Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122148716.4U
Other languages
Chinese (zh)
Inventor
尉学红
朱丙芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122148716.4U priority Critical patent/CN215715275U/en
Application granted granted Critical
Publication of CN215715275U publication Critical patent/CN215715275U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a constructional engineering piling device which comprises a base, wherein a mounting frame is arranged on the upper end surface of the base, a through hole is formed in the upper end surface of the mounting frame, an air cylinder is arranged in the through hole, a solenoid valve is arranged at one end of the air cylinder, an installing head is arranged at the output shaft end of the air cylinder, a damping box is arranged on the outer wall of the installing head, slide rails are arranged on two sides of the inner wall of the damping box, at least two slide blocks are arranged in the slide rails, a damping spring is arranged between the slide blocks, a connecting rod is rotatably arranged on one side of each slide block, a damping block is rotatably arranged at one end of each connecting rod, the damping block is sleeved on the installing head, and a pile head is arranged at one end of the installing head. The electromagnetic valve controls the cylinder to start, the output shaft end of the cylinder drives the pile head on the mounting head to pile, when the mounting head receives impact force, the shock absorption box absorbs the impact force from the pile head, the impact force of the shock absorption box is absorbed by the connecting rod, the sliding block is driven to slide in the sliding rail, and the shock absorption spring secondarily absorbs the impact force.

Description

Constructional engineering pile device
Technical Field
The utility model belongs to the technical field of constructional engineering piling devices, and particularly relates to a constructional engineering piling device.
Background
The building engineering refers to an engineering entity formed by the construction of various house buildings and their auxiliary facilities and the installation of lines, pipelines and equipment matched with the house buildings, wherein the house buildings comprise top covers, beams, columns, walls and foundations and can form internal spaces, so that the requirements of people on production, residence, study, public activities and the like are met, and the building engineering comprises plants, theaters, hotels, shops, schools, hospitals, houses and the like; the 'auxiliary facilities' refer to water towers, bicycle sheds, pools and the like which are matched with the house building. The 'installation of lines, pipelines and equipment' refers to the installation activities of the lines, pipelines and equipment such as electricity, water supply and drainage, communication, elevators and the like which are matched with the building construction and the auxiliary facilities thereof. In the building engineering work progress, need squeeze into the underground with prefabricated small-size concrete pile sometimes, artifical pile is wasted time and energy, and shock attenuation effect is relatively poor when the machine is piled, and the pile head has earth, influences the quality of construction and pile foundation, has the relatively poor problem of shock attenuation effect.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a piling device for constructional engineering, which aims to solve the problem of poor damping effect in the prior art.
In order to achieve the purpose, the utility model provides the following technical scheme: the shock absorber comprises a base, the base up end is provided with the mounting bracket, the mounting bracket up end is equipped with the perforation, the perforation is provided with the cylinder, the one end of cylinder is provided with the solenoid valve, cylinder output shaft end is provided with installation head, be provided with the damper box on the installation head outer wall, both ends are provided with the slide rail about the damper box inner wall, be provided with two at least sliders in the slide rail, be provided with damping spring between the slider, slider one side is rotated and is provided with the connecting rod, be provided with the snubber block between the connecting rod, damper box one end is provided with the pile head.
Preferably, through holes are formed in two sides of the upper end face of the base, an electro-hydraulic push rod is arranged in each through hole, and a pressing block is arranged at one end of each electro-hydraulic push rod.
Preferably, a water tank is arranged on one side of the upper end face of the base, a water suction pump is arranged in the water tank, the water suction pump penetrates out of the water tank through a water pipe, a water delivery port is formed in the upper end face of the base, a water mist spray head is arranged at one end, penetrating out of the water delivery port, of the water pipe, and a water pump controller is arranged on one side of the water tank.
Preferably, an operation opening is formed in the middle of the upper end face of the base, and at least four rollers are arranged on the lower end face of the base.
1. According to the utility model, the device is pushed to a working place, the power input end of the electro-hydraulic push rod is connected with an external power supply through a wire, the electro-hydraulic push rod is started to drive the pressing block to jack up the whole base, then the cylinder is controlled to be started through the electromagnetic valve, the output shaft end of the cylinder drives the pile head on the mounting head to pile, when the mounting head is impacted, the shock absorption box absorbs the impact force from the pile head, the impact force of the shock absorption box is absorbed by the connecting rod to drive the sliding block to slide in the sliding rail, and the shock absorption spring secondarily absorbs the impact force, so that the problem of poor shock absorption effect in the pile driving process is solved.
2. According to the utility model, the water pump is started through the water pump controller, the water pump is transmitted to the water mist spray head through the water delivery pipe, and the water mist spray head sprays mist gas to clean the pile head, so that the practicability of the device is improved.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a front cross-sectional view of FIG. 1;
fig. 3 is an enlarged schematic view of a portion of fig. 2.
In the figure: the device comprises a base 1, a mounting frame 2, a through hole 3, a cylinder 4, an electromagnetic valve 5, a mounting head 6, a damping box 7, a sliding rail 8, a sliding block 9, a damping spring 10, a connecting rod 11, a damping block 12, a pile head 13, a through hole 14, an electro-hydraulic push rod 15, a pressing block 16, a water tank 17, a water pump 18, a water delivery pipe 19, a water delivery port 20, a water mist spray head 21, a water pump controller 22, an operation port 23 and a roller 24.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
As shown in fig. 1, 2 and 3, an embodiment of the utility model provides a pile driving device for building engineering, which comprises a base 1, wherein a mounting frame 2 is welded on the upper end face of the base 1, a perforation 3 is arranged on the upper end face of the mounting frame 2, a cylinder 4 is welded on the perforation 3, the model of the cylinder 4 is STD-63-E-2, the input end of the cylinder 4 is connected with the control end of a solenoid valve 5, the solenoid valve 5 is welded on one end of the cylinder 4, the model of the solenoid valve 5 is 4a210-08, an installation head 6 is welded on the output shaft end of the cylinder 4, a shock absorption box 7 is welded on the outer wall of the installation head 6, slide rails 8 are welded on the upper and lower ends of the inner wall of the shock absorption box 7, two slide blocks 9 are welded in the slide rails 8, a shock absorption spring 10 is welded between the slide blocks 9, the shock absorption spring 10 is in an initial state, the initial force is 20N, a connecting rod 11 is welded on one side of the slide block 9, a shock absorption block 12 is rotatably connected between the connecting rods 11, the damping block 12 is in a ring shape, and one end of the damping box 7 is connected with a pile head 13 through a bolt.
As shown in fig. 1, 2 and 3, through holes 14 are formed in two sides of the upper end face of a base 1, an electric hydraulic push rod 15 is welded in each through hole 14, the type of the electric hydraulic push rod 15 is DYTP, the input end of the electric hydraulic push rod 15 is connected with an external power supply through a wire, a pressing block 16 is welded at one end of the electric hydraulic push rod 15, a water tank 17 is welded at one side of the upper end face of the base 1, a water suction pump 18 is welded in each water tank 17, the type of the water suction pump 18 is YCHM, the input end of the water suction pump 18 is connected with a control module of a water pump controller 22 through a wire, the water suction pump 18 penetrates through the water tank 17 through a water pipe 19, a water delivery port 20 is formed in the upper end face of the base 1, a water mist spray nozzle 21 is welded at one end of the water pipe 19 penetrating through the water delivery port 20, a water pump controller 22 is welded at one side of the water tank 17, the type of the water pump controller 22 is LCR, the water pump controller 22 is integrated with a control module and an information processing module, an operation port 23 is formed in the middle position of the upper end face of the base 1, four rollers 24 are welded on the lower end surface of the base 1.
The working principle of the embodiment is as follows: when the building construction pile driving device is used, firstly, the device is pushed to a working place, the power input end of the electric hydraulic push rod 15 is connected with an external power supply through a wire, the electric hydraulic push rod 15 is started to drive the pressing block 16 to jack up the whole base 1, then the electromagnetic valve 5 controls the cylinder 4 to be started, the output shaft end of the cylinder 4 drives the pile head 13 on the mounting head 6 to carry out pile driving, when the mounting head 6 is impacted, the shock absorption box 7 absorbs the impact force from the pile head 13, the impact force of the shock absorption box 7 is absorbed by the connecting rod 11 to drive the sliding block 9 to slide in the sliding rail 8, the shock absorption spring 10 carries out secondary absorption on the impact force, thus the problem of poor shock absorption effect in the pile driving process is solved, when soil is arranged on the pile head 13, the water pump 18 is started through the water pump controller 22, the water pump 18 is transmitted to the water mist spray nozzle 21 through the water pipe 19, and the mist spray nozzle 21 sprays mist gas to clean the pile head 13, thus improving the practicability of the device.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the scope of the present invention.

Claims (4)

1. The utility model provides a building engineering pile driver equipment which characterized in that: including base (1), base (1) up end is provided with mounting bracket (2), mounting bracket (2) up end is equipped with perforation (3), perforation (3) are provided with cylinder (4), the one end of cylinder (4) is provided with solenoid valve (5), cylinder (4) output shaft end is provided with installation head (6), be provided with damper box (7) on installation head (6) outer wall, both ends are provided with slide rail (8) about damper box (7) inner wall, be provided with two at least slider (9) in slide rail (8), be provided with damping spring (10) between slider (9), slider (9) one side is rotated and is provided with connecting rod (11), be provided with between connecting rod (11) snubber block (12), damper box (7) one end is provided with pile head (13).
2. A construction piling device according to claim 1, wherein: through holes (14) are formed in two sides of the upper end face of the base (1), an electro-hydraulic push rod (15) is arranged in each through hole (14), and a pressing block (16) is arranged at one end of each electro-hydraulic push rod (15).
3. A construction piling device according to claim 1, wherein: base (1) up end one side is provided with water tank (17), be provided with suction pump (18) in water tank (17), suction pump (18) are worn out water tank (17) through raceway (19), base (1) up end is equipped with delivery port (20), the one end that raceway (19) were worn out delivery port (20) is provided with water smoke shower nozzle (21), water tank (17) one side is provided with water pump controller (22).
4. A construction piling device according to claim 1, wherein: the device is characterized in that an operation opening (23) is formed in the middle of the upper end face of the base (1), and at least four rollers (24) are arranged on the lower end face of the base (1).
CN202122148716.4U 2021-09-07 2021-09-07 Constructional engineering pile device Active CN215715275U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122148716.4U CN215715275U (en) 2021-09-07 2021-09-07 Constructional engineering pile device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122148716.4U CN215715275U (en) 2021-09-07 2021-09-07 Constructional engineering pile device

Publications (1)

Publication Number Publication Date
CN215715275U true CN215715275U (en) 2022-02-01

Family

ID=80015989

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122148716.4U Active CN215715275U (en) 2021-09-07 2021-09-07 Constructional engineering pile device

Country Status (1)

Country Link
CN (1) CN215715275U (en)

Similar Documents

Publication Publication Date Title
CN104989027B (en) Joinery and its construction exempts to starch prefabricated assembled walling unit
CN206513037U (en) A kind of precast concrete wall panel position regulator
CN112627528A (en) Static hydraulic earth wall machine and using method thereof
CN113073900A (en) Foundation pit safety fence for bridge engineering construction site
CN207160629U (en) A kind of spliced workmen's running gear
CN215715275U (en) Constructional engineering pile device
CN109024595A (en) A kind of quick sheet pile pile-sinking device and method
CN102587677B (en) Construction method for mounting sand autoclaved aerated side fascias at openings of doors and windows in steel structures
CN2565876Y (en) Environmental protection porous pavement waterhole through device
CN211597747U (en) Construction device for planting bars at beam bottom of secondary structure of frame building
CN212096201U (en) Dustproof device of impact drill for constructional engineering
CN109083282A (en) A kind of liftable house
CN109371978B (en) Civil engineering foundation ditch is safe supporting construction for support
CN212641450U (en) Piling device for constructional engineering
CN113026713A (en) Environment-friendly energy-saving rammer for building construction
CN203756030U (en) Drill machine device
CN215801620U (en) PHC tubular pile is with preventing stifled device
CN214575754U (en) Static hydraulic earth wall machine
CN202531026U (en) Drilling machine for construction of inclined pile
CN216809885U (en) High-efficient type building foundation pile device
CN112459700A (en) Well-digging and well-washing integrated equipment for building construction
CN111911192A (en) Highway tunnel section steel concrete supporting construction
CN206125218U (en) Dig automatic SJH axle device of rig track soon
CN214460348U (en) Powder spraying pile machine with portable dust suppression system
CN212104079U (en) Civil construction is with pile device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant