CN105002816B - Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method - Google Patents
Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method Download PDFInfo
- Publication number
- CN105002816B CN105002816B CN201510454134.5A CN201510454134A CN105002816B CN 105002816 B CN105002816 B CN 105002816B CN 201510454134 A CN201510454134 A CN 201510454134A CN 105002816 B CN105002816 B CN 105002816B
- Authority
- CN
- China
- Prior art keywords
- concrete
- steel
- lower flange
- plate
- ladle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明属于交通运输桥涵工程领域,尤其涉及一种预制拼装的鱼腹工字型预应力钢混组合连续梁桥及施工方法。The invention belongs to the field of transportation bridge and culvert engineering, in particular to a prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous beam bridge and a construction method.
背景技术Background technique
随着立体交通基础设施的发展,在密集人口区域城市桥梁施工、高速公路跨线或跨海大桥施工时,面临着桥梁的快速施工问题,对施工安全性要求高、施工周期要求短,并需要改善钢混组合梁连续梁桥负弯矩区处于混凝土桥面板受拉、钢梁受压的不利状态,以大幅提升连续梁桥混凝土桥面板及钢主梁的耐久性。With the development of three-dimensional transportation infrastructure, in the construction of urban bridges in densely populated areas, expressway cross-lines or sea-crossing bridges, they are faced with the problem of rapid construction of bridges, which require high construction safety and short construction periods. Improve the negative moment zone of continuous girder bridges with steel-concrete composite girders in the unfavorable state where the concrete deck is under tension and the steel girder is under compression, so as to greatly improve the durability of the concrete deck and steel girders of continuous girder bridges.
发明内容Contents of the invention
本发明要解决的技术问题是提出一种跨越能力大、可快速预制拼装、避免负弯矩区桥面板开裂、避免钢混组合梁体外预应力索应用的预制拼装的鱼腹工字型预应力钢混组合连续梁桥。The technical problem to be solved by the present invention is to propose a prefabricated and assembled fish-belly I-shaped prestressed cable with large spanning capacity, rapid prefabricated assembly, avoiding bridge deck cracking in the negative bending moment area, and avoiding the application of external prestressed cables for steel-concrete composite beams. Steel-concrete composite continuous girder bridge.
为解决上述技术问题,本发明采用以下技术方案:预制拼装的鱼腹工字型预应力钢混组合连续梁桥,采用预制鱼腹工字型梁和预制混凝土桥面板,在鱼腹工字型梁在负弯矩区下翼缘采用钢箱-混凝土组合结构,在正弯矩区下翼缘采用钢包混凝土构件,在下翼缘的钢包混凝土构件的混凝土中张拉预应力。In order to solve the above technical problems, the present invention adopts the following technical solutions: the prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge adopts prefabricated fish-belly I-shaped beams and prefabricated concrete bridge decks, and the fish-belly I-shaped The lower flange of the beam in the negative bending moment area adopts steel box-concrete composite structure, and the lower flange of the positive bending moment area adopts steel-clad concrete members, and the concrete of the steel-clad concrete members in the lower flange is tensioned and prestressed.
该钢混组合连续梁桥的跨中最大梁高与跨径之比控制在1/15-1/20之间,下翼缘鱼腹线型为悬链线或抛物线;该钢混组合连续梁桥的边支座截面高度与跨中最大高度之比控制在1/2-2/3之间,中支座截面高度与跨中截面最大高度之比控制在1.0-1.2之间。The ratio of the maximum mid-span girder height to the span of the steel-concrete composite continuous girder bridge is controlled between 1/15-1/20, and the fish belly line of the lower flange is a catenary or parabola; the steel-concrete composite continuous girder The ratio of the section height of side supports to the maximum mid-span height of the bridge is controlled between 1/2-2/3, and the ratio of the section height of mid-support to the maximum mid-span section height is controlled between 1.0-1.2.
上述预制拼装的鱼腹工字型预应力钢混组合连续梁桥的施工方法,包括以下步骤:The construction method of the above-mentioned prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge comprises the following steps:
<1>提前预制混凝土桥面板和预制鱼腹工字型板梁<1> Prefabricated concrete bridge deck and prefabricated fish-belly I-shaped slab girder
焊接加工预制单元的跨中下翼缘钢包混凝土构件的外包钢管板件,采用钢梁制梁台架预制边跨梁预制单元,将跨中下翼缘钢包混凝土构件、腹板、上翼缘板、横向加劲肋、纵向加劲肋、中支座竖向加劲肋、中支座下翼缘钢箱、靠近中支座下翼缘钢管、中支座上翼缘钢包混凝土箱体、边支座构件焊接成单个边跨工字型预制单元,每个预制单元包含两片工字边跨钢梁,工字梁之间采用空腹式横隔板相互连接;Welding and processing the outsourcing steel pipe plate of steel-clad concrete member of the middle span and lower flange of the prefabricated unit, the prefabricated side-span beam prefabricated unit is made of steel girder platform, and the steel-clad concrete member of the middle and lower flange of the span, the web, and the upper flange plate are prefabricated , transverse stiffeners, longitudinal stiffeners, vertical stiffeners in the middle support, steel boxes on the lower flange of the middle support, steel pipes near the lower flange of the middle support, steel-clad concrete boxes on the upper flange of the middle support, side support members Welded into a single side-span I-shaped prefabricated unit, each prefabricated unit contains two pieces of I-shaped side-span steel beams, and the I-beams are connected with each other by vierendeel diaphragms;
采用钢梁制梁台架预制中跨梁预制单元,将跨中下翼缘钢包混凝土构件、腹板、上翼缘板、横向加劲肋、中支座竖向加劲肋、中支座下翼缘钢管、支座上翼缘预应力箱体焊接成单个中跨工字型预制单元,每个预制单元包含两片工字中跨钢梁,工字梁之间采用空腹式横隔板相互连接;之后在下翼缘钢包混凝土构件内绑扎钢筋笼,在跨中下翼缘钢包混凝土构件内通长设置波纹管,波纹管穿过所有带孔横隔板,并分别固定于支座端的桥面板锚固区和跨中下翼缘钢包混凝土构件靠近支座的下表面锚固区处;之后焊接包板,安装混凝土斜模板,浇筑下翼缘内混凝土;中支座附近的下翼缘设置中支座下翼缘钢管构件,中支座靠近上翼缘设置钢包混凝土构件箱体,钢包混凝土构件箱体的钢包板内设置波纹管用以张拉负弯矩预应力筋;The prefabricated mid-span beam prefabricated unit is prefabricated by the steel girder platform, and the steel-clad concrete member, web plate, upper flange plate, transverse stiffener, middle support vertical stiffener, middle support lower flange The steel pipe and the prestressed box of the upper flange of the support are welded into a single mid-span I-shaped prefabricated unit. Each prefabricated unit contains two pieces of I-shaped mid-span steel beams, and the I-beams are connected with each other by hollow diaphragms; Afterwards, the reinforcement cage is bound in the steel-clad concrete member of the lower flange, and the bellows are installed in the steel-clad concrete member of the lower flange of the mid-span. and the steel-clad concrete member of the middle and lower flange of the middle span is close to the anchorage area of the lower surface of the support; after that, the cladding plate is welded, the concrete inclined formwork is installed, and the inner concrete of the lower flange is poured; the lower flange of the middle support is provided with the lower wing of the middle support The edge steel pipe member, the steel-clad concrete member box is arranged near the upper flange of the middle support, and the bellows are arranged in the steel-clad plate of the steel-clad concrete member box to tension the negative moment prestressed tendon;
<2>现场吊装<2>On-site hoisting
在混凝土养护后,将鱼腹工字型梁预制单元运输到施工现场并定位吊装;两个边跨预制单元之间,采用空腹式横隔板横向连接,单片工字中跨钢梁之间的上、下翼缘设置十字交叉斜撑;相邻跨吊装完成后,焊接相邻跨支座焊缝,再灌注负弯矩区下翼缘钢管、钢箱内混凝土,形成支座钢管混凝土、钢箱混凝土组合构件,浇筑支座区预应力锚固混凝土与负弯矩区上翼缘钢包板内混凝土,混凝土养护完成后,吊装跨中预制混凝土桥面板,浇筑桥面板湿接缝混凝土;After the concrete is cured, the fish-belly I-beam prefabricated unit is transported to the construction site and positioned and hoisted; between the two side-span prefabricated units, the hollow diaphragm is used to connect horizontally, and the single-piece I-shaped mid-span steel beam The upper and lower flanges of the upper and lower flanges are provided with cross braces; after the hoisting of adjacent spans is completed, the weld seams of adjacent span supports are welded, and then the steel pipes of the lower flanges in the negative bending moment area and the concrete in the steel box are poured to form concrete filled steel tubes for the supports. For steel box concrete composite components, pour the prestressed anchor concrete in the support area and the concrete in the upper flange steel clad plate in the negative bending moment area. After the concrete curing is completed, lift the mid-span precast concrete bridge deck and pour the bridge deck wet joint concrete;
<3>张拉预应力<3> Tensile prestress
混凝土养护后,张拉跨中下翼缘钢包混凝土构件内预应力束,之后张拉负弯矩区上翼缘预应力束,最后现浇负弯矩区混凝土桥面板,形成预制拼装的鱼腹工字型预应力钢混组合连续梁桥。After the concrete is cured, the prestressed beams in the steel-clad concrete members of the middle and lower flanges of the span are stretched, then the prestressed beams of the upper flange in the negative moment area are stretched, and finally the concrete bridge deck in the negative moment area is cast in place to form a prefabricated fish belly I-shaped prestressed steel-concrete composite continuous girder bridge.
预制混凝土桥面板的吊装龄期在180天以上,混凝土桥面板采用预留现浇孔并在现浇孔内预留钢筋,吊装时通过现浇连接上翼缘集束式剪力钉与孔内预留钢筋连接;桥面板的横向湿接缝采用速凝微膨胀混凝土,纵向湿接缝采用速凝混凝土。The hoisting age of the precast concrete bridge deck is more than 180 days. The concrete bridge deck adopts reserved cast-in-place holes and reserved steel bars in the cast-in-place holes. Rebar connections are reserved; quick-setting micro-expansion concrete is used for the transverse wet joints of the bridge deck, and quick-setting concrete is used for the longitudinal wet joints.
下翼缘钢包混凝土构件与腹板焊接在一起,在腹板的各横向加劲肋位置下部的下翼缘钢包混凝土构件内焊接开洞横隔板,在下翼缘钢包混凝土构件的腹板、底板和包板上布置剪力钉,下翼缘钢包混凝土构件内的混凝土在整个预制单元拼接完成后再进行现浇;下翼缘钢包混凝土构件内的混凝土采用细粒连续级配抗裂混凝土;跨中下翼缘钢包混凝土构件内的预应力筋部分锚固在桥面板锚固区处,部分锚固在跨中下翼缘钢包混凝土构件靠近支座的下表面锚固区处。The steel-clad concrete member of the lower flange is welded with the web, and the open diaphragm is welded in the steel-clad concrete member of the lower flange at the lower part of each transverse stiffener of the web, and the web, bottom plate and Shear studs are arranged on clad slabs, and the concrete in the steel-clad concrete components of the lower flange is poured after the entire prefabricated unit is spliced; the concrete in the steel-clad concrete components of the lower flange is made of fine-grained continuous graded crack-resistant concrete; The prestressed tendons in the steel-clad concrete member of the lower flange are partly anchored at the anchorage area of the bridge deck, and partly anchored at the anchorage area of the lower surface of the steel-clad concrete member of the lower flange of the mid-span near the support.
负弯矩区支座部位的钢板箱体由下翼缘钢箱外侧板、隔板、支座下翼缘板及腹板构成无顶板的开放式箱体,箱体内表面均匀布置剪力钉;在钢梁吊装、相邻梁段焊接后,在开放箱体内浇筑混凝土;靠近支座部位的倾斜钢板箱体由外侧板、顶板、靠近支座下翼缘板、腹板构成封闭箱体,箱体的上部预留浇筑孔,封闭箱体内均匀布置剪力钉;在钢梁吊装、相邻梁段焊接后,在封闭箱体内灌注混凝土。The steel plate box at the support part in the negative bending moment area is composed of the outer plate of the lower flange steel box, the partition plate, the lower flange plate of the support and the web to form an open box without a roof, and the inner surface of the box is uniformly arranged with shear studs; After the steel girders are hoisted and the adjacent beam sections are welded, concrete is poured in the open box; the inclined steel box near the support is composed of an outer plate, a top plate, a lower flange plate near the support, and a web to form a closed box. The pouring holes are reserved in the upper part of the body, and the shear nails are evenly arranged in the closed box; after the steel beams are hoisted and the adjacent beam sections are welded, concrete is poured in the closed box.
负弯矩上翼缘钢包混凝土构件由负弯矩区上翼缘钢包板、负弯矩区上翼缘钢包板内混凝土组成,内预留波纹管。The negative moment upper flange steel clad concrete member is composed of the upper flange steel clad plate in the negative bending moment area and the concrete inside the upper flange steel clad plate in the negative bending moment area, and the bellows are reserved inside.
上翼缘上表面采用长、短两种剪力钉布置方式,短剪力钉为均布式,短剪力钉的长度为5-10cm;长剪力钉为集束式,长度为20-25cm;负弯矩区域上翼缘表面沿纵向每单位长度剪力钉布置剪切刚度为跨中的1/2-1/4,负弯矩区域范围取为中支点向左右各1/8的跨径长度。Long and short shear studs are arranged on the upper surface of the upper flange. The short shear studs are uniformly distributed, and the length of the short shear studs is 5-10cm; the long shear studs are clustered, and the length is 20-25cm. ; The shearing stiffness of shear studs per unit length of the upper flange surface in the negative bending moment area along the longitudinal direction is 1/2-1/4 of the mid-span, and the range of the negative bending moment area is taken as 1/8 of the span from the middle fulcrum to the left and right. diameter length.
空腹式横隔板由横向上弦杆、横隔下弦杆、横隔斜杆组成,各杆件之间采用节点板连接。The hollow-type diaphragm is composed of a transverse upper chord, a diaphragm lower chord, and a transverse diaphragm, and the members are connected by gusset plates.
边支座、中支座横隔板采用空腹式横隔板,其杆件截面面积为跨中空腹式横隔板相应杆件面积的5倍以上;相邻两片工字边跨梁的边支座构件下翼缘之间布置交叉斜撑;中支座竖向加劲肋与支座部位的钢板箱体隔板对焊连接。The diaphragm of the side support and the middle support adopts the hollow diaphragm, and the cross-sectional area of the rod is more than 5 times the area of the corresponding rod of the mid-span hollow diaphragm; the sides of two adjacent I-shaped side span beams Cross braces are arranged between the lower flanges of the support members; the vertical stiffeners of the middle support are butt-welded with the steel plate box partitions at the support.
为满足城市立体交通、高速公路跨线施工与跨海大桥施工的严格要求,发明人设计了一种预制拼装的鱼腹工字型预应力钢混组合连续梁桥,采用预制鱼腹工字型梁和预制混凝土桥面板,在鱼腹工字型梁在负弯矩区下翼缘采用钢箱-混凝土组合结构,在正弯矩区下翼缘采用钢包混凝土构件,在下翼缘的钢包混凝土构件的混凝土中张拉预应力。采用该结构大幅提高了梁体的刚度与抗弯能力,并避免了预应力钢筋的空气暴露,负弯矩区域设置的下翼缘钢管混凝土与负弯矩区域的上翼缘体内预应力筋以及负弯矩区桥面板连接剪力钉合理的布置,大幅提高了梁体的耐久性与可靠性。据此,发明人还建立了相应的施工方法,采用该法施工安全、优质、方便、快捷。In order to meet the strict requirements of urban three-dimensional traffic, expressway cross-line construction and sea-crossing bridge construction, the inventor designed a prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge, which adopts prefabricated fish-belly I-shaped Beam and prefabricated concrete bridge deck, steel box-concrete composite structure is used for the lower flange of the fish-belly I-beam in the negative moment area, steel-clad concrete members are used for the lower flange of the positive bending moment area, and steel-clad concrete members are used for the lower flange Tensile prestress in concrete. The use of this structure greatly improves the stiffness and bending resistance of the beam body, and avoids the air exposure of the prestressed steel bars. The rational arrangement of the shear studs connected to the bridge deck in the negative moment zone greatly improves the durability and reliability of the beam. Accordingly, the inventor has also established a corresponding construction method, which is safe, high-quality, convenient and quick to use.
附图说明Description of drawings
图1是应用本发明的8跨连续钢混组合梁桥立面布置图。Fig. 1 is the facade arrangement diagram of the 8-span continuous steel-concrete composite girder bridge applying the present invention.
图2是本发明连续钢混组合梁桥中一个边跨与半个中跨的立面布置详图。Fig. 2 is a detailed diagram of the facade layout of one side span and half of the middle span in the continuous steel-concrete composite girder bridge of the present invention.
图3是本发明预制拼装的鱼腹工字型预应力钢混组合连续梁桥中预制混凝土桥面板的平面布置图。Fig. 3 is a plane layout diagram of the prefabricated concrete bridge deck in the prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge of the present invention.
图4是图2预制桥面板中单块预制桥面板示意图。Fig. 4 is a schematic diagram of a single prefabricated bridge deck in the prefabricated bridge deck in Fig. 2 .
图5是上翼缘承托混凝土横截面示意图。Fig. 5 is a schematic cross-sectional view of the supporting concrete of the upper flange.
图6是一个边(中)跨预制单元横截面图。Fig. 6 is a cross-sectional view of a side (middle) span prefabricated unit.
图7是中支座立面布置详图。Figure 7 is a detailed diagram of the elevation layout of the middle support.
图8是图2及图6中主梁各横截面布置详图。Fig. 8 is a detailed diagram of cross-sectional layout of main beams in Fig. 2 and Fig. 6 .
图9是边支座立面布置与边支座下翼缘斜撑布置详图。Fig. 9 is a detailed diagram of the vertical arrangement of the side support and the arrangement of the diagonal bracing of the lower flange of the side support.
图10是图1中8跨连续钢混组合梁桥的下翼缘钢包混凝土构件立体图。Fig. 10 is a perspective view of the steel-clad concrete member of the lower flange of the 8-span continuous steel-concrete composite girder bridge in Fig. 1 .
图11是图1中8跨连续钢混组合梁桥的主跨预制钢梁节段立体图。Fig. 11 is a perspective view of the prefabricated steel girder section of the main span of the 8-span continuous steel-concrete composite girder bridge in Fig. 1 .
图12是图1中8跨连续钢混组合梁桥的边跨单片预制板梁立体图。Fig. 12 is a perspective view of the side-span single-piece prefabricated slab girder of the 8-span continuous steel-concrete composite girder bridge in Fig. 1 .
图13是图1中8跨连续钢混组合梁桥的中跨单片预制板梁立体图。Fig. 13 is a perspective view of the mid-span single-piece prefabricated slab girder of the 8-span continuous steel-concrete composite girder bridge in Fig. 1 .
图14是图1中8跨连续钢混组合梁桥的吊装及相邻跨焊接后中支座局部立体图。Fig. 14 is a partial perspective view of the hoisting of the 8-span continuous steel-concrete composite girder bridge in Fig. 1 and the middle support of adjacent spans after welding.
图中:1预制混凝土桥面板,1a预制桥面板预留现浇孔,1b预制桥面板预留孔内钢筋,1c预制桥面板湿接缝钢筋,2下翼缘钢包混凝土构件,2a下翼缘钢包混凝土构件开洞横隔板,2b下翼缘钢包混凝土构件包板,2c下翼缘钢包混凝土构件内混凝土,2d下翼缘钢包混凝土构件内腹板,2e下翼缘钢包混凝土构件底板,2f下翼缘钢包混凝土构件内表面剪力钉,2g下翼缘钢包混凝土构件顶板,3边跨梁预制单元,4钢梁腹板,5钢梁上翼缘板,6横向加劲肋,6a纵向加劲肋,7中支座竖向加劲肋,8中支座下翼缘钢箱,8a下翼缘钢箱外侧板,8b下翼缘钢箱隔板,8c支座下翼缘板,8d钢箱内均布剪力钉,9中支座上翼缘钢包混凝土箱体,9a中支座上翼缘钢包混凝土箱体钢包板,10边支座构件,10a边支座纵向加劲肋,10b边支座的支座加劲肋,10c边支座竖向加劲肋,10d边支座构件下翼缘板,10e边支座构件端斜板,10f边支座构件腹板,11单片工字边跨钢梁,12跨中空腹式横隔板,12a跨中横向上弦杆,12b跨中横向斜杆,12c跨中横向下弦杆,12d跨中空腹式横隔板节点板,13中跨梁预制单元,14单片工字中跨钢梁,15下翼缘钢包混凝土构件内的通长波纹管,16桥面板锚固区,17下翼缘钢包混凝土构件靠近支座的下表面锚固区,18中支座上翼缘钢包混凝土箱体内设置的波纹管,19负弯矩预应力筋,20上、下翼缘十字交叉斜撑,21相邻跨支座焊缝,22负弯矩区下翼缘钢管、钢箱内混凝土,22a钢管内混凝土,22b钢箱内混凝土,23支座预应力锚固区混凝土,24中支点上翼缘钢包板内的混凝土,25桥面板湿接缝,25a横向湿接缝,25b纵向湿接缝,26下翼缘钢包混凝土构件内预应力束,27负弯矩区桥面板,28上翼缘短剪力钉,29上翼缘预浇承托,30集束式长剪力钉,31靠近支座部位的下翼缘倾斜钢箱,31a靠近支座部位的下翼缘倾斜钢箱外侧板,31b靠近支座部位的下翼缘倾斜钢箱顶板,31c靠近支座部位的下翼缘板,32负弯矩预应力筋锚固区,33负弯矩预应力钢筋,34支座,35预制构件间的小纵梁,36支座空腹式横隔板,36a支座横向上弦杆,36b支座横向斜杆,36c支座横向下弦杆,36d支座空腹式横隔板节点板,37边支座下翼缘交叉支撑,38边支座锚固区混凝土,39边支座下翼缘横撑。In the figure: 1 prefabricated concrete bridge deck, 1a reserved cast-in-place holes for prefabricated bridge deck, 1b steel bars in reserved holes for prefabricated bridge deck, 1c prefabricated bridge deck wet joint reinforcement, 2 lower flange steel-clad concrete components, 2a lower flange Opening diaphragm of steel-clad concrete member, 2b cladding plate of steel-clad concrete member of lower flange, 2c inner concrete of steel-clad concrete member of lower flange, 2d inner web of steel-clad concrete member of lower flange, 2e bottom plate of steel-clad concrete member of lower flange, 2f Shear nails on the inner surface of the lower flange steel-clad concrete member, 2g top plate of the lower flange steel-clad concrete member, 3 side span beam prefabricated units, 4 steel beam webs, 5 steel beam upper flange plates, 6 transverse stiffeners, 6a longitudinal stiffeners, 7 vertical stiffeners for the support, 8 the lower flange steel box for the middle support, 8a the outer panel of the lower flange steel box, 8b the lower flange steel box partition, 8c the lower flange plate for the support, 8d the inner steel box Cloth shear nails, steel-clad concrete box with flange on middle support in 9, steel-clad steel clad plate in steel-clad concrete box with flange on middle support in 9a, member on side support on 10, longitudinal stiffener on side support on 10a, and steel clad plate on side support on 10b Support stiffener, 10c side support vertical stiffener, 10d side support member lower flange plate, 10e side support member end slant plate, 10f side support member web, 11 single-piece I-shaped side-span steel beam , 12-span hollow diaphragm, 12a mid-span transverse upper chord, 12b mid-span transverse oblique member, 12c mid-span transverse lower chord, 12d mid-span hollow diaphragm gusset plate, 13 mid-span beam prefabricated unit, 14 Single-piece I-shaped mid-span steel girder, 15 full-length bellows in the steel-clad concrete member of the lower flange, 16 anchorage area of the bridge deck, 17 anchorage area of the lower surface of the steel-clad concrete member of the lower flange near the support, 18 on the support The bellows installed in the flange steel-clad concrete box, 19 negative bending moment prestressed tendons, 20 upper and lower flange cross braces, 21 adjacent span support welds, 22 negative bending moment area lower flange steel pipe, steel Concrete in the box, 22a Concrete in the steel pipe, 22b Concrete in the steel box, 23 Concrete in the prestressed anchorage area of the support, 24 Concrete in the steel clad plate of the upper flange of the middle fulcrum, 25 Bridge deck wet joints, 25a Transverse wet joints, 25b Longitudinal wet joints, 26 inner prestressed beams of steel-clad concrete members on the lower flange, 27 bridge decks in the negative moment zone, 28 short shear studs on the upper flange, 29 precast support on the upper flange, and 30 clustered long shear studs , 31 The lower flange inclined steel box near the support, 31a The lower flange inclined steel box outer plate near the support, 31b The lower flange inclined steel box roof near the support, 31c The lower flange near the support Flange plate, 32 negative moment prestressed tendon anchorage area, 33 negative moment prestressed steel bar, 34 support, 35 small longitudinal beam between prefabricated components, 36 support vierendeel diaphragm, 36a support transverse upper chord , 36b support transverse oblique rod, 36c support horizontal lower chord, 36d support vierendeel diaphragm gusset plate, 37 side support lower flange cross bracing, 38 side support anchorage area concrete, 39 side support lower wing Edge brace.
具体实施方式detailed description
一、预制拼装的鱼腹工字型预应力钢混组合连续梁桥的基本结构1. The basic structure of prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge
采用预制鱼腹工字型梁和预制混凝土桥面板,在鱼腹工字型梁在负弯矩区下翼缘采用钢箱-混凝土组合结构,在正弯矩区下翼缘采用钢包混凝土构件,在下翼缘的钢包混凝土构件的混凝土中张拉预应力。其跨中最大梁高与跨径之比控制在1/15-1/20之间,下翼缘鱼腹线型为悬链线或抛物线;过小跨高比会导致梁的不经济,本发明提供的结构受力方案是梁与预应力束、下翼缘钢板共同承受恒载;其边支座截面高度与跨中最大高度之比控制在1/2-2/3之间,靠近边支座区域腹板沿主梁的长度控制根据主梁的设计剪力确定,中支座截面高度与跨中截面最大高度之比控制在1.0-1.2之间。支座附近的剪力应满足:Prefabricated fish-belly I-beams and prefabricated concrete bridge decks are used. The lower flange of the fish-belly I-beam in the negative moment area adopts a steel box-concrete composite structure, and the lower flange in the positive bending moment area adopts steel-clad concrete members. Tensile prestressing in the concrete of the ladle concrete member of the lower flange. The ratio of the maximum beam height to the span in the span is controlled between 1/15-1/20, and the fish belly line of the lower flange is a catenary or parabola; if the span-height ratio is too small, the beam will be uneconomical. The structural stress scheme provided by the invention is that the beam, the prestressed beam, and the lower flange steel plate jointly bear the dead load; The length control of the web in the support area along the main girder is determined according to the design shear force of the main girder, and the ratio of the section height of the middle support to the maximum height of the mid-span section is controlled between 1.0 and 1.2. The shear force near the support should satisfy:
V≤tfhffv+0.75Agfgtanθ+AsfstanθV≤t f h f f v +0.75A g f g tanθ+A s f s tanθ
式中,V为设计剪力,tf为腹板厚度,hf_为腹板高度,fv为腹板抗剪强度设计值,Ag为钢绞线总面积,fg为钢绞线抗拉强度设计值,θ为钢绞线或钢包混凝土翼缘与水平方向夹角,As为钢包翼缘钢材面积,fs为钢包翼缘钢材抗拉强度设计值。In the formula, V is the design shear force, tf is the thickness of the web, hf_ is the height of the web, fv is the design value of the shear strength of the web, Ag is the total area of the steel strand, and fg is the design value of the tensile strength of the steel strand , θ is the angle between the steel strand or the concrete flange of the ladle and the horizontal direction, As is the steel area of the ladle flange, and fs is the design value of the tensile strength of the steel of the ladle flange.
二、预制拼装的鱼腹工字型预应力钢混组合连续梁桥的施工方法2. Construction method of prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge
<1>提前预制混凝土桥面板和预制鱼腹工字型板梁<1> Prefabricated concrete bridge deck and prefabricated fish-belly I-shaped slab girder
预制混凝土桥面板1的吊装龄期在180天以上,混凝土桥面板1采用预留现浇孔1a并在现浇孔内预留钢筋1b,吊装时通过现浇连接上翼缘集束式剪力钉30与孔内预留钢筋1b连接;桥面板的横向湿接缝25a采用速凝微膨胀混凝土以防止湿接缝开裂,纵向湿接缝25b采用速凝混凝土。The hoisting age of the precast concrete bridge deck 1 is more than 180 days. The concrete bridge deck 1 adopts the reserved cast-in-place hole 1a and the steel bar 1b in the cast-in-place hole. 30 is connected with the reserved steel bar 1b in the hole; the transverse wet joint 25a of the bridge deck is made of quick-setting micro-expansion concrete to prevent cracking of the wet joint, and the longitudinal wet joint 25b is made of quick-setting concrete.
焊接加工预制单元的跨中下翼缘钢包混凝土构件2的外包钢管板件,采用钢梁制梁台架预制边跨梁预制单元3,将跨中下翼缘钢包混凝土构件2、腹板4、上翼缘板5、横向加劲肋6、纵向加劲肋6a、中支座竖向加劲肋7、中支座下翼缘钢箱8、靠近中支座下翼缘钢管31、中支座上翼缘钢包混凝土箱体9、边支座构件10焊接成单个边跨工字型预制单元3,每个预制单元3包含两片工字边跨钢梁11,工字梁之间采用空腹式横隔板12相互连接;The outsourcing steel pipe plate of steel-clad concrete member 2 of middle span and lower flange of the prefabricated unit is prefabricated by steel girder girder frame prefabricated side span beam prefabricated unit 3, and steel clad concrete member 2 of middle span and lower flange, web 4, Upper flange plate 5, transverse stiffener 6, longitudinal stiffener 6a, middle support vertical stiffener 7, middle support lower flange steel box 8, middle support lower flange steel pipe 31, middle support upper wing The edge steel-clad concrete box 9 and the side support members 10 are welded into a single side-span I-shaped prefabricated unit 3, each prefabricated unit 3 includes two pieces of I-shaped side-span steel beams 11, and the hollow-type transverse partitions are used between the I-beams the plates 12 are interconnected;
采用钢梁制梁台架预制中跨梁预制单元13,将跨中下翼缘钢包混凝土构件2、腹板4、上翼缘板5、横向加劲肋6、中支座竖向加劲肋7、中支座下翼缘钢管8、支座上翼缘预应力箱体9焊接成单个中跨工字型预制单元13,每个预制单元13包含两片工字中跨钢梁14,工字梁之间采用空腹式横隔板12相互连接;之后在下翼缘钢包混凝土构件2内绑扎钢筋笼,在跨中下翼缘钢包混凝土构件2内通长设置波纹管15,波纹管15穿过所有带孔横隔板2a,并分别固定于支座端的桥面板锚固区16和跨中下翼缘钢包混凝土构件2靠近支座的下表面锚固区17处;之后焊接包板2b,安装混凝土斜模板,浇筑下翼缘内混凝土2c;中支座附近的下翼缘设置中支座下翼缘钢管构件8,中支座靠近上翼缘设置钢包混凝土构件箱体9,钢包混凝土构件箱体的钢包板内设置波纹管18用以张拉负弯矩预应力筋19;The prefabricated mid-span beam prefabricated unit 13 is prefabricated by a steel girder platform, and the steel-clad concrete member 2 of the mid-span lower flange, the web plate 4, the upper flange plate 5, the transverse stiffener 6, the vertical stiffener 7 of the middle support, The lower flange steel pipe 8 of the middle support and the prestressed box body 9 of the upper flange of the support are welded into a single mid-span I-shaped prefabricated unit 13, each prefabricated unit 13 includes two pieces of I-shaped mid-span steel beams 14, and the I-shaped beam The hollow diaphragms 12 are used to connect with each other; after that, the reinforcement cage is bound in the steel-clad concrete member 2 of the lower flange, and the bellows 15 are set in the steel-clad concrete member 2 of the lower flange of the mid-span, and the bellows 15 pass through all belts Hole diaphragm 2a, and respectively fixed on the anchorage area 16 of the bridge deck at the end of the support and the anchorage area 17 of the lower surface of the steel-clad concrete member 2 of the lower flange of the mid-span near the support; after that, the cladding plate 2b is welded, and the concrete inclined formwork is installed. Concrete 2c is poured in the lower flange; the lower flange near the middle support is provided with the steel pipe member 8 of the lower flange of the middle support, and the steel-clad concrete member box 9 is arranged near the upper flange of the middle support, and the steel-clad plate of the steel-clad concrete member box Bellows 18 are arranged inside to tension the negative bending moment prestressed tendon 19;
其中,下翼缘钢包混凝土构件2与腹板4焊接在一起,在腹板的各横向加劲肋6位置下部的下翼缘钢包混凝土构件内焊接开洞横隔板2a,在下翼缘钢包混凝土构件的腹板2d、底板2e和包板2b上布置剪力钉包板2b先不焊上,下翼缘钢包混凝土构件内的混凝土2c在整个预制单元拼接完成后再进行现浇;下翼缘钢包混凝土构件内的混凝土2c采用细粒连续级配抗裂混凝土,细粒连续级配抗裂混凝土可以很好的包裹波纹管,防止裂纹的出现,提高内部预应力钢筋的耐久性;跨中下翼缘钢包混凝土构件内的预应力筋26部分锚固在桥面板锚固区23处,部分锚固在跨中下翼缘钢包混凝土构件2靠近支座的下表面锚固区17处。将预应力钢筋分开锚固可以减小各锚固区的应力集中问题;部分可锚固在相邻梁段的负弯矩钢筋锚固32处,如此可以使跨中下翼缘钢包混凝土内预应力筋26同时可承受部分支座负弯矩作用。Among them, the steel-clad concrete member 2 of the lower flange is welded together with the web 4, and the open diaphragm 2a is welded in the steel-clad concrete member of the lower flange at the lower part of each transverse stiffener 6 of the web, and the steel-clad concrete member of the lower flange Shear nails are arranged on the web 2d, bottom plate 2e and cladding plate 2b of the cladding plate 2b without welding, and the concrete 2c in the steel-clad concrete member of the lower flange is cast in-situ after the splicing of the entire prefabricated unit is completed; the ladle of the lower flange Concrete 2c in the concrete member adopts fine-grained continuous graded crack-resistant concrete, which can well wrap the bellows, prevent cracks, and improve the durability of internal prestressed steel bars; the mid-span and lower wings The prestressed tendons 26 in the edge steel-clad concrete member are partly anchored at the anchorage area 23 of the bridge deck, and partly anchored at the anchorage area 17 of the lower surface of the steel-clad concrete member 2 of the lower flange of the mid-span near the support. Separate anchoring of prestressed steel bars can reduce the stress concentration problem in each anchorage area; part of them can be anchored at 32 anchorages of negative moment steel bars in adjacent beam sections, so that the steel-clad concrete inner prestressed bars 26 of the middle and lower flanges of the span can be simultaneously It can withstand the negative bending moment of some supports.
负弯矩区支座部位的钢板箱体8由下翼缘钢箱外侧板8a、隔板8b、支座下翼缘板8c及腹板4构成无顶板的开放式箱体,箱体内表面均匀布置剪力钉8d;在钢梁吊装、相邻梁段焊接后,在开放箱体内浇筑混凝土22。由于支座部位为无顶板的开放式箱体,剪力钉可以起到连接混凝土与钢板、提高钢板稳定性及将部分内力传播到混凝土体22中的作用。靠近支座部位的倾斜钢板箱体31由外侧板31a、顶板31b、靠近支座下翼缘板31c、腹板4构成封闭箱体,箱体的上部预留浇筑孔31d,主要根据浇筑的密实性所需的浇筑孔空间考虑确定,封闭箱体内均匀布置剪力钉31e,以防止箱体板件的受压屈曲;在钢梁吊装、相邻梁段焊接后,在封闭箱体内灌注混凝土22。The steel plate box 8 at the support part in the negative bending moment area is composed of the outer plate 8a of the lower flange steel box, the partition plate 8b, the lower flange plate 8c of the support and the web 4 to form an open box without a roof, and the inner surface of the box is uniform Arrange shear studs 8d; pour concrete 22 in the open box after the steel beams are hoisted and adjacent beam sections are welded. Since the support part is an open box without a roof, the shear nail can play a role in connecting the concrete and the steel plate, improving the stability of the steel plate and transmitting part of the internal force to the concrete body 22 . The inclined steel plate box 31 close to the support is composed of an outer plate 31a, a top plate 31b, a lower flange plate 31c close to the support, and a web 4 to form a closed box. The space of the pouring hole required for the stability is considered and determined, and the shear nails 31e are evenly arranged in the closed box to prevent the buckling of the box plate; after the steel beam is hoisted and the adjacent beam sections are welded, pour concrete 22 .
负弯矩上翼缘钢包混凝土构件9由负弯矩区上翼缘钢包板9a、负弯矩区上翼缘钢包板内混凝土24组成,内预留波纹管9b,用以张拉负弯矩区预应力筋33。The negative moment upper flange steel clad concrete member 9 is composed of the upper flange steel clad plate 9a in the negative bending moment area and the inner concrete 24 in the upper flange steel clad plate in the negative bending moment area, and the bellows 9b is reserved inside for tensioning the negative bending moment Area prestressed tendons 33.
上翼缘上表面采用长、短两种剪力钉布置方式,短剪力钉28为均布式,短剪力钉的长度为5-10cm,用以现浇预制上翼缘板承托29;长剪力钉为集束式30,长度为20-25cm,根据预制桥面板预留现浇孔的位置分布,用以连接预制混凝土桥面板1。在上翼缘先预制钢-混组合翼缘可以防止吊装与施工过程中上翼缘可能发生的稳定性问题。负弯矩区域上翼缘表面沿纵向每单位长度剪力钉布置剪切刚度为跨中的1/2-1/4,负弯矩区域范围取为中支点向左右各1/8的跨径长度。负弯矩区剪力钉沿纵向的较低刚度布置可以减小负弯矩区混凝土桥面板参与主梁受力,有效减小负弯矩区混凝土的开裂。The upper surface of the upper flange adopts two arrangements of long and short shear studs. The short shear studs 28 are evenly distributed, and the length of the short shear studs is 5-10 cm, which are used to support the cast-in-place prefabricated upper flange plate 29 The long shear nails are cluster type 30 with a length of 20-25cm, and are used to connect the prefabricated concrete bridge deck 1 according to the position distribution of the reserved cast-in-place holes in the prefabricated bridge deck. Prefabricating the steel-concrete composite flange on the upper flange can prevent possible stability problems of the upper flange during hoisting and construction. The shear studs arranged on the surface of the upper flange in the negative bending moment area along the longitudinal direction per unit length have a shear stiffness of 1/2-1/4 of the mid-span, and the range of the negative bending moment area is taken as 1/8 of the span from the middle fulcrum to the left and right length. The lower rigidity arrangement of the shear studs in the negative moment zone along the longitudinal direction can reduce the participation of the concrete bridge deck in the negative moment zone in the stress of the main girder, and effectively reduce the cracking of the concrete in the negative moment zone.
边支座、中支座横隔板采用空腹式横隔板36,其杆件截面面积为跨中空腹式横隔板相应杆件面积的5倍以上;支座部位的空腹式横隔板需选用大刚度截面,以保证支座横向的扭转变形在规范容许范围内。相邻两片工字边跨梁11的边支座构件10下翼缘之间布置交叉斜撑37,以增大边支座各钢梁之间的整体性;中支座竖向加劲肋7与支座部位的钢板箱体隔板8b对焊连接。The diaphragm of the side support and the middle support adopts the hollow diaphragm 36, and the cross-sectional area of the bar is more than 5 times the area of the corresponding bar of the span hollow diaphragm; the hollow diaphragm of the support part needs A large rigidity section is selected to ensure that the lateral torsional deformation of the support is within the allowable range of the specification. Cross braces 37 are arranged between the lower flanges of the side support members 10 of two adjacent I-shaped side span beams 11 to increase the integrity between the steel beams of the side supports; the vertical stiffeners of the middle support 7 It is connected by butt welding with the steel plate box partition plate 8b at the support position.
<2>现场吊装<2>On-site hoisting
在混凝土养护28天后,将鱼腹工字型梁预制单元3、13运输到施工现场并定位吊装;两个边跨预制单元3之间,采用空腹式横隔板12横向连接,单片工字中跨钢梁14之间的上、下翼缘设置十字交叉斜撑20;相邻跨吊装完成后,焊接相邻跨支座焊缝21,再灌注负弯矩区下翼缘钢管、钢箱内混凝土22,形成支座钢管混凝土、钢箱混凝土组合构件,浇筑支座区预应力锚固混凝土23与负弯矩区上翼缘钢包板内混凝土24,混凝土养护完成后,吊装跨中预制混凝土桥面板1,浇筑桥面板湿接缝混凝土25;After 28 days of concrete curing, the prefabricated fish-belly I-beam units 3 and 13 were transported to the construction site and positioned and hoisted; between the two side-span prefabricated units 3, the hollow diaphragm 12 was used to connect horizontally, and the single-piece I-beam The upper and lower flanges between the mid-span steel girders 14 are provided with cross braces 20; after the hoisting of adjacent spans is completed, the welds 21 of adjacent span supports are welded, and then the lower flange steel pipes and steel boxes in the negative bending moment area are refilled. Inner concrete 22 is used to form the composite member of steel tube concrete and steel box concrete, and the prestressed anchor concrete 23 in the bearing area and the inner concrete 24 in the upper flange steel clad plate in the negative bending moment area are poured. After the concrete curing is completed, the mid-span precast concrete bridge is hoisted Panel 1, pouring bridge deck wet joint concrete 25;
空腹式横隔板12由横向上弦杆12a、横隔下弦杆12b、横隔斜杆12c组成,各杆件之间采用节点板12d连接。The hollow diaphragm 12 is composed of a transverse upper chord 12a, a transverse lower chord 12b, and a transverse diaphragm 12c, and each member is connected by a gusset plate 12d.
<3>张拉预应力<3> Tensile prestress
混凝土养护后,张拉跨中下翼缘钢包混凝土构件内预应力束26,之后张拉负弯矩区上翼缘预应力束19,最后现浇负弯矩区混凝土桥面板27,形成预制拼装的鱼腹工字型预应力钢混组合连续梁桥。After the concrete is cured, the internal prestressed beam 26 of the steel-clad concrete member at the middle and lower flange of the span is stretched, and then the prestressed beam 19 of the upper flange in the negative moment area is stretched, and finally the concrete bridge deck 27 in the negative moment area is cast in place to form a prefabricated assembly The fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge.
三、预制拼装的鱼腹工字型预应力钢混组合连续梁桥的应用3. Application of prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge
某海湾大桥主桥设计主跨跨径120m,8跨连续,桥面宽度为28m,业主要求上部结构迅速施工安装,缩短施工时间,减小施工风险,不影响航道通行,且桥梁的耐久性、桥面铺装性能需非常出色。而普通的钢-混组合梁桥或钢结构桥无论在成桥或吊装阶段中的受力、耐久性等方面都难以满足要求。本发明的预制拼装的鱼腹工字型预应力钢混组合连续梁桥刚度巨大结构轻盈,易于预制吊装,桥面板采用预制混凝土桥面板,铺装性能优良,预应力全部设置在钢包混凝土杆件内,自重轻,耐久性高,故采用本发明提出的桥梁设计方案。The main span of a bay bridge is designed to have a main span of 120m, 8 consecutive spans, and a bridge deck width of 28m. The owner requires rapid construction and installation of the superstructure, shortening the construction time, reducing construction risks, and not affecting the passage of the waterway. The durability of the bridge, The performance of the bridge deck pavement needs to be very good. However, ordinary steel-concrete composite girder bridges or steel structure bridges are difficult to meet the requirements in terms of force and durability in the bridge-building or hoisting stages. The prefabricated and assembled fish-belly I-shaped prestressed steel-concrete combined continuous girder bridge of the present invention has huge rigidity and light structure, and is easy to prefabricate and hoist. Inner, light in weight and high in durability, so the bridge design proposed by the present invention is adopted.
设计主跨为120m,采用8跨连续梁结构(图1、图2)。中跨跨中梁高6m,矢跨比设定为1/20,支座处梁高7.8m,预制桥面板选用30cm,承托高度为15cm,预制面板的平面尺寸为4m×15m(见图3和图4)。承托宽度与上翼缘宽度相同(图5),负弯矩区下翼缘混凝土钢箱最大高度为3.0m。负弯矩钢管与正弯矩区钢包混凝土下翼缘的交点距中支点距离为24m。采用4片钢主梁,分为2个预制单元(图6),两个预制单元之间设置小纵梁。中支座立面见图7,桥梁中支座及附近重要横截面见图8,边支座立面与边支座下翼缘斜撑布置见图9,下翼缘钢包混凝土预制构件立体图见图10,预制构件节段见图11,预制单片边、中跨鱼腹梁的立体图见图12-13,中支点部位的立体图见图14。The designed main span is 120m, adopting 8-span continuous beam structure (Fig. 1, Fig. 2). The mid-span girder height is 6m, the span ratio is set to 1/20, the girder height at the support is 7.8m, the prefabricated bridge deck is 30cm, the supporting height is 15cm, and the plane size of the prefabricated deck is 4m×15m (see Fig. 3 and Figure 4). The supporting width is the same as that of the upper flange (Fig. 5), and the maximum height of the concrete steel box of the lower flange in the negative bending moment area is 3.0m. The distance between the intersection point of the negative bending moment steel pipe and the lower flange of the steel-clad concrete in the positive bending moment area is 24m from the middle fulcrum. Four steel girders are used, which are divided into two prefabricated units (Figure 6), and small longitudinal beams are set between the two prefabricated units. See Figure 7 for the elevation of the middle support, Figure 8 for the important cross-sections of the middle support of the bridge and its vicinity, Figure 9 for the elevation of the side support and the arrangement of the diagonal bracing on the lower flange of the side support, and see Figure 10, see Figure 11 for the prefabricated component segment, see Figure 12-13 for the perspective view of the prefabricated single-piece side and mid-span fishbelly girder, and see Figure 14 for the perspective view of the middle fulcrum.
工程安排Engineering Arrangement
(1)在钢结构加工厂制作预制单元,加工厂应该靠近码头,便于梁段的船运;(1) Manufacture prefabricated units in the steel structure processing plant, the processing plant should be close to the wharf to facilitate the shipping of beam sections;
(2)钢结构焊接完成后,现浇预制单元的钢包混凝土下弦、靠近支座部位、承托的混凝土构件,并在构件内预留足够的波纹管;(2) After the welding of the steel structure is completed, the lower chord of the steel-clad concrete of the cast-in-place prefabricated unit, the concrete member near the support, and the supporting concrete member, and reserve enough bellows in the member;
(3)将预制构件船运至施工现场,采用大型浮吊一次吊装;(3) Ship the prefabricated components to the construction site and use a large floating crane for one-time hoisting;
(4)预制单元之间采用空腹式横隔板连接,工字钢梁之间还在上下翼缘处设置斜撑;(4) The prefabricated units are connected by hollow diaphragms, and diagonal braces are set at the upper and lower flanges between the I-beams;
(5)吊装预制桥面板,浇筑负弯矩区钢箱、钢管内混凝土;(5) Hoisting the prefabricated bridge deck, pouring the steel box and concrete inside the steel pipe in the negative moment area;
(6)混凝土养护完成后,张拉下翼缘钢包混凝土构件内的预应力筋,张拉负弯矩区上翼缘钢包混凝土构件内的预应力筋;(6) After the concrete curing is completed, stretch the prestressed tendons in the steel-clad concrete member of the lower flange, and stretch the prestressed tendons in the steel-clad concrete member of the upper flange in the negative bending moment area;
(7)浇筑负弯矩区桥面板;(7) Pouring the bridge deck in the negative moment zone;
采用本发明可在钢梁预制完成后在5-7天内将一跨主跨钢梁运输吊装完成,现场湿作业量小,运输吊装快速、安全,大幅降低了海上桥梁施工长时间、高风险作业量。Adopting the present invention can complete the transportation and hoisting of a main span steel girder within 5-7 days after the prefabrication of the steel girder is completed, the on-site wet work volume is small, the transportation and hoisting are fast and safe, and the long-term and high-risk operations of offshore bridge construction are greatly reduced quantity.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510454134.5A CN105002816B (en) | 2015-07-29 | 2015-07-29 | Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510454134.5A CN105002816B (en) | 2015-07-29 | 2015-07-29 | Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105002816A CN105002816A (en) | 2015-10-28 |
| CN105002816B true CN105002816B (en) | 2017-03-08 |
Family
ID=54375660
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510454134.5A Active CN105002816B (en) | 2015-07-29 | 2015-07-29 | Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105002816B (en) |
Families Citing this family (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105484147B (en) * | 2015-12-30 | 2017-06-20 | 中铁第四勘察设计院集团有限公司 | Steel case purlin composite continuous bridge and its construction method |
| CN105484148B (en) * | 2015-12-30 | 2017-06-20 | 中铁第四勘察设计院集团有限公司 | Part steel case purlin composite continuous bridge and its construction method |
| CN107841951B (en) * | 2017-09-28 | 2023-08-01 | 苏交科集团股份有限公司 | Preloading device for controlling pier top concrete cracks of steel-concrete composite girder bridge and construction method |
| CN108221634A (en) * | 2018-03-16 | 2018-06-29 | 中交高新科技产业发展有限公司 | The Wavelike steel webplate I-shaped composite beam bridge of maximum assembling |
| CN108221703B (en) * | 2018-03-21 | 2023-05-12 | 西安公路研究院有限公司 | A double-girder type I-beam-concrete composite beam for a bridge and its construction method |
| CN108221704B (en) * | 2018-03-21 | 2023-05-30 | 西安公路研究院有限公司 | Four-beam type I-steel-concrete composite beam for bridge and construction method |
| CN108560392A (en) * | 2018-03-22 | 2018-09-21 | 中交高新科技产业发展有限公司 | With prestressed setback type web combination beam |
| CN108221636B (en) * | 2018-03-28 | 2023-05-02 | 北京市市政工程设计研究总院有限公司 | Steel-concrete composite beam bridge constructed by adopting bracket-free scheme for midspan and bridge forming method |
| CN109722977A (en) * | 2019-01-31 | 2019-05-07 | 深圳市综合交通设计研究院有限公司 | A kind of Composite Steel-Concrete Bridges and its construction method with novel deck structrue |
| CN110067210B (en) * | 2019-06-12 | 2024-04-05 | 中交第四公路工程局有限公司 | Construction system and construction method for bridge flange plate |
| CN110409712B (en) * | 2019-07-22 | 2024-09-20 | 清华大学 | Prestressed composite material-ultra-high performance concrete composite beam |
| CN110924303B (en) * | 2019-11-19 | 2021-08-10 | 东北大学 | Steel beam and built-in steel reinforced concrete slab continuous combination beam and construction method |
| CN113073557B (en) * | 2021-03-19 | 2022-08-30 | 中铁大桥局集团第一工程有限公司 | Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge |
| CN113719152B (en) * | 2021-10-13 | 2022-11-01 | 西安建筑科技大学 | Steel member externally-wrapped prestressed precast concrete reinforced structure and construction method |
| CN115094741B (en) * | 2022-07-04 | 2025-08-12 | 中铁十局集团有限公司 | Prefabricated assembled fish belly I-shaped prestressed steel box continuous beam bridge |
| CN115094742B (en) * | 2022-08-15 | 2025-03-18 | 中机中联工程有限公司 | A truss bridge with spatial torsion shape and construction method thereof |
| CN117051693B (en) * | 2023-08-15 | 2025-10-28 | 安徽省交通规划设计研究总院股份有限公司 | A long-span steel plate composite beam and construction method for solving bridge deck cracking in negative bending moment areas |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN205188793U (en) * | 2015-07-29 | 2016-04-27 | 广西交通科学研究院 | Prefabricated fish belly I shape prestressing force steel and concrete composite continuous bridge of assembling |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS54160027A (en) * | 1978-06-08 | 1979-12-18 | P S Concrete | Suspension bridge in concrete and its constructing method |
| CN1100770A (en) * | 1993-09-25 | 1995-03-29 | 阿尔弗莱德·A·伊 | Large-span post-tensioned reinforced concrete truss and manufacturing method thereof |
| JP4336659B2 (en) * | 2005-01-27 | 2009-09-30 | 三井住友建設株式会社 | Construction method of upper-floor type suspension floor slab bridge |
| WO2011005009A2 (en) * | 2009-07-07 | 2011-01-13 | 주식회사 삼현피에프 | Upper part structure for a continuous bridge, which efficiently supports negative moment and has improved constructability, and method for constructing same |
| CN202466391U (en) * | 2012-02-10 | 2012-10-03 | 中铁第五勘察设计院集团有限公司 | Combined simple strut beam structure for inner prestressed steel pipe truss |
| CN104153284A (en) * | 2014-07-31 | 2014-11-19 | 桂林理工大学 | Partial filling type steel box concrete continuous composite girder bridge and construction method thereof |
-
2015
- 2015-07-29 CN CN201510454134.5A patent/CN105002816B/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN205188793U (en) * | 2015-07-29 | 2016-04-27 | 广西交通科学研究院 | Prefabricated fish belly I shape prestressing force steel and concrete composite continuous bridge of assembling |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105002816A (en) | 2015-10-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105002816B (en) | Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite continuous girder bridge and its construction method | |
| CN104929034B (en) | A kind of modularization steel reinforced concrete rapid construction small box girder bridge and its construction method | |
| CN106758856B (en) | The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block | |
| CN109958049B (en) | Modular steel-concrete combined small box girder simply-supported continuous bridge and construction method thereof | |
| CN105064196B (en) | The fish belly I-shaped combination of prestressing force steel reinforced concrete simply supported girder bridge and its construction method of precast assembly | |
| CN104762871A (en) | Prestressed concrete-steel tank beam bond beam continuous beam bridge | |
| CN114592436B (en) | Pier capping beam lower support system and construction method thereof | |
| CN105064195B (en) | The fish belly Wavelike steel webplate prestressing with bond steel reinforced concrete combination simply supported girder bridge and its construction method of precast assembly | |
| CN105839510A (en) | Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof | |
| CN104294748A (en) | Joint section structure for hybrid beam cable-stayed bridge and construction method thereof | |
| CN108060636B (en) | The construction method of overall assembled composite beam bridge | |
| CN104088221B (en) | A kind of T-shaped plate girder precast segment unit based on steel truss and combined bridge deck | |
| CN105064200B (en) | Prefabricated and assembled fish-belly truss prestressed steel-concrete composite simply supported beam bridge and its construction method | |
| CN104264575A (en) | Prestressed steel box concrete combination continuous beam bridge structure and construction technology | |
| CN205100082U (en) | Prefabricated assembled steel-concrete composite beam bridge | |
| CN110924287A (en) | A semi-fabricated large-span composite box girder and construction method thereof | |
| CN107326794A (en) | A kind of assembled integral prestress steel Combined concrete beam type bridge | |
| CN109024219A (en) | A kind of prefabricated ultra-high performance concrete-normal concrete composite beam bridge girder construction and construction method | |
| CN114457667A (en) | Large-span through-type open-hole web beam-arch combined rigid frame bridge and construction method thereof | |
| CN112962416A (en) | Steel plate girder bridge suitable for mountain area construction and construction method thereof | |
| CN106087711A (en) | Antinode work beam-steel concrete top board-external prestressing combines T-shaped simply supported beam | |
| CN205188793U (en) | Prefabricated fish belly I shape prestressing force steel and concrete composite continuous bridge of assembling | |
| CN106192726B (en) | A kind of V-arrangement web beam structure and its construction method | |
| CN105735099B (en) | Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing | |
| CN113789711B (en) | NC-UHPC combined assembled prestressed concrete box girder, construction method and bridge thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 530007 the Guangxi Zhuang Autonomous Region XiXiangTang Nanning high tech two Road No. 6 Patentee after: Guangxi Jiaoke Group Co.,Ltd. Address before: 530007 the Guangxi Zhuang Autonomous Region XiXiangTang Nanning high tech two Road No. 6 Patentee before: GUANGXI TRANSPORTATION RESEARCH & CONSULTING Co.,Ltd. |
|
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 530007 the Guangxi Zhuang Autonomous Region XiXiangTang Nanning high tech two Road No. 6 Patentee after: GUANGXI TRANSPORTATION RESEARCH & CONSULTING Co.,Ltd. Address before: 530007, No. two, No. 6, hi tech Zone, the Guangxi Zhuang Autonomous Region, Nanning Patentee before: GUANGXI TRANSPORTATION Research Institute |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20210429 Address after: 530001 4th floor, science and technology building, no.6, Gaoxin 2nd Road, Nanning, Guangxi Zhuang Autonomous Region Patentee after: Guangxi Jiaoke Engineering Consulting Co.,Ltd. Patentee after: Guangxi Jiaoke Group Co.,Ltd. Address before: 530007 the Guangxi Zhuang Autonomous Region XiXiangTang Nanning high tech two Road No. 6 Patentee before: Guangxi Jiaoke Group Co.,Ltd. |
|
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 7th, 8th, and 9th floors, Science and Technology Building, No. 6 Gaoxin 2nd Road, Nanning City, Guangxi Zhuang Autonomous Region 530007 Patentee after: Guangxi Jiaoke Engineering Construction Co.,Ltd. Country or region after: China Patentee after: Guangxi Jiaoke Group Co.,Ltd. Address before: 530001 4th floor, science and technology building, no.6, Gaoxin 2nd Road, Nanning, Guangxi Zhuang Autonomous Region Patentee before: Guangxi Jiaoke Engineering Consulting Co.,Ltd. Country or region before: China Patentee before: Guangxi Jiaoke Group Co.,Ltd. |