CN218060420U - Prefabricated power equipment working well convenient to transport and construct - Google Patents
Prefabricated power equipment working well convenient to transport and construct Download PDFInfo
- Publication number
- CN218060420U CN218060420U CN202220787573.3U CN202220787573U CN218060420U CN 218060420 U CN218060420 U CN 218060420U CN 202220787573 U CN202220787573 U CN 202220787573U CN 218060420 U CN218060420 U CN 218060420U
- Authority
- CN
- China
- Prior art keywords
- component
- splitting
- well
- power equipment
- transport
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a prefabricated power equipment foundation and a working well which are convenient to transport and construct, comprising a lower component and an upper component, wherein the lower component is a cuboid with a closed bottom and an open top, and the upper component is a cuboid with an open bottom and an open top; the length and the width of the upper member are consistent with those of the lower member, and the upper member is placed on the top of the lower member; the top of both ends all is equipped with the notch around the component down, goes up the component and all is equipped with the notch bottom both ends around, and goes up the component and correspond the pipeline hole of constituteing the installation cable duct with the notch on the component down. The utility model discloses a with prefabricated electric power worker well split one-tenth a plurality of components concatenation shaping, the weight and the volume of single component reduce greatly, convenient transportation and installation for prefabricated electric power worker well no longer limits in the topography, the effectual efficiency of construction that improves electric power worker well and has reduced construction cost.
Description
Technical Field
The utility model relates to an electric power construction technical field especially relates to a prefabricated power equipment basis and worker's well of convenient transportation and construction.
Background
The existing electric power working well is divided into two types, one type is directly constructed and piled or poured on site, but the construction time is seriously influenced by the environment and weather; the other type is prefabricated in a factory for pouring, but the existing prefabricated electric power well is generally a cuboid with an opening at the top and is additionally provided with a top cover with an inspection opening, but the prefabricated electric power well is too heavy and is not easy to transport, and can be hoisted only by a crane, and is not easy to construct and install in narrow terrains where some cranes are not easy to enter.
Disclosure of Invention
In order to solve above-mentioned current electric power worker well site directness and pour and lead to the engineering time long, and prefabricated electric power worker well is the problem that a whole is difficult to transport and is under construction, the utility model provides a convenient prefabricated power equipment basis and worker well of transporting and being under construction.
In order to achieve the above object, the utility model provides a following technical scheme:
a prefabricated power equipment foundation and a working well convenient to transport and construct comprise a lower component and an upper component, wherein the lower component is a rectangular body with a closed bottom and an open top; the length and the width of the upper member are consistent with those of the lower member, and the upper member is placed on the top of the lower member; the top parts of the front end and the rear end of the lower component are provided with notches, the bottom parts of the front end and the rear end of the upper component are provided with notches, and the notches on the upper component and the lower component correspondingly form pipeline holes for installing cable pipes; a top cover with the same length and width as the upper component is arranged at the top of the upper component, and a closable inspection opening is arranged on the top cover; a plurality of hoisting holes are formed in the upper component and the lower component, and a plurality of hoisting rings are reserved on the top cover, so that the hoisting is facilitated.
Preferably, a plurality of air holes are formed in the front end and the rear end of the upper component, so that ventilation and heat dissipation in the work well are facilitated.
Furthermore, the lower member and the upper member are respectively split into four lower splitting pieces, four upper splitting pieces and two connecting pieces, the corresponding lower splitting pieces and the corresponding upper splitting pieces are spliced in pairs and placed at the top of the base to form an electric power well main body, and the connecting pieces are placed between the two adjacent lower splitting pieces and the two adjacent upper splitting pieces; half holes are reserved at the joints of the lower splitting piece, the upper splitting piece and the connecting piece, and combined to form a pouring connecting hole, and a steel bar is reserved in the pouring connecting hole.
Preferably, the height of the lower splitting part is higher than that of the upper splitting part, and a gap is reserved between the left lower splitting part and the right lower splitting part to form a pipeline hole.
Preferably, the pouring connecting hole is a waist-shaped hole or a rhombic hole.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a with prefabricated electric power worker well split one-tenth a plurality of components concatenation shaping, the weight and the volume of single component reduce greatly, convenient transportation and installation for prefabricated electric power worker well no longer limits in the topography, the effectual efficiency of construction that improves electric power worker well and has reduced construction cost.
Drawings
Fig. 1 is a schematic perspective view of a first embodiment of the present invention;
fig. 2 is a schematic front view of the first embodiment of the present invention;
fig. 3 is a schematic top view of the top cover of the present invention;
fig. 4 is a schematic perspective view of a second embodiment of the present invention.
In the figure: 1. the lower component 11, the lower detaching part 2, the upper component 21, the air holes 22, the upper detaching part 3, the pipeline holes 4, the hoisting holes 5, the top cover 51, the inspection opening 6, the base 7, the connecting piece 8 and the pouring connecting hole.
Detailed Description
In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", "vertical", "horizontal", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of the description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Example one
As shown in fig. 1 to 3, the structure comprises a lower member 1 and an upper member 2, wherein the lower member 1 is a rectangular body with a closed bottom and an open top, and the upper member 2 is a rectangular body with an open bottom and an open top; the length and width of the upper member 2 are consistent with those of the lower member 1, and the upper member 2 is placed on the top of the lower member 1; the tops of the front end and the rear end of the lower component 1 are provided with notches, the bottoms of the front end and the rear end of the upper component 2 are provided with notches, and the notches on the upper component 2 and the lower component 1 correspondingly form a pipeline hole 3 for installing a cable pipe; a top cover 5 with the same length and width as the upper component 2 is arranged at the top of the upper component, and a closable inspection opening 51 is arranged on the top cover 5; a plurality of hoisting holes 4 are formed in the upper member 2 and the lower member 1, and a plurality of hoisting rings are reserved on the top cover 5, so that the hoisting is facilitated; the front end and the rear end of the upper component 2 are respectively provided with a plurality of air holes 21, so that ventilation and heat dissipation in the work well are facilitated.
Divide into top cap 5 with the electric power worker well, go up component 2 and lower component 1 three-layer, it can to pour concrete setting shaping in the mill, then when the construction of electric power worker well, only need dig out earlier the buried hole, then in proper order with lower component 1, go up component 2 and top cap 5 put into the buried hole can, hole for hoist 4 and rings make things convenient for the hoist and mount, pipe hole 3 is used for installing cable duct, bleeder vent 21 makes things convenient for equipment ventilation cooling in the well, the convenient later stage of access hole 51 on the top cap 5 is overhauld. And divide into the three-layer concatenation with electric power worker well, lighten the weight of its single component greatly, make things convenient for transportation and construction installation more.
Example two
As shown in fig. 4, on the basis of the first embodiment, the lower member 1 and the upper member 2 are respectively split into four lower split parts 11, an upper split part 21 and two connecting parts 7, the corresponding lower split parts 11 and upper split parts 22 are spliced two by two and placed on the top of the base 6 to form an electric power work well main body, and the connecting part 7 is placed between the two adjacent lower split parts 11 and upper split parts 22; half holes are reserved at the joints of the lower splitting piece 11, the upper splitting piece 22 and the connecting piece 6, a pouring connecting hole 8 is formed in a combined mode, and a steel bar is reserved in the pouring connecting hole 8.
Firstly, pouring concrete into a base 6, a lower splitting part 11, an upper splitting part 22, a connecting part 7 and a top cover 5 in a factory for solidification forming, reserving reinforcing steel bars in half holes of the connecting positions of the adjacent lower splitting part 11, upper splitting part 22 and connecting part 7, then firstly placing the base 6 into a buried hole, then combining the lower splitting part 11 and the connecting part 7 to form a lower member 1, then placing the corresponding upper splitting part 22 on the top of the lower splitting part 11 for combination to form an upper member 2, then pouring concrete into a pouring connecting hole 8, after the concrete is solidified and formed, combining the upper splitting part 22, the lower splitting part 11 and the connecting part 7 into a main body of the electric power well, and then placing the top cover 5 on the top. Further will descend component 1 and last component 2 to split, can further reduce the weight and the volume of single component, make things convenient for transportation and construction of installation more.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. The utility model provides a convenient prefabricated power equipment worker well of transportation and construction which characterized in that: the lower member is a rectangular body with a closed bottom and an open top, and the upper member is a rectangular body with an open bottom and an open top; the length and the width of the upper member are consistent with those of the lower member, and the upper member is placed on the top of the lower member; the top parts of the front end and the rear end of the lower component are provided with notches, the bottom parts of the front end and the rear end of the upper component are provided with notches, and the notches on the upper component and the lower component correspondingly form pipeline holes for installing cable pipes; a top cover with the same length and width as the upper component is arranged at the top of the upper component, and a closable inspection opening is arranged on the top cover; a plurality of hoisting holes are formed in the upper component and the lower component, and a plurality of hoisting rings are reserved on the top cover, so that the hoisting is facilitated.
2. The prefabricated power equipment well convenient to transport and construct of claim 1, wherein: the front end and the rear end of the upper component are respectively provided with a plurality of air holes, so that ventilation and heat dissipation in the work well are facilitated.
3. The prefabricated power equipment working well convenient to transport and construct according to claim 1 or 2, wherein: the lower component and the upper component are respectively split into four lower splitting parts, four upper splitting parts and two connecting pieces, the corresponding lower splitting parts and the corresponding upper splitting parts are spliced in pairs and placed at the top of the base to form a main body of the electric power working well, and the connecting pieces are placed between the two adjacent lower splitting parts and the two adjacent upper splitting parts; half holes are reserved at the joints of the lower splitting piece, the upper splitting piece and the connecting piece, and combined to form a pouring connecting hole, and a steel bar is reserved in the pouring connecting hole.
4. The prefabricated power equipment well convenient to transport and construct of claim 3, wherein: the height of the lower splitting part is higher than that of the upper splitting part, and a gap is reserved between the left lower splitting part and the right lower splitting part to form a pipeline hole.
5. The prefabricated power equipment working well convenient to transport and construct according to claim 4, wherein: the pouring connecting hole is a waist-shaped hole or a rhombic hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220787573.3U CN218060420U (en) | 2022-04-07 | 2022-04-07 | Prefabricated power equipment working well convenient to transport and construct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220787573.3U CN218060420U (en) | 2022-04-07 | 2022-04-07 | Prefabricated power equipment working well convenient to transport and construct |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218060420U true CN218060420U (en) | 2022-12-16 |
Family
ID=84414899
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220787573.3U Active CN218060420U (en) | 2022-04-07 | 2022-04-07 | Prefabricated power equipment working well convenient to transport and construct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218060420U (en) |
-
2022
- 2022-04-07 CN CN202220787573.3U patent/CN218060420U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106438212A (en) | Bent and spliced type bucket-shaped tower barrel | |
CN101549836A (en) | Method for hoisting ultra-high overweight equipment in closed workshop and special sling | |
CN212052708U (en) | Novel underground continuous wall joint box | |
CN218060420U (en) | Prefabricated power equipment working well convenient to transport and construct | |
CN114575589A (en) | Construction method for lifting template of electric hoist of steel reinforced concrete structural column | |
CN205591529U (en) | Attached lifting scaffold | |
CN112127541A (en) | Assembled floor veneer integrated board convenient to handling | |
CN101967902B (en) | Basic guide rail for helicopter assembly transmission line iron tower leg section | |
CN214658135U (en) | Assembled coincide floor | |
CN210763974U (en) | Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material | |
CN211028010U (en) | Casting weight supporting device for wind power product casting | |
CN211037310U (en) | Novel steel pipe bundle tower crane buttress | |
CN210418434U (en) | Frock is laid fast to metallic steel tank bottom plate in restricted space | |
CN203530950U (en) | Combined type stack counterforce standard block | |
CN209890068U (en) | Temporary fixing device for hoisting reinforcement cage and placing grouting pipe | |
CN206591544U (en) | Pipe gallery with corrugated steel shear wall | |
CN218669310U (en) | Stackable electric control room suitable for low-temperature track drilling machine | |
CN206219080U (en) | A kind of tower crane | |
CN218759056U (en) | Steel structure prefabricated information machine room | |
CN213143130U (en) | Assembled underground pipe gallery | |
CN211006764U (en) | High-safety prefabricated assembly type cable work well | |
CN218860148U (en) | Special holding pole and lifting system for hoisting shaft of Yangtze river large-span tower | |
CN205472319U (en) | Between maintenance of combination mobile formula | |
CN214692854U (en) | Hoist for double-machine hoisting equipment installation | |
CN214114692U (en) | Device for hanging objects in underground auxiliary workshop construction of hydropower station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||