CN213837841U - Precast concrete bolt system - Google Patents

Precast concrete bolt system Download PDF

Info

Publication number
CN213837841U
CN213837841U CN202022537279.0U CN202022537279U CN213837841U CN 213837841 U CN213837841 U CN 213837841U CN 202022537279 U CN202022537279 U CN 202022537279U CN 213837841 U CN213837841 U CN 213837841U
Authority
CN
China
Prior art keywords
precast concrete
concrete
stud
sleeve
wrench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022537279.0U
Other languages
Chinese (zh)
Inventor
闵阁龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202022537279.0U priority Critical patent/CN213837841U/en
Application granted granted Critical
Publication of CN213837841U publication Critical patent/CN213837841U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The precast concrete bolt system is arranged at the position of the reserved hole and comprises a precast concrete sleeve and a precast concrete stud; the prefabricated concrete sleeve is fixed in the structural template, a water stop ring is embedded in the middle outside the prefabricated concrete sleeve, and built-in threads are arranged inside the prefabricated concrete sleeve; the prefabricated concrete stud is externally provided with external threads, the internal threads correspond to the external threads, the exposed end face of the prefabricated concrete stud is provided with a wrench jack, the wrench jack corresponds to an adjustable wrench, and the prefabricated concrete stud can pass in and out of the prefabricated concrete sleeve through the adjustable wrench. The utility model discloses an above-mentioned structure provides a simple and convenient effectual precast concrete bolt system of being under construction.

Description

Precast concrete bolt system
Technical Field
The utility model relates to a precast concrete bolt system utilizes precast concrete bolt to carry out hole shutoff, built-in fitting installation, especially building construction field.
Background
In the construction, because of construction needs or process requirement, it is more to relate to the reservation hole, like interior accuse reservation hole, hot-water heating electrical installation reservation hole, outrigger link wall spare reservation hole, unwrapping wire hole, pump line hole etc. all need the later stage to carry out the shutoff and handle, and the shutoff still needs to satisfy relevant requirements such as fire prevention, waterproof. The main process for plugging the holes at present comprises the following steps: base course treatment → formwork support → concrete pouring (or material filling such as fire prevention) → curing → formwork removal → surface treatment (sanding, waterproofing, rust prevention and the like). The disadvantages are: various holes are different in size, large in quantity and irregular in position, and the plugging process is complicated and requires large labor consumption. And hole shutoff is gone on after basically being in the structure completion, and the main part is accepted construction each side and is generally not enough to this process attention degree, and most only carries out the operation such as rendering coat waterproof after filling the hole at will, and the shutoff quality can not guarantee, has hidden danger such as later stage local not hard up, leak.
In some other cases, some of the attached works, such as outdoor stairs and rainsheds, need to be pre-buried or connected to the structure by means of planting bars and anchoring. The disadvantages are: if the embedded part is embedded, inconvenience is brought to construction of other subsequent processes, the embedded part embedded in advance conflicts with the subsequent processes, structural form removal is influenced, the construction of a working platform of the subsequent processes is influenced, the embedded part can also cause embedded position deviation due to factors such as vibration and template installation errors during structural concrete pouring, and the embedded part needs to be chiseled and corrected if the deviation is large. If post-embedding means such as bar planting, anchoring and the like are adopted, the hidden troubles such as poor safety and durability exist.
Disclosure of Invention
The utility model provides a precast concrete bolt system has solved the complicated, the artifical problem that consumes greatly, the hidden danger is many of construction hole shutoff technology, provides a precast concrete bolt system who has in can direct screw in hole. Meanwhile, the problems that the installation of an embedded part in building construction affects the construction of subsequent processes, the position deviation is large and the safety is poor can be solved, the precast concrete bolt system with the embedded part capable of being directly screwed into a hole in the installation position is provided, and the embedded part is pre-embedded in the precast concrete bolt in advance.
In order to achieve the purpose, the invention adopts the following technical scheme:
the precast concrete bolt system is arranged at the position of the reserved hole and comprises a precast concrete sleeve and a precast concrete stud; the prefabricated concrete sleeve is fixed in the structural template, a water stop ring is embedded in the middle outside the prefabricated concrete sleeve, and built-in threads are arranged inside the prefabricated concrete sleeve; the prefabricated concrete stud is externally provided with external threads, the internal threads correspond to the external threads, the exposed end face of the prefabricated concrete stud is provided with a wrench jack, the wrench jack corresponds to an adjustable wrench, and the prefabricated concrete stud can pass in and out of the prefabricated concrete sleeve through the adjustable wrench.
The wrench jack be F shape, including the regulation spanner mobile jib and the regulation pole of L type, the regulation pole can be followed and adjusted the spanner mobile jib slip adjustment interval.
One end of the adjusting rod is sleeved on the main rod of the adjusting wrench, so that relative sliding is realized.
And a cementing material is extruded between the precast concrete stud and the precast concrete sleeve.
The cementing material is asphalt cement.
And an embedded part is arranged in the precast concrete stud, so that the embedded part concrete stud is formed.
And the end part of the embedded part concrete stud is provided with a wrench jack.
The beneficial effects created by the invention are as follows:
1. the construction speed of hole plugging is accelerated, and the main process of original hole plugging is as follows: base course treatment → formwork support → concrete pouring (or material filling such as fire prevention) → curing → formwork removal → surface treatment (sanding, waterproofing, rust prevention and the like). The hole plugging process comprises the following steps: cleaning in the sleeve → screwing in the concrete bolt → surface treatment (cleaning, rust prevention, etc.).
2. The hole plugging quality is guaranteed, the concrete bolts are all prefabricated, and the plugging quality is guaranteed from the source.
3. The installation of the embedded part can be independently carried out, the embedded part is prevented from influencing the subsequent process construction, and the accurate installation position and the use safety are ensured.
Drawings
FIG. 1: mounting a section view of the precast concrete sleeve;
FIG. 2: a prefabricated concrete sleeve installation schematic diagram;
FIG. 3: a schematic diagram of prefabricated concrete bolt installation during hole plugging construction;
FIG. 4: mounting a section view of a precast concrete bolt during hole plugging construction;
FIG. 5: the schematic diagram of the installation completion of the precast concrete bolt during hole plugging construction is shown;
FIG. 6: the prefabricated concrete bolt is installed to complete a section view during hole plugging construction;
FIG. 7: precast concrete casing schematic diagram;
FIG. 8: a precast concrete bolt schematic diagram;
FIG. 9: a schematic diagram of a dedicated adjustable wrench;
FIG. 10: an installation schematic diagram of the embedded part concrete stud;
FIG. 11: mounting a section view of the concrete stud of the embedded part;
FIG. 12: the installation of the embedded part concrete stud is completed;
FIG. 13: and (5) finishing a section diagram by installing the embedded part concrete stud.
In the figure: (1) prefabricating a concrete bolt; (2) prefabricating a concrete sleeve; (3) a special adjustable wrench; (4) prefabricating internal threads of the concrete sleeve; (5) a water stop sheet; (6) a wrench jack; (7) asphalt mastic; (8) prefabricating external threads of the concrete bolt; (9) adjusting a rod; (10) a main lever of the wrench; (11) embedded part concrete studs; (12) an embedded part.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
The precast concrete bolt system is arranged at the position of the reserved hole and comprises a precast concrete sleeve 2 and a precast concrete stud 1, and the precast concrete stud 1 and the precast concrete sleeve 2 are precast in advance. The precast concrete sleeve 2 is positioned, installed and fixed in the structural formwork and is poured together with the structural concrete. The middle part of the outer part of the precast concrete sleeve 2 is embedded with a water stop ring 5, and the inner part of the precast concrete sleeve 2 is provided with a built-in thread 4.
The external threads 8 are arranged outside the precast concrete stud 1, the internal threads 4 correspond to the external threads 8, the exposed end face of the precast concrete stud 1 is provided with a wrench jack 6, the wrench jack 6 corresponds to the adjustable wrench 3, and the precast concrete stud 1 can pass in and out of the precast concrete sleeve 2 through the adjustable wrench 3.
The wrench jack 6 is F-shaped and comprises an L-shaped adjusting wrench main rod 10 and an adjusting rod 9, and the adjusting rod 9 can slide along the adjusting wrench main rod 10 to adjust the distance. Preferably, one end of the adjusting rod 9 is sleeved on the main rod 10 of the adjusting wrench, thereby realizing relative sliding.
And a cementing material is extruded between the precast concrete stud 1 and the precast concrete sleeve 2. Preferably, the gelling material is asphalt mastic 7.
An embedded part 12 is arranged in the precast concrete stud 1, so that an embedded part concrete stud 11 is formed. Preferably, the end part of the embedded part concrete stud 11 is provided with a wrench inserting hole 6.
When in specific use:
prefabricating: the prefabricated concrete bolt 1 and the corresponding prefabricated concrete sleeve 2 are prefabricated according to planned reserved hole sizes, wherein a water stop ring 5 is buried in the middle of the prefabricated concrete sleeve 2, built-in threads 4 are arranged, external threads 8 of the prefabricated concrete bolt are arranged, a wrench jack 6 is arranged at the end of the prefabricated concrete bolt, and the built-in threads 4 of the prefabricated concrete sleeve 2 at each position correspond to the external threads 8 of the prefabricated concrete bolt 1. And embedding the embedded parts 12 into the precast concrete bolt 1 to form the precast concrete bolt 11 with the embedded parts when the embedded parts are required to be installed in part design. The special adjustable spanner 3 is processed according to the requirement.
Installing a sleeve: the position of the reserved hole is measured and positioned before the structure construction, the precast concrete sleeve 2 is fixed in a structure template, the port of the sleeve is sealed and tightly attached to the template by using an adhesive tape, and a double-sided adhesive tape is attached to the periphery of the port to be sealed with the template if necessary. And carrying out structural concrete pouring after the installation of the structural template is finished and the acceptance is passed.
③ the wrench is used: the special adjustable wrench 3 is divided into an adjusting wrench main rod 10 and an adjusting rod 9, and the adjusting rod 9 can slide along the adjusting wrench main rod 10. The position of the front adjusting rod 9 is used, so that the distance between the spanners corresponds to the distance between the spanner insertion holes 6, and the screwing operation can be carried out.
Plugging holes: and after the hole plugging condition is achieved, mounting the precast concrete bolt 1. Clean up in will precast concrete sleeve pipe 2, extrude into asphalt mastic 7 or have the cementitious material of other functional demands, transfer special adjustable spanner 3 to accurate position, insert in spanner jack 6, rotatory special adjustable spanner 3, with precast concrete bolt 1 screw in precast concrete sleeve pipe 2 in, make bolt both ends and structure surface level mutually, and have a small amount of asphalt mastic 7 to extrude, accomplish the installation after the clean up of surface.
Installing an embedded part: and after the subsequent process is finished and the installation conditions of the embedded part are met, installing the embedded part concrete stud 11. Cleaning the interior of the precast concrete sleeve 2, extruding asphalt mastic 7 or cementing materials with other functional requirements, screwing the precast concrete bolt 11 with the embedded part into the precast concrete sleeve 2 by rotating the embedded part 12, so that two ends of the bolt are flush with the surface of the structure, extruding a small amount of asphalt mastic 7, and cleaning the surface to finish installation.
The embedded part concrete stud 11 can be additionally provided with a wrench jack 6 according to requirements.

Claims (7)

1. Precast concrete bolt system sets up in reservation hole position department, its characterized in that: the device comprises a precast concrete sleeve (2) and a precast concrete stud (1); the prefabricated concrete sleeve (2) is fixed in the structural template, a water stop ring (5) is embedded in the middle of the outer part of the prefabricated concrete sleeve (2), and a built-in thread (4) is arranged inside the prefabricated concrete sleeve (2); the prefabricated concrete stud (1) is externally provided with external threads (8), the internal threads (4) correspond to the external threads (8), the exposed end face of the prefabricated concrete stud (1) is provided with a wrench jack (6), the wrench jack (6) corresponds to the adjustable wrench (3), and the prefabricated concrete stud (1) can pass in and out of the prefabricated concrete sleeve (2) through the adjustable wrench (3).
2. The precast concrete bolt system of claim 1, wherein: spanner jack (6) be F shape, including the regulation spanner mobile jib (10) and the regulation pole (9) of L type, regulation pole (9) can be followed regulation spanner mobile jib (10) and slide the adjustment interval.
3. The precast concrete bolt system of claim 2, wherein: one end of the adjusting rod (9) is sleeved on the main rod (10) of the adjusting wrench, so that relative sliding is realized.
4. The precast concrete bolt system of claim 1, wherein: and a cementing material is extruded between the precast concrete stud (1) and the precast concrete sleeve (2).
5. The precast concrete bolt system of claim 4, wherein: the cementing material is asphalt mastic (7).
6. The precast concrete bolt system of claim 1, wherein: an embedded part (12) is arranged in the precast concrete stud (1), so that an embedded part concrete stud (11) is formed.
7. The precast concrete bolt system of claim 6, wherein: and a wrench jack (6) is arranged at the end part of the embedded part concrete stud (11).
CN202022537279.0U 2020-11-05 2020-11-05 Precast concrete bolt system Active CN213837841U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022537279.0U CN213837841U (en) 2020-11-05 2020-11-05 Precast concrete bolt system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022537279.0U CN213837841U (en) 2020-11-05 2020-11-05 Precast concrete bolt system

Publications (1)

Publication Number Publication Date
CN213837841U true CN213837841U (en) 2021-07-30

Family

ID=77014376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022537279.0U Active CN213837841U (en) 2020-11-05 2020-11-05 Precast concrete bolt system

Country Status (1)

Country Link
CN (1) CN213837841U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115478703A (en) * 2022-10-17 2022-12-16 四川大学 Method for preventing frost heaving cracking of concrete hole
CN115478703B (en) * 2022-10-17 2024-05-10 四川大学 Method for preventing frost heaving and cracking of concrete holes

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115478703A (en) * 2022-10-17 2022-12-16 四川大学 Method for preventing frost heaving cracking of concrete hole
CN115478703B (en) * 2022-10-17 2024-05-10 四川大学 Method for preventing frost heaving and cracking of concrete holes

Similar Documents

Publication Publication Date Title
CN102644362B (en) Method for architectural decoration plastering construction
CN108858665B (en) Production process of ceramic plate facing reverse-beating formed external wall plate or hanging plate
CN110924692A (en) Masonry pipeline direct-buried construction method
CN103061515A (en) Method for perforating and pre-burying polyvinyl chloride (PVC) wiring tubes in concrete hollow block filled walls
CN207177063U (en) A kind of blockwork of pre-buried air conditioner condensate water drain bushing
CN106049862A (en) Inflatable adjustable type construction mold for reserved hole in concrete structure plate, and construction method
CN213837841U (en) Precast concrete bolt system
CN211286635U (en) Perforated pipeline shutoff formwork device behind bathroom
CN212176569U (en) Floor preformed hole plugging device
CN110821174A (en) Die adjusting embedded part and aluminum alloy template diagonal bracing device
CN211286666U (en) Die adjusting embedded part and aluminum alloy template diagonal bracing device
CN201024584Y (en) Water heating ground heat pipeline pavement template
CN215055528U (en) Box body support of recyclable fixing wire box
CN212428082U (en) Electromechanical pre-buried device of high-rise apartment building
CN107313451A (en) The inner supporting device and its construction method of basement prefabricated board loose tool
CN213682407U (en) End plugging device for spiral winding method of urban drainage pipeline
CN110905199A (en) Construction method of aluminum alloy formwork diagonal bracing device
CN209653395U (en) The outspoken dismounting mold of convex-down concrete roof reserved holes of pipes
CN208028536U (en) Embedded terminal box
CN215166787U (en) Water-facing and electricity-facing structure
CN217056644U (en) Embedded part for mounting sewer main pipe in building
CN216896089U (en) Positioning installation groove supplementing die
CN208564007U (en) Support anchor system
CN212773485U (en) Embedded device for directly-embedded water supply points in shear wall
CN217000957U (en) Pre-buried mould of aluminium mould spool location

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant