CN217783570U - Tail water pipe hoist device in tunnel - Google Patents

Tail water pipe hoist device in tunnel Download PDF

Info

Publication number
CN217783570U
CN217783570U CN202221140125.0U CN202221140125U CN217783570U CN 217783570 U CN217783570 U CN 217783570U CN 202221140125 U CN202221140125 U CN 202221140125U CN 217783570 U CN217783570 U CN 217783570U
Authority
CN
China
Prior art keywords
draft tube
hoist
tunnel
mount
buttress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221140125.0U
Other languages
Chinese (zh)
Inventor
何中伟
舒崚峰
朱波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202221140125.0U priority Critical patent/CN217783570U/en
Application granted granted Critical
Publication of CN217783570U publication Critical patent/CN217783570U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model provides a tail pipe hoist device in tunnel, includes hoist and mount frame, lifting hook, buttress and track, on hoist and mount were erect and are located the track, hoist and mount frame and track sliding connection, buttress were used for supporting the tail pipe temporarily, and the top of buttress is located to the lifting hook. Through hoisting frame and orbital setting, can make things convenient for the transfer transportation of draft tube in the tunnel, cooperation buttress and lifting hook can conveniently hoist and mount the transfer draft tube in the tunnel, and are convenient in the use. The utility model discloses can make things convenient for the hoist and mount of draft tube to shift, effectively shorten the time limit for a project of draft tube installation, simple structure, low in manufacturing cost does not need to maintain.

Description

Tail water pipe hoist device in tunnel
Technical Field
The utility model belongs to the technical field of the tunnel construction, especially, relate to a draft tube hoist device in tunnel.
Background
In the tunnel engineering work progress, installation draft tube is often inevitable, but because tunnel entry restriction problem, large-scale bridge crane can't transport the draft tube section accuracy to the mounted position, causes certain difficulty for the construction, consequently in the work progress, urgently needs a draft tube hoist device and method in simple efficient tunnel.
According to the analysis of the patents published in China at present, no device and method for hoisting the draft tube in the tunnel, which are simple in structure, convenient to operate and wide in application range, exist at present. Chinese utility model patent CN202022404370.5 discloses "draft tube hoist device in being applicable to railway tail water culvert", this scheme includes: the hand-operated hoist, the door frame, the walking frame and the traction mechanism hang the tail water pipe on the hand-operated hoist in the air, the walking frame is driven to walk by the traction mechanism, and after the hand-operated hoist is separated from the cargo compartment by a certain distance, the hand-operated hoist is loosened, the tail water pipe is placed on the ground, and unloading of the tail water pipe is realized. Although the device is simple in structure and convenient to operate, the applicability of the device is poor, the device is only suitable for a small draft tube, and when the device is used for transshipping a large draft tube section, the truss and the traction device are feared to be difficult to bear.
Chinese invention patent CN201810618523.0 discloses a draft tube installation method and a draft tube supporting framework, and the draft tube supporting framework has the following specific structure: the steel plate is fixed on the lower I-shaped steel, and the upper I-shaped steel is horizontally arranged on the steel plate; the invention reduces the adjustment time of the center and the elevation when the draft tube is installed, greatly shortens the construction period, improves the working efficiency and the installation progress of the draft tube, but has more complex structure and needs frequent maintenance.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the above-mentioned technical problem that exists among the prior art, provide a draft tube hoist device in tunnel, can make things convenient for the hoist and mount of draft tube to shift, effectively shorten the time limit for a project of draft tube installation, simple structure, low in manufacturing cost does not need to maintain.
In order to solve the technical problem, the utility model discloses a following technical scheme:
the utility model provides a draft tube hoist device in tunnel which characterized in that: including hoist and mount frame, lifting hook, buttress and track, hoist and mount are erect on the track, hoist and mount frame and track sliding connection, the buttress is used for temporarily supporting the draft tube, and the top of buttress is located to the lifting hook. Through hoisting frame and orbital setting, can make things convenient for the transfer transportation of draft tube in the tunnel, cooperation buttress and lifting hook can conveniently hoist and mount the draft tube that shifts in the tunnel, and it is convenient to use, can adjust the position of draft tube, effectively shortens the time limit for a project of draft tube installation, simple structure, low in manufacturing cost need not maintain.
Further, the hoisting frame comprises a frame body and a supporting plate, the supporting plate is arranged on the frame body, and the supporting plate is provided with a supporting groove. Through the setting in support groove, can make things convenient for the draft tube fixed in the backup pad, the draft tube is difficult for rocking in the transfer process, has guaranteed the stability of removal in-process, avoids the draft tube to fall the damage.
Further, the frame body is provided with a traction plate, and the traction plate is provided with a connecting hole. Through the setting of traction plate and connecting hole, can make things convenient for rope etc. to connect on the support body, make things convenient for the pulling removal of support body. The traction plate is arranged in front of and behind the frame body, so that the frame body can be conveniently pulled and moved in front and back.
Further, the support body is equipped with the mounting panel, and the mounting panel is equipped with the mounting groove, and in the mounting groove was located to the backup pad, backup pad and mounting panel bolted connection. Through the setting of mounting panel and mounting groove, can be convenient for the backup pad be connected with the support body, simultaneously can change not unidimensional backup pad according to the size of the draft tube of construction transportation, and it is more nimble convenient in the use, excellent in use effect.
Further, the frame body is provided with a reinforcing rod. The stiffener sets up in the inboard of support body, can improve the bulk strength of support body, improves bearing capacity, guarantees that the support body can transport the great draft tube of volume and weight.
Further, the mounting panel is equipped with rings, and rings set up the integral hoisting that can conveniently hoist and mount the frame and transport.
The utility model discloses owing to adopted above-mentioned technical scheme, following beneficial effect has:
the utility model discloses a hoist and mount frame and orbital cooperation can make things convenient for the removal transportation of draft tube in the tunnel, through the setting of lifting hook and buttress, can be convenient for support fixed draft tube temporarily. The utility model discloses can make things convenient for the hoist and mount of draft tube to shift, effectively shorten the time limit for a project of draft tube installation, simple structure, low in manufacturing cost does not need to maintain.
Drawings
The present invention will be further explained with reference to the accompanying drawings:
fig. 1 is a schematic structural view of a hoisting frame of the utility model;
fig. 2 is a schematic structural view before hoisting of the utility model;
FIG. 3 is a schematic structural view of the utility model in which the draft tube is hoisted to the hoisting frame;
fig. 4 is a schematic structural view of the middle lifting frame of the present invention moving to the upper side of the buttress;
FIG. 5 is a schematic structural view of the draft tube of the present invention being lifted by a hook;
fig. 6 is a schematic structural view of the middle draft tube of the present invention arranged on the buttress.
In the figure, 1-the hoisting frame; 2-a hook; 3-buttress; 4-orbit; 5-a frame body; 6-a support plate; 7-supporting the groove; 8-a traction plate; 9-connecting hole; 10-mounting a plate; 12-a reinforcing rod; 13-a hoisting ring; 14-a draft tube; 15-tunnel.
Detailed Description
As shown in fig. 1 to 6, do the utility model relates to a tail-water pipe hoist device in tunnel, including hoist and mount frame 1, lifting hook 2, buttress 3 and track 4, hoist and mount frame 1 is located on track 4, hoist and mount frame 1 and track 4 sliding connection, buttress 3 is used for supporting tail-water pipe 14 temporarily, and the top of buttress 3 is located to lifting hook 2. Through the setting of hoist and mount frame 1 and track 4, can make things convenient for the transportation of draft tube 14 in the tunnel, cooperation buttress 3 and lifting hook 2 can conveniently hoist and mount the draft tube 14 that shifts in the tunnel, and it is convenient in the use, can adjust the position of draft tube 14, effectively shorten the installation period of draft tube 14 in tunnel 15, simple structure, low in manufacturing cost, need not maintain.
Hoist and mount frame 1 includes support body 5 and backup pad 6, and on support body 5 was located to backup pad 6, backup pad 6 was equipped with support groove 7. Through the setting of supporting groove 7, can make things convenient for draft tube 14 fixed in backup pad 6, draft tube 14 is difficult for rocking in the transfer process, has guaranteed the stability of removal in-process, avoids draft tube 14 to fall to damage.
The frame body 5 is provided with a traction plate 8, and the traction plate 8 is provided with a connecting hole 9. Through the setting of traction plate 8 and connecting hole 9, can make things convenient for rope etc. to connect on support body 5, make things convenient for the pulling of support body 5 to remove. The traction plate 8 is arranged in the front and the back of the frame body 5, so that the frame body 5 can be conveniently pulled and moved in the front and back direction.
The support body 5 is equipped with mounting panel 10, and mounting panel 10 is equipped with the mounting groove, and during the mounting groove was located to backup pad 6, backup pad 6 and mounting panel 10 bolted connection. Through the setting of mounting panel 10 and mounting groove, can be convenient for backup pad 6 and support body 5 be connected, simultaneously can be according to the not unidimensional backup pad 6 of the size change of the draft tube 14 that the construction was transported, more nimble convenience in the use, excellent in use effect.
The frame body 5 is provided with a reinforcing rod 12. The reinforcing rod 12 is arranged on the inner side of the frame body 5, so that the overall strength of the frame body 5 can be improved, the bearing capacity is improved, and the frame body 5 can be guaranteed to convey the draft tube 14 with large volume and weight.
The mounting panel 10 is equipped with rings 13, and rings 13's setting can make things convenient for the integral hoisting of hoist and mount frame 1 to transport.
The utility model discloses a hoist and mount frame 1 and track 4's cooperation can make things convenient for the removal transportation of draft tube 14 in the tunnel, through the setting of lifting hook 2 and buttress 3, can be convenient for support fixed draft tube 14 temporarily. The utility model discloses can make things convenient for the hoist and mount of draft tube 14 to shift, effectively shorten the time limit for a project of draft tube 14 installation, simple structure, low in manufacturing cost does not need to maintain.
The above is only a specific embodiment of the present invention, but the technical features of the present invention are not limited thereto. Any simple changes, equivalent substitutions or modifications made on the basis of the present invention to solve the same technical problems and achieve the same technical effects are all covered by the protection scope of the present invention.

Claims (6)

1. The utility model provides a draft tube hoist device in tunnel which characterized in that: including hoist and mount frame, lifting hook, buttress and track, the hoist and mount is erect on the track, hoist and mount frame with track sliding connection, the buttress is used for supporting the draft tube temporarily, the lifting hook is located the top of buttress.
2. The draft tube hoist device in tunnel according to claim 1, characterized in that: the hoisting frame comprises a frame body and a supporting plate, the supporting plate is arranged on the frame body, and the supporting plate is provided with a supporting groove.
3. The draft tube hoist device in tunnel of claim 2, characterized in that: the frame body is provided with a traction plate, and the traction plate is provided with a connecting hole.
4. The draft tube hoist device in tunnel according to claim 2, characterized in that: the support body is equipped with the mounting panel, the mounting panel is equipped with the mounting groove, the backup pad is located in the mounting groove, the backup pad with mounting panel bolted connection.
5. The draft tube hoist device in tunnel according to claim 2, characterized in that: the frame body is provided with a reinforcing rod.
6. The draft tube hoist device in tunnel of claim 4, characterized in that: the mounting plate is provided with a hanging ring.
CN202221140125.0U 2022-05-11 2022-05-11 Tail water pipe hoist device in tunnel Active CN217783570U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221140125.0U CN217783570U (en) 2022-05-11 2022-05-11 Tail water pipe hoist device in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221140125.0U CN217783570U (en) 2022-05-11 2022-05-11 Tail water pipe hoist device in tunnel

Publications (1)

Publication Number Publication Date
CN217783570U true CN217783570U (en) 2022-11-11

Family

ID=83910764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221140125.0U Active CN217783570U (en) 2022-05-11 2022-05-11 Tail water pipe hoist device in tunnel

Country Status (1)

Country Link
CN (1) CN217783570U (en)

Similar Documents

Publication Publication Date Title
CN208010370U (en) A kind of novel tunnel tunneling boring arch installation trolley
CN104612061A (en) Suspended and open type novel hanging basket device and construction method thereof
CN109653105A (en) Box girder bridge cantilever construction main truss cradle system and its application method
CN216190453U (en) Lifting beam for 16-ton monorail crane
CN215252400U (en) Self-supporting synchronous hanger system for corrugated steel web construction
CN202625655U (en) Tower tube transporter
CN217783570U (en) Tail water pipe hoist device in tunnel
CN213710141U (en) Steel construction dome roofing laying device
CN206692230U (en) A kind of skyscraper row is hung
CN200971610Y (en) Guide lifting platform device for chimney
CN202416190U (en) Formwork for prefabricated box girder of rear poured flange slab
CN208501523U (en) It is a kind of novel for setting up the Bridge Erector for spelling wide beam
CN110758421B (en) Vehicle maintenance vehicle suitable for air rail transit system
CN201132941Y (en) Self floating lower carrying pole beam of moveable formwork
CN209652772U (en) Box girder bridge cantilever construction main truss cradle system
CN107988909B (en) Railway is just roof beam rapid transit erects and uses trailer
CN216072862U (en) Heavy jack translation device for narrow space operation
CN215591798U (en) Curtain wall plate traction transfer device for tower crane dismantling part
CN213950340U (en) Simple hoisting device for lifting lug-free ditch cover plate
CN205132926U (en) Special well word hoist of hydroelectric set tail water ell
CN210264747U (en) Bidirectional mold moving device for tunnel side wall steel template
CN207002133U (en) A kind of slip casting machine lifting mechanism of tunnel rock bolting jumbo
CN207726617U (en) A kind of novel narrow space crane
CN205346714U (en) Prefab hoisting trolley
CN205346673U (en) Prefab hoisting trolley