CN216865370U - Waterproof integrated house - Google Patents

Waterproof integrated house Download PDF

Info

Publication number
CN216865370U
CN216865370U CN202122663451.1U CN202122663451U CN216865370U CN 216865370 U CN216865370 U CN 216865370U CN 202122663451 U CN202122663451 U CN 202122663451U CN 216865370 U CN216865370 U CN 216865370U
Authority
CN
China
Prior art keywords
water
floor
house
integrated house
waterproof integrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122663451.1U
Other languages
Chinese (zh)
Inventor
钟志锋
王晓亮
王道初
曾祥锋
张志鹏
潘亮
谢云辉
苏振
林灿鸿
钟波
文健均
邹鸿艺
林圳耿
林健美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Construction Co Ltd
Original Assignee
Guangzhou Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Construction Co Ltd filed Critical Guangzhou Construction Co Ltd
Priority to CN202122663451.1U priority Critical patent/CN216865370U/en
Application granted granted Critical
Publication of CN216865370U publication Critical patent/CN216865370U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a waterproof integrated house, which comprises: the house main part, a plurality of water collecting component and drainage system, the house main part is including at least one deck floor, a plurality of water collecting component all include the drain pipe, connecting pipe and water collecting part, the drain pipe sets up along the vertical direction of floor, each drain pipe passes each floor, water collecting part passes through connecting pipe and water piping connection, each water collecting part sets up with each floor one-to-one, drainage system includes basement and water drainage tank, the basement sets up the bottom at the house main part, water drainage tank is used for receiving the water of drain pipe output, this waterproof integrated house, collect the water of each floor through setting up water collecting component, then the water discharge that water collecting component collected through drainage system, moreover, the steam generator is simple in structure, and can solve the easy bubble water of current integrated house foundation soil body, the potential risk of seepage can appear in the first floor of building, integrated house's waterproof performance has been promoted.

Description

Waterproof integrated house
Technical Field
The utility model relates to the technical field of fabricated buildings, in particular to a waterproof integrated house.
Background
As a temporary house structure, the light steel integrated plate house is more and more widely applied to engineering construction due to the advantage of rapid construction. Under the background that a medical field is short and rooms for personnel isolation are limited, a temporary hospital or an isolation hotel is built quickly by utilizing the light steel integrated board room and becomes the first choice. Through the assembly and combination, the light steel integrated board house can form a multi-layer lined building. However, the existing light steel integrated plate house does not have a complete rainwater drainage scheme, and usually, a PVC pipe is fixed in a four-corner upright post to directly drain rainwater collected by a roof to the ground without a special collecting and draining device. In addition, because of the requirements for epidemic protection, building corridors cannot be closed, requiring open ventilation. Therefore, when the building meets stormy weather, rainwater flows into the roof surface and the corridor of the board house along with crosswind, the board house cannot efficiently drain water, water collection of the roof, the corridor and other parts is easily caused, indoor water leakage is caused when the water is serious, a mode of directly draining water to the ground also easily causes water soaking of a soil body in the grating, and the rainwater cannot timely seep to the first floor of the building to cause leakage.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve at least one technical problem in the prior art and provides a waterproof integrated house.
According to an embodiment of a first aspect of the present invention, there is provided a waterproof integrated house, including: house main part, a plurality of water collection subassembly and drainage system, the house main part is including at least one deck floor, and a plurality of water collection subassemblies all include drain pipe, connecting pipe and water collection spare, the drain pipe is followed the vertical direction of floor sets up, each the drain pipe passes each the floor, water collection spare passes through the connecting pipe with water piping connection, each water collection spare and each the floor one-to-one sets up, drainage system includes basement and water drainage tank, the basement sets up the bottom of house main part, water drainage tank is used for receiving the water of drain pipe output.
Has the advantages that: this waterproof integrated house includes: the house main part, a plurality of water collecting component and drainage system, the house main part is including at least one deck floor, a plurality of water collecting component all include the drain pipe, connecting pipe and water collecting part, the drain pipe sets up along the vertical direction of floor, each drain pipe passes each floor, water collecting part passes through connecting pipe and water piping connection, each water collecting part sets up with each floor one-to-one, drainage system includes basement and water drainage tank, the basement sets up the bottom at the house main part, water drainage tank is used for receiving the water of drain pipe output, this waterproof integrated house, collect the water of each floor through setting up water collecting component, then the water discharge that water collecting component collected through drainage system, moreover, the steam generator is simple in structure, and can solve the easy bubble water of current integrated house foundation soil body, the potential risk of seepage can appear in the first floor of building, integrated house's waterproof performance has been promoted.
The waterproof integrated house further comprises a roof obliquely arranged on the top of the house main body.
According to the waterproof integrated house disclosed by the embodiment of the first aspect of the utility model, the roof comprises gable walls arranged on two sides and a tile surface arranged between the gable walls.
According to the waterproof integrated house, the tile surface is a resin tile surface which is integrally formed.
According to the waterproof integrated house disclosed by the embodiment of the first aspect of the utility model, each floor is provided with an inlet communicated with the corridor, and the top of the inlet is provided with an arc-shaped canopy.
According to the waterproof integrated house, the drainage groove comprises a longitudinal beam groove and a transverse beam groove, and the longitudinal beam groove is provided with a water outlet for draining water.
According to the waterproof integrated house, the longitudinal ground beam groove and the transverse ground beam groove are obliquely arranged, and the water outlet is arranged at the bottom end of the longitudinal ground beam groove.
According to the waterproof integrated house, the drainage groove is a PVC half pipe arranged on the substrate, and the PVC half pipe receives water drained by the drainage pipe.
According to the waterproof integrated house disclosed by the embodiment of the first aspect of the utility model, each floor is separated by a floor slab, the water drainage pipes are installed through upright posts, and the water collecting pieces are positioned at corner openings of the floor slabs.
According to the waterproof integrated house disclosed by the embodiment of the first aspect of the utility model, each floor comprises a plurality of board room units, and each board room unit is provided with the water collecting assembly.
Drawings
The utility model is further described below with reference to the accompanying drawings and examples;
FIG. 1 is a schematic structural diagram of a waterproof integrated house according to an embodiment of the present invention;
fig. 2 is a schematic view of a water collection assembly and a drainage system according to an embodiment of the present invention.
Detailed Description
Reference will now be made in detail to the present preferred embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like reference numerals refer to like elements throughout.
In the description of the present invention, it should be understood that the orientation or positional relationship referred to in the description of the orientation, such as the upper, lower, front, rear, left, right, etc., is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, the meaning of a plurality of means is one or more, the meaning of a plurality of means is two or more, and larger, smaller, larger, etc. are understood as excluding the number, and larger, smaller, inner, etc. are understood as including the number. If the first and second are described for the purpose of distinguishing technical features, they are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated or implicitly indicating the precedence of the technical features indicated.
In the description of the present invention, unless otherwise explicitly limited, terms such as arrangement, installation, connection and the like should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above terms in the present invention in combination with the specific contents of the technical solutions.
Referring to fig. 1 and 2, a waterproof integrated house includes: house main part 100, a plurality of water collection component 200 and drainage system, house main part 100 is including at least one floor 110, a plurality of water collection component 200 all include drain pipe 210, connecting pipe 220 and water-collecting member 230, drain pipe 210 sets up along the vertical direction of floor 110, each drain pipe 210 passes each floor 110, water-collecting member 230 passes through connecting pipe 220 and is connected with drain pipe 210, each water-collecting member 230 sets up with each floor 110 one-to-one, drainage system 300 includes basement 310 and water drainage tank 320, basement 310 sets up the bottom at house main part 100, water drainage tank 320 is used for receiving the water of drain pipe 210 output.
As a temporary house structure, the waterproof integrated house is more and more widely applied to engineering construction due to the characteristic of rapid construction. This waterproof integrated house has integrateed catchment and drainage structures, can effectively solve the unable high-efficient defect of drainage of current board house.
In a specific embodiment, the waterproof integrated house further includes a roof 400 disposed obliquely, and the roof 400 is disposed on the top of the house main body 100. The roof 400 includes gable 410 disposed at both sides and a shingle 420 disposed between the gable 410. Further, the tile 420 is a resin tile integrally formed. The roof 400 serves as a part of a waterproofing system for the outer surface of the building, and well drains water from the roof to prevent the water from flowing into the house. The gable 410 shields rain from the horizontal direction of the inclined roof, and the resin tile surface formed integrally shields rain from the vertical direction of the inclined roof.
Referring to fig. 1, each floor 110 is provided with an entrance 120 communicating with a corridor, and an arc-shaped canopy 130 is provided on the top of the entrance 120. Through set up curved canopy in entry 120 department, when the rainwater is great, can effectually shelter from, prevent that the rainwater from drifting into indoor or corridor along with the crosswind. The curved rainshed 130 also serves as a part of the waterproofing system for the exterior of the building to prevent rain from entering the hallway through the entrance. The curved canopy 130 may cover most of the corridor opening from rain drifting horizontally.
Referring to fig. 2, the drain groove 320 includes a longitudinal beam groove 321 and a transverse beam groove 322, and the longitudinal beam groove 321 is provided with a water outlet for discharging water. Wherein, the longitudinal ground beam groove 321 and the transverse ground beam groove 322 are obliquely arranged, and the water outlet is arranged at the bottom end of the longitudinal ground beam groove. Further, the drain tank 320 is a PVC half pipe provided on the base 310, and the PVC half pipe receives water discharged from the drain pipe 210. It will be readily appreciated that each floor 110 is divided by a floor, the water discharge pipes 210 are installed by columns, and the water collecting members 230 are located at corner openings of the floor. Each floor 110 includes a plurality of board room units, each of which is provided with a water collecting assembly 200. The water collecting piece 230 and the connecting pipe 220 are positioned in the floor slab, the water collecting piece 230 is arranged at the corner opening of the floor slab, the water discharging pipes 210 are arranged in the upright posts, and the water discharging pipes 210 of all floors can be connected by adopting hoses.
The longitudinal ground beam grooves 321 are arranged on the surface of each longitudinal ground beam in a penetrating manner, the transverse ground beam grooves 322 are arranged on the outermost transverse ground beam surface, the transverse ground beam grooves 322 are used for connecting all the longitudinal ground beam grooves 321, the longitudinal ground beam grooves 321 and the transverse ground beam grooves 322 are communicated and then are converged at a unique water outlet, the longitudinal ground beam grooves 321 and the transverse ground beam grooves 322 are arranged at a certain gradient, and the position of the water outlet is the lowest point. The water collecting assembly 200 can collect the accumulated water formed by the external rainwater on the top surface of the board room and at the corridor position through the water collecting piece 230, guide the accumulated water to the drainage pipe 210 through the connecting pipe 220, collect the accumulated water discharged from the drainage pipe 210 through the longitudinal beam groove 321, and collect the accumulated water collected by the longitudinal beam groove 321 through the transverse beam groove 322 to the water outlet for discharging.
Adopt gable to add sloping roofing integrated into one piece resin tile face and curved canopy to form the first watertight fittings in integrated house, shelter from most rainwater formation, set up water-collecting member 230 on house top surface and corridor, the rainwater that collects these positions wafts into the ponding of formation, and discharge to water drainage tank 320 through the high-efficient of catchment that drain pipe 210 will collect, set up pre-buried half-and-half PVC pipe of cutting as water drainage tank 320 on basement 310, and set up to the grid formula, collect ponding to a delivery port and discharge, avoided directly discharging ponding to ground, the easy bubble water of the soil body of current light steel integrated board house foundation has been solved, the potential risk of seepage probably appears in the first floor of building, the waterproof performance in light steel integrated board house has been promoted.
The embodiments of the present invention have been described in detail with reference to the drawings, but the present invention is not limited to the embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the gist of the present invention.

Claims (10)

1. A waterproof integrated house, characterized by comprising:
the house main body comprises at least one floor;
the water collecting assemblies comprise water discharging pipes, connecting pipes and water collecting pieces, the water discharging pipes are arranged in the vertical direction of the floors, the water discharging pipes penetrate through the floors, the water collecting pieces are connected with the water discharging pipes through the connecting pipes, and the heights of the water collecting pieces are arranged in a one-to-one correspondence mode with the floors; and
and the drainage system comprises a base and a drainage groove, wherein the base is arranged at the bottom of the house main body, and the drainage groove is used for receiving water output by the drainage pipe.
2. The waterproof integrated house of claim 1, wherein: waterproof integrated house still includes the roof that the slope set up, the roof sets up house main part top.
3. The waterproof integrated house of claim 2, wherein: the roof comprises gable walls arranged on two sides and a tile surface arranged between the gable walls.
4. The waterproof integrated house of claim 3, wherein: the tile surface is a resin tile surface which is integrally formed.
5. The waterproof integrated house of claim 1, wherein: each floor is provided with an inlet communicated with the corridor, and the top of the inlet is provided with an arc-shaped canopy.
6. The waterproof integrated house of claim 1, wherein: the drainage channel comprises a longitudinal ground beam channel and a transverse ground beam channel, and the longitudinal ground beam channel is provided with a water outlet for discharging water.
7. The waterproof integrated house of claim 6, wherein: the longitudinal ground beam groove and the transverse ground beam groove are obliquely arranged, and the water outlet is formed in the bottom end of the longitudinal ground beam groove.
8. The waterproof integrated house of claim 6, wherein: the drainage tank is the PVC half-pipe of setting on the basement, the PVC half-pipe is received the drain pipe discharged water.
9. The waterproof integrated house of claim 1, wherein: each floor passes through the floor partition, the drain pipe passes through the column mouting, the piece that catchments is located floor corner opening part.
10. The waterproof integrated house of claim 1, wherein: each floor includes a plurality of board room unit, each board room unit all is provided with the subassembly that catchments.
CN202122663451.1U 2021-11-02 2021-11-02 Waterproof integrated house Active CN216865370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122663451.1U CN216865370U (en) 2021-11-02 2021-11-02 Waterproof integrated house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122663451.1U CN216865370U (en) 2021-11-02 2021-11-02 Waterproof integrated house

Publications (1)

Publication Number Publication Date
CN216865370U true CN216865370U (en) 2022-07-01

Family

ID=82125662

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122663451.1U Active CN216865370U (en) 2021-11-02 2021-11-02 Waterproof integrated house

Country Status (1)

Country Link
CN (1) CN216865370U (en)

Similar Documents

Publication Publication Date Title
US8141322B2 (en) Method and system for using rain water in buildings
US4513545A (en) Apparatus for and method of constructing, transporting and erecting a structure of two or more stories comprised of a plurality of prefabricated core modules and panelized room elements
CN101126242A (en) Method and system for controlling water-level for underground building
CN216865370U (en) Waterproof integrated house
US20220049488A1 (en) Systems and methods for constructing a multi-storey building
WO2009049357A1 (en) Roof water collection and delivery system
US7137755B2 (en) Underground water retention apparatus
JP4280214B2 (en) Roof drainage structure
US10494771B1 (en) Precast park refuge construction method and apparatus
JP5360446B1 (en) Rainwater storage structure in reinforced concrete slabs
CN219732264U (en) Open type weather-proof outer corridor for high-rise residence
CN213773703U (en) Building outer wall structure that blocks water
CN219196197U (en) Civil air defense engineering drainage structures
CN214834187U (en) Tower crane rain-proof shed with rainwater collecting function
CN216766014U (en) Seepage-proofing structure of basement bottom plate
CN219080785U (en) Waterproof drainage structure of roof square deformation joint
CN220229604U (en) Equipment platform structure and system capable of mounting solar energy
JP3517397B2 (en) Drainage structure of dwelling unit
CN219973471U (en) Outer facade envelope that can plant vegetation and outer facade of building
CN217711947U (en) Novel underground substation
CN218508843U (en) Roof drainage structure
JP3848796B2 (en) Semiconductor factory
CN211899183U (en) A roofing canopy structure for baling box
CN210947147U (en) Rain corrosion resistant top support frame for steel structure building
EP1939372A2 (en) Water drain system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant