CN107142830B - Steel pipe web prestress steel-concrete combined girder structure and construction method - Google Patents

Steel pipe web prestress steel-concrete combined girder structure and construction method Download PDF

Info

Publication number
CN107142830B
CN107142830B CN201710575198.XA CN201710575198A CN107142830B CN 107142830 B CN107142830 B CN 107142830B CN 201710575198 A CN201710575198 A CN 201710575198A CN 107142830 B CN107142830 B CN 107142830B
Authority
CN
China
Prior art keywords
steel
concrete
prestressed
web
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710575198.XA
Other languages
Chinese (zh)
Other versions
CN107142830A (en
Inventor
董旭
王保群
邢德进
李志�
张旭
徐向锋
刘金慧
范圣伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Jiaotong University
Original Assignee
Shandong Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Jiaotong University filed Critical Shandong Jiaotong University
Priority to CN201710575198.XA priority Critical patent/CN107142830B/en
Publication of CN107142830A publication Critical patent/CN107142830A/en
Application granted granted Critical
Publication of CN107142830B publication Critical patent/CN107142830B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种钢管腹板预应力钢混组合主梁结构及施工方法,包括混凝土顶板、混凝土底板、腹板钢管、体内预应力钢绞线、体外预应力索、横隔板,所述的腹板钢管埋设在混凝土顶板和混凝土底板之间,相邻两根腹板钢管顶端及底端通过剪力键螺栓板连接,形成纵向三角形稳定结构,多根钢管依次相互连接,形成梁体腹板,承受梁体剪力及部分弯矩,所述的体内预应力钢绞线埋设在顶、底板混凝土内,所述的体外预应力索设置在钢混组合梁框架内部,所述的横隔板位于钢混组合梁框架内部,每隔一段距离设置一道,与顶、底板混凝土浇筑固结为整体。

Figure 201710575198

The invention discloses a steel pipe web prestressed steel-concrete composite main girder structure and a construction method, comprising a concrete roof, a concrete floor, a web steel pipe, internal prestressed steel strands, external prestressed cables, and a diaphragm. The web steel pipes are buried between the concrete roof and the concrete floor, and the top and bottom ends of two adjacent web steel pipes are connected by shear key bolts to form a longitudinal triangular stable structure. Multiple steel pipes are connected to each other in turn to form a beam web. The slab bears the shear force and partial bending moment of the beam body. The internal prestressed steel strands are buried in the concrete of the top and bottom slabs. The external prestressed cables are arranged inside the steel-concrete composite beam frame. The horizontal diaphragm The slabs are located inside the steel-concrete composite beam frame, and are arranged at intervals, and are consolidated with the top and bottom slabs by pouring concrete.

Figure 201710575198

Description

钢管腹板预应力钢混组合主梁结构及施工方法Steel tube web prestressed steel-concrete composite main beam structure and construction method

技术领域technical field

本发明涉及一种用于土木工程桥梁技术领域,更具体涉及一种钢管腹板预应力钢混组合主梁结构及施工方法。The invention relates to the technical field of bridges used in civil engineering, and more specifically relates to a steel pipe web prestressed steel-concrete composite main girder structure and a construction method.

背景技术Background technique

桥梁是公路、铁路、城市道路和农村道路及水利建设中,为了跨越各种障碍(如河流、或其它结构)的结构物。按结构形式,桥梁一般可分梁桥、拱桥、斜拉桥和吊桥;按所使用的材料类型,桥梁一般可分为木桥、圬工桥、钢筋混凝土桥、钢桥、钢混组合结构桥梁等。A bridge is a structure for crossing various obstacles (such as rivers or other structures) in highways, railways, urban roads, rural roads, and water conservancy construction. According to the structural form, bridges can generally be divided into girder bridges, arch bridges, cable-stayed bridges and suspension bridges; according to the type of materials used, bridges can generally be divided into wooden bridges, masonry bridges, reinforced concrete bridges, steel bridges, and steel-concrete composite structure bridges wait.

梁桥是以受弯为主的主梁作为承重构件的桥梁。主梁可以是实腹梁或桁架梁。钢混组合结构梁桥是由钢材和混凝土两种不同性质的主梁材料,经组合而成的一种新型桥梁结构形式。由于此类桥梁充分利用了钢材的抗拉性能与混凝土的抗压性能,能显著改善钢结构的力学性能和提高经济性,且具有施工方便、造型美观、环保节能的优点,因此越来越广泛的应用于桥梁工程建设领域。A girder bridge is a bridge in which the main girder is mainly subjected to bending as the load-bearing member. Main girders can be solid web or truss girders. The steel-concrete composite structure girder bridge is a new type of bridge structure formed by combining two main girder materials with different properties, steel and concrete. Since this type of bridge makes full use of the tensile properties of steel and the compressive properties of concrete, it can significantly improve the mechanical properties of steel structures and improve economic efficiency, and has the advantages of convenient construction, beautiful appearance, environmental protection and energy saving, so it is becoming more and more popular. It is used in the field of bridge engineering construction.

传统钢混凝土组合结构梁桥一般采用混凝土桥面板与钢板梁、钢箱梁、或钢桁架梁相结合的方式。由于实腹钢混组合梁(钢板组合梁、钢箱组合梁)自重较轻,实腹钢板极易受到风荷载影响;空腹钢混组合梁(钢桁架组合梁)无法像传统预应力混凝土梁桥,顶、底板混凝土内施加预应力以抵抗恒载和活载,因此跨越能力受到较大局限;传统钢梁拼装施工时,悬臂施工较为困难,需搭设落地支架用于钢梁拼装临时支撑。由此总体上看,传统钢混凝土组合结构梁桥的主要不足是:(1)实腹钢混组合梁抗风能力较差(2)空腹钢混组合梁预应力施加困难,跨越能力受到局限(3)施工复杂,施工场地占用较大。Traditional steel-concrete composite structure girder bridges generally adopt the combination of concrete bridge deck and steel plate girder, steel box girder, or steel truss girder. Due to the light weight of solid-web steel-concrete composite beams (steel plate composite beams, steel box composite beams), solid-web steel plates are easily affected by wind loads; empty-web steel-concrete composite beams (steel truss composite beams) cannot , Prestressing is applied to the top and bottom concrete to resist dead load and live load, so the spanning capacity is greatly limited; when traditional steel beams are assembled, cantilever construction is more difficult, and floor supports need to be erected for temporary support of steel beams. Generally speaking, the main disadvantages of traditional steel-concrete composite structure girder bridges are: (1) The wind resistance capacity of solid-web steel-concrete composite beams is poor; The construction is complex and the construction site occupies a large area.

所以在这种背景下,开发一种满足具备更大的跨越能力和施工更加方便的,新的钢管腹板预应力钢混组合结构梁桥结构形式,具有很大的实用价值。Therefore, under this background, it is of great practical value to develop a new steel pipe web prestressed steel-concrete composite beam bridge structure that meets the needs of greater spanning capacity and more convenient construction.

发明内容Contents of the invention

本发明的目的是在于提供一种钢管腹板预应力钢混组合主梁结构及施工方法,从结构体系和内在受力机理方面提高传统钢混组合结构梁桥的承载能力,与传统的施工方法衔接良好,便于实施。The purpose of the present invention is to provide a steel pipe web prestressed steel-concrete composite main girder structure and construction method, improve the bearing capacity of the traditional steel-concrete composite structure beam bridge from the structural system and internal force mechanism, and the traditional construction method Well connected and easy to implement.

为了实现上述目的,本发明采用以下技术措施:In order to achieve the above object, the present invention adopts the following technical measures:

一种钢管腹板预应力钢混组合主梁结构,包括混凝土顶板、混凝土底板、腹板钢管、体内预应力钢绞线、体外预应力索和横隔板,所述的腹板钢管设置在混凝土顶板和混凝土底板之间,腹板钢管顶部和底部设有剪力键,腹板钢管通过剪力键、钢管定位钢筋与混凝土顶、底板连接形成钢混组合主梁框架,所述的横隔板横向设置在钢混组合梁框架内部,每隔一段距离设置一道,与混凝土顶、底板浇筑固结为整体,用于增加梁体横向刚度;所述的体内预应力钢绞线埋设在顶、底板混凝土内,所述的体外预应力索设置在钢混组合梁框架内部,一端锚固在梁端的横隔板上,另一端锚固在墩顶的横隔板上,中间部分穿过横隔板上的体外预应力转向钢套管后,完成设计体外预应力竖向转向。进一步的,所述的混凝土顶板和底板为节段施工,浇筑前每个节段均埋设预应力钢筋管道。A steel pipe web prestressed steel-concrete composite main girder structure, comprising a concrete roof, a concrete bottom plate, web steel pipes, internal prestressed steel strands, external prestressed cables and diaphragms, the web steel pipes are arranged on the concrete Between the top slab and the concrete bottom slab, the top and bottom of the web steel pipes are provided with shear keys, and the web steel pipes are connected with the concrete top and bottom slabs through the shear keys and steel pipe positioning steel bars to form a steel-concrete composite main beam frame. It is installed horizontally inside the steel-concrete composite beam frame, and is installed at intervals, and is integrated with the concrete top and bottom slabs to increase the lateral stiffness of the beam body; the internal prestressed steel strands are embedded in the top and bottom slabs In the concrete, the external prestressed cable is arranged inside the steel-concrete composite beam frame, one end is anchored on the diaphragm at the end of the beam, the other end is anchored on the diaphragm at the top of the pier, and the middle part passes through the diaphragm on the diaphragm. After the external prestressed steering steel casing, the designed external prestressed vertical steering is completed. Further, the concrete top slab and bottom slab are constructed in sections, and prestressed steel pipes are embedded in each section before pouring.

进一步的,所述的体内预应力钢筋穿过相应节段预应力钢筋管道张拉锚固,并通过管道压浆后,使体内预应力钢筋与顶、底板混凝土结合为整体后,与顶、底板混凝土共同承受施工荷载及一期恒载。Further, the prestressed steel bars in the body are stretched and anchored through the prestressed steel bar pipelines of the corresponding segments, and after the pipelines are grouted, the prestressed steel bars in the body are combined with the top and bottom slab concrete as a whole, and then combined with the top and bottom slab concrete Jointly bear the construction load and the first phase dead load.

进一步的,所述的腹板钢管为中空钢管,沿着混凝土顶板和混凝土底板的纵向方向,对称布置有两列中空钢管,每列中空钢管包括多个倾斜设置且依次相连的中空钢管。Further, the web steel pipes are hollow steel pipes, two rows of hollow steel pipes are symmetrically arranged along the longitudinal direction of the concrete roof and the concrete floor, and each row of hollow steel pipes includes a plurality of hollow steel pipes arranged obliquely and connected in sequence.

进一步的,相邻两根腹板钢管顶端及底端通过剪力键螺栓板连接,形成纵向三角形稳定结构,多根钢管依次相互连接,形成主梁腹板,承受剪力及部分弯矩。Further, the top and bottom ends of two adjacent web steel pipes are connected by shear key bolt plates to form a longitudinal triangular stable structure, and multiple steel pipes are connected to each other in turn to form a main beam web to withstand shear force and partial bending moment.

进一步的,所述的体外预应力索根据设计承载能力,可横向对称设置多条,承受运营期活载。Further, according to the design bearing capacity, multiple externally prestressed cables can be arranged symmetrically in the lateral direction to bear the live load during the operation period.

进一步的,所述的横隔板为钢筋混凝土结构,包括中横隔板、墩顶横隔板和端横隔板,中横隔板设计有多个,位于墩顶和梁端之间的梁体中部,其内部预埋体外预应力转向钢套管,用于辅助体外预应力索转向;墩顶横隔板位于墩顶位置,端横隔板位于梁端,其内部也预埋锚固套筒,用于体外预应力索锚固。Further, the diaphragm is a reinforced concrete structure, including a middle diaphragm, a pier top diaphragm and an end diaphragm, and the middle diaphragm is designed with a plurality of beams located between the pier top and the beam end. In the middle of the body, external prestressed steering steel casings are pre-embedded inside to assist the steering of external prestressed cables; the diaphragm at the top of the pier is located at the top of the pier, and the end diaphragm is located at the end of the beam, and the anchor sleeve is also pre-embedded inside , for external prestressed cable anchorage.

对所述的钢管腹板预应力钢混组合主梁结构施工方法,包括以下几个步骤:The construction method of the steel pipe web prestressed steel-concrete composite main beam structure includes the following steps:

步骤1:在墩顶托架平台上拼装0号块梁段底板模板并绑扎底板钢筋,按照设计要求布置并预埋预应力管道,拼装本节段腹板钢管,并将钢管底部剪力键临时固定在底板相应设计位置;Step 1: Assemble the floor formwork of the No. 0 beam section on the bracket platform of the pier top and tie the floor steel bars, arrange and pre-embed the prestressed pipes according to the design requirements, assemble the web steel pipes of this section, and temporarily install the shear keys at the bottom of the steel pipes Fixed on the corresponding design position of the bottom plate;

步骤2:浇筑0号块底板混凝土,待混凝土达到设计强度的90%时,进行底板体内预应力钢绞线管道穿束,张拉、锚固;Step 2: Pour the No. 0 base plate concrete, and when the concrete reaches 90% of the design strength, carry out the prestressed steel strand pipeline in the base plate body, tension and anchor;

步骤3:墩顶托架平台上搭设满堂支架及顶板施工平台,同步骤1,进行0号块主梁顶板立模、钢筋绑扎、混凝土浇筑、预应力张拉施工。混凝土浇筑前微调位于顶板内钢管顶部剪力键位置,使其符合设计要求;Step 3: Set up the full hall bracket and the roof construction platform on the pier top bracket platform, and carry out the construction of the No. 0 main girder roof formwork, steel bar binding, concrete pouring, and prestressed tensioning construction as in Step 1. Before concrete pouring, fine-tune the position of the shear key at the top of the steel pipe in the roof to make it meet the design requirements;

步骤4:在墩顶梁段顶面两端对称拼装挂篮系统,并进行加载试验;Step 4: Assemble the hanging basket system symmetrically at both ends of the top surface of the pier top beam section, and conduct a loading test;

步骤5:在挂篮底模平台上拼装1#梁段底板模板并绑扎底板钢筋,按照设计要求布置并预埋预应力管道,拼装连接本节段腹板钢管,并将钢管底部剪力键临时固定在底板相应设计位置;Step 5: Assemble the 1# beam section bottom plate formwork on the bottom formwork platform of the hanging basket and bind the bottom plate steel bars, arrange and pre-embed the prestressed pipeline according to the design requirements, assemble and connect the web steel pipe of this section, and temporarily install the shear key at the bottom of the steel pipe Fixed on the corresponding design position of the bottom plate;

步骤6:浇筑1号块梁段底板混凝土,待混凝土达到设计强度的90%时,进行底板体内预应力钢绞线管道穿束,张拉、锚固;Step 6: Pour the concrete on the bottom plate of the beam section of No. 1 block, and when the concrete reaches 90% of the design strength, carry out the prestressed steel strand pipeline in the bottom plate body, tension and anchor;

步骤7:在挂篮顶板平台上1号块梁段顶板立模、钢筋绑扎、混凝土浇筑、预应力张拉施工。混凝土浇筑前微调位于顶板内钢管顶部剪力键位置,使其符合设计要求;Step 7: On the top platform of the hanging basket, the roof of the No. 1 beam section is erected, the steel bars are bound, the concrete is poured, and the prestressed tension is constructed. Before concrete pouring, fine-tune the position of the shear key at the top of the steel pipe in the roof to make it meet the design requirements;

步骤8:挂篮系统前移,重复步骤5~步骤7,进入下一节段主梁施工,直至全桥合龙;Step 8: Move the hanging basket system forward, repeat steps 5 to 7, and enter the main girder construction of the next section until the whole bridge is closed;

步骤9:当施工至横隔板位置,立模绑扎横隔板钢筋,并预埋转向或锚固装置;Step 9: When the construction reaches the position of the diaphragm, the vertical form is bound to the reinforcement of the diaphragm, and the steering or anchoring device is pre-embedded;

步骤10:体外预应力索穿过相应的锚固块及转向块,张拉至设计荷载锚固。Step 10: The external prestressed cable passes through the corresponding anchor block and steering block, and is tensioned to the design load for anchoring.

本发明相对于现有技术具有以下优点:Compared with the prior art, the present invention has the following advantages:

(1)顶板及底板采用了预应力混凝土结构,与传统顶板为混凝土的钢桁架组合梁相比,极大提高了梁体承载能力(1) The roof and bottom plate adopt prestressed concrete structure, which greatly improves the bearing capacity of the beam body compared with the traditional steel truss composite beam with concrete roof

(2)腹板采用钢管桁架,解决了实腹钢板混凝土组合梁桥极易受到风荷载影响的不足,且材料用量较少,具有良好的工程经济性;(2) The web adopts steel pipe truss, which solves the problem that the solid web steel plate concrete composite girder bridge is easily affected by wind load, and the material consumption is less, which has good engineering economy;

(3)采用挂篮悬臂施工,施工安全可靠,节省了施工场地及机具设备。(3) The hanging basket cantilever construction is adopted, the construction is safe and reliable, and the construction site and equipment are saved.

(4)该结构利用顶底板混凝土及预应力承担大部分的弯矩,腹板钢管承担大部分的剪力,结构体系简单,结构受力明确。(4) The structure uses roof and floor concrete and prestress to bear most of the bending moment, and the web steel pipe bears most of the shear force. The structural system is simple and the structural force is clear.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are For some embodiments of the present invention, those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1为钢管腹板预应力钢混组合主梁结构立面示意图;Figure 1 is a schematic elevation view of the steel pipe web prestressed steel-concrete composite main beam structure;

图2为钢管腹板预应力钢混组合主梁结构局部放大示意图;Figure 2 is a partially enlarged schematic diagram of the steel pipe web prestressed steel-concrete composite main beam structure;

图3为钢管腹板预应力钢混组合主梁结构A-A断面示意图;Figure 3 is a schematic diagram of the A-A section of the steel pipe web prestressed steel-concrete composite main beam structure;

图4为腹板钢管拼装示意图;Fig. 4 is the assembly diagram of web steel pipe;

图5为钢管腹板预应力钢混组合主梁结构悬臂施工示意图;Figure 5 is a schematic diagram of the cantilever construction of the steel pipe web prestressed steel-concrete composite main beam structure;

图中:1-钢管腹板预应力钢混组合主梁结构,2-混凝土顶板,3-混凝土底板,4-腹板钢管,5-体内预应力钢绞线,6-体外预应力索,7-横隔板,8-剪力键,9-体外预应力转向钢套管,10-剪力键螺栓板,11-钢管定位钢筋,12-中横隔板,13-墩顶横隔板,14-端横隔板,15-挂篮系统,16-底板平台、17-顶板平台。In the figure: 1- steel pipe web prestressed steel-concrete composite main beam structure, 2- concrete roof, 3- concrete floor, 4- web steel pipe, 5- internal prestressed steel strand, 6- external prestressed cable, 7 -diaphragm, 8-shear key, 9-external prestressed steering steel casing, 10-shear key bolt plate, 11-steel steel positioning steel bar, 12-middle diaphragm, 13-pier top diaphragm, 14-end transverse partition, 15-hanging basket system, 16-bottom platform, 17-top platform.

具体实施方式Detailed ways

应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed description is exemplary and intended to provide further explanation to the present application. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used here is only for describing specific implementations, and is not intended to limit the exemplary implementations according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural, and it should also be understood that when the terms "comprising" and/or "comprising" are used in this specification, they mean There are features, steps, operations, means, components and/or combinations thereof.

正如背景技术所介绍的,现有技术中存在(1)实腹钢混组合梁抗风能力较差;(2)空腹钢混组合梁预应力施加困难,跨越能力较小;(3)支架施工复杂,施工场地占用较大。为了解决如上的技术问题,本申请提出了一种钢管腹板预应力钢混组合主梁结构及施工方法。As introduced in the background technology, there are (1) poor wind resistance of solid-web steel-concrete composite beams in the prior art; (2) difficulty in applying prestress to empty-web steel-concrete composite beams, and small spanning capacity; (3) complex construction of supports, The construction site occupies a large area. In order to solve the above technical problems, the present application proposes a steel pipe web prestressed steel-concrete composite main girder structure and a construction method.

以下结合附图,对本发明的结构作进一步描述。The structure of the present invention will be further described below in conjunction with the accompanying drawings.

本发明提供了一种相对于传统钢混组合主梁结构,结构受力机理及承载效率较高、具备更大的跨越能力、经济性能优越、现场作业量及施工难度较小的一种钢管腹板预应力钢混组合主梁结构。Compared with the traditional steel-concrete composite main girder structure, the invention provides a steel pipe web with higher structural stress mechanism and bearing efficiency, greater spanning capacity, superior economic performance, less on-site operation and less construction difficulty. Slab prestressed steel-concrete composite main beam structure.

结合图1、图2所示,一种钢管腹板预应力钢混组合主梁结构1,包括混凝土顶板2、混凝土底板3、腹板钢管4、体内预应力钢绞线5、体外预应力索6、横隔板7。As shown in Figure 1 and Figure 2, a steel pipe web prestressed steel-concrete composite main beam structure 1 includes a concrete roof 2, a concrete floor 3, web steel pipes 4, internal prestressed steel strands 5, external prestressed cables 6. Transverse partition 7.

结合图3、图4所示,腹板钢管4设置在混凝土顶板2和混凝土底板3之间,腹板钢管4顶部和底部设有剪力键8,腹板钢管4通过剪力键8、钢管定位钢筋11与顶、底板混凝土连接形成钢混组合梁框架。As shown in Fig. 3 and Fig. 4, the web steel pipe 4 is arranged between the concrete roof 2 and the concrete bottom 3, the top and bottom of the web steel pipe 4 are provided with shear keys 8, and the web steel pipe 4 passes through the shear key 8, the steel pipe The positioning steel bar 11 is connected with the concrete of the roof and the floor to form a steel-concrete composite beam frame.

结合图1、图2、图3所示,体内预应力钢绞线5埋设在顶、底板混凝土内;体外预应力索6设置在钢混组合梁框架内部,一端锚固在梁端横隔板14上,另一端锚固在墩顶横隔板13,中间部分穿过横隔板体外预应力转向钢套管9后,完成设计体外预应力竖向转向;横隔板7位于钢混组合梁框架内部,每隔一段距离设置一道,与顶、底板混凝土浇筑固结为整体,用于增加梁体横向刚度。As shown in Fig. 1, Fig. 2 and Fig. 3, internally prestressed steel strands 5 are buried in the roof and floor concrete; externally prestressed cables 6 are arranged inside the frame of the steel-concrete composite beam, and one end is anchored to the diaphragm 14 at the end of the beam , the other end is anchored to the diaphragm 13 on the top of the pier, and after the middle part passes through the externally prestressed steering steel sleeve 9 of the diaphragm, the designed external prestressed vertical steering is completed; the diaphragm 7 is located inside the frame of the steel-concrete composite beam , set one at a certain distance, consolidated with the top and bottom concrete pouring as a whole, and used to increase the lateral rigidity of the beam body.

结合图1、图2所示,混凝土顶板2和底板3为节段施工,浇筑前每个节段均埋设预应力钢筋管道。As shown in Fig. 1 and Fig. 2, the concrete top slab 2 and the bottom slab 3 are segmented construction, and prestressed steel pipes are embedded in each segment before pouring.

结合图1、图2所示,体内预应力钢筋穿过相应节段预应力钢筋管道张拉锚固,并通过管道压浆后,使体内预应力钢绞线5与顶、底板混凝土结合为整体后,与顶、底板混凝土共同承受施工荷载及一期恒载。As shown in Figure 1 and Figure 2, the prestressed steel bars in the body pass through the corresponding section of the prestressed steel pipe for tension and anchoring, and after the pipeline is grouted, the internal prestressed steel strand 5 is integrated with the top and bottom slab concrete , together with the roof and floor concrete bear the construction load and the first phase dead load.

结合图2、图3、图4所示,腹板钢管4为中空钢管包括多根,沿着沿着混凝土顶板和混凝土底板的纵向方向,对称布置有两列中空钢管,每列中空钢管均竖向斜向设置,相邻两根腹板钢管顶端及底端通过剪力键螺栓板10连接,形成纵向三角形稳定结构,多根钢管依次相互连接,形成主梁腹板,承受剪力及部分弯矩。As shown in Fig. 2, Fig. 3 and Fig. 4, the web steel pipes 4 are hollow steel pipes including multiple, along the longitudinal direction along the concrete roof and the concrete floor, there are two rows of hollow steel pipes symmetrically arranged, and each row of hollow steel pipes is vertical It is arranged obliquely, and the top and bottom ends of two adjacent web steel pipes are connected by shear key bolt plates 10 to form a longitudinal triangular stable structure. Multiple steel pipes are connected to each other in turn to form the main beam web, which can withstand shear force and partial bending. moment.

结合图2、图3所示,体外预应力索6根据设计承载能力,可横向对称设置多条,承受运营期活载。As shown in Fig. 2 and Fig. 3, according to the design bearing capacity, multiple prestressed cables 6 can be installed laterally and symmetrically to bear the live load during the operation period.

结合图1、图2、图3所示,横隔板7为钢筋混凝土结构,分为中横隔板12、墩顶横隔板13和端横隔板14,中横隔板12位于墩顶和梁端之间的梁体中部,内部预埋体外预应力转向钢套管9,用于辅助体外预应力钢筋转向;墩顶横隔板13位于墩顶位置,端横隔板14位于梁端,内部预埋锚固套筒,用于体外预应力索锚固。As shown in Fig. 1, Fig. 2 and Fig. 3, the diaphragm 7 is a reinforced concrete structure, which is divided into a middle diaphragm 12, a pier top diaphragm 13 and an end diaphragm 14, and the middle diaphragm 12 is located at the pier top In the middle of the beam body between the beam end and the beam end, an externally prestressed steering steel casing 9 is embedded inside to assist the steering of the externally prestressed steel bar; the pier top diaphragm 13 is located at the pier top, and the end diaphragm 14 is located at the beam end , The internal embedded anchor sleeve is used for external prestressed cable anchoring.

对钢管腹板预应力钢混组合主梁结施工方法,进行详细说明,包括以下几个步骤:The construction method of the steel pipe web prestressed steel-concrete composite main beam structure is described in detail, including the following steps:

步骤1:在墩顶托架平台上拼装0号块梁段底板模板并绑底板钢筋,按照设计要求布置并预埋预应力管道,拼装连接本节段腹板钢管4,并将钢管底部剪力键8临时固定在底板相应设计位置;Step 1: Assemble the No. 0 beam section bottom slab formwork on the pier top bracket platform and tie the bottom slab reinforcement, arrange and pre-embed the prestressed pipeline according to the design requirements, assemble and connect the web steel pipe 4 of this section, and shear the bottom of the steel pipe Key 8 is temporarily fixed at the corresponding design position of the bottom plate;

步骤2:浇筑0号块底板混凝土,待混凝土达到设计强度的90%时,进行底板体内预应力钢绞线5管道穿束,张拉、锚固;Step 2: Pour the No. 0 bottom plate concrete, and when the concrete reaches 90% of the design strength, carry out the prestressed steel strand 5 pipes in the bottom plate body, stretch and anchor;

步骤3:墩顶托架平台上搭设满堂支架及顶板施工平台,同步骤1,进行0号块主梁顶板立模、钢筋绑扎、混凝土浇筑、预应力张拉施工。混凝土浇筑前微调位于顶板内钢管顶部剪力键8位置,使其符合设计要求;Step 3: Set up the full hall bracket and the roof construction platform on the pier top bracket platform, and carry out the construction of the No. 0 main girder roof formwork, steel bar binding, concrete pouring, and prestressed tensioning construction as in Step 1. Before concrete pouring, fine-tune the position of the shear key 8 at the top of the steel pipe in the roof to make it meet the design requirements;

步骤4:在墩顶梁段顶面两端对称拼装挂篮系统15,并进行加载试验;Step 4: symmetrically assemble the hanging basket system 15 on both ends of the top surface of the pier top beam section, and carry out a loading test;

步骤5:在挂篮底板平台16上拼装1#梁段底板模板并绑扎底板钢筋,按照设计要求布置并预埋预应力管道,拼装连接本节段腹板钢管4,并将钢管底部剪力键8临时固定在底板相应设计位置;Step 5: Assemble the 1# beam section bottom plate formwork on the bottom plate platform 16 of the hanging basket and bind the bottom plate steel bars, arrange and pre-embed the prestressed pipes according to the design requirements, assemble and connect the web steel pipe 4 of this section, and connect the shear key at the bottom of the steel pipe 8 Temporarily fixed at the corresponding design position of the bottom plate;

步骤6:浇筑1号块梁段底板混凝土,待混凝土达到设计强度的90%时,进行底板体内预应力钢绞线5管道穿束,张拉、锚固;Step 6: Pour concrete for the bottom plate of the beam section of No. 1 block, and when the concrete reaches 90% of the design strength, carry out the prestressed steel strand 5 pipes in the bottom plate body, stretch and anchor;

步骤7:在挂篮顶板平台17上1号块梁段顶板立模、钢筋绑扎、混凝土浇筑、预应力张拉施工。混凝土浇筑前微调位于顶板内钢管顶部剪力键8位置,使其符合设计要求;Step 7: On the top plate platform 17 of the hanging basket, formwork for the top plate of the beam section of No. 1 block, steel bar binding, concrete pouring, and prestressed tensioning construction. Before concrete pouring, fine-tune the position of the shear key 8 at the top of the steel pipe in the roof to make it meet the design requirements;

步骤8:挂篮系统15前移,重复步骤5~步骤7,进入下一节段主梁施工,直至全桥合龙;Step 8: Move the hanging basket system 15 forward, repeat steps 5 to 7, and enter the main girder construction of the next section until the whole bridge is closed;

步骤9:当施工至横隔板7位置,立模绑扎横隔板钢筋,并预埋转向或锚固装置;Step 9: When the construction reaches the position of the diaphragm 7, the steel bars of the diaphragm are bound with the vertical form, and the steering or anchoring device is pre-embedded;

步骤10:体外预应力索6穿过相应的锚固块及转向块,张拉至设计荷载锚固。Step 10: The external prestressed cable 6 passes through the corresponding anchor block and steering block, and is tensioned to the design load for anchoring.

上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Although the specific implementation of the present invention has been described above in conjunction with the accompanying drawings, it is not a limitation to the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art do not need to pay creative work Various modifications or variations that can be made are still within the protection scope of the present invention.

Claims (6)

1. The steel pipe web prestressed reinforced concrete combined girder structure is characterized by comprising a concrete top plate, a concrete bottom plate, web steel pipes, in-vivo prestressed steel strands, in-vitro prestressed cables and transverse partition plates, wherein the web steel pipes are arranged between the concrete top plate and the concrete bottom plate, shear keys are arranged at the tops and bottoms of the web steel pipes, the web steel pipes are connected with the concrete top plate and the concrete bottom plate through the shear keys and steel pipe positioning steel bars to form a reinforced concrete combined girder frame, and the transverse partition plates are transversely arranged in the reinforced concrete combined girder frame and are integrally cast and solidified with the concrete top plate and the concrete bottom plate at intervals for increasing the transverse rigidity of a girder body; the in-vivo prestress steel strand is buried in the top and bottom plate concrete, the in-vitro prestress cable is arranged in the steel-concrete composite beam frame, one end of the in-vitro prestress cable is anchored on a diaphragm plate at the beam end, the other end of the in-vivo prestress cable is anchored on a diaphragm plate at the pier top, and the middle part of the in-vivo prestress cable passes through an in-vitro prestress steering steel sleeve on the diaphragm plate to finish the design of in-vitro prestress vertical steering;
the concrete top plate and the concrete bottom plate are constructed in sections, and each section is embedded with a prestressed reinforcement pipeline before pouring;
the in-body prestressed steel strands penetrate through the corresponding segment prestressed steel bar pipelines to be tensioned and anchored, and after grouting through the pipelines, the in-body prestressed steel strands are combined with the top and bottom plate concrete into a whole, and then bear construction load and primary constant load together with the top and bottom plate concrete.
2. The steel pipe web prestressed reinforced concrete combined main girder structure according to claim 1, wherein the web steel pipes are hollow steel pipes, two rows of hollow steel pipes are symmetrically arranged along the longitudinal direction of the concrete top plate and the concrete bottom plate, and each row of hollow steel pipes comprises a plurality of hollow steel pipes which are obliquely arranged and are sequentially connected to form a longitudinal triangular stable structure; thereby forming a web plate of the main girder body to bear shearing force and partial bending moment.
3. The steel tube web prestressed reinforced concrete composite girder structure of claim 2, wherein the top ends and the bottom ends of two adjacent web steel tubes are connected by a shear key bolt plate.
4. The steel pipe web prestressed reinforced concrete combined main girder structure of claim 1, wherein the external prestressed cables are symmetrically arranged along the longitudinal direction of the reinforced concrete combined girder frame according to the designed bearing capacity, so as to bear live load in the operation period.
5. The steel pipe web prestress steel-concrete combined girder structure of claim 1, wherein the diaphragm plate is a reinforced concrete structure and comprises a middle diaphragm plate, a pier top diaphragm plate and end diaphragm plates, wherein a plurality of middle diaphragm plates are arranged in the middle of a girder body between a pier top and a girder end, and an external prestress steering steel sleeve is embedded in the middle of the girder body for assisting external prestress cable steering; the pier top diaphragm plate is positioned at the pier top position, the end diaphragm plate is positioned at the beam end, and an anchoring sleeve is also embedded in the end diaphragm plate and is used for anchoring an external prestressed cable.
6. A method of constructing a steel pipe web prestressed reinforced concrete composite girder structure as claimed in any one of claims 1 to 5, wherein: the method comprises the following steps:
step 1: assembling a No. 0 beam section bottom plate template and binding bottom plate steel bars on a pier top bracket platform, arranging and embedding prestressed pipelines according to design requirements, assembling and connecting the section web steel pipes, and temporarily fixing shear keys at the bottoms of the steel pipes at corresponding design positions of the bottom plates;
step 2: pouring No. 0 bottom plate concrete, and when the concrete reaches 90% of the design strength, carrying out beam penetration, tensioning and anchoring on prestressed steel strand pipelines in the bottom plate body;
step 3: setting up a full framing and a top plate construction platform on a pier top bracket platform, and carrying out the construction of a No. 0 main girder top plate vertical formwork, steel bar binding, concrete pouring and prestress tensioning in the same step 1; before concrete pouring, finely adjusting the position of a shear key at the top of a steel pipe in a concrete roof, so that the shear key meets the design requirement;
step 4: symmetrically assembling hanging basket systems at two ends of the top surface of the pier top beam section, and carrying out a loading test;
step 5: assembling a 1# beam section bottom plate template and binding bottom plate steel bars on a basket bottom die platform, arranging and embedding pre-stressing pipelines according to design requirements, assembling and connecting the section web steel pipes, and temporarily fixing shear keys at the bottoms of the steel pipes at corresponding design positions of the bottom plate;
step 6: pouring the bottom plate concrete of the No. 1 girder segment, and carrying out in-vivo prestress steel strand pipeline beam penetration, tensioning and anchoring when the concrete reaches 90% of the design strength;
step 7: setting a model, binding steel bars, pouring concrete and carrying out prestress tensioning construction on a No. 1 block beam Duan Dingban on a hanging basket top plate platform; before concrete pouring, finely adjusting the position of a shear key at the top of a steel pipe in the top plate to enable the shear key to meet design requirements;
step 8: the basket hanging system moves forward, the steps 5 to 7 are repeated, and the next section of girder construction is carried out until the full bridge closure is achieved;
step 9: when the construction is carried out to the diaphragm plate position, binding diaphragm plate reinforcing steel bars by the vertical mould, and embedding a steering or anchoring device;
step 10: the external prestressed cable passes through the corresponding anchoring block and the steering block and is stretched to the designed load for anchoring.
CN201710575198.XA 2017-07-14 2017-07-14 Steel pipe web prestress steel-concrete combined girder structure and construction method Expired - Fee Related CN107142830B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710575198.XA CN107142830B (en) 2017-07-14 2017-07-14 Steel pipe web prestress steel-concrete combined girder structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710575198.XA CN107142830B (en) 2017-07-14 2017-07-14 Steel pipe web prestress steel-concrete combined girder structure and construction method

Publications (2)

Publication Number Publication Date
CN107142830A CN107142830A (en) 2017-09-08
CN107142830B true CN107142830B (en) 2023-05-23

Family

ID=59776175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710575198.XA Expired - Fee Related CN107142830B (en) 2017-07-14 2017-07-14 Steel pipe web prestress steel-concrete combined girder structure and construction method

Country Status (1)

Country Link
CN (1) CN107142830B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109829254B (en) * 2019-03-19 2022-05-06 中国十九冶集团有限公司 Method for drawing positioning line of diaphragm plate after top and bottom plates of curved steel box bridge are unfolded
CN110067186B (en) * 2019-06-05 2024-03-19 深圳市市政设计研究院有限公司 Steel pipe stiffening web steel-concrete combined box girder
CN117779638B (en) * 2024-01-30 2025-11-18 中铁十五局集团有限公司 A multifunctional hanging basket device for realizing modular construction of bridge main beam steel reinforcement components
CN120925406B (en) * 2025-10-15 2026-01-23 湖南科技大学 A hybrid ultra-high performance concrete continuous structure bridge and its construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006112179A (en) * 2004-10-18 2006-04-27 Sumitomo Mitsui Construction Co Ltd Bridge girder construction method
KR100885663B1 (en) * 2008-05-09 2009-02-26 주식회사 오케이컨설턴트 Continuous construction method of PS composite girder using cross beam as fixing unit and its structure
CN105369729A (en) * 2015-12-11 2016-03-02 河南省交通规划设计研究院股份有限公司 External prestressing corrugated steel web T-shaped beam and construction method
CN106758856A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006112179A (en) * 2004-10-18 2006-04-27 Sumitomo Mitsui Construction Co Ltd Bridge girder construction method
KR100885663B1 (en) * 2008-05-09 2009-02-26 주식회사 오케이컨설턴트 Continuous construction method of PS composite girder using cross beam as fixing unit and its structure
CN105369729A (en) * 2015-12-11 2016-03-02 河南省交通规划设计研究院股份有限公司 External prestressing corrugated steel web T-shaped beam and construction method
CN106758856A (en) * 2017-03-09 2017-05-31 河南省交通规划设计研究院股份有限公司 The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block

Also Published As

Publication number Publication date
CN107142830A (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN106758856B (en) The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN103046463B (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN103924505B (en) Use prefabricated steel-concrete combination T beam and the construction method of Wavelike steel webplate
CN113882238B (en) Large-span top-supported cable-assisted beam-arch composite rigid frame bridge and its construction method
CN109024225B (en) Ultra-high performance concrete truss arch piece unit, truss arch piece bridge and construction method
CN103821079B (en) A kind of combined box beam bridge spanning the sea and construction method thereof
CN106906748B (en) Based on the construction method for mixing prestressed assembled corrugated steel web plate composite box girder
CN104264575B (en) A kind of prestress steel case Concrete Combination Continuous Beam bridge structure and construction technology
CN114457667B (en) Large-span top-decker open-hole web-beam-arch composite rigid frame bridge and its construction method
CN106869316A (en) The beam column edge of a wing is the group frame system and construction method of concrete filled steel tube
CN105064196B (en) The fish belly I-shaped combination of prestressing force steel reinforced concrete simply supported girder bridge and its construction method of precast assembly
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN102691257A (en) Continuous box girder made of corrugated steel web pre-tensioned prestressed concrete and construction method
CN103147385B (en) Double-spliced extradosed cable-stayed bridge
CN105064195B (en) The fish belly Wavelike steel webplate prestressing with bond steel reinforced concrete combination simply supported girder bridge and its construction method of precast assembly
CN105064200B (en) Prefabricated and assembled fish-belly truss prestressed steel-concrete composite simply supported beam bridge and its construction method
CN108951399A (en) A kind of Single-box multi-chamber box beam bridge and its construction method
CN107142830B (en) Steel pipe web prestress steel-concrete combined girder structure and construction method
CN104562918B (en) Self-anchored suspension bridge anchor span cast-in-place concrete box beam and construction method thereof
CN106192726B (en) A kind of V-arrangement web beam structure and its construction method
CN211171558U (en) Modular ultra-high performance concrete prefabricated beams adaptable to different spans
CN109972512B (en) Cast-in-place construction method of profiled steel sheet-concrete combined bridge deck slab
CN106087694B (en) Assembling steel plate-beams of concrete combined bridge structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230523

CF01 Termination of patent right due to non-payment of annual fee