CN216891925U - Wave form steel web combination case girder construction based on arch structure atress - Google Patents

Wave form steel web combination case girder construction based on arch structure atress Download PDF

Info

Publication number
CN216891925U
CN216891925U CN202220243196.7U CN202220243196U CN216891925U CN 216891925 U CN216891925 U CN 216891925U CN 202220243196 U CN202220243196 U CN 202220243196U CN 216891925 U CN216891925 U CN 216891925U
Authority
CN
China
Prior art keywords
concrete
bottom plate
prestressed
precast concrete
pier top
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220243196.7U
Other languages
Chinese (zh)
Inventor
陈宜言
王健
赵秋
王远洋
叶际斌
翁观旺
黄光铃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN202220243196.7U priority Critical patent/CN216891925U/en
Application granted granted Critical
Publication of CN216891925U publication Critical patent/CN216891925U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a corrugated steel web plate combined box girder structure based on stress of an arch structure, which comprises a plurality of piers, wherein pier top cross beams are arranged on the piers, adjacent pier top cross beams are connected through an arched concrete bottom plate, the concrete bottom plate comprises a plurality of precast concrete plates which are sequentially connected, the precast concrete plates are connected in series through prestressed steel hinge lines, and the prestressed steel hinge lines penetrate through steel hinge line channels to extend out and are fixed on the corresponding pier top cross beams. According to the utility model, the prefabricated concrete plates are connected by the pull belts and are integrally hoisted to the pier top cross beam, the construction of the one-span arched concrete bottom plate can be completed by one-time hoisting, a large number of complex temporary supporting devices are not needed, the construction process is simpler and more convenient, the construction cost is saved, and the application prospect is good.

Description

基于拱结构受力的波形钢腹板组合箱梁结构Corrugated steel web composite box girder structure based on arch structure

技术领域technical field

本实用新型涉及一种基于拱结构受力的波形钢腹板组合箱梁结构。The utility model relates to a corrugated steel web composite box girder structure based on the stress of an arch structure.

背景技术Background technique

波形钢腹板组合箱梁桥在支点处梁高较高,跨中处梁高较低,按一定的变化形式由支点向跨中变化,使得主梁的底板通常按一定的线形变化。针对呈一定线形变化的混凝土底板施工,通常采用挂篮施工或支架现浇。挂篮施工或支架现浇都需要进行支模,支模难度大大增加,不仅影响了整体工程进度,还会因模板拼装问题造成混凝土底板浇筑后出现漏浆和漏筋等质量问题。同时,混凝土浇筑时候容易出现振捣不合理,大气泡不能完全排出,混凝土底板外表面会引起蜂窝麻面,不仅影响了桥梁的美观,也无法达到设计的使用要求。支架现浇的施工方法受施工环境影响,且无法运用于一些较大跨径的桥梁。The corrugated steel web composite box girder bridge has higher beam height at the fulcrum and lower beam height at the mid-span. For the construction of the concrete floor with a certain linear change, hanging basket construction or cast-in-place bracket is usually used. The construction of the hanging basket or the cast-in-situ support of the support requires form support, which greatly increases the difficulty of form support, which not only affects the overall project progress, but also causes quality problems such as leakage of slurry and leakage of reinforcement after the concrete floor is poured due to the problem of formwork assembly. At the same time, unreasonable vibration is likely to occur during concrete pouring, large air bubbles cannot be completely discharged, and the outer surface of the concrete floor will cause a honeycomb surface, which not only affects the aesthetics of the bridge, but also fails to meet the design requirements. The construction method of cast-in-place supports is affected by the construction environment, and cannot be applied to some bridges with larger spans.

对于拱形结构桥梁在施工过程中需要大量的专用支撑等临时设施,使得施工过程过于复杂且增大了施工成本,影响了工程进度。A large number of temporary facilities such as special supports are required in the construction process of the arched bridge, which makes the construction process too complicated, increases the construction cost, and affects the progress of the project.

发明内容SUMMARY OF THE INVENTION

有鉴于此,本实用新型的目的是提出一种基于拱结构受力的波形钢腹板组合箱梁结构及施工方法,解决上述技术方案存在的问题。In view of this, the purpose of the present utility model is to propose a corrugated steel web composite box girder structure and construction method based on the stress of the arch structure, so as to solve the problems existing in the above technical solutions.

本实用新型采用以下方案实现: 一种基于拱结构受力的波形钢腹板组合箱梁结构,包括若干桥墩,桥墩上安装有墩顶横梁,相邻的墩顶横梁之间通过拱形的混凝土底板连接,所述混凝土底板包括若干依次连接的预制混凝土板块,各个预制混凝土板块之间通过预应力钢铰线串连,预应力钢铰线的贯穿钢铰线通道伸出并固定于对应的墩顶横梁上。The utility model adopts the following scheme to realize: A corrugated steel web composite box girder structure based on the stress of an arch structure, including a plurality of bridge piers, pier top beams are installed on the bridge piers, and arched concrete is passed between the adjacent pier top beams. The bottom plate is connected, and the concrete bottom plate includes a plurality of prefabricated concrete slabs connected in sequence, and each prefabricated concrete slab is connected in series by a prestressed steel hinge line, and the through-steel hinge channel of the prestressed steel hinge line extends out and is fixed to the corresponding pier on the top beam.

进一步的,所述预制混凝土板块内设置有若干顺桥向贯穿预制混凝土板块的预应力孔洞,相邻的预制混凝土板块上的预应力孔洞一一对应,各个对应的预应力孔洞相互连接形成钢铰线通道,所述预应力钢铰线设置于钢铰线通道内,预应力钢铰线的两端贯穿钢铰线通道伸出并锚固于对应的墩顶横梁上,预应力孔洞与预应力钢铰线空隙灌注水泥砂浆。Further, the precast concrete slabs are provided with a number of prestressed holes penetrating the precast concrete slabs in the bridge direction, the prestressed holes on the adjacent precast concrete slabs are in one-to-one correspondence, and the corresponding prestressed holes are connected to each other to form steel hinges. Line channel, the prestressed steel hinge wire is arranged in the steel hinge line channel, the two ends of the prestressed steel hinge line extend through the steel hinge line channel and are anchored on the corresponding pier top beam, and the prestressed hole is connected to the prestressed steel hinge. The hinged voids are filled with cement mortar.

进一步的,所述混凝土底板上安装有至少一条的拉带,各个混凝土底板与拉带之间可拆连接。Further, at least one pull strap is installed on the concrete base plate, and each concrete base plate and the pull strap are detachably connected.

进一步的,所述预制混凝土板块顺桥向的下表面长于上表面。Further, the lower surface of the precast concrete slab along the bridge direction is longer than the upper surface.

进一步的,所述相邻预制混凝土板块的接缝之间设置混凝土剪力键,所述混凝土剪力键可采用梯形或圆角梯形截面,混凝土剪力键的高度应大于混凝土最大骨料粒径的2倍、小于35mm;混凝土剪力键的高度与其平均宽度比取为1:2。Further, a concrete shear key is set between the joints of the adjacent precast concrete slabs. The concrete shear key can adopt a trapezoidal or rounded trapezoid section, and the height of the concrete shear key should be greater than the maximum aggregate particle size of the concrete. 2 times and less than 35mm; the ratio of the height of the concrete shear key to its average width is taken as 1:2.

进一步的,所述墩顶横梁侧部上对应预制混凝土底板的连接端设置有倾斜交界平面,倾斜交界平面与预制混凝土底板轴线垂直,横梁两侧上对应预应力钢绞线设置有锚固点。Further, an inclined interface plane is provided on the side of the beam on the top of the pier corresponding to the connection end of the precast concrete bottom plate, and the inclined interface plane is perpendicular to the axis of the precast concrete bottom plate, and the corresponding prestressed steel strands on both sides of the beam are provided with anchorage points.

进一步的,所述预制混凝土板块为钢筋混凝土结构,所述预制混凝土板块的左右两侧均预埋一定高度的波形钢腹板,所述墩顶横梁的底面与预制混凝土底板最低点间距不小于0.5m。Further, the prefabricated concrete slab is a reinforced concrete structure, the left and right sides of the prefabricated concrete slab are embedded with corrugated steel webs of a certain height, and the distance between the bottom surface of the pier top beam and the lowest point of the prefabricated concrete bottom plate is not less than 0.5 m.

进一步的,所述预制混凝土板块包括若干左右依次连接的预制并排混凝土底板,前后相邻的预制并排混凝土底板通过预应力钢铰线连接,形成并排混凝土底板肋条,左右相邻的并排混凝土底板肋条间通过横向预应力或湿接缝连接,并沿横桥向依次连接,两侧的并排混凝土底板肋条的外侧预埋波形钢腹板。Further, the prefabricated concrete slabs include a number of prefabricated side-by-side concrete base plates connected in sequence from left to right, and the front and rear adjacent prefabricated side-by-side concrete base plates are connected by prestressed steel hinge lines to form side-by-side concrete floor ribs, and between the left and right adjacent side-by-side concrete floor ribs. Connected by transverse prestressed or wet joints, and connected in sequence along the transverse bridge direction, the outer sides of the side-by-side concrete floor ribs on both sides are pre-embedded with corrugated steel webs.

与现有技术相比,本实用新型有以下有益效果:通过采用拉带连接预制混凝土板块并进行整体吊装至墩顶横梁,通过一次吊装即可完成一跨拱形混凝土底板的施工且无需大量复杂的临时支撑装置,施工工艺更加简便,节省工程造价,具有很好的应用前景。Compared with the prior art, the utility model has the following beneficial effects: by connecting the prefabricated concrete slabs with the tension straps and hoisting them integrally to the pier top beam, the construction of the one-span arched concrete floor can be completed by one hoisting without requiring a large number of complicated The temporary support device, the construction process is simpler, the engineering cost is saved, and the utility model has a good application prospect.

附图说明Description of drawings

图1为本实用新型混凝土板块结构示意图;Fig. 1 is the concrete slab structure schematic diagram of the present utility model;

图2为本实用新型吊装前拉带连接混凝土板块结构示意图;Fig. 2 is the structural schematic diagram of the utility model before hoisting and connecting the concrete plate;

图3为本实用新型吊装时混凝土板块板结构示意图;3 is a schematic diagram of the structure of the concrete slab during hoisting of the utility model;

图4为本实用新型完成吊装混凝土板块结构示意图;Fig. 4 is the structural schematic diagram of the finished hoisting concrete slab of the present invention;

图5为本实用新型墩顶横梁结构示意图;5 is a schematic structural diagram of a pier top beam of the present invention;

图6为本实用新型安装波形钢腹板后结构示意图;Figure 6 is a schematic structural diagram of the utility model after the corrugated steel web is installed;

图7为本实用新型完成顶板施工后结构示意图;7 is a schematic structural diagram of the utility model after the roof construction is completed;

图8为本实用新型实施例2吊装一侧混凝土底板肋条结构示意图;8 is a schematic diagram of the rib structure of a concrete bottom plate on one side of hoisting according to Embodiment 2 of the present utility model;

图9为本实用新型实施例2吊装一侧混凝土底板肋条俯视图;Fig. 9 is the top view of the rib of the concrete bottom plate on one side of hoisting according to the second embodiment of the utility model;

图10为本实用新型实施例2吊装中间混凝土底板肋条结构示意图;10 is a schematic diagram of the rib structure of the hoisting intermediate concrete bottom plate according to Embodiment 2 of the present utility model;

图11为本实用新型实施例2吊装中间混凝土底板肋条俯视图;Fig. 11 is the top view of the rib of the middle concrete floor in the hoisting of the second embodiment of the utility model;

图12为本实用新型实施例2吊装完成混凝土底板结构示意图。FIG. 12 is a schematic structural diagram of the concrete base plate after hoisting according to Embodiment 2 of the present utility model.

图中:1-混凝土底板;2-预埋波形钢腹板;3-混凝土顶板;4-预应力孔洞;5-拉带;6-墩顶横梁;7-混凝土剪力键;8-倾斜交界平面;9-波形钢腹板;10-并排混凝土底板肋条。In the figure: 1- Concrete bottom plate; 2- Pre-embedded corrugated steel web; 3- Concrete roof plate; 4- Prestressed hole; 5- Tension belt; 6- Pier top beam; Plane; 9-corrugated steel web; 10-side-by-side concrete floor ribs.

具体实施方式Detailed ways

下面结合附图及实施例对本实用新型做进一步说明。The present utility model will be further described below in conjunction with the accompanying drawings and embodiments.

应该指出,以下详细说明都是示例性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the application. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that There are features, steps, operations, devices, components, and/or combinations thereof.

如图1-7所示,本实施例提供了一种基于拱结构受力的波形钢腹板组合箱梁结构,包括若干桥墩(未示出),桥墩上安装有墩顶横梁6,相邻的墩顶横梁之间通过拱形的混凝土底板1连接,所述混凝土底板包括若干依次连接的预制混凝土板块,各个预制混凝土板块之间通过预应力钢铰线(未示出)串连,预应力钢铰线的贯穿钢铰线通道伸出并固定于对应的墩顶横梁上。As shown in Figures 1-7, this embodiment provides a corrugated steel web composite box girder structure based on the stress of an arch structure, including a number of bridge piers (not shown), on which a pier top beam 6 is installed, adjacent to The pier top beams are connected by an arched concrete base plate 1, and the concrete base plate includes a number of prefabricated concrete slabs connected in sequence, and each prefabricated concrete slab is connected in series by prestressed steel hinge lines (not shown), and the prestressed concrete slabs are connected in series. The through-steel hinge channel of the steel hinge line extends out and is fixed on the corresponding pier top beam.

在本实施例中,所述预制混凝土板块内设置有若干顺桥向贯穿预制混凝土板块的预应力孔洞4,相邻的预制混凝土板块上的预应力孔洞一一对应,各个对应的预应力孔洞相互连接形成钢铰线通道,所述预应力钢铰线设置于钢铰线通道内,预应力钢铰线的两端贯穿钢铰线通道伸出并锚固于对应的墩顶横梁上,预应力孔洞与预应力钢铰线空隙灌注水泥砂浆。In the present embodiment, the precast concrete slab is provided with a number of prestressed holes 4 which penetrate the precast concrete slab in the bridge direction, the prestressed holes on the adjacent precast concrete slabs are in one-to-one correspondence, and the corresponding prestressed holes are mutually The connection forms a steel hinge channel, the prestressed steel hinge is arranged in the steel hinge channel, and both ends of the prestressed steel hinge extend through the steel hinge channel and are anchored on the corresponding pier top beam, and the prestressed holes Cement mortar is poured into the voids with prestressed steel hinges.

在本实施例中,所述混凝土底板上安装有至少一条的拉带5,各个混凝土底板与拉带之间可拆连接,本装置采用三条拉带,拉带可以转动,并可以拆除。In this embodiment, at least one pull strap 5 is installed on the concrete base plate, and each concrete base plate and the pull strap are detachably connected. The device adopts three pull straps, and the pull strap can be rotated and removed.

在本实施例中,为了设计合理,所述预制混凝土板块顺桥向两侧表面有一定的倾斜,即所述预制混凝土板块顺桥向的下表面长度大于上表面长度。In this embodiment, for the sake of reasonable design, the precast concrete slabs are inclined to a certain extent on both sides along the bridge, that is, the length of the lower surface of the precast concrete slab along the bridge is greater than the length of the upper surface.

在本实施例中,所述相邻预制混凝土板块的接缝之间设置混凝土剪力键7,所述混凝土剪力键可采用梯形或圆角梯形截面,混凝土剪力键的高度应大于混凝土最大骨料粒径的2倍、小于35mm;混凝土剪力键的高度与其平均宽度比取为1:2。In this embodiment, a concrete shear key 7 is arranged between the joints of the adjacent precast concrete slabs. The concrete shear key can adopt a trapezoidal or rounded trapezoid section, and the height of the concrete shear key should be greater than the maximum concrete height. 2 times the aggregate particle size and less than 35mm; the ratio of the height of the concrete shear bond to its average width is taken as 1:2.

在本实施例中,所述墩顶横梁侧部上对应预制混凝土底板的连接端设置有倾斜交界平面8,倾斜交界平面与预制混凝土底板轴线垂直,横梁两侧上对应预应力钢绞线设置有锚固点,预应力钢绞线的端部锚固于锚固点上,所述墩顶横梁的底面与预制混凝土底板最低点间距不小于0.5m。In this embodiment, an inclined interface plane 8 is provided on the side of the beam on the top of the pier corresponding to the connection end of the precast concrete base plate, and the inclined interface plane is perpendicular to the axis of the precast concrete base plate, and the corresponding prestressed steel strands on both sides of the beam are provided with The anchor point, the end of the prestressed steel strand is anchored on the anchor point, and the distance between the bottom surface of the pier top beam and the lowest point of the precast concrete bottom plate is not less than 0.5m.

在本实施例中,所述预制混凝土板块为钢筋混凝土结构,所述预制混凝土板块的左右两侧均预埋一定高度的波形钢腹板2。In this embodiment, the prefabricated concrete slab is a reinforced concrete structure, and the left and right sides of the prefabricated concrete slab are pre-embedded with corrugated steel webs 2 of a certain height.

在本实施例中,所述预埋波形钢腹板2上部焊接波形钢腹板9,相邻的墩顶横梁顶部与对应的两侧波形钢腹板之间所围成的区域顶部通过混凝土顶板3封闭。In this embodiment, the upper part of the embedded corrugated steel web 2 is welded with a corrugated steel web 9, and the top of the area enclosed between the top of the adjacent pier top beam and the corresponding corrugated steel webs on both sides passes through the concrete roof 3 closed.

实施例2:参照图8-12,由于直接吊装整条混凝土底板较为困难,所以混凝土底板采用半宽或分块预制,根据混凝土底板不同的预制方式,采用拉带连接预制混凝土板块,将混凝土底板分为并排的混凝土底板肋条,从一侧依次吊装各个混凝土底板肋条,直至完成混凝土底板的施工。其他与实施例1相同。适用于混凝土底板较宽的组合箱梁桥,减轻吊装难度,具体技术方案为:在本实施例中,所述预制混凝土板块包括若干左右依次对接的预制并排混凝土底板,前后相邻(即顺桥向)的预制并排混凝土底板通过预应力钢铰线连接,形成并排混凝土底板肋条10,左右相邻(即横桥向)的并排混凝土底板肋条沿横桥向依次对接,两侧的并排混凝土底板肋条的外侧预埋波形钢腹板。一种基于拱结构受力的波形钢腹板组合箱梁结构的施工方法:Example 2: Referring to Figures 8-12, since it is difficult to directly hoist the entire concrete floor, the concrete floor is prefabricated in half-width or in blocks. It is divided into side-by-side concrete floor ribs, and each concrete floor rib is hoisted in sequence from one side until the construction of the concrete floor is completed. Others are the same as in Example 1. It is suitable for a composite box girder bridge with a wider concrete floor, and reduces the difficulty of hoisting. The prefabricated side-by-side concrete floors in the horizontal direction are connected by prestressed steel hinge lines to form side-by-side concrete floor ribs 10. The side-by-side concrete floor ribs adjacent to the left and right (that is, in the transverse bridge direction) are connected in turn along the transverse bridge direction, and the side-by-side concrete floor ribs on both sides. The outer side of the embedded corrugated steel web. A construction method of a corrugated steel web composite box girder structure based on the stress of an arch structure:

步骤1:桥梁下部结构施工:进行桥墩和桥台钢筋绑扎,浇筑桥墩和桥台混凝土,并进行养护;Step 1: Construction of the substructure of the bridge: tie the steel bars of the piers and abutments, pour the concrete of the piers and abutments, and perform maintenance;

步骤2:混凝土底板板块预制:按照划分的混凝土底板的尺寸拼装模板,绑扎预制混凝土板块钢筋,并预埋预应力管道和部分高度波形钢腹板,浇筑混凝土,并进行养护;Step 2: Prefabrication of concrete floor slabs: Assemble the formwork according to the size of the divided concrete slabs, bind the steel bars of the prefabricated concrete slabs, embed the prestressed pipes and some highly corrugated steel webs, pour concrete, and perform maintenance;

步骤3:墩顶横梁施工:以桥墩为支撑,安装墩顶横梁支架和模板,进行钢筋绑扎,安装预应力管道,浇筑混凝土,并进行养护;Step 3: Construction of the pier top beam: with the pier as the support, install the pier top beam bracket and formwork, bind the steel bars, install the prestressed pipes, pour the concrete, and carry out maintenance;

步骤4:混凝土底板施工:将预制混凝土底板板块运输至桥位附近,在施工平台上通过定位依次安装预制混凝土底板板块,将拉带紧贴预制混凝土底板板块顶面并进行连接,利用吊机进行整体吊装,混凝土底板形成拱形,将拱形的混凝土底板安装在墩顶横梁上;Step 4: Concrete floor construction: transport the prefabricated concrete floor slabs to the vicinity of the bridge, install the prefabricated concrete floor slabs in sequence on the construction platform by positioning, and attach the pull straps to the top surface of the prefabricated concrete floor slabs and connect them, using a crane to carry out The overall hoisting, the concrete bottom plate forms an arch, and the arched concrete bottom plate is installed on the beam on the top of the pier;

步骤5:预应力施工:在混凝土底板内穿插预应力钢绞线,并张拉预应力钢绞线,完成封锚;Step 5: Prestressed construction: insert prestressed steel strands in the concrete floor, and stretch the prestressed steel strands to complete the anchorage;

步骤6:波形钢腹板施工:将波形钢腹板与预埋在混凝土底板中的波形钢腹板进行焊接连接;Step 6: Construction of the corrugated steel web: Weld the corrugated steel web and the corrugated steel web embedded in the concrete bottom plate by welding;

步骤7:混凝土顶板施工:以波形钢腹板及混凝土底板作为支撑,在波形钢腹板上架设模板,浇筑混凝土顶板;Step 7: Concrete roof construction: use the corrugated steel web and the concrete bottom plate as supports, set up the formwork on the corrugated steel web, and pour the concrete roof;

步骤8:桥面铺装及附属工程施工。Step 8: Bridge deck pavement and ancillary works construction.

在本实施例中,步骤3中,当桥墩顶有支座时,需先安装支座,并采用临时固结措施将墩顶横梁与桥墩固结,并在桥梁主体结构施工完成后,拆除临时固结措施,通过支座支承桥梁上部结构。在步骤4中,混凝土底板横桥向分块安装,混凝土底板由并排混凝土底板肋条组成,所述混凝土底板肋条间由横向预应力连接或湿接缝连接。In this embodiment, in step 3, when there is a support on the top of the bridge pier, the support needs to be installed first, and temporary consolidation measures are used to consolidate the pier top beam and the bridge pier, and after the construction of the main structure of the bridge is completed, the temporary Consolidation measures to support the bridge superstructure through bearings. In step 4, the transverse bridge of the concrete floor is installed in blocks, and the concrete floor is composed of side-by-side concrete floor ribs, and the ribs of the concrete floor are connected by transverse prestressed connections or wet joints.

本实用新型将波形钢腹板组合梁桥拱形底板进行分段预制,在施工平台上通过定位依次安装预制混凝土底板板块,将拉带紧贴预制混凝土底板板块顶面并进行连接,利用吊机进行整体吊装,将拱形的混凝土底板安装在墩顶横梁上,可以有效的提高波形钢腹板组合箱梁桥拱形混凝土底板的架设效率,保证了混凝土底板板块的拼装质量,具有很好的应用前景施工工艺更加简便,节省工程造价,具有很好的应用前景。The utility model prefabricates the arched bottom plate of the corrugated steel web composite girder bridge in sections, installs the prefabricated concrete bottom plate slabs in sequence on the construction platform by positioning, and attaches the tie straps to the top surface of the prefabricated concrete bottom plate slab and connects them. The overall hoisting is carried out, and the arched concrete floor is installed on the pier top beam, which can effectively improve the erection efficiency of the arched concrete floor of the corrugated steel web composite box girder bridge, and ensure the assembly quality of the concrete floor plate. Application prospect The construction process is simpler, the engineering cost is saved, and the utility model has a good application prospect.

上述本实用新型所公开的任一技术方案除另有声明外,如果其公开了数值范围,那么公开的数值范围均为优选的数值范围,任何本领域的技术人员应该理解:优选的数值范围仅仅是诸多可实施的数值中技术效果比较明显或具有代表性的数值。由于数值较多,无法穷举,所以本实用新型才公开部分数值以举例说明本实用新型的技术方案,并且,上述列举的数值不应构成对本实用新型创造保护范围的限制。Unless otherwise stated in any of the technical solutions disclosed in the above-mentioned utility model, if it discloses a numerical range, then the disclosed numerical range is the preferred numerical range, and any person skilled in the art should understand: the preferred numerical range is only It is a numerical value with obvious or representative technical effect among many practicable numerical values. Since the numerical values are too numerous to be exhaustive, only some numerical values are disclosed in the present invention to illustrate the technical solutions of the present invention, and the above-mentioned numerical values shall not constitute a limitation on the protection scope of the present invention.

如果本文中使用了“第一”、“第二”等词语来限定零部件的话,本领域技术人员应该知晓:“第一”、“第二”的使用仅仅是为了便于描述上对零部件进行区别如没有另行声明外,上述词语并没有特殊的含义。If words such as "first" and "second" are used herein to define components, those skilled in the art should know that the use of "first" and "second" is only for the convenience of describing components The above terms have no special meaning unless otherwise stated.

本实用新型如果公开或涉及了互相固定连接的零部件或结构件,那么,除另有声明外,固定连接可以理解为:能够拆卸地固定连接( 例如使用螺栓或螺钉连接),也可以理解为:不可拆卸的固定连接(例如铆接、焊接),当然,互相固定连接也可以为一体式结构(例如使用铸造工艺一体成形制造出来) 所取代(明显无法采用一体成形工艺除外)。If the present invention discloses or involves parts or structural parts that are fixedly connected to each other, then, unless otherwise stated, fixed connection can be understood as: detachable fixed connection (for example, using bolts or screws), can also be understood as : Non-removable fixed connection (such as riveting, welding), of course, the mutual fixed connection can also be replaced by a one-piece structure (for example, using a casting process to integrally form) (except that it is obviously impossible to use an integral forming process).

另外,上述本实用新型公开的任一技术方案中所应用的用于表示位置关系例如“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本专利,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本专利的限制,且上述本实用新型公开的任一技术方案中所应用的用于表示形状的术语除另有声明外其含义包括与其近似、类似或接近的形状。In addition, any of the above-mentioned technical solutions disclosed in the present utility model is used to represent positional relationships such as "vertical", "horizontal", "upper", "lower", "front", "rear", "left", The orientation or positional relationship indicated by "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the purpose of It is convenient to describe this patent, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, so it cannot be construed as a limitation on this patent, and any technical solutions disclosed in the above-mentioned present utility model The terms used to denote a shape as used in <RTI ID=0.0></RTI>

本实用新型提供的任一部件既可以是由多个单独的组成部分组装而成,也可以为一体成形工艺制造出来的单独部件。Any component provided by the present invention may be assembled from a plurality of individual components, or may be a single component manufactured by an integral molding process.

最后应当说明的是:以上实施例仅用以说明本实用新型的技术方案而非对其限制;尽管参照较佳实施例对本实用新型进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本实用新型的具体实施方式进行修改或者对部分技术特征进行等同替换;而不脱离本实用新型技术方案的精神,其均应涵盖在本实用新型请求保护的技术方案范围当中。Finally it should be noted that: the above embodiment is only used to illustrate the technical scheme of the present invention and not to limit it; although the present invention has been described in detail with reference to the preferred embodiment, those of ordinary skill in the art should understand: still The specific embodiments of the present invention can be modified or some technical features can be equivalently replaced; without departing from the spirit of the technical solutions of the present invention, all of them should be included in the scope of the technical solutions claimed in the present invention.

Claims (8)

1. The utility model provides a wave form steel web combination box girder structure based on arch structure atress, includes a plurality of piers, installs the pier top crossbeam on the pier, connects through arched concrete bottom plate between the adjacent pier top crossbeam, a serial communication port, concrete bottom plate includes a plurality of precast concrete plates that connect gradually, through prestressing force hinge line polyphone between each precast concrete plate, on the steel hinge line passageway that runs through of prestressing force hinge line stretched out and was fixed in corresponding pier top crossbeam.
2. The corrugated steel web combination box girder structure based on arch structure stress as claimed in claim 1, wherein the precast concrete slabs are provided with a plurality of prestressed holes penetrating through the precast concrete slabs in the bridge direction, the prestressed holes of adjacent precast concrete slabs are in one-to-one correspondence, each corresponding prestressed hole is connected with each other to form a steel strand channel, the prestressed steel strand is arranged in the steel strand channel, both ends of the prestressed steel strand extend through the steel strand channel and are anchored on the corresponding pier top beams, and cement mortar is poured into the prestressed hole and the prestressed steel strand gap.
3. The arched structure stress-based corrugated steel web composite box girder structure of claim 2, wherein at least one drawstring is installed on the concrete bottom plate, and each concrete bottom plate is detachably connected with the drawstring.
4. An arch stress based corrugated steel web composite box girder structure according to claim 3, wherein the lower surface of the precast concrete slab in the bridge direction is longer than the upper surface.
5. The corrugated steel web combination box girder structure based on arch structure stress as claimed in claim 4, wherein a concrete shear key is arranged between the joints of the adjacent precast concrete plates, the concrete shear key can adopt a trapezoidal or rounded trapezoid cross section, and the height of the concrete shear key is more than 2 times of the maximum aggregate grain size of the concrete and less than 35 mm; the ratio of the height of the concrete shear key to the average width thereof was taken to be 1: 2.
6. The arched structure stress-based corrugated steel web combination box girder structure according to claim 5, wherein the connection ends of the pier top beam side parts corresponding to the precast concrete bottom plates are provided with inclined boundary planes perpendicular to the precast concrete bottom plate axis, and the beam side parts are provided with anchoring points corresponding to the prestressed steel strands.
7. The arched structure stress-based corrugated steel web combined box girder structure of claim 6, wherein the precast concrete slab is of a reinforced concrete structure, the corrugated steel webs with a certain height are pre-embedded in the left side and the right side of the precast concrete slab, and the distance between the bottom surface of the pier top beam and the lowest point of the precast concrete bottom plate is not less than 0.5 m.
8. The corrugated steel web combination box girder structure based on arch structure stress of claim 7, wherein the precast concrete slabs comprise a plurality of precast side-by-side concrete bottom plates which are sequentially connected from left to right, the precast side-by-side concrete bottom plates which are adjacent from front to back are connected through a prestressed steel hinge line to form side-by-side concrete bottom plate ribs, the left and right adjacent side-by-side concrete bottom plate ribs are connected through transverse prestress or wet joints, and are sequentially connected along a transverse bridge direction, and the corrugated steel webs are pre-buried at the outer sides of the side-by-side concrete bottom plate ribs on both sides.
CN202220243196.7U 2022-01-29 2022-01-29 Wave form steel web combination case girder construction based on arch structure atress Active CN216891925U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220243196.7U CN216891925U (en) 2022-01-29 2022-01-29 Wave form steel web combination case girder construction based on arch structure atress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220243196.7U CN216891925U (en) 2022-01-29 2022-01-29 Wave form steel web combination case girder construction based on arch structure atress

Publications (1)

Publication Number Publication Date
CN216891925U true CN216891925U (en) 2022-07-05

Family

ID=82182299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220243196.7U Active CN216891925U (en) 2022-01-29 2022-01-29 Wave form steel web combination case girder construction based on arch structure atress

Country Status (1)

Country Link
CN (1) CN216891925U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114411523A (en) * 2022-01-29 2022-04-29 福州大学 Corrugated steel web composite box girder structure based on the stress of arch structure and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114411523A (en) * 2022-01-29 2022-04-29 福州大学 Corrugated steel web composite box girder structure based on the stress of arch structure and its construction method

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN105002816B (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN114892552B (en) Box girder type bridge reconstruction construction method
CN111364350A (en) A light-weight steel-concrete composite cover beam with quick installation of large cantilever arm
CN104762871A (en) Prestressed concrete-steel tank beam bond beam continuous beam bridge
CN105064196B (en) The fish belly I-shaped combination of prestressing force steel reinforced concrete simply supported girder bridge and its construction method of precast assembly
CN105064200B (en) Prefabricated and assembled fish-belly truss prestressed steel-concrete composite simply supported beam bridge and its construction method
CN110792164B (en) A kind of horizontal assembly device and assembly method of prefabricated shear wall
CN110924287A (en) Semi-fabricated large-span combined box girder and construction method thereof
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
CN111877129B (en) Arch ring construction method of continuous arch bridge
CN105735099B (en) Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing
CN216891925U (en) Wave form steel web combination case girder construction based on arch structure atress
CN103556564B (en) A kind of assembled slab bridge based on the connection of steel diaphragm plate and construction method thereof
CN113789711A (en) An NC-UHPC combined prestressed concrete box girder, construction method and bridge thereof
CN108411801A (en) One kind reinforcing the old hollow slab bridge construction of single hole and construction method by real abdomen Bars In Poured Concrete Slab
CN113494055A (en) Double-locking structure for closure section of long-span bridge and construction method
CN209114299U (en) A single box multi-chamber box girder bridge
CN117248438A (en) Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof
CN114411523B (en) Corrugated steel web plate combined box girder structure based on arch structure stress and construction method thereof
CN216616865U (en) High-efficient construction system of super high-rise structure of encorbelmenting
CN107142830B (en) Steel pipe web prestress steel-concrete combined girder structure and construction method
CN1186509C (en) Post-stretching prestressed concrete arch bar roof and its construction method
CN114263094A (en) Longitudinally segmented steel concrete mixed prefabricated small box girder bridge and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant