CN117248438A - Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof - Google Patents
Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof Download PDFInfo
- Publication number
- CN117248438A CN117248438A CN202311368782.XA CN202311368782A CN117248438A CN 117248438 A CN117248438 A CN 117248438A CN 202311368782 A CN202311368782 A CN 202311368782A CN 117248438 A CN117248438 A CN 117248438A
- Authority
- CN
- China
- Prior art keywords
- web
- uhpc
- steel
- butterfly
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种基于桁式结构形式的装配化UHPC腹板美兰拱构造及其施工方法,其中本发明基于桁式结构形式的装配化UHPC腹板美兰拱构造包括钢管混凝土弦管、UHPC蝶形腹板、横联钢管和腹板与弦管接头;位于上部的两根平行设置的钢管混凝土弦管之间间隔垂直固定连接有横联钢管,位于下部的两根平行设置的钢管混凝土弦管之间间隔垂直固定连接有横联钢管,在同一立面内位于上部的钢管混凝土弦管与位于下部的钢管混凝土弦管之间通过UHPC蝶形腹板进行连接,所述钢管混凝土弦管与UHPC蝶形腹板之间通过腹板与弦管接头进行连接,所述腹板与弦管接头由焊接在钢管混凝土弦管上的带孔钢板与UHPC蝶形腹板通过螺栓连接形成接头;与传统美兰拱构造形式相比,本申请结构构造新颖、力学性能良好、施工相对简便的装配化UHPC腹板美兰拱构造及其施工方法。
The present invention relates to an assembled UHPC web Meilan arch structure based on a truss structure and a construction method thereof. The assembled UHPC web Meilan arch structure based on a truss structure includes steel tube concrete chords, UHPC Butterfly web, cross-connected steel pipes and web-chord joints; the two parallel concrete-filled steel pipe chords at the upper part are connected vertically and vertically with a cross-connected steel pipe, and the two parallel concrete-filled steel pipe chords at the lower part are connected Horizontal steel pipes are vertically fixedly connected between the pipes. In the same facade, the upper concrete-filled steel pipe chords and the lower concrete-filled steel pipe chords are connected through UHPC butterfly webs. The concrete-filled steel pipe chords and The UHPC butterfly webs are connected through web and chord joints. The web and chord joints are formed by bolting the perforated steel plate welded on the steel tube concrete chord to the UHPC butterfly web; and Compared with the traditional Meilan arch structure form, this application has a novel structural structure, good mechanical properties, and relatively simple construction of an assembled UHPC web Meilan arch structure and its construction method.
Description
技术领域:Technical areas:
本发明涉及桥梁技术领域,是一种基于桁式结构形式的装配化UHPC腹板美兰拱构造及其施工方法The invention relates to the technical field of bridges and is an assembled UHPC web Meilan arch structure based on a truss structure and a construction method thereof.
背景技术:Background technique:
拱桥是一种古老的建筑结构,具有养护费用低、造型美观等优点,在我国应用颇广;目前,世界上最大的石拱桥(丹河大桥,2000年建成,主跨146m)、钢拱桥(重庆朝天门大桥,2009年建成,主跨552)、钢管混凝土拱桥(平南三桥,2020年建成,主跨575m)和美兰拱桥(北盘江特大桥,2016年建成,主跨445m)均在中国;这些拱桥的成功实践,为我国特大跨拱桥的建设积累了宝贵的经验,更使得我国拱桥建设技术处于世界引领地位。Arch bridge is an ancient architectural structure with the advantages of low maintenance cost and beautiful appearance. It is widely used in our country; currently, the world's largest stone arch bridge (Dan River Bridge, built in 2000, main span 146m), steel arch bridge ( Chongqing Chaotianmen Bridge, completed in 2009, main span 552), steel tube concrete arch bridge (Pingnan Third Bridge, completed in 2020, main span 575m) and Meilan Arch Bridge (Beipanjiang Super Bridge, completed in 2016, main span 445m) are all In China, the successful practice of these arch bridges has accumulated valuable experience for the construction of my country's extra-long-span arch bridges, and has made my country's arch bridge construction technology a leader in the world.
相比其它桥型,采用美兰拱桥跨越山谷往往会节省1/3~1/2的成本,而且美兰拱具有承载能力高、刚度大、耐久性好以及后期维护工作量小等优点,但是目前美兰拱结构仍存在自重过大、施工高空作业多、工期长等问题,制约着美兰拱的应用与发展。Compared with other bridge types, using Meilan arch bridge to cross valleys often saves 1/3 to 1/2 of the cost, and Meilan arch has the advantages of high load-bearing capacity, high stiffness, good durability, and low later maintenance workload. However, At present, the Meilan Arch structure still has problems such as excessive self-weight, frequent high-altitude construction operations, and long construction period, which restricts the application and development of the Meilan Arch.
为解决上述问题,有学者提出过采用钢腹杆(板)替代混凝土腹板,但该方法使得拱圈截面刚度较低,且钢构件需长期养护。In order to solve the above problems, some scholars have proposed using steel web bars (plates) to replace concrete webs. However, this method makes the cross-section stiffness of the arch ring low, and the steel components require long-term maintenance.
发明内容:Contents of the invention:
本发明的目的在于针对大跨径美兰拱存在的腹杆数量较多、拱圈自重较大和腹板浇筑较为困难的问题,提供了一种结构构造新颖、力学性能良好、施工相对简便的装配化UHPC腹板美兰拱构造及其施工方法。The purpose of this invention is to provide an assembly with novel structural structure, good mechanical properties and relatively simple construction in order to solve the problems of large-span Meilan arch, which has a large number of web rods, a large self-weight of the arch ring and difficult web pouring. UHPC web Meilan arch structure and its construction method.
本发明基于桁式结构形式的装配化UHPC腹板美兰拱构造,其特征在于:包括钢管混凝土弦管、UHPC蝶形腹板、横联钢管和腹板与弦管接头;位于上部的两根平行设置的钢管混凝土弦管之间间隔垂直固定连接有横联钢管,位于下部的两根平行设置的钢管混凝土弦管之间间隔垂直固定连接有横联钢管,在同一立面内位于上部的钢管混凝土弦管与位于下部的钢管混凝土弦管之间通过UHPC蝶形腹板进行连接,所述钢管混凝土弦管与UHPC蝶形腹板之间通过腹板与弦管接头进行连接,所述腹板与弦管接头由焊接在钢管混凝土弦管上的带孔钢板与UHPC蝶形腹板通过螺栓连接形成接头。The present invention is based on the assembled UHPC web Meilan arch structure in the form of a truss structure, which is characterized by: including steel tube concrete chords, UHPC butterfly webs, transverse steel pipes and web and chord joints; two upper There are cross-connected steel pipes connected vertically and vertically between the parallel concrete-filled steel tube chords. There are cross-connected steel pipes vertically fixed between the two parallel steel-tube concrete chords located at the lower part. The upper steel pipes are located on the same facade. The concrete chord tube and the steel tube concrete chord tube located at the bottom are connected through a UHPC butterfly web, and the steel tube concrete chord tube and the UHPC butterfly web plate are connected through a web and chord joint. The web plate The joint with the chord is formed by bolting the perforated steel plate welded on the steel tube concrete chord to the UHPC butterfly web.
进一步的,上述钢管混凝土弦管、横联钢管与腹板与弦管接头的外围包覆有混凝土顶底板,所述混凝土顶底板内设有顶底板箍筋、顶底板纵筋和混凝土,顶底板箍筋从UHPC蝶形腹板预留的腹板预留钢筋孔穿过,以提高UHPC蝶形腹板与混凝土顶底板界面的抗剪性能。Further, the above-mentioned steel tube concrete chords, transverse steel pipes, webs and chord pipe joints are covered with concrete roof and bottom plates. The top and bottom plates are provided with top and bottom plate stirrups, top and bottom plate longitudinal bars and concrete. The top and bottom plates are The stirrups pass through the reserved steel holes in the UHPC butterfly web to improve the shear resistance of the interface between the UHPC butterfly web and the concrete roof and floor.
进一步的,上述钢管混凝土弦管由钢管内填混凝土固化形成。Further, the above-mentioned concrete-filled steel pipe chord is formed by solidifying concrete filled inside the steel pipe.
进一步的,上述钢管混凝土弦管上焊接有两块平行间隔设置的带孔钢板,两块平行间隔设置的带孔钢板的间距小于钢管混凝土弦管的直径,两块平行间隔设置的带孔钢板之间插入所述UHPC蝶形腹板,所述带孔钢板上的孔与UHPC蝶形腹板上穿入所述螺栓锁紧固定。Further, the above-mentioned concrete steel tube chord is welded with two parallel spaced perforated steel plates. The distance between the two parallel spaced perforated steel plates is smaller than the diameter of the steel tube chord. The distance between the two parallel spaced perforated steel plates is smaller than the diameter of the steel tube chord. The UHPC butterfly web is inserted in between, and the bolts inserted into the holes on the perforated steel plate and the UHPC butterfly web are locked and fixed.
进一步的,上述UHPC蝶形腹板为预制板,UHPC蝶形腹板上、下缘预留多个用于安装高强螺栓的孔和腹板预留钢筋孔。Furthermore, the above-mentioned UHPC butterfly web is a prefabricated plate, and multiple holes for installing high-strength bolts are reserved on the upper and lower edges of the UHPC butterfly web, as well as reserved steel holes in the web.
进一步的,上述UHPC蝶形腹板两侧中部宽度尺寸小于上、下部的宽度尺寸,UHPC蝶形腹板两侧中部设置圆弧过渡段,相邻的两个UHPC蝶形腹板的侧部形成梭形镂空。Furthermore, the width dimension of the middle parts of both sides of the above-mentioned UHPC butterfly web is smaller than the width dimension of the upper and lower parts. Arc transition sections are provided in the middle parts of both sides of the UHPC butterfly web. The sides of two adjacent UHPC butterfly webs form Fusiform cutout.
进一步的,上述同一立面内位于上部的钢管混凝土弦管与位于下部的钢管混凝土弦管之间还设有临时钢腹杆,该临时钢腹杆与UHPC蝶形腹板在钢管混凝土弦管1的长度方向上错位设置。Furthermore, a temporary steel web rod is provided between the upper concrete-filled steel tube chord and the lower concrete-filled steel tube chord in the same facade. The temporary steel web rod and the UHPC butterfly web are in the concrete-filled steel tube chord 1 offset in the length direction.
本发明基于桁式结构形式的装配化UHPC腹板美兰拱构造的施工方法,其步骤如下:The present invention is based on the construction method of the assembled UHPC web Meilan arch structure in the form of a truss structure. The steps are as follows:
(1)按设计尺寸及其要求进行吊装装置的搭设,在搭设吊装装置的同时,在预制厂对钢管混凝土弦管、临时钢腹杆和横联钢管进行加工,并将横联钢管、临时钢腹杆和带孔钢板焊接在钢管混凝土弦管上形成劲性骨架节段;(1) Set up the hoisting device according to the design size and requirements. While erecting the hoisting device, process the concrete-filled steel tube chords, temporary steel web bars and cross-connected steel pipes in the prefabrication plant, and install the cross-connected steel pipes and temporary steel pipes. The web rods and perforated steel plates are welded to the concrete-filled steel tube chords to form stiff skeleton segments;
(2)在加工劲性骨架节段的同时,平行进行UHPC蝶形腹板的预制,在吊装工作开始之前,上述工作应完成;(2) While processing the rigid frame segments, the UHPC butterfly webs are prefabricated in parallel. The above work should be completed before the hoisting work begins;
(3)在吊装装置搭设完毕之后,对劲性骨架节段进行吊装并固定到设计位置;(3) After the hoisting device is set up, hoist the rigid frame segments and fix them to the designed position;
(4)在劲性骨架节段安装完成之后,对UHPC蝶形腹板进行吊装,通过两块带孔钢板之间形成的预留安装口滑入到上、下钢管混凝土弦管间的设计位置,使得UHPC蝶形腹板上的螺栓孔与钢管混凝土弦管上的带孔钢板对接,再用高强螺栓将两者连接起来,各UHPC蝶形腹板不连续布置且UHPC蝶形腹板上、下缘与钢管混凝土弦管之间留有间距;(4) After the rigid frame segments are installed, the UHPC butterfly web is hoisted and slid into the designed position between the upper and lower steel tube concrete chords through the reserved installation opening formed between the two perforated steel plates. , so that the bolt holes on the UHPC butterfly web are connected to the perforated steel plates on the concrete-filled steel tube chords, and then high-strength bolts are used to connect the two. Each UHPC butterfly web is arranged discontinuously and on the UHPC butterfly web, There is a gap between the lower edge and the concrete-filled steel tube chord;
(5)待一节段的UHPC蝶形腹板2拼装完成之后,即可进行下一个节段的安装工作,重复步骤④工作;(5) After one segment of UHPC butterfly web 2 is assembled, the next segment can be installed and repeat step ④;
(6)合龙采用瞬时合龙装置,合龙前对主拱圈线形、位置进行全面复核和调整,合龙时须安排操作人员进行双肋同时合龙,待拱肋合龙形成完整的拱圈之后,灌注钢管混凝土弦管内混凝土;(6) The instant closing device is used for closing. Before closing, the line shape and position of the main arch ring must be comprehensively reviewed and adjusted. During closing, operators must be arranged to close both ribs at the same time. After the arch ribs are closed to form a complete arch ring, the steel tube concrete is poured. Concrete inside the chord;
(7)待管内混凝土强度达到一定程度时,拆除扣索和临时钢腹杆,绑扎顶底板的顶底板箍筋、顶底板纵筋并进行模板的安装,最后进行顶底板混凝土的浇筑工作。(7) When the strength of the concrete in the pipe reaches a certain level, remove the buckles and temporary steel web bars, tie the top and bottom plate stirrups and roof and bottom plate longitudinal bars, install the formwork, and finally pour the top and bottom plate concrete.
与传统美兰拱构造形式相比,此结构构造新颖、力学性能良好、施工相对简便,能够比较好地解决大跨径美兰拱存在的腹杆数量较多和腹板浇筑较为困难的问题,采用UHPC蝶形腹板有效地降低了拱圈自重,在拱圈施工时还能起到支撑作用,在保证美兰拱的承载能力前提下,减少了大量的钢腹杆,缩短了施工周期,提高了大跨径美兰拱桥的经济性,具有非常广泛的应用前景。Compared with the traditional Meilan arch structural form, this structure has a novel structure, good mechanical properties, and relatively simple construction. It can better solve the problems of a large number of web rods and difficult web pouring in the long-span Meilan arch. The use of UHPC butterfly webs effectively reduces the weight of the arch ring and can also play a supporting role during the construction of the arch ring. On the premise of ensuring the load-bearing capacity of the Meilan Arch, a large number of steel web rods are reduced and the construction period is shortened. It improves the economy of the long-span Meilan arch bridge and has very broad application prospects.
附图说明:Picture description:
图1是装配化UHPC蝶形腹板美兰拱桥总体布置图;Figure 1 is the overall layout of the Meilan arch bridge with assembled UHPC butterfly webs;
图2是UHPC蝶形腹板装配示意图(即图1的K部视图);Figure 2 is a schematic assembly diagram of the UHPC butterfly web (i.e., the K view of Figure 1);
图3是装配化UHPC腹板美兰拱的构造剖面图(即图2的A-A剖面图);Figure 3 is a structural cross-sectional view of the assembled UHPC web Meilan arch (i.e., the A-A cross-section in Figure 2);
图4是本发明的腹板与弦管接头的细部大样图。Figure 4 is a detailed enlarged view of the web and chord joint of the present invention.
图中:1-钢管混凝土弦管,2-UHPC蝶形腹板,3-横联钢管,4-临时钢腹杆,5-混凝土顶底板,6-腹板与弦管接头,7-带孔钢板,8-高强螺栓,9-顶底板箍筋,10-顶底板纵筋,11-腹板预留钢筋孔。In the picture: 1-Concrete steel tube chord, 2-UHPC butterfly web, 3-Transverse steel pipe, 4-Temporary steel web rod, 5-Concrete roof and bottom plate, 6-Web and chord joint, 7-With holes Steel plate, 8-high-strength bolts, 9-top and bottom plate stirrups, 10-top and bottom plate longitudinal bars, 11-reserved steel holes in the web.
具体实施方式:Detailed ways:
为让本发明的上述特征和优点能更明显易懂,下文特举实施例,并配合附图,作详细说明如下。In order to make the above-mentioned features and advantages of the present invention more obvious and easy to understand, embodiments are given below and described in detail with reference to the accompanying drawings.
将UHPC蝶形腹板应用于美兰拱桥中,总体布置如图1所示,一种基于桁式结构形式的装配化UHPC腹板美兰拱构造及其施工方法如图2~3所示,装配化UHPC腹板的美兰拱构造包括钢管混凝土弦管1、UHPC蝶形腹板2、横联钢管3和腹板与弦管接头6,钢管混凝土弦管1由钢管内填混凝土固化形成;位于上部的两根平行设置的钢管混凝土弦管1之间间隔垂直固定连接有横联钢管3,位于下部的两根平行设置的钢管混凝土弦管1之间间隔垂直固定连接有横联钢管3,在同一立面内位于上部的钢管混凝土弦管1与位于下部的钢管混凝土弦管1之间通过UHPC蝶形腹板2进行连接,所述钢管混凝土弦管1与UHPC蝶形腹板2之间通过腹板与弦管接头6进行连接,所述腹板与弦管接头6由焊接在钢管混凝土弦管1上的带孔钢板7与UHPC蝶形腹板2通过螺栓8连接形成接头。UHPC butterfly webs are applied to the Meilan arch bridge. The overall layout is shown in Figure 1. An assembled UHPC web Meilan arch structure based on the truss structure and its construction method are shown in Figures 2~3. The Meilan arch structure of the assembled UHPC web includes a concrete-filled steel tube chord 1, a UHPC butterfly web 2, a cross-connected steel pipe 3, and a web-chord joint 6. The concrete-filled steel tube chord 1 is formed by solidifying the steel tube filled with concrete; The two parallel concrete-filled steel tube chords 1 located at the upper part are vertically and fixedly connected to each other with cross-connected steel pipes 3 , and the two parallel-disposed steel tube concrete chords 1 located at the lower part are connected to each other with horizontally connected steel pipes 3 at intervals. In the same facade, the concrete-filled steel tube chord 1 located at the upper part and the concrete-filled steel tube chord 1 located at the lower part are connected through UHPC butterfly web 2. The concrete-filled steel tube chord 1 and the UHPC butterfly web 2 are connected. The web and chord joints 6 are connected by the perforated steel plate 7 welded on the steel tube chord 1 and the UHPC butterfly web 2 through bolts 8 to form a joint.
钢管混凝土弦管1、横联钢管3与腹板与弦管接头6的外围包覆有混凝土顶底板5,所述混凝土顶底板5内设有顶底板箍筋9、顶底板纵筋10和混凝土,顶底板箍筋9从UHPC蝶形腹板2预留的腹板预留钢筋孔11穿过,以提高UHPC蝶形腹板2与混凝土顶底板5界面的抗剪性能。The periphery of the concrete-filled steel tube chord 1, the transverse steel pipe 3 and the web-chord joint 6 is covered with a concrete roof and bottom plate 5. The concrete roof and bottom plate 5 is provided with top and bottom plate stirrups 9, top and bottom plate longitudinal bars 10 and concrete , the roof and bottom plate stirrups 9 pass through the reserved web steel holes 11 of the UHPC butterfly web 2 to improve the shear resistance of the interface between the UHPC butterfly web 2 and the concrete roof and bottom plate 5.
钢管混凝土弦管1上焊接有两块平行间隔设置的带孔钢板7,两块平行间隔设置的带孔钢板7的间距小于钢管混凝土弦管1的直径,两块平行间隔设置的带孔钢板7之间形成预留安装口,该预留安装口插入所述UHPC蝶形腹板2,所述带孔钢板7上的孔与UHPC蝶形腹板2上穿入所述螺栓8锁紧固定;其中UHPC蝶形腹板2为预制板,UHPC蝶形腹板2上、下缘预留多个用于安装高强螺栓8的孔和腹板预留钢筋孔11。Two parallel-spaced perforated steel plates 7 are welded on the concrete-filled steel tube chord 1. The distance between the two parallel-spaced perforated steel plates 7 is smaller than the diameter of the concrete-filled steel tube chord 1. The two parallel-spaced perforated steel plates 7 are welded to the steel tube chord 1. A reserved installation opening is formed between them, and the reserved installation opening is inserted into the UHPC butterfly web 2. The holes on the perforated steel plate 7 are locked and fixed with the bolts 8 inserted into the UHPC butterfly web 2; The UHPC butterfly web 2 is a prefabricated plate, and multiple holes for installing high-strength bolts 8 are reserved on the upper and lower edges of the UHPC butterfly web 2, as well as reserved steel holes 11 in the web.
其中UHPC蝶形腹板2两侧中部宽度尺寸小于上、下部的宽度尺寸,UHPC蝶形腹板2两侧中部设置圆弧过渡段(有利于防止应力集中,),相邻的两个UHPC蝶形腹板2的侧部形成梭形镂空;同一立面内位于上部的钢管混凝土弦管1与位于下部的钢管混凝土弦管1之间还设有临时钢腹杆4,该临时钢腹杆4与UHPC蝶形腹板2在钢管混凝土弦管1的长度方向上错位设置。The width of the middle parts of both sides of the UHPC butterfly web 2 is smaller than the width of the upper and lower parts. Arc transition sections are provided in the middle of both sides of the UHPC butterfly web 2 (which is helpful in preventing stress concentration). The two adjacent UHPC butterflies A fusiform hollow is formed on the side of the shaped web 2; a temporary steel web bar 4 is provided between the upper concrete-filled steel tube chord 1 and the lower concrete-filled steel tube chord 1 in the same facade. The temporary steel web bar 4 It is offset from the UHPC butterfly web 2 in the length direction of the concrete-filled steel tube chord 1.
上述实施例中,钢管混凝土弦管的尺寸和混凝土强度根据实际工程受力情况而定,UHPC蝶形腹板2的UHPC强度和构造尺寸根据实际工程受力情况和拱圈构造而定,临时钢腹杆4数量和布置间距可根据拱圈施工需求而定;顶底板箍筋9的布置形式决定腹板预留钢筋孔11的间距;UHPC蝶形腹板与弦管接头6上的带孔钢板7的尺寸和孔距需根据节点受力情况而定,考虑到腹板安装;螺栓8的尺寸和数量根据节点的受力情况确定。In the above embodiment, the size of the concrete-filled steel tube chord and the concrete strength are determined according to the actual engineering stress conditions. The UHPC strength and structural dimensions of the UHPC butterfly web 2 are determined according to the actual engineering stress conditions and the arch ring structure. The temporary steel The number and arrangement spacing of web bars 4 can be determined according to the construction requirements of the arch ring; the arrangement form of the top and bottom plate stirrups 9 determines the spacing of the reserved steel bar holes 11 in the web; the perforated steel plate on the UHPC butterfly web and chord joint 6 The size and hole spacing of 7 need to be determined according to the stress condition of the node, taking into account the web installation; the size and number of bolts 8 are determined according to the stress condition of the node.
本发明基于桁式结构形式的装配化UHPC腹板美兰拱构造的施工方法,其步骤如下:The present invention is based on the construction method of the assembled UHPC web Meilan arch structure in the form of a truss structure. The steps are as follows:
(1)按设计尺寸及其要求进行吊装装置的搭设,在搭设吊装装置的同时,在预制厂对钢管混凝土弦管1、临时钢腹杆4和横联钢管3进行加工,并将横联钢管3、临时钢腹杆4和带孔钢板7焊接在钢管混凝土弦管1上形成劲性骨架节段;(1) Set up the hoisting device according to the design size and requirements. While erecting the hoisting device, process the concrete-filled steel tube chord 1, temporary steel web rod 4 and cross-connected steel pipe 3 in the prefabrication plant, and install the cross-connected steel pipe. 3. Temporary steel web rods 4 and perforated steel plates 7 are welded to the concrete-filled steel tube chord 1 to form a stiff skeleton segment;
(2)在加工劲性骨架节段的同时,平行进行UHPC蝶形腹板2的预制,在吊装工作开始之前,上述工作应完成;(2) While processing the rigid frame segments, prefabricate the UHPC butterfly web 2 in parallel. The above work should be completed before the hoisting work begins;
(3)在吊装装置搭设完毕之后,对劲性骨架节段进行吊装并固定到设计位置;(3) After the hoisting device is set up, hoist the rigid frame segments and fix them to the designed position;
(4)在劲性骨架节段安装完成之后,对UHPC蝶形腹板2进行吊装,通过两块带孔钢板7之间形成的预留安装口滑入到上、下钢管混凝土弦管1间的设计位置,使得UHPC蝶形腹板2上的螺栓孔与钢管混凝土弦管1上的带孔钢板7对接,再用高强螺栓8将两者连接起来,各UHPC蝶形腹板2不连续布置且UHPC蝶形腹板2上、下缘与钢管混凝土弦管1之间留有间距;(4) After the installation of the rigid frame segments is completed, hoist the UHPC butterfly web 2 and slide it into the space between the upper and lower steel tube concrete chords 1 through the reserved installation opening formed between the two perforated steel plates 7 The design position is such that the bolt holes on the UHPC butterfly web 2 are docked with the perforated steel plate 7 on the concrete-filled steel tube chord 1, and then high-strength bolts 8 are used to connect the two. Each UHPC butterfly web 2 is arranged discontinuously. And there is a gap between the upper and lower edges of the UHPC butterfly web 2 and the concrete-filled steel tube chord 1;
(5)待一节段的UHPC蝶形腹板2拼装完成之后,即可进行下一个节段的安装工作,重复步骤④工作;(5) After one segment of UHPC butterfly web 2 is assembled, the next segment can be installed and repeat step ④;
(6)合龙采用瞬时合龙装置,合龙前对主拱圈线形、位置进行全面复核和调整,合龙时须安排操作人员进行双肋同时合龙,待拱肋合龙形成完整的拱圈之后,灌注钢管混凝土弦管内混凝土;(6) The instant closing device is used for closing. Before closing, the line shape and position of the main arch ring must be comprehensively reviewed and adjusted. During closing, operators must be arranged to close both ribs at the same time. After the arch ribs are closed to form a complete arch ring, the steel tube concrete is poured. Concrete inside the chord;
(7)待管内混凝土强度达到一定程度时,拆除扣索和临时钢腹杆4,绑扎顶底板5的顶底板箍筋9、顶底板纵筋10并进行模板的安装,最后进行顶底板5混凝土的浇筑工作。(7) When the strength of the concrete in the pipe reaches a certain level, remove the buckles and temporary steel web bars 4, tie the top and bottom plate stirrups 9 and top and bottom plate longitudinal bars 10 of the top and bottom plates 5 and install the formwork, and finally concrete the top and bottom plates 5 pouring work.
上述的吊装装置为现有设备,其包括扣塔、锚碇、扣索和吊塔等,其具体构造简述如下:The above-mentioned hoisting device is an existing equipment, which includes buckle towers, anchors, buckle cables and hanging towers, etc. Its specific structure is briefly described as follows:
扣挂缆索吊装系统采用斜拉扣挂缆索吊装系统施工,扣挂缆索吊装系统由起吊安装缆索吊机、斜拉扣挂系统和平衡稳定系统三部分组成;起吊安装缆索吊机由主承重索、主索锚碇、吊锚、起吊、牵引、动力机械等部分组成;斜拉扣挂系统由拱圈上锚固点、钢绞线扣索、扣塔前后平衡索、扣索锚梁含扣索张拉端等部分组成;平衡稳定系统由拱圈锚固点、钢丝绳风缆、地锚等部分组成;扣塔采用万能杆件拼装成全焊接门式格构柱,塔脚固结;在交界墩顶搭设扣塔并设置扣索锚梁,分别向沟谷和两岸张拉节段扣索和锚索,配合吊装进度二者同步、均衡进行,张拉过程中始终使锚梁所受水平分力处于平衡状态。The buckle cable hoisting system is constructed using a diagonal-stay buckle cable hoisting system. The buckle-cable hoisting system consists of three parts: a lifting and installation cable crane, a diagonal-stay buckle system and a balance and stability system; the lifting and installation cable crane consists of the main load-bearing cable, It consists of main cable anchorage, hanging anchor, hoisting, traction, power machinery and other parts; the cable-stayed fastening system consists of the anchor point on the arch ring, the steel strand buckle cable, the front and rear balance cables of the buckle tower, the buckle anchor beam with the buckle cable tensioning end It is composed of other parts; the balance and stability system is composed of arch ring anchor points, steel wire rope wind cables, ground anchors and other parts; the buckle tower is assembled into a fully welded portal lattice column using universal rods, and the tower feet are consolidated; the buckle tower is erected on the top of the junction pier Cable anchor beams are also set up, and the segmental buckle cables and anchor cables are stretched to the ravine and both sides of the river respectively. The two are synchronized and balanced with the hoisting progress. During the tensioning process, the horizontal component of the anchor beam is always in a balanced state.
步骤(5)中,拱肋位置(也即不同节段的弦杆位置)可以先使用法兰盘连接定位,而后再进行焊接固定。In step (5), the arch rib position (that is, the chord position of different segments) can be positioned using flange connections first, and then welded and fixed.
本发明基于桁式结构形式的装配化UHPC腹板美兰拱构造及其施工方法,其中装配化UHPC腹板的美兰拱构造主要由钢管混凝土弦管、UHPC蝶形腹板、横联钢管、临时钢腹杆、外包混凝土顶底板和腹板与弦管接头组成,腹板与弦管接头由焊接在弦管上的带孔钢板和UHPC蝶形腹板通过螺栓连接形成接头;所述钢管混凝土弦管由钢管内填混凝土构成,钢管制作时需焊接带孔钢板,钢管尺寸和混凝土强度根据实际工程受力情况而定;所述UHPC蝶形腹板为预制板,腹板上下缘预留一定数量的螺栓孔和钢筋孔,为防止应力集中,腹板两侧中部设置圆弧过渡段,腹板的UHPC强度和构造尺寸根据实际工程受力情况和拱圈构造而定;所述横联钢管用于连接横向弦管,布置形式可根据拱圈施工需求而定;所述临时钢腹杆用于连接上下弦管,每个劲性骨架节段按一定间距布置少量的直腹杆,腹杆数量和布置间距可根据拱圈施工需求而定;所述外包混凝土顶底板的箍筋需从腹板预留的钢筋孔穿过,以提高腹板与混凝土顶底板界面的抗剪性能,顶底板箍筋的布置形式决定腹板预留钢筋孔的间距;所述腹板与弦管接头上的带孔钢板的尺寸和孔距需根据节点受力情况而定。考虑到腹板安装,可在相邻钢腹杆之间取一片带孔钢板留有略大于腹板宽度的安装口;所述腹板与弦管接头上的带孔钢板和UHPC蝶形腹板通过螺栓连接,螺栓一般采用高强螺栓,而螺栓的尺寸和数量根据节点的受力情况确定。本发明结构构造新颖、力学性能良好、施工相对简便,能够比较好地解决传统美兰拱施工时劲性骨架腹杆数量较多和腹板浇筑较为困难的问题,并且将蝶形和UHPC材料结合可以较大程度地降低拱圈自重。因此,在满足美兰拱承载能力要求的同时,可以节省大量钢材、降低结构自重、提高施工效率和结构耐久性,使得大跨径美兰拱桥更加经济性,具有非常广泛的应用前景。The present invention is based on the assembled UHPC web Meilan arch structure in the form of a truss structure and its construction method. The Meilan arch structure of the assembled UHPC web mainly consists of steel tube concrete chords, UHPC butterfly webs, horizontally connected steel pipes, It is composed of temporary steel web rods, outer concrete roof and bottom plates, and web and chord pipe joints. The web and chord pipe joints are formed by bolting the perforated steel plate welded on the chord pipe and the UHPC butterfly web; the concrete-filled steel tube The chord tube is composed of a steel pipe filled with concrete. Perforated steel plates need to be welded during the production of the steel pipe. The size of the steel pipe and the strength of the concrete are determined according to the stress conditions of the actual project; the UHPC butterfly web is a prefabricated plate, and a certain amount of space is reserved on the upper and lower edges of the web. A large number of bolt holes and steel bar holes. In order to prevent stress concentration, arc transition sections are set in the middle of both sides of the web. The UHPC strength and structural dimensions of the web are determined according to the actual engineering stress conditions and the arch ring structure; the cross-connected steel pipe It is used to connect the transverse chords, and the layout can be determined according to the construction requirements of the arch ring; the temporary steel web bars are used to connect the upper and lower chords, and a small number of straight web bars are arranged at a certain distance in each rigid skeleton segment. The number and arrangement spacing can be determined according to the construction requirements of the arch ring; the stirrups of the outer concrete roof and floor need to pass through the reserved steel holes in the web to improve the shear resistance of the interface between the web and the concrete roof and floor. The layout of the stirrups determines the spacing of reserved steel holes in the web; the size and hole spacing of the perforated steel plate at the joint between the web and the chord must be determined according to the stress conditions of the node. Considering the web installation, a perforated steel plate can be taken between adjacent steel web bars to leave an installation opening slightly larger than the width of the web; the perforated steel plate and UHPC butterfly web on the web and chord joint Through bolt connection, the bolts generally use high-strength bolts, and the size and number of the bolts are determined according to the stress of the node. The structure of the invention is novel, has good mechanical properties, and is relatively simple to construct. It can better solve the problems of a large number of rigid skeleton webs and difficult web pouring during traditional Meilan arch construction. It also combines butterfly-shaped and UHPC materials. The self-weight of the arch ring can be reduced to a great extent. Therefore, while meeting the load-bearing capacity requirements of Meilan Arch, it can save a large amount of steel, reduce the structure's dead weight, improve construction efficiency and structural durability, making the long-span Meilan Arch Bridge more economical and has a very wide range of application prospects.
上列较佳实施例,对本发明的目的、技术方案和优点进行了进一步详细说明,所应理解的是,本发明不局限于上述的最佳实施方式,任何人在本发明的启示下都可以得出各种腹板形式的美兰拱构造及施工方法。凡依本发明申请专利范围所做的均等变化与修饰,均应包含在本发明的保护范围之内。The above preferred embodiments further describe the purpose, technical solutions and advantages of the present invention in detail. It should be understood that the present invention is not limited to the above preferred embodiments, and anyone can do so under the inspiration of the present invention. The Meilan arch structures and construction methods of various web forms are obtained. All equivalent changes and modifications made in accordance with the patentable scope of the present invention shall be included in the protection scope of the present invention.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202311368782.XA CN117248438A (en) | 2023-10-23 | 2023-10-23 | Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202311368782.XA CN117248438A (en) | 2023-10-23 | 2023-10-23 | Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN117248438A true CN117248438A (en) | 2023-12-19 |
Family
ID=89131256
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202311368782.XA Pending CN117248438A (en) | 2023-10-23 | 2023-10-23 | Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN117248438A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117845718A (en) * | 2024-01-29 | 2024-04-09 | 重庆交通大学 | Reinforced concrete skeleton outsourcing prefabricated UHPC board arched bridge |
-
2023
- 2023-10-23 CN CN202311368782.XA patent/CN117248438A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117845718A (en) * | 2024-01-29 | 2024-04-09 | 重庆交通大学 | Reinforced concrete skeleton outsourcing prefabricated UHPC board arched bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111997193A (en) | Assembly type prefabricated beam column connecting joint and construction method | |
CN106481023B (en) | Prefabricated steel-concrete composite beam structure and its implementation method | |
CN114592436B (en) | Pier capping beam lower support system and construction method thereof | |
CN110042741A (en) | A kind of casing constraint Precast Concrete Segmental Bridges pier stud and its construction method | |
CN108951399A (en) | A kind of Single-box multi-chamber box beam bridge and its construction method | |
CN111962372A (en) | Road-rail combined construction steel web member double-combination continuous truss girder and construction method thereof | |
CN113882238A (en) | Long-span top-supporting cable-aided beam-arch composite rigid-frame bridge and its construction method | |
CN110644349A (en) | Superstructure for wide box girder and short tower cable-stayed bridge and construction method | |
CN105064195B (en) | The fish belly Wavelike steel webplate prestressing with bond steel reinforced concrete combination simply supported girder bridge and its construction method of precast assembly | |
CN117248438A (en) | Truss structure form-based assembled UHPC web plate flange arch structure and construction method thereof | |
CN115450102A (en) | Half-supported network suspension rod arch bridge and its construction method | |
CN110820519A (en) | Tunnel arch bridge convenient for rapid construction and construction method thereof | |
CN106087694A (en) | Assembling steel plate beams of concrete combined bridge structure and construction method | |
CN211815522U (en) | External prestress steering structure | |
CN209114299U (en) | A single box multi-chamber box girder bridge | |
CN107142830B (en) | Steel pipe web prestress steel-concrete combined girder structure and construction method | |
CN217974005U (en) | Combined box girder structure | |
CN216891925U (en) | Wave form steel web combination case girder construction based on arch structure atress | |
CN115387234B (en) | A formwork system and construction method for the lower cross beam of an ultra-high diamond-shaped tower pier | |
CN114457667B (en) | Large-span top-decker open-hole web-beam-arch composite rigid frame bridge and its construction method | |
CN116716809A (en) | Construction method of light large-span cast-in-situ bracket of V-shaped pier lower beam of cable-stayed bridge | |
CN214089440U (en) | Large-span stiff skeleton concrete arch bridge accurate assembling construction structure | |
CN214459548U (en) | Assembled steel and concrete combined rigid frame bridge | |
CN211171563U (en) | An arch bridge between tunnels that is convenient for rapid construction | |
CN221741360U (en) | Structure is assembled outward to underground station roof beam and post node |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |