CN217815400U - Pre-buried quick positioner of water and electricity engineering construction pipeline - Google Patents

Pre-buried quick positioner of water and electricity engineering construction pipeline Download PDF

Info

Publication number
CN217815400U
CN217815400U CN202220922186.6U CN202220922186U CN217815400U CN 217815400 U CN217815400 U CN 217815400U CN 202220922186 U CN202220922186 U CN 202220922186U CN 217815400 U CN217815400 U CN 217815400U
Authority
CN
China
Prior art keywords
buried
pipeline
arc
mounting plate
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220922186.6U
Other languages
Chinese (zh)
Inventor
刘光兴
曾辉
高娜
赵小梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Jierui Construction And Installation Engineering Co ltd
Original Assignee
Sichuan Jierui Construction And Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Jierui Construction And Installation Engineering Co ltd filed Critical Sichuan Jierui Construction And Installation Engineering Co ltd
Priority to CN202220922186.6U priority Critical patent/CN217815400U/en
Application granted granted Critical
Publication of CN217815400U publication Critical patent/CN217815400U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a pre-buried quick positioner of water and electricity engineering construction pipeline, it can promote the assembly efficiency of pre-buried formula pipeline, and this pre-buried quick positioner of pipeline includes from the supreme setting gradually down: the pipe mounting seat comprises a pre-buried base, a damping layer and a mounting plate, wherein positioning holes are formed in the pre-buried base, the damping layer and the mounting plate, positioning pins penetrate through the pre-buried base, the damping layer and the mounting plate to be fixed, longitudinal sliding grooves and transverse sliding grooves are arranged on the mounting plate in a vertically and horizontally staggered mode, threaded holes are formed in the bottoms of the longitudinal sliding grooves and the transverse sliding grooves, and the pipe mounting seat is assembled in the longitudinal sliding grooves or the transverse sliding grooves.

Description

Pre-buried quick positioner of water and electricity engineering construction pipeline
Technical Field
The utility model relates to a pipeline construction field particularly, relates to a pre-buried quick positioner of water and electricity engineering construction pipeline.
Background
In the pipeline construction process in the prior art, a digger is used for digging gullies firstly, then pipeline butt joint work is carried out, because the pipeline is heavy, a specific machine is required to be adopted for lifting to complete the butt joint work, and because the ground dug by the gullies is not smooth enough, the mechanical adjustment work is difficult to implement during butt joint, and the construction progress is delayed.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a pre-buried quick positioner of water and electricity engineering construction pipeline, its assembly efficiency that can promote pre-buried formula pipeline.
The embodiment of the utility model is realized like this:
the utility model provides a pre-buried quick positioner of water and electricity engineering construction pipeline, this pre-buried quick positioner of pipeline includes from supreme setting gradually down: pre-buried base, buffer layer and mounting panel are provided with the locating hole on pre-buried base, buffer layer and the mounting panel, and it is fixed that the locating pin passes pre-buried base, buffer layer and mounting panel, is provided with vertically and horizontally staggered's vertical spout and horizontal spout on the mounting panel, and the cell body bottom of vertical spout and horizontal spout is provided with the screw hole, and the pipeline installation seat assembly is in vertical spout or horizontal spout.
In a preferred embodiment of the present invention, the top view surface of the embedded base/mounting plate is zigzag.
In the preferred embodiment of the present invention, the positioning holes are distributed at four corners of the embedded base/mounting plate.
The utility model discloses a in the preferred embodiment, above-mentioned pipeline installation seat is including assembling slider, supporting shoe and reinforcing component, and the sectional shape of assembling slider and vertical spout and horizontal spout matches, and the supporting shoe is fixed to be set up at the top of assembling the slider, and reinforcing component connects the supporting shoe.
In a preferred embodiment of the present invention, the supporting block comprises: the cross section of the support body is a rectangle with an arc-shaped notch in the middle, and a liftable arc-shaped adjusting block is arranged at the bottom of the arc-shaped notch; a through groove is arranged at the bottom of the support body in a penetrating manner, an adjusting screw rod is assembled in the through groove, an adjusting handle is assembled at the part of the adjusting screw rod, which penetrates out of the support body, and an opposite adjusting wedge block is assembled on the adjusting screw rod in the through groove; the adjusting handle is rotated to adjust the wedge block to jack up the arc adjusting block.
The utility model discloses a preferred embodiment, the both sides of above-mentioned arc breach still are provided with arc piece and screw rod, and arc breach department is worn from the outside that supports the body to the screw rod, and the arc piece is connected to screw rod one end.
In a preferred embodiment of the present invention, the reinforcing member includes a U-shaped reinforcing ring, and the U-shaped reinforcing ring passes through the supporting body and is fastened and connected by a nut.
The embodiment of the utility model provides a beneficial effect is: the utility model provides a quick positioner of pipeline pre-buried is provided with pre-buried base, buffer layer and mounting panel, installs through the form of prefabricated plate, guarantees the levelness of pipeline installation, possesses the damping characteristic simultaneously, prevents later stage pipeline because the vibration produces the problem such as the pipe connection is not hard up; the pre-buried base, the shock absorption layer and the mounting plate are effectively integrated through positioning pins; be provided with vertically and horizontally staggered's vertical spout and horizontal spout on the mounting panel, the pipeline installation seat can carry out quick position revision when the installation, accomplishes the back in the position revision, adds set screw in the cell body bottom, can realize that the pipeline installation seat is fixed, again with the pipeline assembly on the pipeline installation seat, carry out at last again cover such as earth or concrete and can use.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are required to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
Fig. 1 is a schematic structural view of a fast positioning device according to an embodiment of the present invention;
fig. 2 is a schematic view of a mounting plate structure according to an embodiment of the present invention;
fig. 3 is a schematic structural view of a pipe installation seat according to an embodiment of the present invention;
an icon: 100-embedding a base; 200-a shock-absorbing layer; 300-mounting plate; 400-positioning pins; 310-longitudinal sliding chutes; 320-a transverse chute; 330-threaded hole; 331-set screws; 500-a pipe mount; 510-assembling a slide block; 520-a support block; 530-a reinforcement component; 521-a support body; 522-arc adjusting block; 523-adjusting screw rod; 524-adjusting the handle; 525-adjusting the wedge; 526-arc-shaped pieces; 527-screw; 531-U shaped reinforcing ring.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the accompanying drawings, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without making creative efforts belong to the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined or explained in subsequent figures.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate the position or positional relationship based on the position or positional relationship shown in the drawings, or the position or positional relationship which is usually placed when the product of the present invention is used, and are only for convenience of description and simplification of the description, but do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," "third," and the like are used solely to distinguish one from another, and are not to be construed as indicating or implying relative importance.
Furthermore, the terms "horizontal", "vertical", "overhang" and the like do not imply that the components are required to be absolutely horizontal or overhang, but may be slightly inclined. For example, "horizontal" merely means that the direction is more horizontal than "vertical" and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
First embodiment
Please refer to fig. 1-3, this embodiment provides a pre-buried quick positioner of water electrical engineering construction pipeline, and this pre-buried quick positioner of pipeline includes from supreme setting gradually down: the embedded base 100, the shock-absorbing layer 200 and the mounting plate 300 are arranged, positioning holes are formed in the embedded base 100, the shock-absorbing layer 200 and the mounting plate 300, and the positioning pin 400 penetrates through the embedded base 100, the shock-absorbing layer 200 and the mounting plate 300 to be fixed.
The embedded base 100 in the embodiment adopts a precast slab form, so that compared with concrete pouring in the prior art, the construction time is saved, and the overlooking surface of the embedded base 100/the mounting plate 300 is in a zigzag shape and is used for preventing the displacement of the precast slab after mounting; the shock-absorbing layer 200 is adopted between the embedded base 100 and the mounting plate 300, and the pipeline is usually installed below the road surface, so that the shock-absorbing layer is used for increasing the shock-absorbing characteristic of the engineering. The locating hole distributes on the four corners of pre-buried base 100/mounting panel 300, effectively prevents the displacement. The shock absorbing layer 200 includes a rubber pad, a shock absorbing rubber pad, and other flexible pads. The positioning pin 400 may be a circular or square positioning pin, and a circular positioning pin is used in this embodiment.
More specifically, the mounting plate 300 is provided with longitudinal sliding grooves 310 and transverse sliding grooves 320 which are criss-cross, threaded holes 330 are formed in the bottoms of the longitudinal sliding grooves 310 and the transverse sliding grooves 320, the pipeline mounting seat 500 is assembled in the longitudinal sliding grooves 310 or the transverse sliding grooves 320, during assembly, the pipeline mounting seat 500 is inserted from the longitudinal sliding grooves 310 or the transverse sliding grooves 320 on the side surface of the mounting plate 300, is installed in the sliding grooves and then is moved to a preset position, and after positioning is completed, the pipeline mounting seat is installed in the threaded holes 330 in the bottom by using positioning screws 331 to realize positioning and fixing.
Then, the pipeline installation base 500 is debugged, the pipeline installation base 500 comprises an assembly slider 510, a support block 520 and a reinforcing component 530, the assembly slider 510 is matched with the cross-sectional shapes of the longitudinal sliding groove 310 and the transverse sliding groove 320, so that the whole pipeline installation base 500 can slide on the installation plate 300, the support block 520 is fixedly arranged at the top of the assembly slider 510, in the embodiment, a fixed connection mode of clamping is selected, and the reinforcing component 530 is connected with the support block 520.
More specifically, the supporting block 520 includes: the cross section of the support body 521 is a rectangle with an arc-shaped gap in the middle, and the bottom of the arc-shaped gap is provided with a liftable arc-shaped adjusting block 522; a through groove is arranged at the bottom of the support body 521 in a penetrating manner, an adjusting screw 523 is assembled in the through groove, an adjusting handle 524 is assembled at the part of the adjusting screw 523, which penetrates out of the support body 521, and an opposite adjusting wedge 525 is assembled on the adjusting screw 523 in the through groove; when the adjusting handle 524 is rotated, the adjusting wedges 525 jack up the arc-shaped adjusting block 522, and when the pipe diameter is maximum, the arc-shaped adjusting block 522 is not adjusted. Meanwhile, arc-shaped pieces 526 and screw rods 527 are further arranged on two sides of the arc-shaped notch, the screw rods 527 penetrate through the arc-shaped notch from the outer side of the support body 521, one ends of the screw rods 527 are connected with the arc-shaped pieces 526, the arc-shaped pieces 526 are jacked up by rotating the screw rods 527, and the screw rods 527 and the arc-shaped pieces 526 are further connected with inclined telescopic cylinders, so that a pipeline with a small pipe diameter is reinforced; the reinforcing assembly 530 comprises a U-shaped reinforcing ring 531, the U-shaped reinforcing ring 531 penetrates through the support body 521 to be fastened and connected through nuts, the U-shaped reinforcing ring 531 is various in type, and different U-shaped reinforcing rings 531 can be selected according to different pipe diameters.
In conclusion, the pipeline embedded quick positioning device in the utility model is provided with the embedded base 100, the damping layer 200 and the mounting plate 300, and the installation is carried out in the form of the prefabricated plate, so that the levelness of the pipeline installation is ensured, and meanwhile, the device has the damping characteristic, and the problems of loose pipeline connection and the like caused by vibration of the pipeline in the later period are prevented; the pre-buried base 100, the shock absorption layer 200 and the mounting plate 300 are effectively integrated with the prefabricated plate through the positioning pins 400; the mounting plate 300 is provided with longitudinal sliding grooves 310 and transverse sliding grooves 320 which are criss-cross, the pipeline mounting seat 500 can be quickly revised in position during mounting, after the position revision is completed, the positioning screws are added to the bottom of the groove body, the pipeline mounting seat 500 can be fixed, then a pipeline is assembled on the pipeline mounting seat 500, and finally covering with soil or concrete and the like can be performed for use.
This description describes examples of embodiments of the invention, and is not intended to illustrate and describe all possible forms of the invention. It should be understood that the embodiments described in the specification may be embodied in many alternate forms. The figures are not necessarily to scale; some features may be exaggerated or minimized to show details of particular components. Specific structural and functional details disclosed are not to be interpreted as limiting, but merely as a representative basis for teaching one skilled in the art to variously employ the present invention. It will be appreciated by persons skilled in the art that a plurality of features illustrated and described with reference to any one of the figures may be combined with features illustrated in one or more other figures to form embodiments which are not explicitly illustrated or described. The described combination of features provides a representative embodiment for a typical application. However, various combinations and modifications of the features consistent with the teachings of the present invention may be used as desired for particular applications or implementations.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides a pre-buried quick positioner of water and electricity engineering construction pipeline, a serial communication port, the pre-buried quick positioner of pipeline includes from supreme setting gradually down: the shock absorption structure comprises a pre-buried base, a shock absorption layer and a mounting plate, wherein positioning holes are formed in the pre-buried base, the shock absorption layer and the mounting plate, positioning pins penetrate through the pre-buried base, the shock absorption layer and the mounting plate are fixed, longitudinal sliding grooves and transverse sliding grooves are arranged on the mounting plate in a vertically and horizontally staggered mode, threaded holes are formed in the bottom of each longitudinal sliding groove and the bottom of each transverse sliding groove, and a pipeline mounting seat is assembled in each longitudinal sliding groove or each transverse sliding groove.
2. The pre-buried quick positioner of hydroelectric engineering construction pipeline of claim 1, characterized in that, the plane of depression of pre-buried base/mounting panel is the zigzag.
3. The device for quickly positioning embedded pipelines in hydroelectric engineering construction according to claim 1, wherein the positioning holes are distributed at four corners of the embedded base/the mounting plate.
4. The pre-buried quick positioner of hydroelectric engineering construction pipeline of claim 1, characterized in that, the pipe erection seat includes assembly slider, supporting shoe and reinforcement subassembly, the assembly slider with the cross-sectional shape of longitudinal sliding groove and horizontal spout matches, the supporting shoe is fixed to be set up the top of assembly slider, the reinforcement subassembly is connected the supporting shoe.
5. A hydroelectric engineering construction pipeline embedded quick positioning device as claimed in claim 4, wherein the supporting shoe comprises: the cross section of the support body is a rectangle with an arc-shaped notch in the middle, and a liftable arc-shaped adjusting block is arranged at the bottom of the arc-shaped notch; a through groove is arranged at the bottom of the supporting body in a penetrating manner, an adjusting screw rod is assembled in the through groove, an adjusting handle is assembled at the part of the adjusting screw rod, which penetrates out of the supporting body, and a relative adjusting wedge block is assembled on the adjusting screw rod in the through groove; and the adjusting handle is rotated, and the adjusting wedge block jacks up the arc-shaped adjusting block.
6. The pre-buried quick positioner of hydroelectric engineering construction pipeline of claim 5, characterized in that, the both sides of arc breach still are provided with arc piece and screw rod, the screw rod is followed the outside of supporting the body is worn arc breach department, screw rod one end is connected the arc piece.
7. The pre-buried quick positioner of hydroelectric engineering construction pipeline of claim 5, characterized in that, the reinforcement subassembly includes U type reinforcement ring, U type reinforcement ring passes support body passes through nut fastening connection.
CN202220922186.6U 2022-04-20 2022-04-20 Pre-buried quick positioner of water and electricity engineering construction pipeline Active CN217815400U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220922186.6U CN217815400U (en) 2022-04-20 2022-04-20 Pre-buried quick positioner of water and electricity engineering construction pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220922186.6U CN217815400U (en) 2022-04-20 2022-04-20 Pre-buried quick positioner of water and electricity engineering construction pipeline

Publications (1)

Publication Number Publication Date
CN217815400U true CN217815400U (en) 2022-11-15

Family

ID=83982221

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220922186.6U Active CN217815400U (en) 2022-04-20 2022-04-20 Pre-buried quick positioner of water and electricity engineering construction pipeline

Country Status (1)

Country Link
CN (1) CN217815400U (en)

Similar Documents

Publication Publication Date Title
JP7059618B2 (en) Main landing gear installation method and anchor frame installation jig
JP2013112926A (en) Foundation structure for photovoltaic generation device, and construction method for the same
JP2017150248A (en) Foundation structure for solar panel
CN111945764A (en) Ground anchor press-in type well sinking method
JP5635048B2 (en) Basics for installing solar panels
CN217815400U (en) Pre-buried quick positioner of water and electricity engineering construction pipeline
KR102052591B1 (en) Geobelt support device, geobelt fix device and retaining wall construction method
JP2008308945A (en) Concrete foundation combined with tension pile, and construction method thereof
CN209923938U (en) Assembled supporting construction of small-size rectangle foundation ditch
KR101282333B1 (en) Cross-type supporting structure and method for super-structure of bridge
US20140224751A1 (en) Solar panel mounting stand
KR101146252B1 (en) Ankar for distriuting Tensile load
JP3179843U (en) Base support for field structure
KR102180213B1 (en) Concrete Formwork for Installation of Water and Sewer Pipes and Construction Method using the same
KR102146577B1 (en) Fixed structure of high strength support material with easy to install at the construction site and construction method thereof
CN111576920B (en) Reinforced foundation for building foundation and construction method thereof
CN113565119A (en) High-rise building steel-concrete foundation structure capable of reducing settlement and construction process
CN211693790U (en) Natural gas line strutting arrangement
KR101633729B1 (en) Structure of retaining wall
CN211228586U (en) Foundation structure of machine tool
CN217580582U (en) Building shock insulation support mounting structure
JP4313741B2 (en) Tombstone with seismic isolation device and tombstone with seismic isolation device
JP4154492B2 (en) Pile head connection structure of ready-made piles
KR102144108B1 (en) Retaining wall construction structure using prestressed concrete and method thereof
KR20210062825A (en) Foundation work method for installation of prop of solar power device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant