CN217870193U CN202222121502.2U CN202222121502U CN217870193U CN 217870193 U CN217870193 U CN 217870193U CN 202222121502 U CN202222121502 U CN 202222121502U CN 217870193 U CN217870193 U CN 217870193U
Authority
CN
China
Prior art keywords
reserved
guardrail
foundation
flange
base layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222121502.2U
Other languages
Chinese (zh)
Inventor
周逸文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Kejia Design Group Co.,Ltd.
Original Assignee
Jiangsu Kejia Engineering Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Kejia Engineering Design Co ltd filed Critical Jiangsu Kejia Engineering Design Co ltd
Priority to CN202222121502.2U priority Critical patent/CN217870193U/en
Application granted granted Critical
Publication of CN217870193U publication Critical patent/CN217870193U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a central anti-collision guardrail structure, which comprises a guardrail and a foundation, wherein the guardrail and the foundation are internally provided with reinforcing steel bars, and the guardrail and the foundation are poured into a whole through concrete; the guardrail includes the same two parts of structure, sets up the both ends of basis still include: the reserved structure is arranged between the two parts of the guardrail; the reserved structure comprises a reserved cable pipeline, a flange steel bar, a reserved flange and a concrete package; the reserved flange is arranged on the upper surface of the foundation and used for mounting a street lamp rod piece; the reserved flange is provided with flange steel bars, and the lower parts of the flange steel bars are inserted into and fixed in the foundation; concrete encapsulation is arranged on the reserved flange; the upper end of the reserved cable pipeline extends out of the reserved flange, and the lower end of the reserved cable pipeline extends into the foundation and extends outwards. The utility model discloses the influence of the construction that can avoid all the other facilities simultaneously to the guardrail quality.

Description

Central anti-collision guardrail structure
Technical Field
The utility model relates to a central authorities 'anticollision barrier structure belongs to highway central authorities' anticollision barrier field.
Background
Along with the increasing importance of traffic safety in recent years, the requirements on traffic safety facilities in the regulations are also higher, and according to the requirements in the existing regulations, the requirements on the arrangement mode of the guardrail are improved besides the specific size of the central anti-collision guardrail is specified. When the guardrail is independently constructed, the related requirements in specifications can be basically met, but part of facilities cannot be synchronously constructed with the guardrail, excavation construction needs to be carried out after the guardrail construction is finished, and the quality of the guardrail is easily influenced.
Disclosure of Invention
To the not enough of existence among the prior art, the embodiment of the utility model provides a central authorities' anticollision barrier structure under the condition that can satisfy the requirement of using, can avoid the influence of the construction of all the other facilities to the guardrail quality simultaneously.
In order to realize the technical purpose, the embodiment of the utility model provides an adopt technical scheme is:
a central anti-collision guardrail structure comprises a guardrail and a foundation, wherein reinforcing steel bars are arranged inside the guardrail and the foundation, and the guardrail and the foundation are poured into a whole through concrete; the guardrail includes the same two parts of structure, sets up the both ends of basis still include:
the reserved structure is arranged between the two parts of the guardrail; the reserved structure comprises a reserved cable pipeline, a flange steel bar, a reserved flange and a concrete envelope; the reserved flange is arranged on the upper surface of the foundation and used for mounting a street lamp rod piece; the reserved flange is provided with a flange steel bar, and the lower part of the flange steel bar is inserted into and fixed in the foundation; the reserved flange is provided with a concrete envelope; the upper end of the reserved cable pipeline extends out of the reserved flange, and the lower end of the reserved cable pipeline extends into the foundation and extends outwards.
The road structure comprises a subbase layer, a lower base layer, an upper base layer and an asphalt surface layer which are sequentially arranged from bottom to top; the foundation is arranged above the lower base layer, and the side part of the foundation is surrounded by the upper base layer and the asphalt surface layer.
Furthermore, the bottom of the guardrail is provided with a drain hole, and the drain hole is used for discharging accumulated water in the guardrail outwards.
Furthermore, a stiffening rib for supporting the street lamp rod piece is arranged on the reserved flange.
Furthermore, greening soil is filled between the two parts of the guardrail.
The embodiment of the utility model provides a beneficial effect that technical scheme brought is:
1) Avoid the influence of secondary excavation and excavation when other facilities are implemented to guardrail quality.
2) The construction process is simple, and the whole size and elevation of the guardrail are convenient to control.
Drawings
Fig. 1 is a schematic structural diagram in an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
A central anti-collision guardrail structure comprises a guardrail 1 and a foundation 2, wherein reinforcing steel bars 4 are arranged inside the guardrail 1 and the foundation 2, and the guardrail 1 and the foundation 2 are integrally cast through concrete; the guardrail 1 comprises two parts with the same structure, and is arranged at two ends of the foundation 2.
In order to solve the problem that the quality of the guardrail is easily influenced, part of facilities cannot be constructed synchronously with the guardrail, excavation construction needs to be carried out after the construction of the guardrail is finished. The utility model discloses still including setting up the reservation structure, the reservation structure sets up between the two parts of guardrail 1.
The reserved structure comprises a reserved cable pipeline 21, a flange steel bar 22, a reserved flange 23 and a concrete envelope 25; the reserved flange 23 is arranged on the upper surface of the foundation 2 and used for mounting a street lamp rod piece 24 or a sign rod piece; the reserved flange 23 is provided with flange steel bars 22, and the lower parts of the flange steel bars 22 are inserted into and fixed in the foundation 2; a concrete envelope 25 is arranged on the reserved flange 23; the upper end of the reserved cable duct 21 extends out of the reserved flange 23, and the lower end of the reserved cable duct 21 extends into the foundation 2 and extends outwards.
In the field of the existing highway central anti-collision guardrail, the guardrail 1 and the foundation 2 are placed by re-excavating the positions after a road is paved, and further the top standard heights of the guardrails are inconsistent. In order to solve the problems, the utility model also comprises a road structure 3, wherein the road structure 3 comprises a subbase layer 34, a lower base layer 33, an upper base layer 32 and an asphalt surface layer 31 which are arranged from bottom to top in sequence; the foundation 2 is placed over the lower base layer 33 with the sides of the foundation 2 being surrounded by the upper base layer 32 and the asphalt overlay 31.
In a specific embodiment, a drainage hole 13 is formed in the bottom of the guardrail 1, and the drainage hole 13 is used for draining accumulated water in the guardrail 1 outwards.
In one embodiment, the flanges 23 are provided with stiffening ribs 231 for supporting the street light pole members 24.
After the construction and maintenance of the road sub-base layer 34 and the lower base layer 33 are completed, the elevation of the road is basically stable, and the guard rails and the foundation are placed above the lower base layer 34, so that the top elevation of the guard rails can be ensured to be consistent, and the size of the guard rails can be controlled easily; then, reinforcing steel bars can be bound, a template can be supported, the guardrail and the foundation are integrally poured together, and the integrity of the guardrail can be ensured; finally, implementing the upper base course 32 and the asphalt surface course 31 of the road; the middle of the guardrail can be filled with greening soil, and the bottom of the guardrail 1 is provided with a reserved drain hole 13, so that accumulated water in rainwater can be conveniently discharged. According to the invention, firstly, the integral quality of the guardrail structure is easy to control, and secondly, the influence of the implementation of other facilities on the quality of the guardrail structure in the later period can be effectively avoided.
Finally, it should be noted that the above embodiments are only used for illustrating the technical solutions of the present invention and not for limiting, and although the present invention has been described in detail with reference to the examples, those skilled in the art should understand that the technical solutions of the present invention can be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should be covered by the scope of the claims of the present invention.

Claims (5)

1. A central anti-collision guardrail structure comprises a guardrail (1) and a foundation (2), wherein reinforcing steel bars (4) are arranged inside the guardrail (1) and the foundation (2), and the guardrail (1) and the foundation (2) are cast into a whole through concrete; guardrail (1) includes the same two parts of structure, sets up the both ends of basis (2), its characterized in that still includes:
the reserved structure is arranged between two parts of the guardrail (1); the reserved structure comprises a reserved cable pipeline (21), a flange steel bar (22), a reserved flange (23) and a concrete encapsulation (25); the reserved flange (23) is arranged on the upper surface of the foundation (2) and used for mounting a street lamp rod piece (24); the reserved flange (23) is provided with a flange steel bar (22), and the lower part of the flange steel bar (22) is inserted into and fixed in the foundation (2); a concrete envelope (25) is arranged on the reserved flange (23); the upper end of the reserved cable pipeline (21) extends out of the reserved flange (23), and the lower end of the reserved cable pipeline (21) extends into the foundation (2) and extends outwards.
2. A central crash barrier structure according to claim 1, further comprising a roadway structure (3), the roadway structure (3) comprising a sub-base layer (34), a lower base layer (33), an upper base layer (32) and an asphalt surface layer (31) arranged in this order from bottom to top; the foundation (2) is arranged above the lower base layer (33), and the side part of the foundation (2) is surrounded by the upper base layer (32) and the asphalt surface layer (31).
3. A central crash barrier structure according to claim 1, characterized in that the bottom of the guardrail (1) is provided with a drainage hole (13), and the drainage hole (13) is used for draining accumulated water in the guardrail (1) outwards.
4. A central crash barrier structure according to claim 1, characterized in that the flanges (23) are provided with stiffening ribs (231) for supporting the street light poles (24).
5. A central crash barrier structure according to claim 1, characterized in that greening soil is filled between the two parts of the barrier (1).
CN202222121502.2U 2022-08-12 2022-08-12 Central anti-collision guardrail structure Active CN217870193U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222121502.2U CN217870193U (en) 2022-08-12 2022-08-12 Central anti-collision guardrail structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222121502.2U CN217870193U (en) 2022-08-12 2022-08-12 Central anti-collision guardrail structure

Publications (1)

Publication Number Publication Date
CN217870193U true CN217870193U (en) 2022-11-22

Family

ID=84077378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222121502.2U Active CN217870193U (en) 2022-08-12 2022-08-12 Central anti-collision guardrail structure

Country Status (1)

Country Link
CN (1) CN217870193U (en)

Similar Documents

Publication Publication Date Title
CN208965337U (en) A kind of Anti-settling device of highway subgrade
CN202577157U (en) Simple support arch bridge straining beam construction support system
CN204125872U (en) A kind of highway barrier bracing means
CN217870193U (en) Central anti-collision guardrail structure
CN109339087A (en) A kind of foundation structure system of low-rise building
CN211848641U (en) Light roadbed structure of high-speed railway
CN111778800B (en) Highway subgrade reinforcing structure and method
CN208430396U (en) Pedestrian's runway structure that embankment road is added
CN210797313U (en) Device for reinforcing lower border stone of bridge anti-collision guardrail
CN212077584U (en) Green type bridge of steel construction equipment
CN111058386B (en) Viaduct construction method for overpass existing ground bridge
CN204509922U (en) Underpasses structure
CN209619831U (en) A kind of bridge with sunk type greening band structure
CN208717919U (en) A kind of road based on contrary sequence method changes bridge section foundation pit supporting construction
CN201924270U (en) Environmental-protection ecological assembled bridge
CN214695101U (en) Multi-functional city elevated bridge structure
CN201826260U (en) Bridge drag chute device
CN206736789U (en) Ready-package reusable edible railway protective fence
CN111395160A (en) Rapid construction method for bridge guardrail with flower bed and prefabricated external flower bed
CN111058338A (en) Light roadbed structure of high-speed railway
CN210658117U (en) Mounting structure of traffic signal lamp pole
CN217480042U (en) Prefabricated assembled guardrail of curve roadside
CN218175695U (en) Waveform guardrail foundation structure
CN219527732U (en) Multifunctional common ditch access hole component transformation module
CN215518200U (en) Soft basic highway section protective structure of highway subgrade

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 214000 21-14a, Jiefang North Road, Wuxi City, Jiangsu Province

Patentee after: Jiangsu Kejia Design Group Co.,Ltd.

Country or region after: China

Address before: 214000 21-14a, Jiefang North Road, Liangxi District, Wuxi City, Jiangsu Province

Patentee before: JIANGSU KEJIA ENGINEERING DESIGN Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address