CN216839787U - Prefabricated assembly type reinforced concrete sewage streetwork reserved well - Google Patents

Prefabricated assembly type reinforced concrete sewage streetwork reserved well Download PDF

Info

Publication number
CN216839787U
CN216839787U CN202123316673.2U CN202123316673U CN216839787U CN 216839787 U CN216839787 U CN 216839787U CN 202123316673 U CN202123316673 U CN 202123316673U CN 216839787 U CN216839787 U CN 216839787U
Authority
CN
China
Prior art keywords
well
reserved
module
outlet pipe
sewage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123316673.2U
Other languages
Chinese (zh)
Inventor
吴杰
吴典文
左云
苏志豪
张高升
郭欣欣
黄源涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Original Assignee
Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Provincial Communications Planning Survey and Design Institute Co Ltd filed Critical Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Priority to CN202123316673.2U priority Critical patent/CN216839787U/en
Application granted granted Critical
Publication of CN216839787U publication Critical patent/CN216839787U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

A prefabricated reinforced concrete sewage streetscape reserved well is characterized in that the sewage streetscape reserved well comprises a well ring, a shaft adjusting module, a well cover plate, a well chamber upper portion adjusting module, a well chamber reserved sewage outlet pipe access hole module and a well chamber water outlet pipe module which are prefabricated reinforced concrete modules, wherein the well cover and a reinforced concrete bottom plate are arranged on the well ring; the outer walls of the prefabricated reinforced concrete modules are provided with hoisting holes; the reserved well chamber consists of three sections, namely a well chamber upper part adjusting module, a well chamber reserved sewage outlet pipe access hole module and a well chamber outlet pipe module. When the prefabricated reinforced concrete sewage street workshop reserved well is built for the first time, the concrete cushion layer, the reinforced concrete bottom plate and the well chamber water outlet pipe module are completely solidified and molded by adopting cement mortar, and the other modules are only connected through the occluding parts and are not completely solidified.

Description

Prefabricated assembly type reinforced concrete sewage streetwork reserved well
Technical Field
The utility model belongs to the technical field of municipal drainage pipe network engineering, a prefabricated assembled reinforced concrete sewage street shop reserves well.
Background
The urban domestic sewage generally enters a municipal sewage pipe network through a reserved well in a street, and is transferred to a municipal sewage plant to complete purification treatment. The street reserve well is a connecting link of a parcel sewage pipe and a municipal sewage pipe, and plays a vital role in a sewage pipe network system. In specific engineering construction, municipal sewage pipe network construction is generally developed before plots, namely, a reserved well in a street workshop is used firstly, and then a plot sewage outlet pipe is used. Due to the influence of factors such as the building layout in the plot, the height difference of the terrain and the like, the uncertainty of the angle and the elevation of the plot sewage outlet pipe entering the reserved well often causes the problem that an inspection well or a reserved well in a street is required to be additionally built to meet the requirement of the position of the plot sewage outlet pipe entering, so that the construction investment is wasted.
The sewage street reserved well in the prior art mainly comprises three methods of brick laying, reinforced concrete cast-in-place and reinforced concrete prefabricated assembly. The bricked reserved well is low in construction cost and easy to remove, can better adapt to the transformation requirement when the land sewage pipe is connected, but is poor in integrity and seepage resistance, easy to cause sewage leakage and pollute underground water, and is gradually eliminated; the cast-in-place reinforced concrete well has good integrity and strong seepage-proofing capability, but has poor adaptability to the requirement of the access angle of the sewage outlet pipe of the land, and the subsequent transformation is difficult to implement, thus easily causing construction investment waste; the prefabricated assembled well of reinforced concrete construction is fast, the anti-seepage performance is good, but the construction of the prefabricated assembled well of tradition is concerned with more and reserves the well swift and convenient, go out the country sewage to manage, connect out the preformed hole of pipe and establish on same module, lead then reserve the well and to the country sewage to go out the household pipe access angle of family and elevation adaptability poor, and each assembly intermodule concreties completely, when the country sewage goes out the household pipe and connects, the pin-connected panel reserve well exists and demolishs inconveniently, need abolish the reconstruction even.
Therefore, the three methods for reserving the well in the sewage street in the prior art have the common defects that: after the building, the flexible adjustment can not be carried out according to the requirements of the access angle and the elevation of the sewage outlet pipe of the later-stage plot, so that the engineering waste is caused.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a well is reserved in prefabricated assembled reinforced concrete sewage street, solve the weak point that above-mentioned prior art exists, can require to go up and down to reserve the well and carry out the adjustment of elevation and angle to parcel sewage pipe preformed hole after building by laying bricks or stones according to the parcel later stage, can adapt to parcel sewage pipe access direction and elevation demand of leaving household, compromise the wholeness again strong, the advantage that barrier propterty is high, and assembled reinforced concrete well green is energy-conserving, site operation simple to operate is swift, do not increase the engineering cost.
The technical scheme of the utility model:
the well cover comprises a well cover body, a well ring, a shaft adjusting module, a well cover plate, a well chamber upper portion adjusting module, a well chamber reserved sewage outlet pipe access hole module, a well chamber outlet pipe module, a reinforced concrete bottom plate, a concrete cushion layer, an outlet pipe and a ladder stand, wherein the well cover body is located on the prefabricated well ring. Except the well cover and the reinforced concrete bottom plate, the well ring, the shaft adjusting module, the well cover plate, the well chamber upper adjusting module, the well chamber reserved sewage outlet pipe access hole module and the well chamber water outlet pipe module are all prefabricated reinforced concrete modules which are connected through a meshing piece; the reserved well chamber consists of three sections, namely a well chamber upper part adjusting module, a well chamber reserved sewage outlet pipe access hole module and a well chamber outlet pipe module; the prefabricated well ring is sequentially provided with a prefabricated shaft, a prefabricated well cover plate, a well chamber upper part adjusting module, a well chamber reserved sewage outlet pipe access hole module, a well chamber outlet pipe module, a reinforced concrete bottom plate and a concrete cushion layer from top to bottom; hoisting holes are formed in the outer walls of the walling crib, the shaft adjusting module, the well cover plate, the well chamber upper portion adjusting module and the well chamber reserved sewage outlet pipe inlet hole module, and crawling ladders are arranged on the inner walls of the well chamber reserved sewage outlet pipe inlet hole module; when the building is built for the first time, except that the concrete cushion layer, the reinforced concrete bottom plate and the well chamber water outlet pipe module are formed by completely solidifying cement mortar, the other modules are connected through the occlusion piece and are not completely solidified, when the parcel sewage outlet pipe is connected into the well chamber, the reserved sewage outlet pipe in the reserved well chamber is detached to be connected into the hole module and the above parts, the position of the reserved sewage outlet pipe in the well chamber is adjusted to be connected into the hole, the parcel sewage outlet pipe is vertically connected into the hole module, the upper module is assembled again, and waterproof mortar is completely solidified between the occlusion pieces.
Furthermore, a plug is arranged outside the hoisting hole, so that silt is prevented from entering the hoisting hole.
Furthermore, a sewage outlet pipe is reserved in the well chamber and connected into the hole module, and the reserved hole is plugged by adopting an easily-broken material, such as low-grade plain concrete.
Furthermore, the sewage outlet pipe is reserved in the well chamber and connected with the crawling ladder inside the hole module, and three groups of crawling ladder installation reserved holes are arranged in other areas except the reserved hole area. After the plot sewage outlet pipe is connected, the crawling ladder is detached and installed on a reserved hole of the appropriate crawling ladder again, so that the crawling ladder is basically in line with the crawling ladder of the upper module and the lower module.
The utility model has the advantages that: the prefabricated reinforced concrete well is used as a block reserved well, and the block sewage pipe access direction does not need to be considered during municipal pipe network construction, so that the construction difficulty is reduced. When the sewage outlet pipe in the subsequent land is implemented, the reserved holes can be flexibly adjusted, the requirements of the access angle and the elevation of the sewage outlet pipe in the land are met, and the condition that the whole body needs to be dismantled or an inspection well needs to be additionally built in front of the reserved well when the reserved holes do not meet the requirements of the access pipe like a cast-in-place reinforced concrete well is avoided. The prefabricated reinforced concrete well has the advantages of wide applicability, good integrity, strong seepage resistance, greenness, low carbon, energy conservation, environmental protection and low manufacturing cost, is suitable for a sewage reserved well and a rainwater reserved well, and has strong popularization value.
Drawings
FIG. 1 is a diagram showing the relationship between the access of the sewage in the land to the municipal sewage pipe network.
Fig. 2 is a plan view of a prefabricated reinforced concrete reserved well.
Fig. 3 is a sectional view of fig. 2 taken along line 1-1.
Fig. 4 is a cross-sectional view taken at 2-2 in fig. 2.
Fig. 5 is a cross-sectional view taken along line 3-3 of fig. 2.
Fig. 6 is a schematic view of a reserved hole for mounting the ladder stand.
In the figure: 1. a street reservation well; 2. a land sewage outlet pipe; 3. a discharge pipe is connected; 4. a main line inspection well; 5. a main sewer pipe; 1-1, well cover; 1-2, a well ring; 1-3, a wellbore conditioning module; 1-4, well cover plate; 1-5, a well chamber upper part adjusting module; 1-6, reserving a sewage outlet pipe access hole module in a well chamber; 1-6-1. connecting the land sewage into a reserved hole of the pipe; 1-7. a well chamber water outlet pipe module; 1-8. reinforced concrete bottom plate; 1-9. concrete cushion; 1-10, hoisting holes; 1-10-1. plug; 1-11, climbing a ladder; 1-11-1; the ladder stand is provided with a reserved hole.
Detailed Description
The following further describes the embodiments with reference to the drawings.
FIG. 1 shows: the plot sewage is connected into a municipal sewage pipe network and comprises a street house reserved well 1, a plot sewage outlet pipe 2, a receiving outlet pipe 3, a main line inspection well 4 and a main sewage pipe 5. The plot sewage outlet pipe 2 enters a municipal sewage pipe network through a street workshop reserved well 1.
Fig. 2, 3, 4, and 5 show: a prefabricated reinforced concrete sewage street reserved well is a circular well and comprises a well cover 1-1, a well ring 1-2, a shaft adjusting module 1-3, a well cover plate 1-4, a well chamber upper portion adjusting module 1-5, a well chamber reserved sewage outlet pipe access hole module 1-6, a well chamber water outlet pipe module 1-7, a reinforced concrete bottom plate 1-8, a concrete cushion layer 1-9, an outlet pipe 3, a hoisting hole 1-10 and a ladder stand 1-11. The well cover 1-1 is a finished product and can be purchased in the market. The well lid 1-1 is located on the prefabricated well ring 1-2, a hoisting hole 1-10 is reserved on the outer wall of the well ring 1-2, a plug 1-10-1 is arranged outside the hoisting hole 1-10, and a ladder 1-11 is arranged on the inner wall of the hoisting hole; a shaft module 1-3 is arranged below the well ring 1-2, a hoisting hole 1-10 is reserved on the outer wall of a shaft, and a ladder 1-11 is arranged on the inner wall of the shaft; a prefabricated cover plate is arranged below the shaft, and a hoisting hole is reserved in the outer wall of the cover plate; a well chamber upper adjusting module 1-5 is arranged below the cover plate, a hoisting hole 1-10 is reserved on the outer wall of the well chamber upper adjusting module 1-5, and a ladder 1-11 is arranged on the inner wall; a well room reserved sewage outlet pipe access hole module 1-6 is arranged below the well room upper part adjusting module 1-5, a land block sewage outlet pipe reserved hole 1-6-1 is reserved in the well room reserved sewage outlet pipe 1-6-1, and the land block sewage outlet pipe reserved hole 1-6-1 is filled with a breakable material; 1-6, a hoisting hole 1-10 is reserved on the outer wall, and a ladder 1-11 is arranged on the inner wall; a well chamber water outlet pipe module 1-7 is arranged below the well chamber reserved sewage outlet pipe hole module 1-6, and a ladder 1-11 is arranged on the inner wall of the well chamber water outlet pipe module 1-7; and reinforced concrete bottom plates 1-8 are arranged below the well chamber water outlet pipe modules 1-7, and concrete cushions 1-9 are arranged below the reinforced concrete bottom plates 1-8.
FIG. 6 shows: the climbing ladders 1-11 of the well chamber reserved sewage outlet pipe access hole module avoid the sewage outlet pipe hole area, and three groups of climbing ladders are reserved at other positions of the inner wall of the module to install reserved holes 1-11-1; after the plot sewage outlet pipe is connected, the ladder stand originally installed is detached and is installed on the reserved hole of the proper ladder stand again, so that the ladder stand is basically in line with the upper module ladder stand and the lower module ladder stand.
A construction method of a prefabricated reinforced concrete sewage street workshop reserved well comprises the following steps:
(1) according to the specification of a reserved well of a land parcel designed by a sewage pipeline, the manufacturing of parts such as a well curb 1-2, a shaft adjusting module 1-3, a well cover plate 1-4, a well chamber upper portion adjusting module 1-5, a well chamber reserved sewage outlet pipe access hole module 1-6, a well chamber water outlet pipe module 1-7 and the like is completed in a prefabricated field.
(2) And excavating a foundation pit of the reserved well according to the design standard height and other parameters of the reserved well.
(3) And reserving 1-9 parts of a cast-in-place concrete cushion layer and 1-8 parts of a reinforced concrete bottom plate at the bottom of the well foundation pit.
(4) And after the reinforced concrete bottom plates 1-8 reach early strength, assembling all parts of the reserved well. Wherein the well chamber water outlet pipe modules 1-7 and the reinforced concrete bottom plates 1-8 are completely consolidated by adopting cement mortar.
(5) Laying an outlet pipe 3.
(6) Assembling a well reserved sewage outlet pipe access hole module 1-6, a well upper part adjusting module 1-5, a well cover plate 1-4, a shaft adjusting module 1-3, a well ring 1-2 and a well cover 1-1 from bottom to top in sequence, connecting the reserved sewage outlet pipe access hole module 1-6 and the modules at the upper part through snap-in pieces, and conveniently dismantling the block sewage outlet pipe when connecting the well;
(7) backfilling around the well and compacting.
(8) And (3) excavating a reserved well before the block sewage outlet pipe is connected, and re-measuring the direction and elevation of a reserved hole 1-6-1 of the block sewage outlet pipe.
(9) Dismantling the reserved sewage outlet pipe access hole module 1-6 and the modules, crushing 1-6-1 plugging materials, and adjusting the direction and elevation of the 1-6 hole 1-6-1 to be vertical to the outlet pipe.
(10) Laying a plot sewage outlet pipe, connecting the plot sewage outlet pipe to a reserved well in a street, and compacting the outlet pipe and the reserved hole by using waterproof mortar.
(11) And assembling the modules 1-5 and the modules above the upper adjusting module of the well chamber again, and pointing and compacting the occlusion pieces among the modules by adopting cement mortar and completely consolidating the occlusion pieces.
(12) And taking out the reserved sewage outlet pipe of the well chamber, connecting the hole module 1-6 with the crawling ladder, and adjusting the height to 1-6-1 to enable the crawling ladder to be in a line with the crawling ladder of the upper module and the lower module.
(13) And backfilling and compacting the periphery of the reserved well again, and finishing construction.

Claims (4)

1. The utility model provides a well is reserved in prefabricated assembled reinforced concrete sewage street shop, includes well lid, walling crib, pit shaft adjusting module, well apron, well room upper portion adjusting module, well room reservation sewage outlet pipe access hole module, well room outlet pipe module, reinforced concrete bottom plate, concrete cushion, contact tube, cat ladder, and the well lid is located prefabricated walling crib, its characterized in that: except the well cover and the reinforced concrete bottom plate, the well ring, the shaft adjusting module, the well cover plate, the well chamber upper adjusting module, the well chamber reserved sewage outlet pipe access hole module and the well chamber water outlet pipe module are all prefabricated reinforced concrete modules which are connected through a meshing piece; the reserved well chamber consists of three sections, namely a well chamber upper part adjusting module, a well chamber reserved sewage outlet pipe access hole module and a well chamber outlet pipe module; the prefabricated well ring is sequentially provided with a prefabricated shaft, a prefabricated well cover plate, a well chamber upper adjusting module, a well chamber reserved sewage outlet pipe access hole module, a well chamber outlet pipe module, a reinforced concrete bottom plate and a concrete cushion layer from top to bottom; the device comprises a well ring, a shaft adjusting module, a well cover plate, a well chamber upper portion adjusting module, a well chamber reserved sewage outlet pipe access hole module, a well chamber outlet pipe module, hoisting holes formed in the outer wall of the well chamber outlet pipe module, and crawling ladders formed in the inner wall of the well chamber reserved sewage outlet pipe access hole module, wherein three groups of crawling ladder mounting holes are reserved in the well chamber reserved sewage outlet pipe access hole module.
2. The prefabricated assembly type reinforced concrete sewage street reserved well as defined in claim 1, which is characterized in that: the well chamber is reserved with a sewage outlet pipe access hole module, the reserved hole is blocked by a breakable material, and the breakable material comprises low-grade plain concrete.
3. The prefabricated assembly type reinforced concrete sewage street reserved well as defined in claim 1, which is characterized in that: and the outer end of the hoisting hole is provided with a plug for preventing silt from entering the hoisting hole.
4. The prefabricated assembly type reinforced concrete sewage street reserved well as defined in claim 1, which is characterized in that: the sewage pipe-in-and-out pipe is reserved in the well chamber and connected to the crawling ladder inside the hole module, and three groups of crawling ladder installation reserved holes are arranged in other areas except the reserved hole area.
CN202123316673.2U 2021-12-27 2021-12-27 Prefabricated assembly type reinforced concrete sewage streetwork reserved well Active CN216839787U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123316673.2U CN216839787U (en) 2021-12-27 2021-12-27 Prefabricated assembly type reinforced concrete sewage streetwork reserved well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123316673.2U CN216839787U (en) 2021-12-27 2021-12-27 Prefabricated assembly type reinforced concrete sewage streetwork reserved well

Publications (1)

Publication Number Publication Date
CN216839787U true CN216839787U (en) 2022-06-28

Family

ID=82109768

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123316673.2U Active CN216839787U (en) 2021-12-27 2021-12-27 Prefabricated assembly type reinforced concrete sewage streetwork reserved well

Country Status (1)

Country Link
CN (1) CN216839787U (en)

Similar Documents

Publication Publication Date Title
CN201125391Y (en) Basement waterproofing drainage structure
CN109723071B (en) Construction method of double-layer steel drum drainage system built in basement floor post-cast strip
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN207633496U (en) A kind of super large square sponge city Integral rain recycling system
CN110093965A (en) A kind of water discharge method of construction site
CN201212156Y (en) Interception and drainage system of basement engineering
CN216839787U (en) Prefabricated assembly type reinforced concrete sewage streetwork reserved well
CN107023061B (en) Assembled plastic municipal drainage inspection well and construction method
CN202247922U (en) Water lowering and discharging device for water collecting well in blind ditch with deep base pit
CN215055647U (en) Cover drainage system that covers on vehicle
CN212835785U (en) Green environmental protection cement blanket and escape canal structure
CN210140780U (en) Anti-clogging ecological permeable box culvert
CN116356929A (en) Prefabricated reinforced concrete sewage neighborhood reservation well and construction method thereof
CN103015457A (en) Method for building rural brick buried sewage treatment facility
CN106592635A (en) Integrated inspection shaft and installation method thereof
CN111962632A (en) Rainwater sewer and construction method thereof
CN202000461U (en) Novel anti-seepage drainage system
CN205677031U (en) A kind of sewage piece well
CN204098068U (en) Prefabricated assembled concrete drainage inspection well
CN216920628U (en) Novel precast concrete drainage inspection shaft
CN219327154U (en) Large-scale earthing basement roof drainage system
CN212715237U (en) Municipal works road laying structure
CN214424165U (en) Formula of sinking communication single-pipe tower
CN115369984B (en) Annular sponge seepage well and construction method thereof
CN216552069U (en) Prefabricated cable tunnel module with soil retaining wall and assembled prefabricated cable tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant