CN216896089U - Positioning installation groove supplementing die - Google Patents
Positioning installation groove supplementing die Download PDFInfo
- Publication number
- CN216896089U CN216896089U CN202220355966.7U CN202220355966U CN216896089U CN 216896089 U CN216896089 U CN 216896089U CN 202220355966 U CN202220355966 U CN 202220355966U CN 216896089 U CN216896089 U CN 216896089U
- Authority
- CN
- China
- Prior art keywords
- angle steel
- positioning
- distance
- die
- adjusting gasket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Domestic Plumbing Installations (AREA)
Abstract
The utility model provides a location installation groove supplementing mould, relates to for drainage engineering technical field, and it can effectively improve installation quality and construction quality that PPR pipeline and pipe fitting laid in the wall body, and simple structure and technology, easily operation, low cost. In the positioning and mounting groove supplementing die, two ends of one side of the angle steel are respectively provided with an adjusting gasket; and one side of the angle steel, which is provided with the adjusting gasket, is provided with two positioning holes which are distributed at intervals, and the distance between the positioning holes is consistent with that between the water supply pipes, and the angle steel is used for enabling the outer threads of the plugging cap to be in threaded connection with the inner thread elbow or the tee.
Description
Technical Field
The utility model relates to the technical field of water supply and drainage engineering, in particular to a positioning and mounting groove supplementing mold, and more particularly relates to a self-made PP-R positioning and mounting groove supplementing mold.
Background
At present, a civil building is provided with water supply branch pipes in a water room, and is constructed by adopting PPR pipelines; moreover, in order to ensure the later decoration effect, the PPR pipeline is hidden in the wall.
In the prior art, when PPR pipe fittings are installed, the left-right distance elevation and the distance between a pipe orifice and a wall surface need to be determined, and the distance between the centers of outlets of adjacent pipe fittings needs to be determined for PPR row pipe fittings, and then the PPR row pipe fittings are hot-melted on a pipeline; then, two nails are crossed to push the pipeline pipe fitting into the groove, or binding the pipeline pipe fitting on the nails in the groove by using binding wires, or fixing the pipeline pipe fitting in the wall groove by using gypsum; and finally plastering and repairing the wall surface to finish construction.
However, the utility model discloses the people of this application discover to have following defect among the prior art: the pipeline is fixed by nails or binding wires, so that the pipeline is damaged; the gypsum is used for fixing the pipeline, so that the later plastering part is easy to crack; in addition, the distance between the outlet of the pipe fitting and the wall surface is not easy to master, the decoration effect is influenced, and the installation of water utilization equipment is influenced; the elevation of the row of pipe fittings is difficult to control, and the installation of water using equipment is influenced or cannot be realized at all.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a positioning installation groove supplementing mould and an installation and use method thereof, which can effectively improve the installation quality and the construction quality of PPR pipelines and pipe fittings laid in a wall body, and have the advantages of simple structure and process, easy operation and low cost.
In order to achieve the purpose, the utility model adopts the following technical scheme:
a positionally-fixed groove compensating die, comprising: the two ends of one side of the angle steel are respectively provided with an adjusting gasket; one side of the angle steel, which is provided with the adjusting gasket, is provided with two positioning holes which are distributed at intervals, and the distance between the positioning holes is consistent with the distance between the water supply pipes, and the angle steel is used for enabling the outer threads of the plugging cap to be in threaded connection with the inner thread elbow or the tee;
the positioning and mounting groove supplementing die utilizes the angle steel and the combined device of the adjusting gasket to effectively fix the pipeline and the pipe fitting of the water supply pipe.
The angle steel is connected with the adjusting gasket through a fastener.
Specifically, the fastener employs a self-drilling tail.
Furthermore, the positioning hole adopts a round hole structure.
Furthermore, the adjusting gasket is of a square tube structure.
A method for installing and using a positioning and installing groove repairing mold comprises the following steps:
marking and cutting the angle steel;
determining an adjusting gasket at the back of the angle steel according to the control distance of the outlet wall so as to adjust the distance between the pipe fitting opening and the wall surface, and intercepting the adjusting gasket with an indefinite specification so as to adjust the pipe fitting, so that the pipe fitting openings are parallel and the outlet wall distance is consistent;
fixedly connecting the angle steel and the adjusting gasket through a self-drilling tail wire;
adjusting the distance between the pipe fittings, forming circular positioning holes in the angle steel according to the distance between the water supply pipes so as to accurately determine the center distance between the pipe fittings and determine the opening distance between the two positioning holes in the angle steel;
and (4) completing the self-made PP-R positioning and groove supplementing die structure, and performing screw thread connection on the outer screw of the plugging cap and the inner screw elbow or the tee.
Compared with the prior art, the positioning installation groove repairing die and the installation and use method thereof have the following advantages:
in the positioning installation groove supplementing mould and the installation and use method thereof, the combined device of the angle steel and the adjusting gasket is used for effectively fixing the pipelines and the pipe fittings of the water supply pipe, so that the distance between the pipelines is fixed, the heights of the rows of pipe fittings are consistent, and the distances between the pipe fitting openings and the wall surface are consistent, thereby effectively improving the construction quality of the pipelines; and the position of the pipeline in the wall groove is fixed by using the die, and the distance between the pipeline outer skin and the wall outer vertical surface is fixed, so that the plastering forming is facilitated, the plastering quality is effectively improved, and the installation quality and the construction quality of the PPR pipeline and the pipe fitting laid in the wall are improved.
Drawings
Fig. 1 is a schematic structural diagram of a positioning and mounting groove repairing mold according to an embodiment of the present invention;
fig. 2 is a schematic view of a first view structure of a positioning and mounting groove repairing mold according to an embodiment of the present invention;
fig. 3 is a second view structural diagram of the positioning and mounting groove repairing mold according to the embodiment of the present invention;
fig. 4 is a schematic view of an installation and use state of a positioning and installation groove repairing mold according to an embodiment of the present invention;
fig. 5 is a schematic flow chart of an installation and use method of a positioning installation groove repairing mold according to an embodiment of the present invention.
Reference numerals:
1-angle steel; 11-a positioning hole; 2-adjusting the gasket; 3-a fastener; 31-self drilling fibers;
4-a water supply pipe; 5-blocking the cap external thread; 6-T connection.
Detailed Description
For the convenience of understanding, the positioning and mounting groove repairing die and the mounting and using method thereof provided by the embodiment of the utility model are described in detail below with reference to the attached drawings of the specification.
The embodiment of the utility model provides a positioning and mounting groove repairing die, as shown in fig. 1-4, comprising: two ends of one side of the angle steel 1 are respectively provided with an adjusting gasket 2; one side of the angle steel 1, which is provided with the adjusting gasket 2, is provided with two positioning holes 11 which are distributed at intervals, and the distance between the positioning holes 11 is consistent with the distance between the water supply pipes 4, and the angle steel is used for enabling the outer screw 5 of the plugging cap to be in screw thread connection with the elbow or the tee 6 of the inner screw;
the positioning installation groove supplementing die utilizes a combined device of angle steel 1 and an adjusting gasket 2 to effectively fix pipelines and pipe fittings of a water supply pipe 4.
The embodiment of the utility model further provides an installation and use method of the positioning and installation slot repairing die, as shown in fig. 5 and fig. 4, the installation and use method comprises the following steps:
step S1, carrying out scribing and cutting on the angle steel 1;
step S2, determining an adjusting gasket 2 at the back of the angle steel 1 according to the control distance of the outlet wall to adjust the distance between the opening of the pipe fitting and the wall surface, and intercepting the adjusting gasket 2 with an indefinite specification to adjust the pipe fitting to ensure that the opening of the pipe fitting is parallel and the outlet wall distance is consistent;
step S3, fixedly connecting the angle steel 1 and the adjusting shim 2 through the self-drilling tail wire 31;
step S4, adjusting the distance between the pipe fittings, arranging circular positioning holes 11 on the angle steel 1 according to the distance between the water supply pipes 4 so as to accurately determine the center distance between the pipe fittings and determine the opening distance between the two positioning holes 11 on the angle steel 1;
and S5, finishing the positioning and mounting of the groove supplementing mould structure by self-control PP-R, and performing screw thread connection on the outer screw 5 of the plugging cap and the inner screw elbow or the tee joint 6.
Compared with the prior art, the positioning and mounting groove repairing die and the mounting and using method thereof provided by the embodiment of the utility model have the following advantages:
in the positioning installation groove supplementing mould and the installation and use method thereof provided by the embodiment of the utility model, as the combined device of the angle steel 1 and the adjusting gasket 2 is utilized to effectively fix the pipelines and the pipe fittings of the water supply pipe 4, the distance between the pipelines is fixed, the heights of the rows of pipe fittings are consistent, and the distances between the pipe fitting openings and the wall surface are consistent, thereby effectively improving the pipeline construction quality; and the position of the pipeline in the wall groove is fixed by using the die, and the distance between the pipeline outer skin and the wall outer vertical surface is fixed, so that the plastering forming is facilitated, the plastering quality is effectively improved, and the installation quality and the construction quality of the PPR pipeline and the pipe fitting laid in the wall are improved.
As shown in fig. 1 to 4, the angle steel 1 and the adjusting shim 2 may be connected by a fastener 3, so as to facilitate the detachment of the adjusting shim 2.
Specifically, as shown in fig. 1-4, the fastener 3 may preferably employ a self-drilling tail 31 to further facilitate removal. The tail of the self-drilling tail wire, namely the self-drilling tail screw, is in a shape of a drill tail or a sharp tail, auxiliary processing is not needed, and drilling, tapping and locking can be directly carried out on the setting material and the base material, so that the construction time is greatly saved; compared with common screws, the screw has high drawing force and holding force, can not loosen after being combined for a long time, and is easy to operate by using safe punching and tapping once.
Further, as shown in fig. 1-4, the positioning hole 11 may be a circular hole structure, so as to better adapt to the tee joint 6 or other pipe fittings in the water supply pipe 4.
Further, as shown in fig. 1 to 4, the adjusting shim 2 may be a square tube structure, so as to effectively ensure the stability of the mold.
In summary, the positioning and mounting groove repairing mold and the mounting and using method thereof provided by the embodiment of the utility model mainly have the following advantages:
the utility model provides an, improve the installation quality that PPR pipeline and pipe fitting laid in the wall body inslot:
the distance between the pipelines is fixed, the heights of the rows of pipe fittings are consistent, and the distances between the pipe fitting openings and the wall surface are consistent, so that the construction quality of the pipelines is effectively improved;
secondly, improve the construction quality of structure behind the groove:
the position of the pipeline in the wall groove is fixed by using the die, and the distance between the pipeline outer skin and the wall outer vertical surface is fixed, so that plastering forming is facilitated, and the plastering quality is effectively improved; the wall outlet distance of the pipe fitting opening is fixed by using the die, so that the construction of matching with a wall surface decoration layer is facilitated, and the decoration construction quality is effectively improved;
thirdly, the process is simple and easy to operate:
compared with the traditional fixed installation process of the PPR pipeline in the wall groove, the technical scheme of the application is convenient to operate and easy to master, the installation of the pipeline and the pipe fitting can be efficiently and highly-standard completed after the technology is finished, and the construction is safe and efficient;
fourthly, prefabricating and assembling the die, and carrying out standardized processing:
the mold is processed and produced in the processing area, the efficiency is high, and the quality of engineering acceptance is improved by standardizing the mold;
fifthly, environmental protection is facilitated, and the cost is low:
the processing material is derived from construction leftover materials, and has low cost and obvious effect.
It should be noted that, PPR is an abbreviation for Polypropylene Random copolymer (Polypropylene Random); commonly known as type III polypropylene. The PPR pipe is a renewal product of a UPVC water supply pipe, an aluminum plastic pipe, a PE-X pipe and a PE-RT pipe; because it uses random copolymerization technology, the strength and high temperature resistance of polypropylene are well guaranteed, thus becoming the main force of water pipe material.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily think of the changes or substitutions within the technical scope of the present invention, and shall cover the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the appended claims.
Claims (5)
1. A location installation groove filling mould, its characterized in that includes: the two ends of one side of the angle steel are respectively provided with an adjusting gasket; and one side of the angle steel, which is provided with the adjusting gasket, is provided with two positioning holes which are distributed at intervals, and the distance between the positioning holes is consistent with that between the water supply pipes, and the angle steel is used for enabling the outer threads of the plugging cap to be in threaded connection with the inner thread elbow or the tee.
2. The locating and mounting groove supplementing mould according to claim 1, wherein the angle steel is connected with the adjusting shim through a fastener.
3. The positionally-fixed groove compensating die of claim 2 wherein the fastener comprises a self-drilling tail.
4. The mold of claim 1, wherein the positioning hole is a circular hole.
5. The mold according to claim 1, wherein the adjusting shim is of a square tube structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220355966.7U CN216896089U (en) | 2022-02-22 | 2022-02-22 | Positioning installation groove supplementing die |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220355966.7U CN216896089U (en) | 2022-02-22 | 2022-02-22 | Positioning installation groove supplementing die |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216896089U true CN216896089U (en) | 2022-07-05 |
Family
ID=82184285
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220355966.7U Active CN216896089U (en) | 2022-02-22 | 2022-02-22 | Positioning installation groove supplementing die |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216896089U (en) |
-
2022
- 2022-02-22 CN CN202220355966.7U patent/CN216896089U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103061504A (en) | Concrete board pipeline installation reserved hole construction mould and construction method | |
CN216896089U (en) | Positioning installation groove supplementing die | |
CN114458027A (en) | Positioning installation groove supplementing mold and installation and use method thereof | |
CN211714221U (en) | Plugging device for reserved hole of water supply and drainage sleeve of structural top plate | |
CN107514097B (en) | Prestressed corrugated pipe assembly and installation and construction method thereof | |
CN105649279A (en) | Fixing base, metal roof system with fixed base and installing method of metal roof system | |
CN210563409U (en) | Face wall and hang hole construction structures | |
KR200418916Y1 (en) | Pipe laying device for attacing valve to house wall | |
CN211524087U (en) | Wall structure with reserved equipment wall chase | |
CN203684332U (en) | Water pipe mounting auxiliary tool | |
US7043777B2 (en) | Single control faucet installation apparatus and method | |
CN218818575U (en) | Auxiliary installation tool for pipeline | |
CN113187027A (en) | Double-circular-arc flat pipeline water supply system for building | |
CN212773485U (en) | Embedded device for directly-embedded water supply points in shear wall | |
CN219367019U (en) | Cold and hot water pipe water outlet port goes out wall locator | |
CN214302512U (en) | Pipeline built-in keel connecting piece | |
CN216672525U (en) | Electrical butt-joint structure of prefabricated wallboard, roof board and floor | |
CN202280957U (en) | Adjustable pvc pipe socket joint | |
CN213837841U (en) | Precast concrete bolt system | |
CN209876172U (en) | Threaded connection thin-wall stainless steel water supply pipe and water supply pipe combination | |
CN208348669U (en) | A kind of fixed clamp of tubing | |
CN214302513U (en) | Pipeline built-in keel system | |
CN210623775U (en) | Concealed connection structure of shower water mixer | |
CN217000957U (en) | Pre-buried mould of aluminium mould spool location | |
CN213682407U (en) | End plugging device for spiral winding method of urban drainage pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |