CN217921272U CN202222424767.XU CN202222424767U CN217921272U CN 217921272 U CN217921272 U CN 217921272U CN 202222424767 U CN202222424767 U CN 202222424767U CN 217921272 U CN217921272 U CN 217921272U
Authority
CN
China
Prior art keywords
fixed
steel column
lifting
rod
installation device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222424767.XU
Other languages
Chinese (zh)
Inventor
赵亮
赵伟
贾力东
李文静
李斌
李向宁
王尉丽
巨红梅
赵玉
刘冲
贾朋飞
梁飞
高启铭
汪高辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongding Yicheng Beijing Construction Engineering Co ltd
Hebei Construction Group Corp Ltd
Original Assignee
Zhongding Yicheng Beijing Construction Engineering Co ltd
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongding Yicheng Beijing Construction Engineering Co ltd, Hebei Construction Group Corp Ltd filed Critical Zhongding Yicheng Beijing Construction Engineering Co ltd
Priority to CN202222424767.XU priority Critical patent/CN217921272U/en
Application granted granted Critical
Publication of CN217921272U publication Critical patent/CN217921272U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an ultrahigh steel column bracket plate lifting and mounting device, which comprises a truss base arranged on a structural plate, symmetrical double-output-shaft electric chain blocks arranged on the truss base and steel wire ropes connected with the two ends of the symmetrical double-output-shaft electric chain blocks; two first fixed pulleys and two second fixed pulleys are arranged on the truss base, and the two second fixed pulleys are respectively arranged right below the two first fixed pulleys; the free ends of the two steel wire ropes respectively pass around the first fixed pulley and the second fixed pulley on the same side, the end parts of the two steel wire ropes are provided with lifting hooks, the two lifting hooks are connected with a lifting platform, and Niu Tuiban is placed on the lifting platform; the truss base is fixed on the structural plate through the fixing plate. The utility model adopts the above structure an superelevation steel column bracket board promotes installation device, safe when having realized superelevation steel column bracket board construction, reliable, saved the manpower, the bracket board promotes installation device simple, quick detachable, can have enough to meet the need the use, convenient to use accomplishes the back and transports from the building.

Description

Superelevation steel column cow leg board promotes installation device
Technical Field
The utility model belongs to the technical field of building construction equipment technique and specifically relates to a superelevation steel column bracket board promotes installation device is related to.
Background
With the progress of industrial development, industrial plants are constructed more in recent years all over the country, and the shapes of the outer facades of the industrial plants are different day by day. At present, the integral frame of a multi-layer industrial factory building adopts a steel structure frame form, and the outer wall adopts an ALC (autoclaved lightweight concrete) slat wall. For ALC slat wall construction, generally, steel beams and steel columns are needed to be adopted to divide positions of doors, windows, shutters and the like on the outer sides. After the partition installation is finished, the installation work of ALC slat walls, doors, windows and shutters can be carried out. The steel beam is added on the steel structure frame, and the bracket plates are added on the steel column, the door, the window and the shutter.
In the current construction process, a method for mounting the cow leg plate on the outer vertical surface of the structure generally adopts a crank arm vehicle, a lifter and other machinery for mounting, and when the mounting height is not very high, the lifter is adopted. When the installation height exceeds 8m, a crank arm vehicle is adopted. According to the use requirement of the construction machine, at most 2 persons are allowed to construct on each machine simultaneously. When the bracket board was installed, 1 individual lifted definite position, and 1 individual carries out the welding machine, when bracket board quality was great, needs 2 people to lift definite position simultaneously. The accuracy of the position of the bracket plate is difficult to guarantee, and the bracket plate wastes time and labor.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an ultrahigh steel column bracket board promotes installation device, safe when having realized ultrahigh steel column bracket board construction, reliable, saved the manpower, bracket board promotes installation device simple, quick detachable, can have enough to meet the need the use, transport out from the building after convenient to use accomplishes.
In order to achieve the purpose, the utility model provides an ultrahigh steel column bracket plate lifting and mounting device, which comprises a truss base arranged on a structural plate, a symmetrical double-output-shaft electric chain block arranged on the truss base and a steel wire rope connected with two ends of the symmetrical double-output-shaft electric chain block;
two first fixed pulleys and two second fixed pulleys are arranged on the truss base, and the two second fixed pulleys are respectively arranged right below the two first fixed pulleys;
the free ends of the two steel wire ropes respectively pass around the first fixed pulley and the second fixed pulley on the same side, lifting hooks are arranged at the end parts of the two steel wire ropes, lifting platforms are connected to the two lifting hooks, and Niu Tuiban is placed on the lifting platforms;
the truss base is fixed on the structural plate through a fixing plate.
Preferably, the truss base comprises two vertical rods, a long transverse rod arranged at the tops of the two vertical rods, a short transverse rod arranged in the middle of the vertical rods and outer inclined rods arranged at the two ends of the short transverse rod and the long transverse rod, and the bottom ends of the outer inclined rods are fixed on the vertical rods.
Preferably, an inner inclined rod is arranged between the top ends of the two vertical rods and the two ends of the short cross rod.
Preferably, the first fixed pulley is fixed at the joint of the short transverse rod and the vertical rod.
Preferably, the second fixed pulley is fixed at the joint of the vertical rod and the outer inclined rod.
Preferably, the symmetrical double-output-shaft electric chain block is fixed between the two vertical rods.
Preferably, the lifting hook is connected with the lifting platform through a hook.
Preferably, the fixing plate is fixed to the long cross bar and the short cross bar by expansion bolts.
Therefore, the utility model adopts the above structure an ultrahigh steel column bracket board promotes installation device, safe when having realized ultrahigh steel column bracket board construction, reliable, saved the manpower, bracket board promotes installation device simple, quick detachable, can have enough to meet the need the use, transport out from the building after convenient to use accomplishes.
The technical solution of the present invention is further described in detail by the accompanying drawings and examples.
Drawings
Fig. 1 is a schematic structural view of an embodiment of a lifting and mounting device for a bracket plate with an ultrahigh steel column of the present invention;
fig. 2 is a side view of an embodiment of the lifting and mounting device for the bracket plate of the ultrahigh steel column of the present invention;
fig. 3 is a side view of an embodiment of the lifting and mounting device for the bracket plate with an ultrahigh steel column of the present invention;
fig. 4 is a bracket plate diagram of the embodiment of the utility model relates to a superelevation steel column bracket plate lifting installation device.
Detailed Description
The technical solution of the present invention is further explained by the accompanying drawings and examples.
Unless defined otherwise, technical or scientific terms used herein shall have the ordinary meaning as understood by those of ordinary skill in the art to which the invention belongs. The use of "first," "second," and similar terms in the description herein do not denote any order, quantity, or importance, but rather the terms are used to distinguish one element from another. The word "comprising" or "comprises", and the like, means that the element or item listed before the word covers the element or item listed after the word and its equivalents, but does not exclude other elements or items. The terms "connected" or "coupled" and the like are not restricted to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "upper", "lower", "left", "right", and the like are used merely to indicate relative positional relationships, and when the absolute position of the object being described is changed, the relative positional relationships may also be changed accordingly.
Examples
Fig. 1 is the utility model relates to a superelevation steel column bracket board promotes the structural schematic diagram of installation device embodiment, fig. 2 is the utility model relates to a superelevation steel column bracket board promotes the side view of installation device embodiment, fig. 3 is the utility model relates to a superelevation steel column bracket board promotes the side view of installation device embodiment, fig. 4 is the utility model relates to a superelevation steel column bracket board promotes the bracket board of installation device embodiment and plans. As shown in the figures, the utility model provides a lifting and mounting device for a bracket plate of an ultrahigh steel column, which comprises a truss base 1 arranged on a structural plate, symmetrical double-output-shaft electric chain blocks 2 arranged on the truss base 1 and steel wire ropes 3 connected with two ends of the symmetrical double-output-shaft electric chain blocks 2; the truss base 1 is provided with two first fixed pulleys 4 and two second fixed pulleys 5, and the two second fixed pulleys 5 are respectively arranged right below the two first fixed pulleys 4; the free ends of the two steel wire ropes 3 respectively bypass the first fixed pulley 4 and the second fixed pulley 5 on the same side, the end parts of the two steel wire ropes are provided with lifting hooks 6, the two lifting hooks 6 are connected with a lifting platform 7, a cow leg plate 8 is placed on the lifting platform 7, and the bottom of the lifting platform is made into a grid form in order to ensure that the cow leg plate can be stably placed on the lifting platform; the truss mount 1 is fixed to the structural slab by a fixing plate 9. The symmetrical double-output-shaft electric chain block drives the steel wire rope to ascend or descend, the steel wire rope drives the lifting platform to ascend or descend, the lifting platform drives the bracket plate to ascend or descend, ascending or descending of the bracket plate is achieved, after the device is used and completed, the expansion bolt is screwed off, the device can be moved to other positions to be fixedly installed and constructed again, or after the device is dismantled, the expansion bolt is conveyed to the outside of a site through the construction elevator, and installation and disassembly are facilitated.
The truss base 1 comprises two vertical rods 11, a long cross rod 12 arranged at the tops of the two vertical rods 11, a short cross rod 13 arranged at the middle position of the vertical rods 11 and outer oblique rods 14 arranged at the two end parts of the short cross rod 13 and the long cross rod 12, and the bottom ends of the two outer oblique rods 14 are fixed on the vertical rods 11. An inner oblique rod 15 is arranged between the top ends of the two vertical rods 11 and the two ends of the short transverse rod 13. The first fixed pulley 4 is fixed at the joint of the short cross rod 13 and the vertical rod 11. The second fixed pulley 5 is fixed at the joint of the vertical rod 11 and the outer inclined rod 14. The symmetrical double-output-shaft electric chain block 2 is fixed between the two vertical rods 11, and the power device is provided by the symmetrical double-output-shaft electric chain block, so that the vertical displacement of the two steel wire ropes is consistent.
The lifting hook 6 is connected with the lifting platform 7 through a hook. The fixing plate 9 is fixed to the long cross bar 12 and the short cross bar 13 by expansion bolts.
Therefore, the utility model adopts the above structure an ultrahigh steel column bracket board promotes installation device, safe when having realized ultrahigh steel column bracket board construction, reliable, saved the manpower, bracket board promotes installation device simple, quick detachable, can have enough to meet the need the use, transport out from the building after convenient to use accomplishes.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting the same, and although the present invention is described in detail with reference to the preferred embodiments, those skilled in the art should understand that: the technical solution of the present invention can still be modified or replaced with equivalents, and these modifications or replacements do not make the modified technical solution depart from the spirit and scope of the technical solution of the present invention.

Claims (8)

1. The utility model provides an ultrahigh steel column bracket board promotes installation device which characterized in that:
the device comprises a truss base arranged on a structural plate, symmetrical double-output-shaft electric chain blocks arranged on the truss base and steel wire ropes connected with two ends of the symmetrical double-output-shaft electric chain blocks;
two first fixed pulleys and two second fixed pulleys are arranged on the truss base, and the two second fixed pulleys are respectively arranged right below the two first fixed pulleys;
the free ends of the two steel wire ropes respectively pass around the first fixed pulley and the second fixed pulley on the same side, lifting hooks are arranged at the end parts of the two steel wire ropes, lifting platforms are connected to the two lifting hooks, and Niu Tuiban is placed on the lifting platforms;
the truss base is fixed on the structural plate through a fixing plate.
2. The ultra-high steel column corbel plate lifting installation device according to claim 1, wherein: the truss base comprises two vertical rods, a long transverse rod arranged at the top of each vertical rod, a short transverse rod arranged in the middle of each vertical rod, and outer inclined rods arranged at the two ends of each short transverse rod and the two ends of each long transverse rod, wherein the bottom ends of the outer inclined rods are fixed on the vertical rods.
3. The ultra-high steel column corbel plate lifting and mounting device as claimed in claim 2, wherein: and an inner oblique rod is arranged between the top ends of the two vertical rods and the two ends of the short cross rod.
4. The ultra-high steel column corbel plate lifting and mounting device as claimed in claim 3, wherein: and the first fixed pulley is fixed at the joint of the short cross rod and the vertical rod.
5. The ultra-high steel column corbel plate lifting installation device according to claim 4, wherein: the second fixed pulley is fixed at the joint of the vertical rod and the outer inclined rod.
6. The ultra-high steel column corbel plate lifting installation device according to claim 5, wherein: and the symmetrical double-output-shaft electric chain block is fixed between the two vertical rods.
7. The ultra-high steel column corbel plate lifting and mounting device as claimed in claim 6, wherein: the lifting hook is connected with the lifting platform through a hook.
8. The ultra-high steel column corbel plate lifting and mounting device as claimed in claim 7, wherein: the fixing plates are fixed on the long cross rod and the short cross rod through expansion bolts.
CN202222424767.XU 2022-09-13 2022-09-13 Superelevation steel column cow leg board promotes installation device Active CN217921272U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222424767.XU CN217921272U (en) 2022-09-13 2022-09-13 Superelevation steel column cow leg board promotes installation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222424767.XU CN217921272U (en) 2022-09-13 2022-09-13 Superelevation steel column cow leg board promotes installation device

Publications (1)

Publication Number Publication Date
CN217921272U true CN217921272U (en) 2022-11-29

Family

ID=84173624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222424767.XU Active CN217921272U (en) 2022-09-13 2022-09-13 Superelevation steel column cow leg board promotes installation device

Country Status (1)

Country Link
CN (1) CN217921272U (en)

Similar Documents

Publication Publication Date Title
CN108532769B (en) Jacking construction method of assembled additional elevator shaft structure
CN107399656B (en) Outdoor elevator and construction method thereof
CN108625483B (en) Equipment for jacking construction of assembled additional elevator shaft structure
WO2013175156A1 (en) High rise building elevation concept
CN112663971A (en) Steel structure roof pre-assembly sliding installation device and installation method
CN217921272U (en) Superelevation steel column cow leg board promotes installation device
US2217115A (en) Method of building houses
CN108483190B (en) Intelligent aluminum alloy template material conveying device and operation method thereof
CN111997345B (en) Lifting scaffold hangs hoist system upside down
CN114541729A (en) Operation method for super high-rise building
CN209353740U (en) A kind of building constructing device
CN2128653Y (en) Multi-function mutual rise and fall framing scaffold
CN103359625A (en) Automatic construction equipment for building hoisting and platform elevating of new rural construction
CN218539085U (en) Precast concrete wallboard lifting device
CN115288451B (en) Self-lifting type vertical material conveying system and application method thereof
CN105178602A (en) Building construction system
CN110847616B (en) Method for mounting large-volume steel frame flue
US3435583A (en) Method of forming buildings
CN108518075A (en) A kind of modular architectural Lift-on/Lift-off System and its hanging method
CN217461450U (en) Electric formwork climbing frame
CN116181041B (en) Building machine of multilayer quick construction
CN220845069U (en) Dedicated balance gallows of prefabricated component
CN204876576U (en) Building construction system
CN215160470U (en) Vertical transportation cantilever crane for curtain wall plate
CN113216650B (en) Integral lifting type automatic building construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant