CN215290851U - Curtain wall arranging mechanism for curtain wall engineering construction - Google Patents
Curtain wall arranging mechanism for curtain wall engineering construction Download PDFInfo
- Publication number
- CN215290851U CN215290851U CN202121102735.7U CN202121102735U CN215290851U CN 215290851 U CN215290851 U CN 215290851U CN 202121102735 U CN202121102735 U CN 202121102735U CN 215290851 U CN215290851 U CN 215290851U
- Authority
- CN
- China
- Prior art keywords
- curtain
- curtain wall
- engineering construction
- sleeve
- arranging mechanism
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Curtains And Furnishings For Windows Or Doors (AREA)
Abstract
The utility model relates to an engineering construction technical field especially relates to a curtain arrangement mechanism for curtain engineering construction, has solved current curtain among the prior art and when being connected with the outer wall, and the adjustment is removed to the horizontal position of curtain to the inconvenience, consequently, after a plurality of curtain concatenations, has if a curtain concatenation is crooked, just need all pull down the repacking, and is comparatively troublesome, and has reduced the problem of installation effect. The utility model provides a curtain arrangement mechanism for curtain engineering construction, includes stand and curtain, and the curtain passes through connecting portion and is connected with the stand, and connecting portion include vertical setting and can dismantle the montant of being connected and two levels and the horizontal pole of symmetry setting at the montant both ends with the stand. The utility model discloses rational in infrastructure, it is convenient to install, installs connecting portion to the stand in advance, installs the curtain again, has improved the precision of curtain installation, and is convenient for carry out the regulation of horizontal direction to single curtain, has improved the efficiency and the convenience of installation.
Description
Technical Field
The utility model relates to an engineering construction technical field especially relates to a curtain is arranged mechanism for curtain engineering construction.
Background
The curtain wall is an outer wall enclosure of a building, does not bear load, is hung like a curtain, is also called as a curtain wall, is a light wall with a decorative effect commonly used by modern large and high-rise buildings, is usually spliced and arranged on the wall through a plurality of curtain walls, is convenient for replacing and maintaining a single curtain wall in the later period, and has the advantage of low replacement cost.
However, when the existing curtain wall is connected with an outer wall, the horizontal position of the curtain wall is inconvenient to move and adjust, and therefore after a plurality of curtain walls are spliced, if one curtain wall is spliced obliquely, the curtain wall is required to be completely disassembled and reassembled, which is troublesome, and the installation efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a curtain arrangement mechanism for curtain engineering construction has solved prior art, and current curtain is when being connected with the outer wall, and the adjustment is removed to the horizontal position of curtain to the inconvenience, therefore after a plurality of curtain concatenations, if there is a curtain concatenation crooked, just need all pull down the repacking, comparatively troublesome, and reduced the problem of installation effectiveness.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a curtain arrangement mechanism for curtain engineering construction, includes stand and curtain, the curtain passes through connecting portion and is connected with the stand, connecting portion include vertical setting and can dismantle the montant of being connected and two levels and the symmetry with the stand and set up the horizontal pole at the montant both ends, every the both ends position that one side of stand was kept away from to the horizontal pole has all seted up the straight flute, the top and the bottom position that the curtain is close to one side of horizontal pole all are connected with the installation pole, four corners of one side that the installation pole was kept away from to the curtain all are provided with the screw rod with straight flute looks adaptation, every the one end of screw rod all runs through curtain and straight flute bolt fixed connection through the swivel nut.
Preferably, two the horizontal pole all with the tip fixed connection of montant, a plurality of screw rod groove has been seted up to one side of montant, every screw rod inslot all threaded connection has the fixed bolt pole that runs through screw rod groove and stand bolt fixed connection.
Preferably, the center of one side of the vertical rod is rotatably connected with a sleeve, and the center of one side of the curtain wall close to the vertical rod is provided with a connecting column matched with the sleeve.
Preferably, the sleeve is rotationally connected with the vertical rod through a rotating shaft, a sliding rail fixedly connected with the connecting column is arranged between the connecting column and the curtain wall, and a sliding block detachably connected with the curtain wall is slidably connected inside the sliding rail.
Preferably, the sliding block is fixedly connected with a curtain wall bolt, and openings are formed in two ends of the sliding rail.
Preferably, telescopic inner chamber fixedly connected with magnet board, the spliced pole is close to telescopic one end fixedly connected with magnet board one.
The utility model discloses possess following beneficial effect at least:
before the curtain wall is installed, firstly, the vertical rods and the transverse rods of the connecting parts are arranged on the vertical columns in order, the curtain wall is connected with the sliding rails through the sliding blocks, then the connecting columns on one sides of the sliding rails are inserted into the sleeves, the second magnet plate and the first magnet plate are magnetically attracted during insertion, the convenience of connection is improved, the curtain wall can be rotated through the sleeves after connection is completed, the screw rods at four corners of the curtain wall are aligned to the straight grooves, the end parts of the screw rods are firstly clamped into the straight grooves, then, the position between the curtain wall to be installed and the curtain wall with the periphery installed is observed, the curtain wall can be adjusted in the horizontal direction through the sliding blocks and the sliding rails, the screw rods are continuously screwed after being adjusted to a proper position, the screw rods are fixedly connected with bolts on the inner walls of the straight grooves, the structure is reasonable, the installation is convenient, the connecting parts are installed on the vertical columns in advance, then, the curtain wall is installed, and the installation precision of the curtain wall is improved, and the horizontal direction adjustment is convenient to carry out on a single curtain wall, the installation efficiency and convenience are improved, the curtain wall is supported during installation, and the labor intensity of workers is reduced.
The utility model discloses still possess following beneficial effect:
through the setting of connecting portion, before the installation curtain, at first with the montant and the horizontal pole neatly arranged of connecting portion install to the stand on, aim at the straight flute with the screw rod of four corners of curtain again, with the tip of screw rod at first in the joint advances the straight flute, observe the position between the curtain that the curtain of waiting to install and the peripheral curtain that finishes again, can make the curtain remove at the horizontal direction of horizontal pole through the straight flute, remove to suitable position after, continue to twist again and move the screw rod, make screw rod and straight flute inner wall bolt fixed connection, rational in infrastructure, it is convenient to install, install connecting portion in advance to the stand, install the curtain again, the precision of curtain installation has been improved, and be convenient for carry out the regulation of horizontal direction to single curtain, the efficiency and the convenience of installation have been improved.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without any creative effort.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the curtain wall structure of the present invention;
FIG. 3 is a schematic view of the structure of the connection portion of the present invention;
fig. 4 is a schematic view of the slide rail structure of the present invention.
In the figure: 1. a column; 2. curtain wall; 3. a connecting portion; 4. mounting a rod; 5. connecting columns; 6. a first magnet plate; 7. a slide rail; 8. a screw; 9. a slider; 301. a straight groove; 302. a screw channel; 303. a sleeve; 304. a vertical rod; 305. a cross bar; 306. and a second magnet plate.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Referring to fig. 1-4, a curtain wall arranging mechanism for curtain wall engineering construction, comprising a vertical column 1 and a curtain wall 2, wherein the curtain wall 2 is connected with the vertical column 1 through a connecting portion 3, the connecting portion 3 comprises a vertical rod 304 which is vertically arranged and detachably connected with the vertical column 1 and two horizontal rods 305 which are horizontally and symmetrically arranged at two ends of the vertical rod 304, two end positions of one side of each horizontal rod 305 away from the vertical column 1 are respectively provided with a straight groove 301, the top and bottom positions of one side of the curtain wall 2 close to the horizontal rod 305 are respectively connected with an installation rod 4, four corners of one side of the curtain wall 2 away from the installation rod 4 are respectively provided with a screw 8 which is matched with the straight grooves 301, one end of each screw 8 penetrates through the curtain wall 2 through a screw sleeve and is fixedly connected with the straight grooves 301 through a bolt, specifically, through the arrangement of the connecting portion 3, before the curtain wall 2 is installed, the vertical rod 304 and the horizontal rods 305 of the connecting portion 3 are orderly arranged and installed on the vertical column 1, aim at the straight flute 301 with the screw rod 8 of four corners of curtain 2 again, with the tip of screw rod 8 at first the joint enter the straight flute 301, observe the position between curtain 2 that waits to install and the peripheral curtain 2 that finishes of installing again, can make curtain 2 remove at the horizontal direction of horizontal pole 305 through straight flute 301, remove to suitable position after, continue to twist screw rod 8 again, make screw rod 8 and straight flute 301 inner wall bolt fixed connection, rational in infrastructure, it is convenient to install, install connecting portion 3 to stand 1 in advance, install curtain 2 again, the precision of curtain 2 installation has been improved, and be convenient for carry out the regulation of horizontal direction to single curtain 2, the efficiency and the convenience of installation have been improved.
The scheme has the following working processes:
before the curtain wall 2 is installed, firstly, the vertical rods 304 and the cross rods 305 of the connecting parts 3 are arranged on the upright posts 1 in order, the curtain wall 2 is connected with the slide rail 7 through the slide blocks 9, then the connecting post 5 on one side of the slide rail 7 is inserted into the sleeve 303, the magnet plate II 306 and the magnet plate I6 are magnetically attracted and connected during insertion, the convenience of connection is improved, after the connection is completed, the curtain wall 2 can be rotated through the sleeve 303, the screw rods 8 at the four corners of the curtain wall 2 are aligned to the straight groove 301, the end parts of the screw rods 8 are firstly clamped into the straight groove 301, then the position between the curtain wall 2 to be installed and the curtain wall 2 which is installed at the periphery is observed, the curtain wall 2 can be adjusted in the horizontal direction through the slide blocks 9 and the slide rails 7, after the curtain wall is adjusted to the proper position, the screw rods 8 are continuously screwed, the screw rods 8 are fixedly connected with the bolts on the inner wall of the straight groove 301, the structure is reasonable, and the installation is convenient, install connecting portion 3 to stand 1 in advance, install curtain 2 again, improved the precision of curtain 2 installation, and be convenient for carry out the regulation of horizontal direction to single curtain 2, improved the efficiency and the convenience of installation to realized supporting curtain 2 when the installation, reduced staff's intensity of labour.
According to the working process, the following steps are known:
through connecting portion 3's setting, before installation curtain 2, at first with connecting portion 3's montant 304 and horizontal pole 305 neatly arrange install to stand 1 on, aim at straight flute 301 with the screw rod 8 of four corners of curtain 2 again, with screw rod 8's tip at first in the joint straight flute 301, observe the position between curtain 2 that waits to install and the peripheral curtain 2 that finishes of installing again, can make curtain 2 remove at the horizontal direction of horizontal pole 305 through straight flute 301, remove to suitable position after, continue to twist screw rod 8 again, make screw rod 8 and straight flute 301 inner wall bolt fixed connection, and is rational in infrastructure, it is convenient to install connecting portion 3 to stand 1 in advance, install curtain 2 again, the precision of curtain 2 installation has been improved, and be convenient for carry out the regulation of horizontal direction to single curtain 2, the efficiency and the convenience of installation have been improved.
Further, two horizontal poles 305 all with the tip fixed connection of montant 304, a plurality of screw rod groove 302 has been seted up to one side of montant 304, and equal threaded connection has the fixed bolt pole that runs through screw rod groove 302 and stand 1 bolt fixed connection in every screw rod groove 302, and is concrete, through the setting of screw rod groove 302, be convenient for with montant 304 and stand 1 bolt fixed connection, the dismouting of being convenient for.
Further, one side center department of montant 304 rotates and is connected with sleeve 303, and curtain 2 is close to one side center department of montant 304 and is provided with the spliced pole 5 with sleeve 303 looks adaptation, and is concrete, through sleeve 303 and spliced pole 5's setting, and when the curtain 2 of being convenient for was installed, at first was connected with sleeve 303 through spliced pole 5, formed the fulcrum, and the later stage of being convenient for is connected and is adjusted, installs labour saving and time saving more.
Further, sleeve 303 rotates through pivot and montant 304 to be connected, is provided with between spliced pole 5 and the curtain 2 with spliced pole 5 fixed connection's slide rail 7, the inside sliding connection of slide rail 7 has the slider 9 of being connected with curtain 2 can dismantle, and is concrete, through the setting of slide rail 7 and slider 9, is convenient for adjust curtain 2 in the horizontal direction.
Further, slider 9 and 2 bolt fixed connection of curtain, the opening has all been seted up at the both ends of slide rail 7, and is concrete, through the open-ended setting, be convenient for slider 9 to install into slide rail 7 in.
Further, two 306 of inner chamber fixedly connected with magnet board of sleeve 303, the one end fixedly connected with magnet board 6 that spliced pole 5 is close to sleeve 303, it is specific, through two 306 and the setting of magnet board 6 of magnet board for it is more swift when spliced pole 5 is connected with sleeve 303.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the principles of the present invention may be applied to any other embodiment without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.
Claims (6)
1. A curtain wall arranging mechanism for curtain wall engineering construction comprises upright posts (1) and curtain walls (2), it is characterized in that the curtain wall (2) is connected with the upright post (1) through a connecting part (3), the connecting part (3) comprises a vertical rod (304) which is vertically arranged and is detachably connected with the upright post (1) and two horizontal rods (305) which are horizontally and symmetrically arranged at the two ends of the vertical rod (304), the two ends of one side of each horizontal rod (305) far away from the upright post (1) are respectively provided with a straight groove (301), the top and the bottom of one side of the curtain wall (2) close to the cross bar (305) are both connected with mounting rods (4), four corners of one side of installing pole (4) are kept away from in curtain (2) all are provided with screw rod (8) with straight flute (301) looks adaptation, every the one end of screw rod (8) all runs through curtain (2) and straight flute (301) bolt fixed connection through the swivel nut.
2. The curtain wall arranging mechanism for curtain wall engineering construction according to claim 1, wherein two cross rods (305) are fixedly connected with the end of a vertical rod (304), one side of the vertical rod (304) is provided with a plurality of screw grooves (302), and each screw groove (302) is internally and threadedly connected with a fixed bolt rod which penetrates through the screw groove (302) and is fixedly connected with a vertical column (1) through bolts.
3. The curtain wall arranging mechanism for curtain wall engineering construction as claimed in claim 1, wherein a sleeve (303) is rotatably connected to the center of one side of the vertical rod (304), and a connecting column (5) matched with the sleeve (303) is arranged at the center of one side of the curtain wall (2) close to the vertical rod (304).
4. The curtain wall arranging mechanism for curtain wall engineering construction according to claim 3, wherein the sleeve (303) is rotatably connected with the vertical rod (304) through a rotating shaft, a sliding rail (7) fixedly connected with the connecting column (5) is arranged between the connecting column (5) and the curtain wall (2), and a sliding block (9) detachably connected with the curtain wall (2) is slidably connected inside the sliding rail (7).
5. The curtain wall arranging mechanism for curtain wall engineering construction according to claim 4, wherein the sliding block (9) is fixedly connected with the curtain wall (2) through bolts, and openings are formed in two ends of the sliding rail (7).
6. The curtain wall arranging mechanism for curtain wall engineering construction as claimed in claim 5, wherein a second magnet plate (306) is fixedly connected to the inner cavity of the sleeve (303), and a first magnet plate (6) is fixedly connected to one end, close to the sleeve (303), of the connecting column (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121102735.7U CN215290851U (en) | 2021-05-21 | 2021-05-21 | Curtain wall arranging mechanism for curtain wall engineering construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121102735.7U CN215290851U (en) | 2021-05-21 | 2021-05-21 | Curtain wall arranging mechanism for curtain wall engineering construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215290851U true CN215290851U (en) | 2021-12-24 |
Family
ID=79541432
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121102735.7U Active CN215290851U (en) | 2021-05-21 | 2021-05-21 | Curtain wall arranging mechanism for curtain wall engineering construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215290851U (en) |
-
2021
- 2021-05-21 CN CN202121102735.7U patent/CN215290851U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110644774B (en) | Aluminum alloy template fixing bolt building structure | |
CN112837903A (en) | Transformer mounting structure | |
CN215290851U (en) | Curtain wall arranging mechanism for curtain wall engineering construction | |
CN216076412U (en) | Steel stand straightness deviation of hanging down handles part | |
CN214464674U (en) | Wind power tower cylinder with safety protection device | |
CN217151174U (en) | Construction is with convenient to detach's supplementary installation device of scaffold frame | |
CN212773638U (en) | Strutting arrangement for building engineering | |
CN220486857U (en) | Suspension type curtain wall plate | |
CN215858457U (en) | Exhibition hall curtain of easily buildding fast and dismantling | |
CN219548347U (en) | Cantilever scaffold | |
CN217734448U (en) | Energy-saving prefabricated shear wall for building construction | |
CN220998942U (en) | Hanging fixture for mounting glass curtain wall | |
CN216616981U (en) | Make things convenient for adjustable formwork mounting structure of dismouting | |
CN221748518U (en) | Quick detachable switch | |
CN221567603U (en) | Building curtain mount of convenient regulation | |
CN220747865U (en) | Assembled protective net for building engineering construction | |
CN218028955U (en) | Aluminum alloy template convenient to concatenation | |
CN219672115U (en) | Tool type suspension steel template system | |
CN218205170U (en) | Stepped aluminum plate ceiling mounting structure | |
CN217150859U (en) | Suspended ceiling fixing mechanism for architectural decoration | |
CN215516338U (en) | Shaped steel superimposed sheet hoist | |
CN219219754U (en) | Construction carrying frame | |
CN217760165U (en) | Vertical combination plate of prefabricated building | |
CN221663998U (en) | Stable support for curtain wall convenient to install | |
CN221878491U (en) | Glass curtain wall skeleton connecting piece |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |