CN217760165U - Vertical combination plate of prefabricated building - Google Patents

Vertical combination plate of prefabricated building Download PDF

Info

Publication number
CN217760165U
CN217760165U CN202221553992.7U CN202221553992U CN217760165U CN 217760165 U CN217760165 U CN 217760165U CN 202221553992 U CN202221553992 U CN 202221553992U CN 217760165 U CN217760165 U CN 217760165U
Authority
CN
China
Prior art keywords
plate
supporting
support
middle position
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221553992.7U
Other languages
Chinese (zh)
Inventor
胡继华
万显龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Dingsheng Heavy Industry Technology Co ltd
Original Assignee
Changsha Dingsheng Heavy Industry Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Dingsheng Heavy Industry Technology Co ltd filed Critical Changsha Dingsheng Heavy Industry Technology Co ltd
Priority to CN202221553992.7U priority Critical patent/CN217760165U/en
Application granted granted Critical
Publication of CN217760165U publication Critical patent/CN217760165U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a vertical combination plate of prefabricated building, including the support plate piece, first U type seat, the bracing piece, the slide bar, lock nut can splice the support and place box structure and portable support and promote the tubular construction, the right side upper portion intermediate position bolted connection of support plate piece have first U type seat. The utility model discloses the setting of support plate, slide bar, lock nut, place box and slide opening is favorable to loosening lock nut in the use, then reciprocates the support plate, screws up lock nut, adjusts the height of support plate, conveniently adjusts work according to the construction environment in the use; the support plate, first U type seat, the bracing piece, the stay tube, the setting of second U type seat and bottom plate is favorable to carrying out the support work that supports the plate through bracing piece and stay tube at the in-process that uses, prevents to influence work after the in-process support plate that uses inclines.

Description

Vertical combination plate of prefabricated building
Technical Field
The utility model belongs to the technical field of architectural equipment, especially, relate to a vertical combination plate of prefabricated building.
Background
The fabricated building is a building which is formed by prefabricating and finishing part or all of the building in a factory, transporting the building to a construction site and assembling the building in a reliable connection mode. Due to the characteristics of energy conservation, environmental protection and the like, the vertical combined plate is more and more concerned, and needs to be used in the process of performing the assembly type building construction.
However, the existing vertical combined plate also has the problems that the height of the intelligent combined plate is inconvenient to adjust according to the specification of a building in the using process and the intelligent combined plate is inconvenient to support in the using process.
Therefore, the invention is necessary to invent the vertical combination plate of the prefabricated building.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a vertical combination plate of prefabricated building to solve current vertical combination plate and still having the height and the inconvenient problem of supporting at the in-process that uses of the inconvenient in-process according to the specification adjustment intelligence combination plate of building. A vertical combined plate of an assembly type building comprises a supporting plate, a first U-shaped seat, a supporting rod, a sliding rod and a locking nut, wherein a placing box structure and a movable supporting push pipe structure can be spliced and supported; a supporting rod is connected with the middle position of the inside of the right side of the first U-shaped seat through a pin shaft; the middle position of the lower part of the front surface and the middle position of the lower part of the rear surface of the supporting plate are respectively connected with a sliding rod through bolts; the outer wall of the sliding rod is respectively in threaded connection with a locking nut; the splicing supporting and placing box structure is fixed on the outer wall of the supporting plate; the movable support push pipe structure is arranged on the outer wall of the support rod.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses in, the support plate, the slide bar, lock nut places the setting of box and slip hole, is favorable to loosening lock nut at the in-process that uses, then reciprocates the support plate, screwing up lock nut, adjusted the height of support plate, the convenient in-process that uses is according to construction environment regulation work.
2. The utility model discloses in, the setting of support plate piece, first U type seat, bracing piece, stay tube, second U type seat and bottom plate is favorable to carrying out the support work of support plate piece through bracing piece and stay tube at the in-process that uses, prevents to influence work after the in-process support plate piece slope that uses.
3. The utility model discloses in, the box of placing, solid fixed ring, the peg graft pole, the setting of sliding hole and splice plate is favorable to running through solid fixed ring back through the peg graft pole at the in-process that uses, sets up the right side intermediate position placing the box, the convenience is consolidated the support work to the box of placing after the concatenation.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is the utility model discloses a can splice and support the structural schematic diagram of placing box structure.
Fig. 3 is a schematic structural diagram of the movable support push tube structure of the present invention.
In the figure:
1. a support plate; 2. a first U-shaped seat; 3. a support bar; 4. a slide bar; 5. locking the nut; 6. the box structure can be spliced and supported; 61. placing the box; 62. a fixing ring; 63. a plug rod; 64. a slide hole; 65. splicing plates; 7. a movable support push pipe structure; 71. supporting a pipe; 72. a second U-shaped seat; 73. a base plate; 74. an inverted U-shaped frame; 75. a moving wheel; 76. and (7) fixing holes.
Detailed Description
The present invention is described in detail with reference to the accompanying drawings, as shown in fig. 1 and fig. 2, a vertical combination plate of a prefabricated building comprises a support plate 1, a first U-shaped seat 2, a support rod 3, a sliding rod 4, a locking nut 5, a support placing box structure 6 and a movable support pushing tube structure 7, wherein the middle position of the upper part of the right side of the support plate 1 is connected with the first U-shaped seat 2 through a bolt; a supporting rod 3 is connected with the middle position of the inside of the right side of the first U-shaped seat 2 through a pin shaft; the middle position of the lower part of the front surface and the middle position of the lower part of the rear surface of the supporting plate 1 are respectively connected with a sliding rod 4 through bolts; the outer wall of the sliding rod 4 is respectively in threaded connection with a locking nut 5; the support placing box structure 6 capable of being spliced is fixed on the outer wall of the support plate 1; the movable supporting push pipe structure 7 is arranged on the outer wall of the supporting rod 3; the splicing supporting placing box structure 6 comprises a placing box 61, a fixing ring 62, an inserting rod 63, a sliding hole 64 and a splicing plate 65, wherein the fixing ring 62 is connected to the middle position of the right side of the placing box 61 through a bolt; the inside of the fixed ring 62 is inserted with an insertion rod 63; the middle position of the front surface and the middle position of the rear surface of the placing box 61 are respectively provided with a sliding hole 64; the splicing plates 65 are respectively bolted on the left side of the front surface and the left side of the rear surface of the placing box 61; when using, according to building construction needs and building environment, will place box 61 and fix in suitable position, loosening lock nut 5, according to the working needs, adjust the height of support plate 1, conveniently adjust the work according to the working needs at the in-process of construction, then according to needs, use the box 61 of placing of suitable quantity to adsorb the setting through splice plate 65, and run through solid fixed ring 62 respectively with bayonet pole 63 after to place box 61 and carry out the support work.
In this embodiment, referring to fig. 3, the movable supporting push tube structure 7 includes a supporting tube 71, a second U-shaped seat 72, a bottom plate 73, an inverted U-shaped frame 74, a moving wheel 75 and a fixing hole 76, wherein the lower end of the supporting tube 71 is pivotally connected to the middle position inside the upper end of the second U-shaped seat 72; the second U-shaped seat 72 is connected to the middle position of the upper end of the bottom plate 73 through a bolt; the middle position of the lower end of the bottom plate 73 is connected with an inverted U-shaped frame 74 through a bolt; a moving wheel 75 is arranged in the middle of the lower end of the inverted U-shaped frame 74; the fixing holes 76 are respectively arranged at the middle positions inside the left side and the right side of the bottom plate 73; then according to the construction environment, the supporting pipe 71 is rotated, the supporting pipe 71 and the supporting rod 3 are in threaded connection, the position of the bottom plate 73 is adjusted, and the external stainless steel rods are used to respectively penetrate through the fixing holes 76, so that the supporting plate block 1 and the placing box 61 are supported in the using process, the supporting plate block 1 and the placing box 61 are prevented from being inclined, and then the work of combining the plate blocks is completed.
In this embodiment, specifically, the support rod 3 is a stainless steel threaded rod and is disposed at the middle position of the right side of the support plate 1.
In this embodiment, specifically, the insertion rod 63 is a cylindrical stainless steel rod and is disposed at the middle position of the right side of the placing box 61; the splicing plate 65 is a rectangular magnet plate.
In this embodiment, specifically, the lower end of the supporting plate 1 is inserted into the middle inside the upper end of the placing box 61; the sliding rods 4 respectively penetrate through the sliding holes 64 in a sliding manner; the locking nuts 5 are respectively arranged on the front surface and the rear surface of the placing box 61; the placing boxes 61 are arranged in an adsorption mode through splicing plates 65.
In this embodiment, specifically, the second U-shaped seat 72 and the inverted U-shaped frame 74 are disposed between the fixing holes 76; the supporting tube 71 is a stainless steel tube with internal threads.
In this embodiment, specifically, the supporting tube 71 is screwed on the lower portion of the outer wall of the supporting rod 3, and the supporting tube 71 is disposed at the right middle position of the supporting plate 1.
Principle of operation
The utility model discloses in, when using, according to building construction needs and building environment, to place box 61 and fix in suitable position, loosening lock nut 5, according to the work needs, adjust the height of support plate 1, the work is adjusted according to the work needs to the convenient in-process at the construction, then according to needs, use the box 61 of placing of suitable quantity to adsorb the setting through splice plate 65, and run through solid fixed ring 62 with insertion rod 63 respectively and carry out the support work to placing box 61, then according to the construction environment, rotatory stay tube 71, set up through stay tube 71 and 3 threaded connection of bracing piece, adjust the position of bottom plate 73, run through fixed orifices 76 respectively using outside stainless steel pole, be favorable to supporting plate 1 and placing box 61 and carry out the support work at the in-process that uses, prevent support plate 1 and place box 61 and incline after influence the work, thereby accomplish the work of combination plate.
Utilize technical scheme, or technical personnel in the field are in the utility model discloses under technical scheme's the inspiration, design similar technical scheme, and reach above-mentioned technological effect, all fall into the utility model discloses a protection scope.

Claims (5)

1. A vertical combined plate of a fabricated building comprises a supporting plate block (1), a first U-shaped seat (2), a supporting rod (3), a sliding rod (4), a locking nut (5), a splicing supporting and placing box structure (6) and a movable supporting and pushing pipe structure (7), wherein the middle position of the upper part of the right side of the supporting plate block (1) is connected with the first U-shaped seat (2) through a bolt; a supporting rod (3) is connected with the middle position of the inside of the right side of the first U-shaped seat (2) through a pin shaft; the middle position of the lower part of the front surface and the middle position of the lower part of the rear surface of the supporting plate block (1) are respectively connected with a sliding rod (4) through bolts; the outer wall of the sliding rod (4) is respectively in threaded connection with a locking nut (5); the splicing support placing box structure is characterized in that the splicing support placing box structure (6) in the vertical combined plate of the prefabricated building is fixed on the outer wall of the support plate (1); the movable supporting push pipe structure (7) is arranged on the outer wall of the supporting rod (3).
2. The vertical combination plate of the fabricated building as claimed in claim 1, wherein the splicing supporting box structure (6) comprises a box (61), a fixing ring (62), a plug rod (63), a sliding hole (64) and a splicing plate (65), the fixing ring (62) is bolted to the middle position of the right side of the box (61); the inner part of the fixed ring (62) is inserted with an insertion rod (63); the middle position of the front surface and the middle position of the rear surface of the placing box (61) are respectively provided with a sliding hole (64); the splicing plates (65) are respectively connected to the left side of the front surface and the left side of the rear surface of the placing box (61) through bolts.
3. The vertical modular panel for prefabricated buildings according to claim 1, wherein said movable supporting push pipe structure (7) comprises a supporting pipe (71), a second U-shaped seat (72), a bottom plate (73), an inverted U-shaped frame (74), a moving wheel (75) and a fixing hole (76), wherein the lower end of said supporting pipe (71) is pivotally connected to the middle position inside the upper end of said second U-shaped seat (72); the second U-shaped seat (72) is connected to the middle position of the upper end of the bottom plate (73) through a bolt; the middle position of the lower end of the bottom plate (73) is connected with an inverted U-shaped frame (74) through a bolt; a moving wheel (75) is arranged in the middle of the lower end of the inverted U-shaped frame (74); the fixing holes (76) are respectively formed in the middle of the inner portions of the left side and the right side of the bottom plate (73).
4. The vertical combination block of a prefabricated building according to claim 2, wherein the lower end of the support block (1) is inserted into the middle of the upper end of the placing box (61); the sliding rods (4) respectively penetrate through the sliding holes (64) in a sliding manner; the locking nuts (5) are respectively arranged on the front surface and the rear surface of the placing box (61); the placing boxes (61) are arranged in an adsorption mode through splicing plates (65).
5. The vertical modular panel for prefabricated buildings as claimed in claim 3, wherein the support pipe (71) is screw-coupled to the lower portion of the outer wall of the support rod (3), and the support pipe (71) is disposed at the right middle position of the support panel (1).
CN202221553992.7U 2022-06-21 2022-06-21 Vertical combination plate of prefabricated building Active CN217760165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221553992.7U CN217760165U (en) 2022-06-21 2022-06-21 Vertical combination plate of prefabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221553992.7U CN217760165U (en) 2022-06-21 2022-06-21 Vertical combination plate of prefabricated building

Publications (1)

Publication Number Publication Date
CN217760165U true CN217760165U (en) 2022-11-08

Family

ID=83894519

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221553992.7U Active CN217760165U (en) 2022-06-21 2022-06-21 Vertical combination plate of prefabricated building

Country Status (1)

Country Link
CN (1) CN217760165U (en)

Similar Documents

Publication Publication Date Title
CN110303341B (en) Multifunctional steel structure cutting and drilling device
CN217760165U (en) Vertical combination plate of prefabricated building
CN217782356U (en) Novel house of steel construction of prefabricated building
CN217518226U (en) Turbo generator base direct-burried sleeve adjusting device
CN217151174U (en) Construction is with convenient to detach's supplementary installation device of scaffold frame
CN212743530U (en) Positioning and fastening device suitable for assembled transformer substation module wallboard
CN215168502U (en) Environment-friendly energy-saving type steel structure factory building has
CN112900913A (en) Auxiliary reinforcing device for building wall
CN216552960U (en) Scaffold frame for building repair convenient to dismantle installation
CN214194978U (en) Structure is built in quick detachable interim room
CN221073411U (en) Temporary frame for building structure
CN216038226U (en) Mountain region pipeline salvagees portal frame
CN214169565U (en) Transverse connection structure of cast-in-place shear wall and prefabricated shear wall
CN218648758U (en) Grouting-free dry prefabricated assembly type photovoltaic support base
CN216664493U (en) Assembled equipment room
CN221125660U (en) Transformer installation support frame
CN219159885U (en) Fixing device for installing electromechanical equipment
CN217150149U (en) Joist pulls out post and subsides observation device
CN221479262U (en) Hoisting equipment for photovoltaic bracket
CN219045218U (en) Steel construction assembled wallboard node
CN113309307B (en) Assembled stair with height-adjustable steps
CN216640906U (en) Precast concrete beam column node structure
CN214101263U (en) Adjustable photovoltaic support of manual push rod
CN221348667U (en) Adjustable extension rod support frame
CN216276145U (en) Assembled steel structure building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A vertical composite panel for prefabricated buildings

Granted publication date: 20221108

Pledgee: Ningxiang sub branch of Bank of Changsha Co.,Ltd.

Pledgor: Changsha Dingsheng Heavy Industry Technology Co.,Ltd.

Registration number: Y2024980037998