CN217515172U CN202221613465.0U CN202221613465U CN217515172U CN 217515172 U CN217515172 U CN 217515172U CN 202221613465 U CN202221613465 U CN 202221613465U CN 217515172 U CN217515172 U CN 217515172U
Authority
CN
China
Prior art keywords
pipeline
transfer device
inclined strut
bottom plate
cross beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221613465.0U
Other languages
Chinese (zh)
Inventor
龚露露
余鹏
袁俊
刘恩辉
刘豪
马骋慧
高攀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongyifeng Construction Group Co Ltd
Original Assignee
Zhongyifeng Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongyifeng Construction Group Co Ltd filed Critical Zhongyifeng Construction Group Co Ltd
Priority to CN202221613465.0U priority Critical patent/CN217515172U/en
Application granted granted Critical
Publication of CN217515172U publication Critical patent/CN217515172U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Handcart (AREA)

Abstract

The utility model relates to a novel pipeline transfer device, pipeline transfer device include pipeline hoist mechanism and pipeline transport mechanism, and pipeline transport mechanism establishes in pipeline hoist mechanism below, and pipeline hoist mechanism includes portal and draw gear, and the draw gear hoist and mount is on the portal for with the pipeline lifting, pipeline transport mechanism is including transporting dolly and pipeline standing groove, and the pipeline standing groove is established on transporting the dolly, and the pipeline standing groove is used for the joint through the pipeline of draw gear lifting. The utility model discloses an information pipeline transfer device, simple structure is reasonable, as the transportation instrument of pipeline at the construction site, does not receive the narrow and small restriction in place, utilizes balanced principle, and need not too much artifical supplementary, when guaranteeing construction safety, has saved the manpower, under the circumstances of raising the efficiency, the cost has been practiced thrift to the maximize, has solved traditional transportation mode inefficiency, and the problem that the potential safety hazard is big is applicable to the transportation demand of indoor outer all kinds of heavier pipelines.

Description

Novel pipeline transportation device
Technical Field
The utility model relates to a transfer apparatus technical field, concretely relates to novel pipeline is transported device.
Background
When building buildings such as factory building, house, need use a large amount of pipelines, like fire control pipeline, water supply pipe, gas supply line, sewage pipes etc. in the construction of building site, to the pipeline that weight is big, the pipe diameter is big, length is long, adopt hook machine and manual fit to transport the pipeline more, this kind of transportation mode is transported speed slowly, is restricted by the place, still needs many people to cooperate the transportation that just can accomplish the pipeline simultaneously, not only transports inconveniently, still is unfavorable for safety.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a novel pipeline transportation device solves the above-mentioned problem that present pipeline transportation mode exists.
Now for realizing the above-mentioned purpose, the utility model adopts the following technical scheme:
a novel pipeline transfer device comprises a pipeline lifting mechanism and a pipeline transfer mechanism, wherein the pipeline transfer mechanism is arranged below the pipeline lifting mechanism; the pipeline lifting mechanism comprises a gantry and a traction device, and the traction device is hoisted on the gantry and used for lifting the pipeline; the pipeline transfer mechanism comprises a transfer trolley and a pipeline placing groove, the pipeline placing groove is formed in the transfer trolley, and the pipeline placing groove is used for clamping the pipeline lifted by the traction device.
Furthermore, the portal frame comprises two bottom plates arranged at intervals, supporting tubes in the vertical direction are arranged on each bottom plate, a cross beam is erected at the upper ends of the two supporting tubes, a hanging ring is arranged at the lower end of the cross beam, and the traction device is installed on the hanging ring.
Furthermore, a lower inclined strut is arranged on the bottom plate, one end of the lower inclined strut is fixed on the bottom plate, the other end of the lower inclined strut is fixed on the supporting tube, and the inclined strut, the bottom plate and the supporting tube form a triangular structure; the supporting device is characterized in that an upper inclined strut is arranged on the cross beam, one end of the upper inclined strut is fixed on the cross beam, the other end of the upper inclined strut is fixed on the supporting tube, and the cross beam, the upper inclined strut and the supporting tube form a triangular structure.
Further, the bottom plate downside is equipped with the universal wheel, the universal wheel is equipped with two, sets up respectively the both ends of bottom plate.
Furthermore, the lower ends of the two lower inclined struts on the same side are provided with universal wheels.
Furthermore, the upper end of the cross beam is provided with a pull ring.
Further, the transfer trolley comprises a rotating shaft and wheels, the wheels are rotatably installed at two ends of the rotating shaft, and the pipeline placing grooves are formed in the rotating shaft.
Further, the pipeline placing groove comprises a groove body and an installation plate, wherein the installation plate is axially arranged on the rotating shaft, and the groove body is arranged on the installation plate and is perpendicular to the installation plate.
Furthermore, a handle is arranged on the mounting plate and arranged along the advancing direction of the transfer trolley.
The utility model has the advantages that:
the utility model discloses a novel pipeline transfer device, through setting up portal and draw gear, can remove the portal to pipeline department very conveniently, and with the pipeline lifting through draw gear, accept the pipeline of lifting through the transportation dolly that sets up in pipeline hoist mechanism below, be equipped with the pipeline standing groove on transporting the dolly, can be with the pipeline joint in the pipeline standing groove, play the positioning action to the pipeline, can carry out the pipeline fast through transporting the dolly, transport safely, thereby not receive the restriction of narrow and small in place, and need not too much manual work and assist, in the time of guaranteeing construction safety, the manpower has been saved, under the condition of raising the efficiency, the cost has been practiced thrift to the maximize, traditional transportation mode inefficiency has been solved, the big problem of potential safety hazard, be applicable to the transportation demand of indoor all kinds of indoor outer heavier pipelines.
Drawings
Fig. 1 is a schematic structural diagram of a usage scenario of the present invention in embodiment 1;
fig. 2 is a schematic structural view of a pipe lifting mechanism according to the present invention in embodiment 1;
fig. 3 is a schematic structural view of a pipeline transfer mechanism according to the present invention in example 1;
fig. 4 is a schematic structural view of the pipe lifting mechanism in embodiment 2.
Names corresponding to the marks in the figure:
1. the pipeline transportation device comprises a pipeline lifting mechanism 11, a portal frame 111, a bottom plate 112, a supporting pipe 113, a cross beam 114, a lifting ring 115, a lower inclined strut 116, an upper inclined strut 12, a traction device 13, a universal wheel 14, a pull ring 2, a pipeline transportation mechanism 21, a transportation trolley 211, a rotating shaft 212, wheels 22, a pipeline placing groove 221, a groove body 222, a mounting plate 23, a handle 3 and a pipeline.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art all belong to the protection scope of the present invention.
Embodiment 1 of the utility model:
the embodiment of the utility model provides an in novel pipeline transfer device is through pipeline hoist mechanism and pipeline transport mechanism's cooperation, and pipeline hoist mechanism lifts up the pipeline, and pipeline transport mechanism transports the pipeline to the destination to realize the quick transportation of pipeline.
Specifically, as shown in fig. 1, the novel pipeline transfer device comprises a pipeline lifting mechanism 1 and a pipeline transfer mechanism 2, wherein the pipeline transfer mechanism 2 is arranged below the pipeline lifting mechanism 1, the pipeline lifting mechanism 1 comprises a gantry 11 and a traction device 12, the traction device 12 is hoisted on the gantry 11 and can lift a pipeline 3, the pipeline transfer mechanism 2 comprises a transfer trolley 21 and a pipeline placing groove 22, the pipeline placing groove 22 is arranged on the transfer trolley 21, and the pipeline placing groove 22 is used for placing the pipeline 3.
During actual use, earlier remove portal 11 to the one end of the pipeline 3 that needs transported, through draw gear 12 with the lifting of pipeline 3, then will transport dolly 21 and push into pipeline 3 below for pipeline 3 card is in pipeline standing groove 22, and is fixed with pipeline 3, then falls pipeline 3 with draw gear 12 whereabouts, can transport pipeline 3 through transporting dolly 21.
In this embodiment, the traction device 12 is a chain block or an electric block, which can be selected according to the field situation of the construction site, and is not limited herein.
As shown in fig. 2, the gantry 11 includes two bottom plates 111 arranged at an interval, support pipes 112 are arranged on the two bottom plates 111, the support pipes 112 are arranged up and down, a cross beam 113 is erected at the upper ends of the two support pipes 112, a hanging ring 114 is arranged at the lower end of the cross beam 113, and the traction device 12 is mounted on the hanging ring 114.
Meanwhile, in order to improve the strength of the portal 11, in this embodiment, the bottom plate 111 is provided with an inclined strut, which is denoted as a lower inclined strut 115, one end of the lower inclined strut 115 is fixed on the bottom plate 111, and the other end of the lower inclined strut is fixed on the supporting tube 112, and the inclined strut, the bottom plate 111 and the supporting tube 112 form a triangular structure, so as to improve the strength of the portal 11.
In this embodiment, bottom plate 111 adopts the galvanized square pipe to make, and intensity is high, and rust preventative ability is good, and stay tube 112 adopts the galvanized pipe to make, and crossbeam 113 adopts the channel-section steel to make, all has very high intensity, can bear the weight of the heavier lifting work of pipeline 3.
For the convenience of moving the gantry 11 and saving manpower, in this embodiment, the universal wheels 13 are arranged on the lower side surface of the bottom plate 111, two universal wheels 13 are arranged on each bottom plate 111, the two universal wheels 13 are respectively arranged at two ends of the bottom plate 111, and by arranging the universal wheels 13, the maneuverability of the gantry 11 is improved, and the movement of the gantry at each place of a construction site is facilitated.
In this embodiment, the universal wheels 13 with the maximum load bearing capacity of 450KG are adopted, so that the lifting safety and reliability of the pipeline 3 are ensured.
As shown in fig. 3, the transfer cart 21 includes a rotating shaft 211 and wheels 212, the wheels 212 are rotatably mounted on both ends of the rotating shaft 211, and the pipe placement grooves 22 are provided on the rotating shaft 211. The transfer trolley 21 in this embodiment is a two-wheeled trolley, and is flexible and easy to move, the pipeline placement groove 22 includes a groove body 221 and a mounting plate 222, the mounting plate 222 is axially disposed on the rotating shaft 211, the groove body 221 is disposed on the mounting plate 222 and perpendicular to the mounting plate 222, so that the directions of the groove body 221 and the pipeline 3 are kept consistent.
In this embodiment, a handle 23 is further provided on the mounting plate 222 to facilitate the movement of the cart on the construction site by a worker.
The working principle is as follows:
when needing to transport pipeline 3, push away the 3 tip of pipeline to be transported with portal 11 earlier, then lift pipeline 3 through draw gear 12, pipeline 3 lifts to a take the altitude after, will transport dolly 21 and push pipeline 3 below for the cell body 221 of pipeline standing groove 22 corresponds with pipeline 3, then slowly falls pipeline 3, loads pipeline 3 on transport dolly 21, removes portal 11 at last, can transport the pipeline through transport dolly 21.
The utility model discloses a novel pipeline transfer device, simple structure is reasonable, as the transportation instrument of pipeline at the construction site, does not receive the narrow and small restriction in place, utilizes balanced principle, and need not too much artifical supplementary, when guaranteeing construction safety, has saved the manpower, under the circumstances of raising the efficiency, the cost has been practiced thrift to the maximize, has solved traditional transportation mode inefficiency, and the problem that the potential safety hazard is big is applicable to the transportation demand of indoor outer all kinds of heavier pipelines.
Embodiment 2 of the utility model:
different from embodiment 1, in this embodiment, as shown in fig. 4, the universal wheel 13 is disposed at the lower end of the lower inclined strut 115, and only two universal wheels 13 need to be disposed, two universal wheels 13 are disposed on the same side, and no universal wheel is disposed at the lower end of the bottom plate 111, in this embodiment, the universal wheel 13 is used for facilitating the movement of the gantry 11, when the gantry 11 is moved, the gantry 11 is turned on one side, the universal wheel 13 can be in contact with the ground, so that the gantry 11 can be easily pulled away, the movement of the gantry 11 is more convenient and faster, and meanwhile, the pull ring 14 is disposed at the upper end of the beam 113, so that the gantry 11 can be conveniently transferred manually or mechanically.

Claims (9)

1. The utility model provides a novel pipeline is transported device which characterized in that: the pipeline transfer mechanism is arranged below the pipeline lifting mechanism; the pipeline lifting mechanism comprises a gantry and a traction device, and the traction device is hoisted on the gantry and used for lifting the pipeline; the pipeline transfer mechanism comprises a transfer trolley and a pipeline placing groove, the pipeline placing groove is formed in the transfer trolley, and the pipeline placing groove is used for clamping the pipeline lifted by the traction device.
2. The novel pipe transfer device according to claim 1, wherein: the gantry comprises two bottom plates arranged at intervals, supporting pipes in the up-down direction are arranged on each bottom plate, a cross beam is erected at the upper ends of the two supporting pipes, a hanging ring is arranged at the lower end of the cross beam, and the traction device is installed on the hanging ring.
3. The novel pipe transfer device of claim 2, wherein: a lower inclined strut is arranged on the bottom plate, one end of the lower inclined strut is fixed on the bottom plate, the other end of the lower inclined strut is fixed on the supporting tube, and the inclined strut, the bottom plate and the supporting tube form a triangular structure; the supporting device is characterized in that an upper inclined strut is arranged on the cross beam, one end of the upper inclined strut is fixed on the cross beam, the other end of the upper inclined strut is fixed on the supporting tube, and the cross beam, the upper inclined strut and the supporting tube form a triangular structure.
4. The novel pipe transfer device of claim 3, wherein: the bottom plate downside is equipped with the universal wheel, the universal wheel is equipped with two, sets up respectively the both ends of bottom plate.
5. The novel pipe transfer device according to claim 3, wherein: the lower ends of the two lower inclined struts on the same side are provided with universal wheels.
6. The novel pipe transfer device of claim 5, wherein: and the upper end of the cross beam is provided with a pull ring.
7. The novel pipe transfer device of claim 1, wherein: the transfer trolley comprises a rotating shaft and wheels, the wheels are rotatably installed at two ends of the rotating shaft, and the pipeline containing grooves are formed in the rotating shaft.
8. The novel pipe transfer device of claim 7, wherein: the pipeline standing groove comprises a groove body and an installation plate, wherein the installation plate is axially arranged on the rotating shaft, the groove body is arranged on the installation plate, and the installation plate is perpendicular to the groove body.
9. The novel pipe transfer device of claim 8, wherein: be equipped with the handle on the mounting panel, the handle is followed the setting of transportation dolly direction of advance.
CN202221613465.0U 2022-06-24 2022-06-24 Novel pipeline transportation device Active CN217515172U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221613465.0U CN217515172U (en) 2022-06-24 2022-06-24 Novel pipeline transportation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221613465.0U CN217515172U (en) 2022-06-24 2022-06-24 Novel pipeline transportation device

Publications (1)

Publication Number Publication Date
CN217515172U true CN217515172U (en) 2022-09-30

Family

ID=83393516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221613465.0U Active CN217515172U (en) 2022-06-24 2022-06-24 Novel pipeline transportation device

Country Status (1)

Country Link
CN (1) CN217515172U (en)

Similar Documents

Publication Publication Date Title
CN201377184Y (en) Ultra-long roofing contour plate vertical lifting transporting device
CN217515172U (en) Novel pipeline transportation device
CN214834720U (en) Tool type unilateral formwork system
CN205077842U (en) Multi -use architecture support
CN107235422A (en) It is exclusively used in the crane device of lifting steel pipes and welding
CN206955487U (en) It is exclusively used in lifting steel pipes and the crane device of welding
CN103486330B (en) Either inside high-altitude pipeline mounting construction method
CN214573175U (en) A distributing device for town road engineering curb
CN211110825U (en) Automatic feeding machine for pipeline installation
CN213738242U (en) Horizontal installation utility tool for internal parts of large tower
CN208996055U (en) A kind of bracing members axle power application jack fixing device
CN112813777A (en) Material distribution device for municipal road engineering kerbstone and kerbstone construction method
CN110759248A (en) Auxiliary replacing device for main pump motor of hydraulic station
CN216918538U (en) I-shaped steel transportation equipment for construction site
CN206580174U (en) Soil transporter for pile foundation construction
CN217917949U (en) Pipeline transportation device
CN217535310U (en) Building indoor material lifting device
CN212503687U (en) Horizontal conveying device for large spiral steel pipes
CN113954722B (en) Transfer device for electric power pole tower frame
CN218859108U (en) Electric power construction cable transfer device
CN218661955U (en) Transfer device of automatic beveling machine for pipeline
CN211223420U (en) Spiral water-cooling wall installation moves fortune device
CN213892623U (en) Be used for prosthetic multitube trailer of pipe factory oil pipe
CN217126756U (en) Movable electric material hoister for indoor pipeline installation
CN220332756U (en) Stainless steel straight seam welding steel pipe transport bracket for structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant