic rod 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; two annular plates 3 are arranged, and the two annular plates 3 are oppositely arranged and connected through a telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; the supporting frame 1 is also provided with a bolt fixing frame 5, the bolt fixing frame 5 comprises a plurality of symmetrically arranged horizontal plates 6, and the bottom ends of the horizontal plates 6 are provided with bolt fixing sleeves 7; the supporting frame 1 is provided with a vertical chute 8, and the bolt fixing frame 5 is connected with the supporting frame 1 in a sliding way through the vertical chute 8; the balance bar mechanism further comprises at least two balance bars 9, wherein the balance bars 9 are telescopic and are provided with vertical length scales; a first horizontal sliding groove is formed in the horizontal plate 6, the lower end of the balancing rod 9 is connected with the horizontal plate 6 in a sliding mode through the first horizontal sliding groove, and the upper end of the balancing rod is clamped with the annular plate 3; the bolt fixing frame 5 comprises a sliding frame 10, and the sliding frame 10 is fixedly connected with the horizontal plate 6; a plurality of vertical sliding chutes 8 are arranged, and the sliding frame 10 is connected with the plurality of vertical sliding chutes 8 in a sliding manner; the horizontal plate 6 comprises an outer plate and an inner plate, the outer plate is provided with a second horizontal sliding groove, and the inner plate is connected with the second horizontal sliding groove in a sliding manner; a first level is provided on carriage 10. This example is substantially the same as example 1, and the main difference is that: the telescopic rod 4 comprises a first inner rod 11, a second inner rod 12 and a sleeve seat 13; the sleeve seat 13 is provided with two parallel horizontal through grooves, and the first inner rod 11 and the second inner rod 12 are respectively sleeved with the two horizontal through grooves.
In some embodiments of the present invention, the sleeve seat 13 is provided with a gear 14 between the two horizontal through grooves; racks are arranged on one sides of the first inner rod 11 and the second inner rod 12 opposite to the gear 14, and the gear 14 is meshed with the racks. The first inner rod 11 and the second inner rod 12 are meshed through the gear 14, so that the relative contraction conditions are further ensured to be the same, and the annular plate 3 is ensured to be symmetrical.
In some embodiments of the present invention, a second level is disposed on the sleeve base 13. The arrangement of the second level ruler is convenient for the staff to observe the horizontal condition of the sleeve seat 13
Example 5
Referring to fig. 6, fig. 6 is a top view of the annular base 2 of the present embodiment.
The embodiment provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and a telescopic rod 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; the two annular plates 3 are oppositely arranged and connected through the telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; the supporting frame 1 is also provided with a bolt fixing frame 5, the bolt fixing frame 5 comprises a plurality of symmetrically arranged horizontal plates 6, and the bottom ends of the horizontal plates 6 are provided with bolt fixing sleeves 7; the supporting frame 1 is provided with a vertical chute 8, and the bolt fixing frame 5 is connected with the supporting frame 1 in a sliding way through the vertical chute 8; the balance bar mechanism further comprises at least two balance bars 9, wherein the balance bars 9 are telescopic and are provided with vertical length scales; the horizontal plate 6 is provided with a first horizontal sliding groove, the lower end of the balancing rod 9 is connected with the horizontal plate 6 in a sliding mode through the first horizontal sliding groove, and the upper end of the balancing rod is connected with the annular plate 3 in a clamping mode; the bolt fixing frame 5 comprises a sliding frame 10, and the sliding frame 10 is fixedly connected with the horizontal plate 6; a plurality of vertical sliding chutes 8 are arranged, and the sliding frame 10 is connected with the plurality of vertical sliding chutes 8 in a sliding manner; the horizontal plate 6 comprises an outer plate and an inner plate, the outer plate is provided with a second horizontal sliding groove, and the inner plate is connected with the second horizontal sliding groove in a sliding manner; a first level bar is arranged on the sliding frame 10; the telescopic rod 4 comprises a first inner rod 11, a second inner rod 12 and a sleeve seat 13; the sleeve seat 13 is provided with two parallel horizontal through grooves, and the first inner rod 11 and the second inner rod 12 are respectively sleeved with the two horizontal through grooves; the sleeve seat 13 is provided with a gear 14 between the two horizontal through grooves; racks are arranged on one sides of the first inner rod 11 and the second inner rod 12 opposite to the gear 14, and the gear 14 is meshed with the racks; the sleeve seat 13 is provided with a second level. This example is substantially the same as example 1, and the main differences are as follows: the annular plate 3 is annularly provided with a number of circular holes 15. A plurality of round holes 15 that the annular set up make the staff pass through unwrapping wire location through round hole 15, confirm circular tower rag bolt's position, carry out quick inspection to it, further guarantee that rag bolt sets up in the correct position.
To sum up, the embodiment of the utility model provides a circular tower foundation bolt construction device for petrochemical engineering construction, which comprises a support frame 1, wherein an annular base 2 is arranged at the upper end of the support frame 1; the annular base 2 comprises an annular plate 3 and an expansion link 4, and the annular plate 3 is in a semi-annular plate 3-shaped structure; two annular plates 3 are arranged, and the two annular plates 3 are oppositely arranged and connected through a telescopic rod 4; the telescopic rod 4 is fixedly connected with the support frame 1; still be provided with bolt fixing frame 5 on support frame 1, bolt fixing frame 5 includes horizontal plate 6 that a plurality of symmetries set up, and 6 bottoms of horizontal plate are provided with bolt fastening cover 7. The two annular plates 3 connected through the telescopic rod 4 can be adjusted according to different circular towers, and workers can simulate the bottoms of different circular towers after adjusting the annular base 2 according to actual conditions, so that foundation bolts can be arranged better; simultaneously, be provided with the fixed cover of bolt 7 through 6 bottoms of horizontal plate, can fix rag bolt effectively, avoid appearing the condition appearance that rag bolt takes place the skew in the concrete solidification process gradually. And, a plurality of horizontal plates 6 that the symmetry set up have also guaranteed a plurality of rag bolt's setting needs.
The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and various modifications and changes will occur to those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (10)
1. A circular tower foundation bolt construction device for petrochemical engineering construction is characterized by comprising a support frame, wherein an annular base is arranged at the upper end of the support frame; the annular base comprises an annular plate and a telescopic rod, and the annular plate is of a semi-annular plate-shaped structure; the two annular plates are oppositely arranged and connected through a telescopic rod; the telescopic rod is fixedly connected with the support frame; the bolt fixing frame is further arranged on the supporting frame and comprises a plurality of symmetrical horizontal plates, and bolt fixing sleeves are arranged at the bottom ends of the horizontal plates.
2. The circular tower foundation bolt construction device for petrochemical engineering construction according to claim 1, wherein a vertical sliding groove is formed in the support frame, and the bolt fixing frame is slidably connected with the support frame through the vertical sliding groove.
3. The circular tower foundation bolt construction device for petrochemical engineering construction according to claim 2, further comprising at least two balancing rods, wherein the balancing rods are telescopic and provided with vertical length scales; the balance bar is characterized in that a first horizontal sliding groove is formed in the horizontal plate, the lower end of the balance bar is connected with the horizontal plate in a sliding mode through the first horizontal sliding groove, and the upper end of the balance bar is connected with the annular plate in a clamping mode.
4. The circular tower foundation bolt construction device for petrochemical engineering construction according to claim 2, wherein the bolt fixing frame comprises a sliding frame, and the sliding frame is fixedly connected with the horizontal plate; the vertical sliding groove is provided with a plurality of sliding frames, and the sliding frames are connected with the vertical sliding grooves in a sliding mode.
5. The circular tower anchor bolt construction device for petrochemical engineering construction according to claim 4, wherein the horizontal plate comprises an outer plate and an inner plate, the outer plate is provided with a second horizontal sliding groove, and the inner plate is slidably connected with the second horizontal sliding groove.
6. The circular tower anchor bolt construction device for petrochemical engineering construction according to claim 4, wherein a first level is arranged on the sliding frame.
7. The circular tower foundation bolt construction device for petrochemical engineering construction according to claim 1, wherein the telescopic rod comprises a first inner rod, a second inner rod and a sleeve seat; the sleeve seat is provided with two parallel horizontal through grooves, and the first inner rod and the second inner rod are respectively sleeved with the two horizontal through grooves.
8. The circular tower anchor bolt construction device for petrochemical engineering construction according to claim 7, wherein the sleeve base is provided with a gear between the two horizontal through grooves; and racks are arranged on one sides of the first inner rod and the second inner rod, which are opposite to the gears, and the gears are meshed with the racks.
9. The circular tower anchor bolt construction device for petrochemical engineering construction according to claim 8, wherein a second level is arranged on the sleeve base.
10. The circular tower anchor bolt construction device for petrochemical engineering construction according to claim 1, wherein a plurality of circular holes are annularly arranged on the annular plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222282777.4U CN218149932U (en) | 2022-08-29 | 2022-08-29 | Petrochemical construction is with circular tower rag bolt construction equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222282777.4U CN218149932U (en) | 2022-08-29 | 2022-08-29 | Petrochemical construction is with circular tower rag bolt construction equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218149932U true CN218149932U (en) | 2022-12-27 |
Family
ID=84557258
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222282777.4U Active CN218149932U (en) | 2022-08-29 | 2022-08-29 | Petrochemical construction is with circular tower rag bolt construction equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218149932U (en) |
-
2022
- 2022-08-29 CN CN202222282777.4U patent/CN218149932U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106638726B (en) | Static test counterforce structure and static test system | |
CN108729353A (en) | A kind of General reinforced cage binding moulding bed | |
CN110318340A (en) | A kind of cantilever construction hanging basket formwork fast-positioning device and localization method | |
CN218149932U (en) | Petrochemical construction is with circular tower rag bolt construction equipment | |
CN206637189U (en) | A kind of large-scale tower crane foundation pre-embedded bolt fixing device | |
CN220150941U (en) | Pre-buried rag bolt locating component | |
CN117344751A (en) | Portable slot supporting tool | |
CN215801763U (en) | Foundation bolt positioning device suitable for power transmission tower | |
CN216339647U (en) | Novel pre-buried bolt structure of tower crane foundation location | |
CN215801769U (en) | Pre-buried fixing device of roll line rag bolt | |
CN210621745U (en) | Foundation bolt fixing frame assembly | |
CN114960456A (en) | Prefabricated pier stud bearing platform embedded steel bar positioning device and method | |
CN210658021U (en) | Quick positioner of basket template is hung in cantilever construction | |
CN209894184U (en) | Tunnel shaft construction measuring device | |
CN206330577U (en) | A kind of mobile integrated concrete measuring table | |
CN209310816U (en) | A kind of wall column formwork verticality measurement device | |
CN208136945U (en) | A kind of foundation of iron tower bolt fixture | |
CN106759280B (en) | A kind of extra-long foundation pile foundation joint bar positioning construction method | |
CN107178075B (en) | Railway subgrade settlement observation scale protection column and manufacturing and using method thereof | |
CN205242439U (en) | Big shaped steel constructs post positioner | |
CN221663681U (en) | Steel reinforcement cage installation positioner | |
CN218758861U (en) | Supporting device for accurately binding constructional steel bars | |
CN211873878U (en) | Cast-in-place concrete plate thickness control device | |
CN217356170U (en) | Direct-buried foundation bolt mounting part | |
CN213236856U (en) | Rainfall monitoring facilities for hydraulic engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240329 Address after: 100020 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen Patentee after: SINOPEC Group Country or region after: China Patentee after: SINOPEC TENTH CONSTRUCTION Co. Address before: 677 Lijiang West Road, Huangdao District, Qingdao City, Shandong Province 266500 Patentee before: Zhang Baichuan Country or region before: China |
|
TR01 | Transfer of patent right |