CN215164542U - Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope - Google Patents

Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope Download PDF

Info

Publication number
CN215164542U
CN215164542U CN202120885852.9U CN202120885852U CN215164542U CN 215164542 U CN215164542 U CN 215164542U CN 202120885852 U CN202120885852 U CN 202120885852U CN 215164542 U CN215164542 U CN 215164542U
Authority
CN
China
Prior art keywords
steel trestle
steel
packway
pavement
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120885852.9U
Other languages
Chinese (zh)
Inventor
李聪安
梁现培
杨锋
杨硕
崔恩豪
邬志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Zhejiang Huadong Engineering Construction Management Co Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Zhejiang Huadong Engineering Construction Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd, Zhejiang Huadong Engineering Construction Management Co Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202120885852.9U priority Critical patent/CN215164542U/en
Application granted granted Critical
Publication of CN215164542U publication Critical patent/CN215164542U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model relates to a mend steel trestle structure of neat high steep rock excavation slope disappearance packway. The utility model aims at providing a mend steel trestle structure of neat high steep rock excavation side slope disappearance packway can effectively solve the high slope excavation in-process and lead to the unable current problem of packway disappearance because of surpassing to dig to guarantee the current safety of side slope inspection staff or observation personnel on the high slope packway. The technical scheme of the utility model is that: the utility model provides a mend steel trestle structure of high steep rock excavation slope disappearance packway which characterized in that: the steel trestle is used for filling the missing part of the pavement, is fixed at the position horizontal to the pavement through a pavement supporting structure, and forms a new channel by combining the steel trestle and the pavement. The utility model is suitable for a side slope excavation engineering among civil engineering such as water conservancy and hydropower, building and traffic is particularly useful for arranging the high steep rock slope excavation packway of observation instrument.

Description

Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope
Technical Field
The utility model relates to a mend steel trestle structure of neat high steep rock excavation slope disappearance packway. The method is suitable for slope excavation engineering in civil engineering such as water conservancy and hydropower engineering, buildings, traffic engineering and the like, and is particularly suitable for excavating the packway on the steep rock slope with the observation instrument.
Background
In the construction of large-scale hydroelectric hydraulic engineering, high slope excavation engineering is mostly involved, such as high arch dam abutment excavation, stone yard excavation and the like. In order to ensure the safety of the construction period and the operation period of the excavated high slope and timely master the safety condition of key parts, a safety worker needs to regularly patrol the slope, monitoring instruments are arranged on the high and steep excavated slope, and an observer needs to regularly maintain the observation instruments, collect data and the like. In the actual side slope excavation process, when unfavorable geological structures such as unfavorable structural planes or steep dip cracks are met, the side slope berm is mostly subjected to an over-excavation phenomenon, so that the berm is lost, and personnel cannot pass.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is: in order to solve the technical problem, the utility model provides a mend steel trestle structure of neat high steep rocky excavation side slope disappearance packway can effectively solve the high slope excavation in-process and lead to the unable current problem of packway disappearance because of the overexcavation to guarantee the current safety of side slope inspection personnel or observation personnel on the high slope packway.
The utility model adopts the technical proposal that: the utility model provides a mend steel trestle structure of high steep rock excavation slope disappearance packway which characterized in that: the steel trestle is used for filling the missing part of the pavement, is fixed at the position horizontal to the pavement through a pavement supporting structure, and forms a new channel by combining the steel trestle and the pavement.
Preferably, the pavement supporting structure is provided with a plurality of anchor bars, channel steel and connecting bars, the anchor bars are respectively arranged below the inner side and the outer side of the steel trestle, the anchor bars are inserted into bedrock of a missing part of the pavement, the channel steel for increasing the supporting stress area of the steel trestle is arranged between the anchor bars and the steel trestle, the channel steel is in welded connection with the anchor bars, the channel steel is in welded connection with the steel trestle, the anchor bars are connected with one another through the connecting bars, and the anchor bars are welded with the connecting bars.
As preferred, install handrail in the outside of steel trestle, handrail is formed by a plurality of horizontal handrails and the welding of vertical handrail, a plurality of dowel bars of evenly distributed around the bottom of vertical handrail, and in the dowel bar inserted the bedrock at packway disappearance position, dowel bar and vertical handrail welded connection.
Preferably, the steel trestle is made of a fish scale pattern steel plate.
The utility model has the advantages that: the utility model discloses simple structure, construction convenience, the construction does not relate to heavy material and equipment, is convenient for transport and construction on high abrupt slope packway. The steel trestle adopts the fish scale pattern steel plate, so that the safety of the riding track in the passing process is improved; channel steel is welded between the steel trestle and the anchor bars, so that the supporting stress area of the steel trestle is increased, and the structural stability of the steel trestle is ensured; the steel landing stage outside sets up the effective current safety of guarantee of handrail, and the last welding of handrail has the joint bar of anchor on the basement rock, has increased handrail's stability.
Drawings
Fig. 1 is a typical cross-sectional layout of the present invention.
Fig. 2 is a schematic plan view of the present invention.
Fig. 3 is a vertical view of the steel trestle structure of the present invention.
Fig. 4 is a layout view of the handrail of the present invention.
Fig. 5 is a sectional view a-a of fig. 4.
In the figure: 1. handrail, 101, dowel bar, 102, horizontal handrail, 103, vertical handrail, 2, steel trestle, 3, channel-section steel, 4, anchor bar, 401, the connection muscle.
Detailed Description
The embodiment is a steel trestle structure for filling up a high and steep rock excavation slope missing pavement, and the steel trestle structure is provided with a steel trestle, a handrail and a supporting structure.
In the embodiment, the steel trestle is erected on the missing part of the pavement formed by excavation through the supporting structure, the steel trestle is supported at the same horizontal position as the existing pavement, the steel trestle and the pavement are combined to form a new channel, and the steel trestle adopts the fish scale pattern steel plate, so that the anti-skidding capacity is good, and the passing requirement of personnel is met.
In this embodiment, the steel trestle passes through the anchor bar support, and the anchor bar is arranged respectively in the inside and outside of steel trestle bottom packway, and the anchor bar adopts the C32 reinforcing bar, and long 1m, anchor go into basement rock length and be not less than 0.5m, and anchor bar top welding channel-section steel increases the lifting surface area of steel trestle, makes the steel trestle structure more stable. The outside anchor bars of the packway are connected through the contact bars, the exposed length of the inside anchor bars of the packway exceeds 0.5m and is also connected through the contact bars, the contact bars are C16 steel bars, and the contact bars are welded with the anchor bars.
In this embodiment, the handrail installed in the steel trestle outside is formed by horizontal handrail and the welding of vertical handrail, and horizontal handrail interval 0.4m arranges, and vertical handrail interval 1m arranges, has enclosed 3 dowels respectively around the bottom of every vertical handrail, and the dowel adopts the C25 reinforcing bar, long 1m, and the dowel anchor goes into bed rock 0.6m, and every dowel all with the two-sided welding of vertical handrail.
The above-mentioned embodiment is only used for explaining the utility model concept, and not to the limit of the utility model protection, and all utilize this concept to be right the utility model discloses carry out insubstantial change, all shall fall into the scope of protection of the utility model.

Claims (4)

1. The utility model provides a mend steel trestle structure of high steep rock excavation slope disappearance packway which characterized in that: the steel trestle is used for filling the missing part of the pavement, is fixed at the position horizontal to the pavement through a pavement supporting structure, and is combined with the missing pavement to form a new channel.
2. The steel trestle structure for supplementing missing packways on steep rocky excavation slopes according to claim 1, wherein: the road surface supporting structure is provided with a plurality of anchor bars, channel steel and connection bars, the anchor bars are arranged below the inner side and the outer side of the steel trestle respectively, the anchor bars are inserted into bedrock of a missing part of a packway, the channel steel for increasing the supporting stress area of the steel trestle is arranged between the anchor bars and the steel trestle, the channel steel is connected with the anchor bars in a welding mode, the channel steel is connected with the steel trestle in a welding mode, the anchor bars are connected with the connection bars in a connecting mode, and the anchor bars are welded with the connection bars.
3. The steel trestle structure for supplementing missing packways on steep rocky excavation slopes according to claim 1, wherein: install handrail in the outside of steel trestle, handrail is formed by a plurality of horizontal handrail and the welding of vertical handrail, a plurality of dowel bars of evenly distributed around the bottom of vertical handrail, and in the dowel bar inserted the bedrock at packway disappearance position, dowel bar and vertical handrail welded connection.
4. The steel trestle structure for supplementing missing packways on steep rocky excavation slopes according to claim 1, wherein: the steel trestle is made of a fish scale pattern steel plate.
CN202120885852.9U 2021-04-27 2021-04-27 Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope Active CN215164542U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120885852.9U CN215164542U (en) 2021-04-27 2021-04-27 Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120885852.9U CN215164542U (en) 2021-04-27 2021-04-27 Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope

Publications (1)

Publication Number Publication Date
CN215164542U true CN215164542U (en) 2021-12-14

Family

ID=79364121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120885852.9U Active CN215164542U (en) 2021-04-27 2021-04-27 Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope

Country Status (1)

Country Link
CN (1) CN215164542U (en)

Similar Documents

Publication Publication Date Title
CN101963061B (en) Construction method for underground box culvert of existing railway line
CN201962558U (en) High-steepness side slope subgrade structure for mountainous area
CN110359540B (en) Manual pipe jacking construction method for shallow-covered large-pipe-diameter high-water-level existing road
CN102926299A (en) Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN102352590A (en) Method for splicing highfill roadbed by adopting pile-sheet retaining wall
CN105714831A (en) Abnormal-shape double-row pile for supporting foundation pit side wall and construction method of abnormal-shape double-row pile
CN103711056B (en) Steel tool-type temporary construction road and construction method thereof
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
CN207017275U (en) Recyclable system of deep foundation pit support can be assembled
CN107905809B (en) Double-hole hollow rectangular section beam bearing cutting type arched tunnel lining structure
CN111997043A (en) Segmented reinforcement cage and diaphragm wall construction method under low-clearance high-voltage line
CN102146676A (en) High-steep side slope subgrade structure for mountain area
CN113389558B (en) TBM (Tunnel boring machine) starting platform for narrow space and construction method thereof
CN108708290B (en) Box bridge frame hollow structure of small-radius railway curve unit and cast-in-place construction method
CN108397198A (en) Assembly recovery type prestressing force branch protecting assembly for underground shaft
US11821316B1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN211200459U (en) Piping lane normal position protection architecture
CN215164542U (en) Steel trestle structure for filling missing sidewalks of high and steep rock excavation slope
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN207293981U (en) The hanging apparatus of two lining trolleys in a kind of sand gravel tunnel
CN204590035U (en) Single layered stereo is prefabricated with excavation of foundation pit assembling sunk type construction cat ladder
CN201883453U (en) Combined pipe jacking working well
CN113898006B (en) Stable and rapid jacking construction method for box culvert under large excavation surface
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN208441831U (en) Assembly recovery type prestressing force branch protecting assembly for underground shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant