CN218030228U CN202220970700.3U CN202220970700U CN218030228U CN 218030228 U CN218030228 U CN 218030228U CN 202220970700 U CN202220970700 U CN 202220970700U CN 218030228 U CN218030228 U CN 218030228U
Authority
CN
China
Prior art keywords
leg
fixed
tunnel
platform
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202220970700.3U
Other languages
Chinese (zh)
Inventor
贾海军
王文祥
梁瑞
王正才
罗晶鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN202220970700.3U priority Critical patent/CN218030228U/en
Application granted granted Critical
Publication of CN218030228U publication Critical patent/CN218030228U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to the technical field of scaffolds basically consisting of special base structures, and discloses a portable tunnel waterproof plate lap joint construction platform which is arranged in a side ditch of a tunnel and comprises two bipods and an overhanging platform plate horizontally extending from the tops of the two bipods to a tunnel lining; the bottom ends of the fixed supporting legs and the movable supporting legs are respectively provided with a caster, the advancing direction of the caster is arranged along the extending direction of the side ditch, and the caster is provided with a locking device. In the utility model, the two-foot stand is arranged in the side ditch of the tunnel, and then the two-foot stand is used for supporting the overhanging platform plate extending from the side ditch to the lining wall, thereby providing a safe and stable operation platform for constructors; the casters are arranged at the bottoms of the two foot stands, and the two foot stands are supported on the side ditch wall after being opened, so that the construction platform can be pushed along the tunnel to efficiently complete construction, and meanwhile, the platform is not unstable due to the casters, and the whole device is foldable.

Description

Portable tunnel waterproof board overlap joint construction platform
Technical Field
The utility model relates to a scaffold technical field who comprises special base structure basically especially relates to a portable tunnel waterproof board overlap joint construction platform.
Background
For tunnels with wet interior, such as a through-the-hill tunnel, a series of waterproofing and drainage measures are required, including waterproof boards attached to the lining walls, side walls and side ditches on both sides of the bottom of the tunnel.
When the waterproof operation of the lining wall of the tunnel is carried out, the lap construction between the waterproof plate reserved at the bottom of the tunnel and the waterproof plate newly laid above the waterproof plate is a difficult problem. The platform truck is adopted as construction platform in the tunnel lining construction, and for avoiding influencing the walking, the bottommost layer of platform truck need be higher than the drain bar top of reserving, and the platform truck can not freely adjust according to the field conditions, and this lapping construction that leads to between the waterproof board that the waterproof board of tunnel bottom reservation and the waterproof board of top new laying can't go on the platform truck.
In the prior art, the lap construction between the waterproof board reserved at the bottom of the tunnel and the waterproof board newly laid above depends on a worker standing on an arch-shaped reserved steel bar at the top of the side wall, the top of the reserved steel bar is narrow and smooth, a falling accident is very easy to happen when the tunnel is standing above the tunnel, and the construction efficiency is very low (the tunnel is stuck to a wall and is unstable in standing, and the tunnel cannot move).
These two problems are particularly acute for long tunnels. Take a certain project in the southwest area that this application relates to as an example, its tunnel overall length is 2.44 kilometers, and wherein waterproof board connects installation work volume about 4880m, if adopt traditional method construction, must appear many and fall the accident, the time limit for a project also prolongs greatly simultaneously.
SUMMERY OF THE UTILITY MODEL
The utility model provides a portable tunnel waterproof board overlap joint construction platform.
The technical problem to be solved is that: the lap joint construction between the waterproof board of reserving in the tunnel bottom and the waterproof board of newly laying in the top relies on the workman to stand and goes on the reservation reinforcing bar at side wall top, easily falls and the efficiency of construction is low.
In order to solve the technical problem, the utility model adopts the following technical scheme: a portable tunnel waterproof plate lap joint construction platform is arranged in a side ditch of a tunnel and comprises two bipods and an overhanging platform plate which extends from the tops of the two bipods to a tunnel lining horizontally;
the two-leg stand is arranged in the side ditch at intervals along the extending direction of the side ditch, each two-leg stand comprises a fixed leg propped at the wall root of the side wall and a movable leg propped on the wall of the side ditch far away from the side wall, the top end of the movable leg is hinged with the top end of the fixed leg, and a hinged shaft at the joint is arranged in parallel to the extending direction of the side ditch;
the top ends of the fixed supporting legs are fixed with plate edge rods which are horizontally arranged and extend towards the tunnel wall, the plate edge rods are higher than the reserved steel bars at the top of the side wall, and the edges of the overhanging platform plate are respectively fixedly connected with the two plate edge rods;
the bottom ends of the fixed supporting legs and the movable supporting legs are respectively provided with a caster, the traveling direction of the caster is arranged along the extending direction of the side ditch, and the caster is provided with a locking device which is used for enabling the caster not to rotate.
Furthermore, the truckle is the auto-lock universal wheel.
Furthermore, the truckle is the envelope wheel, still the parcel of fixed leg's truckle is wrapped up outward and is used for avoiding lacerating the cushion of the waterproof board on the side wall.
Further, flange pole one end shore on the tunnel lining wall and the other end is fixed on fixed landing leg top, and the tip parcel that flange pole shore on the tunnel lining wall has the cushion, leaves the space that is used for avoiding the waterproof board between stiffener and the side wall.
Furthermore, a reinforcing rod is vertically arranged between the fixed supporting leg and the plate edge rod, and two ends of the reinforcing rod are respectively fixedly connected with the fixed supporting leg and the plate edge rod.
Further, fixed landing leg, activity landing leg, board limit pole and stiffener are the steel pipe, the landing slab of encorbelmenting is the steel sheet net, the stiffener both ends respectively with fixed landing leg and flange limit pole welded connection, board limit pole respectively with fixed landing leg and the landing slab welded connection of encorbelmenting.
Furthermore, a locking device for locking an included angle between the fixed supporting leg and the movable supporting leg is arranged between the fixed supporting leg and the movable supporting leg.
The utility model relates to a portable tunnel waterproof board overlap joint construction platform compares with prior art, has following beneficial effect:
in the utility model, the two-foot stand is arranged in the side ditch of the tunnel, and then the two-foot stand is used for supporting the overhanging platform plate extending from the side ditch to the lining wall, thereby providing a safe and stable operation platform for constructors; the casters are arranged at the bottoms of the two foot stands, and the two foot stands are supported on the side ditch wall after being opened, so that the construction platform can be pushed along the tunnel to efficiently complete construction, and meanwhile, the platform is not unstable due to the casters, and the whole device is foldable.
Drawings
Fig. 1 is a schematic view of a portable tunnel waterproof plate lap joint construction platform of the present invention in use;
fig. 2 is a perspective view of the portable tunnel waterproof plate lap joint construction platform of the present invention;
the side wall is 1-side wall, the side ditch is 2-side ditch, the fixed supporting legs are 31-movable supporting legs, the movable supporting legs are 32-caster wheels, the plate side rods are 4-cantilever platform plates, and the reinforcing rods are 6-reinforcing rods.
Detailed Description
As shown in fig. 1-2, a portable tunnel waterproof plate lap-joint construction platform is arranged in a side ditch 2 of a tunnel and comprises two bipods and an overhanging platform plate 5 which horizontally extends from the tops of the two bipods to a tunnel lining;
here, the use of the bipod and the overhanging platform plate 5 has many considerations: one of the two-leg frame structure is that a large opening is formed between the two-leg frame and the overhanging platform plate 5, so that the utility model can be pushed along the side ditch 2 without being blocked by the waterproof plate and other members reserved at the bottom of the tunnel; secondly, the two foot rests can be propped against the wall of the side ditch 2, so that the whole platform cannot shake left and right when in use on the premise of the casters 33; it is third in making the utility model discloses collapsible to adapt to the narrow construction scene in the tunnel.
The bipod sets up in the gutter 2 along 2 extending direction intervals in the gutter, and every bipod includes a shore at the fixed landing leg 31 of the wall root department of side wall 1 and a shore and keeps away from the movable landing leg 32 on the gutter wall of side wall 1 at the gutter 2, and the top of movable landing leg 32 is connected with the top of fixed landing leg 31 is articulated, and the articulated shaft of junction is on a parallel with 2 extending direction settings in the gutter.
Fixed landing leg 31 top is fixed with the flange pole 4 that the level set up and extend to the tunnel wall, and flange pole 4 is higher than the setting of the reservation reinforcing bar at 1 top of boundary wall, and the border of encorbelmenting landing slab 5 respectively with two 4 fixed connection on the board limit pole.
Casters 33 are provided at the bottom ends of the fixed leg 31 and the movable leg 32, respectively, the casters 33 are provided in the direction in which the gutter 2 extends, and the casters 33 are provided with locking means for preventing the casters 33 from rotating. Here locking means for locking the castors 33 when the platform is in use.
In this embodiment, the caster 33 is a self-locking universal wheel, and a cover is provided outside the caster 33, and a cushion for preventing the waterproof board on the side wall 1 from being scratched is further wrapped outside the cover of the caster 33 of the fixed leg 31.
4 one ends shore of board limit pole is on the tunnel lining wall and the other end is fixed on fixed landing leg 31 top, and 4 tip parcels of board limit pole shore on the tunnel lining wall have the cushion, leave the space that is used for avoiding the waterproof board between stiffener 6 and side wall 1. The end of the plate edge rod 4 is propped on the lining wall, so that the stability of the platform is further improved, but the waterproof plate on the wall can be broken through, and therefore, a cushion needs to be wrapped on the plate edge rod 4.
A reinforcing rod 6 is vertically arranged between the fixed supporting leg 31 and the plate edge rod 4, and two ends of the reinforcing rod 6 are respectively fixedly connected with the fixed supporting leg 31 and the plate edge rod 4. Stiffener 6 has formed the triangular structure with fixed landing leg 31 and flange limit pole 4, promotes the firm degree of the platform board 5 of encorbelmenting, avoids encorbelmenting the end downwarping of platform board 5.
Fixed leg 31, activity landing leg 32, flange limit pole 4 and stiffener 6 are the steel pipe, and the landing slab 5 of encorbelmenting is the steel sheet net, 6 both ends of stiffener respectively with fixed leg 31 and 4 welded connection of flange limit pole, flange limit pole 4 respectively with fixed leg 31 and 5 welded connection of the landing slab of encorbelmenting.
A locking device for locking the included angle between the fixed leg 31 and the movable leg 32 is arranged between the two. Here, the hinge shaft between the fixed leg 31 and the movable leg 32 can be a bolt, the locking device is a nut on the bolt, and the locking device can fix the included angle between the fixed leg 31 and the movable leg 32, thereby enabling the utility model discloses also can regard as the dolly outside the gutter 2 and push away, conveniently transport.
The application provides a use method of a portable tunnel waterproof plate lap joint construction platform, which comprises the following steps:
the method comprises the following steps: the utility model is put into the side ditch 2, and two foot rests are stretched to prop against the two sides of the side ditch 2;
step two: the utility model is pushed to the using position, the caster 33 is locked, and the construction is started;
the above-mentioned embodiments are only for describing the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention, and various modifications and improvements made by those skilled in the art without departing from the design spirit of the present invention should fall into the protection scope defined by the claims of the present invention.

Claims (6)

1. The utility model provides a portable tunnel waterproof board overlap joint construction platform which characterized in that: the device is arranged in a side ditch (2) of the tunnel and comprises two bipods and an overhanging platform plate (5) which horizontally extends from the tops of the two bipods to the tunnel lining;
the two-leg stand is arranged in the side ditch (2) at intervals along the extending direction of the side ditch (2), each two-leg stand comprises a fixed leg (31) which is propped at the wall root of the side wall (1) and a movable leg (32) which is propped on the wall of the side ditch (2) far away from the side wall (1), the top end of the movable leg (32) is hinged with the top end of the fixed leg (31), and a hinged shaft at the joint is arranged in parallel to the extending direction of the side ditch (2);
plate edge rods (4) which are horizontally arranged and extend towards the tunnel wall are fixed at the top ends of the fixed supporting legs (31), the plate edge rods (4) are higher than the reserved steel bars at the top of the side wall (1), and the edges of the overhanging platform plate (5) are respectively fixedly connected with the two plate edge rods (4);
the bottom ends of the fixed supporting legs (31) and the movable supporting legs (32) are respectively provided with a caster (33), the advancing direction of the caster (33) is arranged along the extending direction of the side ditch (2), and the caster (33) is provided with a locking device which is used for preventing the caster (33) from rotating; a locking device for locking an included angle between the fixed supporting leg (31) and the movable supporting leg (32) is arranged between the fixed supporting leg and the movable supporting leg; after the locking device is locked, the included angle between the fixed supporting leg (31) and the movable supporting leg (32) is fixed, so that the construction platform becomes a trolley which can be pushed away.
2. The portable tunnel waterproof plate lap construction platform of claim 1, characterized in that: the caster wheel (33) is a self-locking universal wheel.
3. The portable tunnel waterproof plate lap construction platform of claim 2, characterized in that: the truckle (33) are the envelope wheel, the envelope of truckle (33) of fixed leg (31) is wrapped up still outward and is used for avoiding lacerating the cushion of the waterproof board on the side wall (1).
4. The portable tunnel waterproof plate lap construction platform of claim 1, characterized in that: board side bar (4) one end shore on the wall is built to the tunnel lining and the other end is fixed on fixed landing leg (31) top, and board side bar (4) shore tip parcel on the wall is built to the tunnel lining has the cushion, leaves the space that is used for avoiding the waterproof board between stiffener (6) and side wall (1).
5. The portable tunnel waterproof plate lap construction platform of claim 1, characterized in that: and a reinforcing rod (6) is vertically arranged between the fixed supporting leg (31) and the plate edge rod (4), and two ends of the reinforcing rod (6) are respectively fixedly connected with the fixed supporting leg (31) and the plate edge rod (4).
6. The portable tunnel waterproof plate lap construction platform of claim 5, wherein: fixed landing leg (31), activity landing leg (32), flange limit pole (4) and stiffener (6) are the steel pipe, the landing slab (5) of encorbelmenting is the steel sheet net, stiffener (6) both ends respectively with fixed landing leg (31) and flange limit pole (4) welded connection, flange limit pole (4) respectively with fixed landing leg (31) and encorbelment landing slab (5) welded connection.
CN202220970700.3U 2022-04-26 2022-04-26 Portable tunnel waterproof board overlap joint construction platform Expired - Fee Related CN218030228U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220970700.3U CN218030228U (en) 2022-04-26 2022-04-26 Portable tunnel waterproof board overlap joint construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220970700.3U CN218030228U (en) 2022-04-26 2022-04-26 Portable tunnel waterproof board overlap joint construction platform

Publications (1)

Publication Number Publication Date
CN218030228U true CN218030228U (en) 2022-12-13

Family

ID=84372153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220970700.3U Expired - Fee Related CN218030228U (en) 2022-04-26 2022-04-26 Portable tunnel waterproof board overlap joint construction platform

Country Status (1)

Country Link
CN (1) CN218030228U (en)

Similar Documents

Publication Publication Date Title
CN105736016A (en) Tunnel secondary lining steel bar framework construction equipment and application thereof
CN212079327U (en) Hydraulic pressure regulation formula side wall template platform truck
CN111364505B (en) Aluminum template supporting system for comprehensive pipe rack
CN204676881U (en) Large span intersection truss steel structure supporting system
CN218030228U (en) Portable tunnel waterproof board overlap joint construction platform
CN205578009U (en) Two lined steel bones RACK in tunnel equipment of being under construction
CN211143800U (en) Reusable rainproof steam-curing dual-purpose shed for beam yard
CN108951384A (en) The laying apparatus and its laying method of TGXG
CN211692503U (en) Novel bridge tunnel supporting member
CN212534206U (en) Cast-in-place formula piping lane erects wall construction platform truck
CN210589859U (en) Movable precast beam concrete cloth construction platform
CN216767417U (en) Platform is spread and hung to tunnel side wall waterproof board
CN208167715U (en) A kind of navigation channel bored concrete pile operation platform
CN206591796U (en) Movable Scaffold with overhanging type operating platform
CN221856736U (en) Waterproof board trolley and two lining trolley integrated construction system
CN206800204U (en) A kind of highway bridge bent cap reinforcement cage mold
CN217734765U (en) Movable tunnel operation platform
CN216894438U (en) Support for assisting shield launching
CN212978313U (en) Angle bead is deposited to precast beam board
CN204781885U (en) Novel crown cornice shaped steel operation platform that encorbelments
CN214195803U (en) Folding telescopic sand prevention thermal insulation shed
CN221002059U (en) Building construction safety protection canopy
CN217581089U (en) Movable operating platform that encorbelments
CN215857843U (en) A template support system for vault underground structure engineering construction
CN215170086U (en) Bury formula waterstop fixing device in tunnel

Legal Events

Date Code Title Description
GR01 Patent grant