CN217047854U - Preparation device of graphene metal laminated composite material - Google Patents

Preparation device of graphene metal laminated composite material Download PDF

Info

Publication number
CN217047854U
CN217047854U CN202220219711.8U CN202220219711U CN217047854U CN 217047854 U CN217047854 U CN 217047854U CN 202220219711 U CN202220219711 U CN 202220219711U CN 217047854 U CN217047854 U CN 217047854U
Authority
CN
China
Prior art keywords
cavity
sub
metal
hot
composite material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220219711.8U
Other languages
Chinese (zh)
Inventor
马金鑫
李昕
史浩飞
徐鑫
余杰
姜浩
段银武
黄德萍
邵丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Institute of Green and Intelligent Technology of CAS
Chongqing Graphene Technology Co Ltd
Original Assignee
Chongqing Institute of Green and Intelligent Technology of CAS
Chongqing Graphene Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Institute of Green and Intelligent Technology of CAS, Chongqing Graphene Technology Co Ltd filed Critical Chongqing Institute of Green and Intelligent Technology of CAS
Priority to CN202220219711.8U priority Critical patent/CN217047854U/en
Application granted granted Critical
Publication of CN217047854U publication Critical patent/CN217047854U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Carbon And Carbon Compounds (AREA)

Abstract

The utility model relates to a graphite alkene metal combined material production facility field discloses a preparation facilities of graphite alkene metal stromatolite combined material, including integration cavity, heating system and to ventilating in the integration cavity and supply the gas combustion gas circuit system in the integration cavity, be equipped with main cavity room, transfer mechanism and a plurality of sub-cavities that are used for placing metallic material in the integration cavity, sub-cavity room and main cavity room intercommunication, transfer mechanism are used for shifting metallic material to main cavity room by sub-cavity room. The utility model discloses in, different metal material is behind the indoor growth graphite alkene of sub-chamber of difference, and transfer mechanism shifts it by sub-chamber to directly carry out hot pressing sintering in the main cavity to obtain the graphite alkene metal stromatolite combined material who contains metal material more than two kinds, obtained the graphite alkene metal stromatolite combined material that has different conductibilities and materialization performance promptly, reduced operation flow, shortened production cycle, improved production efficiency.

Description

Preparation facilities of graphite alkene metal stromatolite combined material
Technical Field
The utility model relates to a graphite alkene metal composite production facility field, concretely relates to preparation facilities of graphite alkene metal stromatolite combined material.
Background
With the continuous development of the technical fields of electronics, conduction and the like, the requirement on the conduction performance of the conductor is gradually improved. Graphene is a material with high conductivity and high electron mobility, and its application in the technical fields of conduction, transmission and the like is highly expected. Heretofore, researchers have utilized CVD (Chemical Vapor Deposition) technology to grow graphene on the surface of copper powder, and then densified graphene-copper by hot-pressing sintering technology to obtain a composite material, but after detection, it was found that although the conductivity of the composite material is improved, the conductivity still does not meet the requirement, mainly because the graphene is distributed and dispersed in the composite material and does not have continuity of large size, so that the high conductivity and high electron mobility of the graphene cannot be fully embodied. Later, researchers grow graphene on the surface of a copper-based foil/plate by using a CVD (chemical vapor deposition) technology, and then prepare a composite material by using a hot-pressing sintering densification technology, so that the graphene on the obtained composite material has two-dimensional continuity, and the excellent conductivity of the graphene is fully shown, and the electric conductivity of the copper-based graphene composite material is close to or even higher than that of pure silver.
In the process of preparing the composite material by using the CVD technology to grow the graphene on the copper-based foil/plate and then using the hot-pressing sintering densification technology, the same metal material is generally selected as a base material for graphene growth, the obtained graphene single-metal composite material is obtained, and more than two (including two) metal materials are selected as the base material for graphene growth, so that the composite material containing more than two metals is obtained, and then a plurality of graphene metal composite materials with different electric conductivities and physical and chemical properties are obtained, so that the requirements of different application fields are met. However, the existing production equipment for graphene metal composite materials is usually used for producing graphene single metal composite materials, and if composite materials containing more than two metals are to be produced, more than two pieces of equipment are needed to be used for producing graphene single metal foils respectively, then various graphene single metal foils are stacked, and finally the composite materials containing more than two metals are obtained through a hot-pressing sintering densification technology, so that the operation process is multiple, the production period is long, and the production efficiency is low. Therefore, the existing graphene metal composite material production equipment is not suitable for producing the composite material containing more than two metals. Therefore, it is necessary to design a production facility that can be applied to the above composite material containing two or more metals.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a preparation facilities of graphite alkene metal stromatolite combined material to when solving current graphite alkene metal composite production facility production and containing the combined material of more than two kinds of metals, problem that production efficiency is low.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides a preparation facilities of graphite alkene metal stromatolite combined material, includes integration cavity, heating system and ventilates and supply the gas combustion gas path system in the integration cavity to the integration cavity, be equipped with main cavity room, transfer mechanism and a plurality of sub-cavities that communicate with the main cavity room in the integration cavity, transfer mechanism is used for shifting metal substrate to the main cavity room from the sub-cavity room, is equipped with the hot briquetting mechanism that is used for hot pressing metal substrate in the main cavity room.
The principle and the advantages of the scheme are as follows:
1. in this scheme, the metal material of different materials is graphite alkene of growing in the sub-chamber of difference, and graphite alkene grows the back of accomplishing, and transfer mechanism shifts metal material to the main cavity by the sub-chamber and carries out hot pressing sintering in to obtain the graphite alkene metal stromatolite combined material who contains two kinds of above metal materials. In other words, the graphene metal laminated composite material with different conductivities and physical and chemical properties can be prepared by the method, so that the requirements of different application fields can be met.
2. In the scheme, the growth of graphene on the metal material and the subsequent hot-pressing sintering forming are carried out in the integrated cavity, so that the metal material can not contact with the outside air in the process of preparing the graphene metal laminated composite material, the adverse effect of the outside environment is avoided, and the yield, the stability and the uniformity of the product are improved. Moreover, compared with the processes of firstly cooling, taking out the graphene metal foil, stacking the graphene metal foil, transferring and finally heating, hot-pressing, sintering and forming in the prior art, the method reduces the operation flow, shortens the production period and improves the production efficiency.
Optionally, the hot-pressing forming mechanism includes a liftable hot-pressing platform, the transfer mechanism includes a first driving assembly for driving the first conveying assembly and a first conveying assembly for conveying the first conveying assembly, and the first conveying assembly is used for conveying the metal base material onto the hot-pressing platform.
In this scheme, hot pressing platform can go up and down in the main cavity room, and the conveying subassembly conveys metal substrate to hot pressing platform under the drive of drive assembly one on to realize metal substrate's transfer, be convenient for subsequent hot briquetting.
Optionally, the conveyor assembly comprises a conveyor belt and at least two rotatable rollers, the conveyor belt being wrapped around all of the rollers and the conveyor belt being tensioned by the rollers.
In this scheme, the structure of conveying subassembly has been refined, utilizes the rotation of conveyer belt, with the conveying of the metal substrate on the conveyer belt to hot pressing platform on.
Optionally, the first driving assembly includes a driving rod horizontally disposed, one end of the driving rod is connected to the conveyor belt, the other end of the driving rod extends out of the integrated chamber, and the driving rod is movably and hermetically connected to a side wall of the integrated chamber.
In this scheme, refined the structure of drive assembly one, utilized the actuating lever direct drive conveyer belt to rotate.
Optionally, the first driving assembly comprises a driving rod horizontally arranged, a gear is fixedly connected to the end of the roller wheel coaxially, a rack portion meshed with the gear is arranged on the driving rod, one end, far away from the rack portion, of the driving rod extends out of the integrated cavity, and the driving rod is movably connected with the side wall of the integrated cavity in a sealing mode.
In this scheme, refined the structure of drive assembly one, utilized rack portion on the actuating lever and the gear on the running roller to mesh mutually, realized the rotation of conveyer belt.
Optionally, the transfer mechanism further comprises a transfer main body and a second driving assembly for driving the transfer main body to move horizontally, and the conveying assembly is mounted on the transfer main body.
In this scheme, transfer mechanism has still included the transfer main part, and the conveying subassembly is installed in transferring the main part to when conveying subassembly goes wrong, take out conveying subassembly and maintain, or change new conveying subassembly. And the transfer main body can horizontally move under the driving of the second driving assembly, so that the lengths of the transfer main body and the transfer belt can be reduced, and the using amount of manufacturing materials of the transfer mechanism is reduced.
Optionally, a limiting component for limiting the displacement of the transfer main body is arranged on one side, close to the main chamber, in the sub-chamber.
In this scheme, utilize stop part, avoided the displacement of transfer main part to the hot pressing platform direction too big, ensure that the one end that the conveying subassembly is close to hot pressing platform links up with the one end that hot pressing platform is close to the subchamber mutually just to convey metal substrate smoothly.
Optionally, the bottom end of the transfer body is provided with a plurality of rollers.
In this scheme, the setting of gyro wheel has made things convenient for the horizontal migration who shifts the main part.
Optionally, the heating system includes a heating system one and a plurality of heating systems two corresponding to the sub-chambers one to one, the heating system one is used for heating the hot-pressing platform, and the heating system two is used for heating the sub-chambers.
In the scheme, the heating system is used for heating the hot-pressing platform, so that the temperature of the metal base material in the hot-pressing forming process is ensured. Utilize two pairs of subchambers of heating system to heat, ensure that the suitable metal substrate of temperature in each subchamber goes up growth graphite alkene.
Optionally, the gas circuit system includes air intake manifold, air intake manifold stretches into the integration intracavity and sets up, and air intake manifold runs through each subchamber, and air outlet has been seted up on air intake manifold is located the pipe wall in the subchamber.
In this scheme, the venthole has been seted up on the pipe wall that inlet manifold is located sub-chambeies to make process gas can get into each sub-chamber, and then ensure to grow graphite alkene smoothly on each sub-indoor metal substrate.
Optionally, one side of the hot pressing platform, which is close to the conveying assembly, is connected with a guide component for guiding the metal base material, and one side of the hot pressing platform, which is far away from the conveying assembly, is connected with a drop-preventing component for preventing the metal base material from dropping from the hot pressing platform.
In this scheme, when the conveying subassembly conveyed metal substrate, the metal substrate can be led to the guide part on the hot pressing platform for metal substrate shifts to the hot pressing platform smoothly on. And the anti-falling part on the hot pressing platform can prevent the metal base material on the hot pressing platform from falling off from the hot pressing platform.
Drawings
Fig. 1 is a front cross-sectional view of a device for manufacturing a graphene metal laminated composite according to a first embodiment of the present invention;
FIG. 2 is a schematic structural view of a neutron chamber and a transfer mechanism according to an embodiment of the invention;
fig. 3 is a front cross-sectional view of a manufacturing apparatus of a graphene metal laminated composite according to a second embodiment of the present invention;
FIG. 4 is a schematic structural view of a neutron chamber and a transfer mechanism according to a second embodiment of the invention;
FIG. 5 is a top view of a second embodiment of the transfer mechanism of the present invention;
fig. 6 is a top view of a transfer mechanism according to a third embodiment of the present invention.
Detailed Description
The following is further detailed by way of specific embodiments:
reference numerals in the drawings of the specification include: the integrated chamber 100, the main chamber 110, the sub-chambers 120, the limiting strips 121, the heat insulation partition plates 130, the pressure plate 210, the hot pressing platform 220, the guide part 221, the drop-proof part 222, the first driving part 230, the second driving part 240, the transfer mechanism 300, the transfer component 310, the conveyor belt 311, the rollers 312, the longitudinal rod 313, the gears 314, the driving rods 320, the transfer main body 330, the rollers 331, the push rods 340, the heating component 410, the air inlet manifold 510, the carbon source pipe 511, the auxiliary gas pipe 512, the protective gas pipe 513, the vacuum pipeline 520, the cooling cavity 610, the water inlet pipe 620, the water outlet pipe 630, the feed inlet 710, the discharge outlet 720, the sealing door 730 and the metal foil 800.
Example one
This embodiment is substantially as shown in fig. 1 and 2: a preparation device of a graphene metal laminated composite material comprises an integrated chamber 100, a heating system and a gas path system which is used for ventilating the integrated chamber 100 and exhausting gas in the integrated chamber 100. The integrated chamber 100 is provided with a main chamber 110, a transfer mechanism 300 and a plurality of sub-chambers 120 communicated with the main chamber 110, in this embodiment, the number of the sub-chambers 120 is twenty two, and it should be noted that, a person skilled in the art can design a suitable number of sub-chambers 120 in the integrated chamber 100 according to actual situations. The sub-chamber 120 in this embodiment is formed by a plurality of heat insulating partitions 130 separating the space on the left side inside the integrated chamber 100.
The main chamber 110 is provided with a hot-press forming mechanism for hot-pressing a metal substrate, the hot-press forming mechanism includes a pressing plate 210 and a liftable hot-press platform 220, the pressing plate 210 is located above the hot-press platform 220, a first driving member 230 for driving the pressing plate 210 to move vertically and a second driving member 240 for driving the hot-press platform 220 to lift are fixedly installed outside the integrated chamber 100 (the first driving member 230 and the second driving member 240 are fixedly installed on the rack through bolts, the rack is not shown in fig. 1), in this embodiment, the first driving member 230 and the second driving member 240 are hydraulic cylinders. A guide part 221 for guiding the metal base material is integrally formed at the left side of the hot pressing platform 220, a drop-preventing part 222 for preventing the metal base material from dropping from the hot pressing platform 220 is integrally formed at the right side of the hot pressing platform 220, and both the guide part 221 and the drop-preventing part 222 are plate-shaped objects.
The transferring mechanism 300 is used for transferring the metal substrate from the sub-chamber 120 to the main chamber 110, the transferring mechanism 300 includes a first conveying assembly 310 and a first driving assembly for driving the first conveying assembly 310, the first conveying assembly 310 is used for conveying the metal substrate onto the hot pressing platform 220, as shown in fig. 2, the first conveying assembly 310 includes a first conveying belt 311 and two horizontally arranged and rotatable rollers 312, the first conveying belt 311 surrounds all the rollers 312, the first conveying belt 311 is tensioned by the rollers 312, two ends of the rollers 312 are rotatably connected to the front side wall and the rear side wall of the integrated chamber 100, respectively, and a right end of the first conveying belt 311 can be connected to a top end of the guiding member 221. The first driving assembly comprises a driving rod 320 which is horizontally arranged, the right end of the driving rod 320 is fixedly connected with the conveyor belt 311, specifically, a longitudinal rod 313 is fixedly connected to the conveyor belt 311, the longitudinal rod 313 is parallel to the roller 312, the right end of the driving rod 320 is welded to the longitudinal rod 313, the left end of the driving rod 320 extends out of the integrated chamber 100, and the driving rod 320 is movably and hermetically connected with the left side wall of the integrated chamber 100.
The heating system comprises a heating system I and a heating system II, the heating system I is used for heating the hot-pressing platform 220 and the pressing plate 210, the number of the heating system II is the same as that of the sub-chambers 120, the heating system II corresponds to the sub-chambers 120 one by one, and the heating system II is used for heating the corresponding sub-chambers 120. Heating system is unified and heating system two all includes heating element 410, temperature sensor and controller, the temperature in the temperature sensor monitoring subchamber 120 of heating system two, the temperature of heating system's temperature sensor monitoring hot pressing platform 220 and clamp plate 210 to convert temperature signal into the signal of telecommunication and transmit for the controller, the controller is according to opening and close of received signal of telecommunication control heating element 410, thereby the temperature of control subchamber 120/hot pressing platform 220 and clamp plate 210. Since it is the prior art to detect signals by using the sensor and transmit the related signals to the controller, and the controller controls the actuator to perform actions according to the received signals, the details are not described herein. In this embodiment, the heating element 410 is a resistance wire heater. In this embodiment, the number of the heating elements 410 in the heating system one and the heating system two are two, and the two heating elements 410 in the heating system one are connected in series, and the two heating elements 410 in the heating system two are connected in series. In the heating system, one heating element 410 is embedded in the hot-pressing platform 220, and the other heating element 410 is embedded in the pressing plate 210; in the second heating system, two groups of heating assemblies 410 are provided, one heating assembly 410 is positioned above the conveyor belt 311, and the other heating assembly 410 is positioned between the two rollers 312 and is surrounded by the conveyor belt 311.
The air path system comprises an air inlet main pipe 510 and a vacuum pipeline 520, the air inlet main pipe 510 and the vacuum pipeline 520 are both communicated with the integrated chamber 100, the top end of the air inlet main pipe 510 is communicated with a carbon source pipe 511, an auxiliary gas pipe 512 and a protective gas pipe 513 through four-way joints, and valves and flow controllers are arranged on the carbon source pipe 511, the auxiliary gas pipe 512 and the protective gas pipe 513. The end of the vacuum line 520 away from the integrated chamber 100 is connected to a vacuum pump (not shown), and the vacuum line 520 is provided with a vacuum valve and an air pressure gauge. The bottom end of the air inlet manifold 510 extends into the integrated chamber 100, the air inlet manifold 510 penetrates through each sub-chamber 120, and the air outlet holes are formed in the pipe wall of the air inlet manifold 510 in each sub-chamber 120, so that gas (gaseous carbon source, auxiliary gas and protective gas) can be introduced into each sub-chamber 120. The communication of the vacuum line 520 with the main chamber 110 is at the lower right end of the main chamber 110.
A cooling cavity 610 is arranged in the side wall of the integrated cavity 100, the bottom end of the cooling cavity 610 is communicated with a water inlet pipe 620, and the top end of the cooling cavity 610 is communicated with a water outlet pipe 630. The left side wall of the integrated cavity 100 is provided with a feed inlet 710, the right side upper wall of the integrated cavity 100 is provided with a discharge outlet 720, the feed inlet 710 and the discharge outlet 720 are sealed by a sealing door 730, and the sealing door 730 is fixedly installed on the outer side wall of the integrated cavity 100 through a flange.
The specific implementation process for preparing the graphene metal laminated composite material by using the preparation device is as follows:
s1, placing the metal substrate in the sub-cavity: the feed inlet 710 on the left side wall of the integrated chamber 100 is opened, and 11 copper foils with the thickness of 25 μm are placed one by one on the conveyor belt 311 in the sub-chamber 120, so that a vacant sub-chamber 120 is left between two adjacent copper foils during the placement. Then, 10 silver foils with a thickness of 15 μm are placed one by one on the conveyor belt 311 in the vacant sub-chamber 120 between two adjacent copper foils, and finally the sealing door 730 is fixedly mounted on the left side wall of the integrated chamber 100 again by using a flange, and the feed opening 710 is sealed again.
S2, adjusting parameters in the integrated cavity: the air in the integrated chamber 100 is evacuated through the vacuum line 520, so that the air pressure in the integrated chamber 100 reaches 100Pa (the air pressure in the integrated chamber 100 is obtained through a pressure gauge on the vacuum line 520), and then the vacuum valve is closed, and the vacuum pump is closed to stop working. Then, a valve of the shielding gas pipe 513 is opened, and a shielding gas (in this embodiment, the shielding gas is nitrogen, in other embodiments, the shielding gas may be other inert gas such as argon, etc.) enters the integrated chamber 100, and in this step, the flow rate of the shielding gas may be controlled by a flow controller of the shielding gas pipe 513. After the internal pressure of the integration chamber 100 is restored to the normal pressure, the vacuum valve is opened so that the excessive shielding gas is discharged through the vacuum line 520, thereby making the inside of the integration chamber 100 in a micro-positive pressure state. Then, a second heating system corresponding to the sub-chamber 120 with the metal foil 800 placed inside is started, and the two pairs of corresponding sub-chambers 120 are heated by the second heating system, so that the temperature in the sub-chamber 120 with the copper foil is raised to 1020 ℃, and the temperature in the sub-chamber 120 with the silver foil is raised to 890 ℃.
S3, graphene growth: the valves of the carbon source pipe 511 and the auxiliary gas pipe 512 are opened, and a gaseous carbon source is introduced into the integrated chamber 100 through the carbon source pipe 511, in this embodiment, the gaseous carbon source is methane, and meanwhile, an auxiliary gas is introduced into the integrated chamber 100 through the auxiliary gas pipe 512, and the auxiliary gas is hydrogen. During this period, the protective gas is continuously introduced into the integrated chamber 100, and graphene grows on the surfaces of the copper foil and the silver foil. The time for introducing the gaseous carbon source and the hydrogen is 10 min. In this process, gaseous carbon source (methane), auxiliary gas (hydrogen) and protective gas (nitrogen) enter each sub-chamber 120 through the gas outlet on the gas inlet manifold 510, and each sub-chamber 120 can be filled with all the above-mentioned gases, so that graphene can grow smoothly.
S4, hot press forming: after the gaseous carbon source (methane) and the auxiliary gas (hydrogen) are introduced for 10min, the valves on the carbon source pipe 511 and the auxiliary gas pipe 512 are closed, and the protective gas is continuously introduced into the integrated chamber 100 so as to flush away the residual methane and hydrogen. Meanwhile, the second heating system is turned off and the first heating system is turned on, the heating and the heat preservation of the sub-chamber 120 are stopped, and the hot pressing platform 220 and the pressing plate 210 are heated and heat preserved (because part of heat is dissipated into the main chamber 110 during the operation of the second heating system, the hot pressing platform 220 and the pressing plate 210 have a certain temperature, and the time required for the temperature of the hot pressing platform 220 and the pressing plate 210 to rise to the preset temperature is short). The metal foil 800 (copper foil and silver foil) grown with graphene in the sub-chamber 120 is transferred into the main chamber 110 by using the transfer mechanism 300, specifically, the driving rod 320 is pushed rightward, so that the conveyor belt 311 is driven by a rightward driving force to rotate clockwise, thereby driving the metal foil 800 (copper foil or silver foil) on the conveyor belt 311 to move rightward, the metal foil 800 moves to the right end of the conveyor belt 311, and then the right end of the metal foil 800 slides onto the hot-pressing platform 220 along the guide part 221, so that the metal foil 800 is transferred once. Then, the second driving member 240 drives the hot pressing platform 220 to rise by a distance which is the same as the distance between the same points on the two vertically adjacent conveyor belts 311, so that the top end of the guiding component 221 on the hot pressing platform 220 can be connected with the right end of the previous conveyor belt 311. The above operation is repeated, so that the metal foil 800 in each sub-chamber 120 is transferred onto the hot pressing platform 220 by the transfer mechanism 300, and the stacking of the metal foil 800 is completed. Moreover, since the copper foil and the silver foil are sequentially disposed from top to bottom in the sub-chamber 120 according to the sequence of copper foil-silver foil- … … copper foil-silver foil-copper foil, after the metal foil 800 is transferred onto the hot-pressing platform 220, the two metal foils 800 (copper foil and silver foil) are vertically stacked in an alternating manner by twenty-one layers. After all the metal foils 800 are transferred to the hot-pressing platform 220, the first driving part 230 drives the pressing plate 210 to move downwards, the pressing plate 210 applies pressure to the metal foils 800 stacked on the hot-pressing platform 220, in the step, the pressure of hot-pressing forming is 30MPa, and the pressure maintaining time of the hot-pressing forming is 30min, so that the copper foil and the silver foil in the main cavity 110 are subjected to hot-pressing sintering, and the graphene-copper-silver laminated composite material is obtained.
S5, cooling and taking materials: after hot press molding, the first driving part 230 drives the pressing plate 210 to move upwards for resetting, the second driving part 240 drives the hot pressing platform 220 to move downwards for resetting, meanwhile, cooling water is continuously input into the cooling cavity 610 in the side wall of the integrated cavity 100 through the water inlet pipe 620, and the cooling water flows out from the water outlet pipe 630 after absorbing heat, so that the integrated cavity 100 is cooled. After the temperature in the integrated chamber 100 is reduced to room temperature, the sealing door 730 at the discharge port 720 is opened, the graphene-copper-silver laminated composite material is taken out through the discharge port 720, and finally, the valve on the protective gas pipe 513 is closed to stop the introduction of the protective gas.
In this embodiment, the graphene growth step and the hot press molding step are integrated in the integrated chamber 100, so that the metal foil does not contact with the outside air in the process of preparing the composite material, thereby avoiding adverse effects of the outside environment and improving the yield, stability and uniformity of the product. In addition, the embodiment also avoids the processes of cooling and taking out firstly, stacking and transferring later and heating and hot press molding in the prior art, thereby not only reducing the operation flow, shortening the production period, improving the production efficiency, but also effectively reducing the energy consumption.
Example two
The present embodiment is different from the first embodiment only in that: as shown in fig. 3, 4 and 5, in this embodiment, the transfer mechanism 300 further includes a horizontally movable transfer main body 330 and a second driving component for driving the transfer main body 330, wherein the rollers 312 of the conveying component 310 are rotatably mounted on the transfer main body 330, and a plurality of rollers 331 are disposed at the bottom end of the transfer main body 330, so that the transfer main body 330 can easily move horizontally under the action of an external force. The heating element 410 of the second heating system is fixedly installed on the transfer main body 330, and the heating element 410 of the second heating system is located below the conveyor belt 311, so that the heating element 410 of the second heating system heats the metal foil 800 on the conveyor belt 311 in a close distance. The second driving assembly comprises a horizontally arranged push rod 340, the right end of the push rod 340 is welded with the transfer main body 330, the left end of the push rod 340 extends out of the integrated chamber 100, and the push rod 340 is movably and hermetically connected with the left side wall of the integrated chamber 100.
The limiting component for limiting the displacement of the transfer main body 330 is integrally formed on the bottom wall of the right side in the sub-chamber 120, in this embodiment, the limiting component is a limiting strip 121, and when the limiting strip 121 abuts against the roller 331 on the rightmost side of the transfer main body 330, the right end of the conveyor belt 311 is connected with the top end of the guide component 221.
Compared with the first embodiment, the specific implementation process of the preparation device in the present embodiment for preparing the graphene metal laminated composite material is different only in that:
in the process of transferring the metal foil 800 (copper foil and silver foil) grown with graphene inside the sub-chamber 120 into the main chamber 110 using the transfer mechanism 300 in "S4, the push rod 340 and the driving rod 320 are pushed rightward, so that the transfer body 330 moves rightward, when the rightmost roller 331 on the transfer main body 330 abuts against the position-limiting strip 121 in the sub-chamber 120, the right end of the transfer belt 311 of the transfer body 330 is engaged with the top end of the guide member 221 on the left side of the hot press stage 220, then, the driving rod 320 is pushed to the right, so that the conveyor belt 311 is driven by the driving force to the right to rotate clockwise, thereby driving the metal foil 800 (copper foil or silver foil) on the conveyor belt 311 to move to the right, the metal foil 800 moves to the right end of the conveyor belt 311, then, the right end of the metal foil 800 slides along the guide member 221 onto the hot pressing stage 220, and thus, the transfer of the metal foil 800 is completed once.
EXAMPLE III
The present embodiment is different from the second embodiment only in that: as shown in fig. 6, the first driving assembly includes a driving rod 320 horizontally disposed, a gear 314 is coaxially and fixedly connected to an end of the roller 312, a rack portion engaged with the gear 314 is disposed on the driving rod 320, a left end of the driving rod 320 extends out of the integrated chamber 100, and the driving rod 320 is movably and hermetically connected to a side wall of the integrated chamber 100.
Compared with the embodiment, the specific implementation process of the preparation device in the embodiment for preparing the graphene metal laminated composite material only differs from the embodiment in that:
in the process of "S4, hot press molding", the transfer mechanism 300 is used to transfer the metal foil 800 (copper foil and silver foil) growing with graphene in the sub-chamber 120 into the main chamber 110, the driving rod 320 is continuously pushed rightwards, the rack portion on the driving rod 320 is engaged with the gear 314 on the roller 312, so as to drive the roller 312 to rotate clockwise, further drive the conveyor belt 311 to rotate clockwise, and convey the metal foil 800 on the conveyor belt 311 to the hot press platform 220.
The above description is only an example of the present invention, and the common general knowledge of the known technical solutions and/or characteristics is not described herein. It should be noted that, for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. The scope of the claims of the present application shall be defined by the claims, and the description of the embodiments and the like in the specification shall be used to explain the contents of the claims.

Claims (10)

1. A preparation facilities of graphite alkene metal stromatolite combined material which characterized in that: including integration cavity, heating system and to ventilating in the integration cavity and supply the gas off-gas road system in the integration cavity, be equipped with main cavity room, transfer mechanism and a plurality of sub-cavities that communicate with main cavity room in the integration cavity, transfer mechanism is used for shifting metal substrate to main cavity room from sub-cavity room, is equipped with the hot briquetting mechanism that is used for hot pressing metal substrate in the main cavity room.
2. The apparatus for preparing a graphene metal laminated composite material according to claim 1, wherein: the hot-pressing forming mechanism comprises a liftable hot-pressing platform, the transfer mechanism comprises a conveying assembly and a first driving assembly for driving the conveying assembly, and the conveying assembly is used for conveying the metal base material to the hot-pressing platform.
3. The apparatus for preparing a graphene metal laminated composite material according to claim 2, wherein: the conveying assembly comprises a conveying belt and at least two rotatable rollers, the conveying belt is wrapped around all the rollers, and the conveying belt is tensioned by the rollers.
4. The apparatus for preparing a graphene metal laminated composite material according to claim 3, wherein: the first driving assembly comprises a driving rod which is horizontally arranged, one end of the driving rod is connected with the conveying belt, the other end of the driving rod extends out of the integrated cavity, and the driving rod is movably and hermetically connected with the side wall of the integrated cavity.
5. The apparatus for preparing a graphene metal laminated composite material according to claim 3, wherein: the first driving assembly comprises a driving rod arranged horizontally, a gear is fixedly connected with the end of the roller wheel in a coaxial mode, a rack portion meshed with the gear is arranged on the driving rod, one end, far away from the rack portion, of the driving rod extends out of an integrated cavity, and the driving rod is movably connected with the side wall of the integrated cavity in a sealing mode.
6. The apparatus for preparing a graphene metal laminated composite material according to claim 2, wherein: the transfer mechanism further comprises a transfer main body and a second driving assembly for driving the transfer main body to horizontally move, and the conveying assembly is installed on the transfer main body.
7. The apparatus for preparing a graphene metal laminated composite material according to claim 6, wherein: and a limiting component for limiting the displacement of the transfer main body is arranged on one side, close to the main chamber, in the sub-chamber.
8. The apparatus for preparing a graphene metal laminated composite material according to claim 2, wherein: the heating system comprises a heating system I and a plurality of heating systems II which are in one-to-one correspondence with the sub-chambers, the heating system I is used for heating the hot-pressing platform, and the heating system II is used for heating the sub-chambers.
9. The apparatus for preparing a graphene metal laminated composite material according to claim 1, wherein: the gas circuit system comprises a gas inlet main pipe, wherein the gas inlet main pipe extends into the integrated cavity and is arranged in the integrated cavity, the gas inlet main pipe penetrates through each sub-cavity, and the gas outlet hole is formed in the pipe wall of the gas inlet main pipe in the sub-cavity.
10. The apparatus for preparing a graphene metal laminate composite according to any one of claims 2 to 8, wherein: one side of the hot pressing platform, which is close to the conveying assembly, is connected with a guide component for guiding the metal base material, and one side of the hot pressing platform, which is far away from the conveying assembly, is connected with an anti-dropping component for preventing the metal base material from dropping from the hot pressing platform.
CN202220219711.8U 2022-01-26 2022-01-26 Preparation device of graphene metal laminated composite material Active CN217047854U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220219711.8U CN217047854U (en) 2022-01-26 2022-01-26 Preparation device of graphene metal laminated composite material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220219711.8U CN217047854U (en) 2022-01-26 2022-01-26 Preparation device of graphene metal laminated composite material

Publications (1)

Publication Number Publication Date
CN217047854U true CN217047854U (en) 2022-07-26

Family

ID=82485692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220219711.8U Active CN217047854U (en) 2022-01-26 2022-01-26 Preparation device of graphene metal laminated composite material

Country Status (1)

Country Link
CN (1) CN217047854U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114425901A (en) * 2022-01-26 2022-05-03 重庆墨希科技有限公司 Method and device for regulating and controlling conductivity of graphene metal laminated composite material
CN117870351A (en) * 2024-03-13 2024-04-12 福建福碳新材料科技有限公司 Production roasting device for isostatic pressing graphite product for third-generation semiconductor

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114425901A (en) * 2022-01-26 2022-05-03 重庆墨希科技有限公司 Method and device for regulating and controlling conductivity of graphene metal laminated composite material
CN117870351A (en) * 2024-03-13 2024-04-12 福建福碳新材料科技有限公司 Production roasting device for isostatic pressing graphite product for third-generation semiconductor
CN117870351B (en) * 2024-03-13 2024-05-28 福建福碳新材料科技有限公司 Production roasting device for isostatic pressing graphite product for third-generation semiconductor

Similar Documents

Publication Publication Date Title
CN217047854U (en) Preparation device of graphene metal laminated composite material
CN114425901A (en) Method and device for regulating and controlling conductivity of graphene metal laminated composite material
CN201016120Y (en) Continuous three-chamber air cooling vacuum annealing oven
WO2022027994A1 (en) Coating apparatus, method and system, solar cell, module, and power generation system
AU2011358318B2 (en) Device for continuously processing vacuum glass member
KR101751814B1 (en) Multi-layer vacuum insulation material manufacturing system
CN103122448B (en) Vertical Heat Treatment Furnace Structure
TW202023974A (en) Multi-mold hot-bending forming apparatus
CN103801693A (en) Rare earth permanent magnetic alloy flexible sintering process method
CN111540809A (en) Solar cell silicon chip drying and curing integrated equipment
CN201447502U (en) Continuous vacuum coater with multiple chambers
CN111705304A (en) Continuous and uniform coating hot wire chemical vapor deposition equipment and method
EP1890339B1 (en) Laminating apparatus
CN107056029A (en) A kind of 3D glass heat pressing forming machines
CN103801692A (en) Rare earth permanent magnetic alloy flexible sintering equipment
CN206915994U (en) A kind of 3D glass heat pressing forming machines
JP2011084009A (en) Laminate device, article processing apparatus, and method for manufacturing solar cell panel
CN216828449U (en) Growth forging and pressing split type equipment for preparing graphene metal composite material
CN217455262U (en) Large-scale production device for high-conductivity graphene metal composite material
JP5922461B2 (en) Laminating equipment
CN216801533U (en) A growth forging and pressing integration equipment for preparing graphite alkene metal composite
CN113493904B (en) High-temperature high-vacuum annealing furnace
CN217459595U (en) Device for preparing high-conductivity graphene metal composite material with assistance of plasma
CN214612209U (en) Vacuum glass high-temperature exhaust packaging equipment
CN216827919U (en) Integrated production device for growth and rolling of graphene-reinforced metal composite material

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant