CN214819511U - Concrete curing room - Google Patents

Concrete curing room Download PDF

Info

Publication number
CN214819511U
CN214819511U CN202120819107.4U CN202120819107U CN214819511U CN 214819511 U CN214819511 U CN 214819511U CN 202120819107 U CN202120819107 U CN 202120819107U CN 214819511 U CN214819511 U CN 214819511U
Authority
CN
China
Prior art keywords
scraper blade
scraper
room body
maintenance room
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120819107.4U
Other languages
Chinese (zh)
Inventor
左军平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Fengdong Xincheng Concrete Co ltd
Original Assignee
Shaanxi Fengdong Xincheng Concrete Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Fengdong Xincheng Concrete Co ltd filed Critical Shaanxi Fengdong Xincheng Concrete Co ltd
Priority to CN202120819107.4U priority Critical patent/CN214819511U/en
Application granted granted Critical
Publication of CN214819511U publication Critical patent/CN214819511U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a concrete curing room, it includes the curing room body, collecting vat and clearance mechanism, this internal top slope setting of curing room, this internal lateral wall top of curing room is located to the collecting vat, and the collecting vat is located the lower one side in curing room body top, and the collecting vat sets up along the length direction of curing room body lateral wall, and clearance mechanism is used for clearing up the water that condenses at curing room body top to the collecting vat. This application has and avoids the direct concrete test block surface that drips, causes the effect of damage to the concrete test block.

Description

Concrete curing room
Technical Field
The application relates to the technical field of concrete curing, in particular to a concrete curing room.
Background
The concrete curing room is a room with specific temperature and humidity and used for storing concrete test pieces and performing standard curing on the concrete test pieces and cement test bodies. When the concrete does not have sufficient strength, the early evaporation of water causes large shrinkage deformation and cracks due to drying shrinkage, so that the test block after concrete pouring needs to be cured in a concrete curing chamber.
The utility model discloses a chinese utility model patent that is applying for CN202020116122.8 discloses a concrete curing room, including the maintenance cavity, maintenance cavity one side is equipped with steam generator, steam generator one side is equipped with the water source, the water source intercommunication has the water pump inlet tube, water service pipe perisporium intercommunication has a plurality of spray pipes, the spray pipe tip is equipped with a plurality of shower nozzles, maintenance cavity diapire is equipped with the recess, be equipped with the motor in the recess, motor output shaft free end fixedly connected with first bevel gear, the recess diapire just rotates to be connected with the second bevel gear with first bevel gear engaged with the water service pipe, the second bevel gear centre of a circle is fixed with the pivot, the pivot perisporium is fixed with a plurality of dwangs that are the circumference and distribute as the centre of a circle with the pivot axis, the dwang end fixing has the annular rolling stock that sets up as the centre of a circle with the pivot axis, annular rolling stock bottom is equipped with the universal wheel.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: when carrying out the maintenance through the shower nozzle to the indoor water spray of maintenance, can condense into the water droplet at indoor top easily, when the water droplet grow of condensing, the water droplet directly falls and causes concrete test piece surface damage easily to influence the performance of concrete test piece.
SUMMERY OF THE UTILITY MODEL
In order to avoid the water droplet to drip the concrete test block surface, cause the damage to the concrete test block, this application provides a concrete curing room.
The application provides a concrete curing room adopts following technical scheme:
the utility model provides a concrete curing room, includes the curing room body, collecting vat and clearance mechanism, this internal top slope of curing room sets up, the collecting vat is located this internal lateral wall top of curing room, the collecting vat is located the lower one side in curing room body top, the collecting vat sets up along the length direction of curing room body lateral wall, clearance mechanism is used for clearing up the water that condenses at curing room body top to the collecting vat.
Through adopting above-mentioned technical scheme, when carrying out the maintenance to the concrete test block through the curing room, because water smoke is at indoor top condensate water droplet, through the top slope setting of the curing room body that sets up, the water droplet at this internal top of curing room is continuously cleared up through clearance mechanism to collect in the collection groove, avoid the top water droplet to condense on the too big direct falling area test block, avoid the concrete test block surface to be destroyed.
Optionally, clearance mechanism includes scraper blade, water receiving tank and drive assembly, the scraper blade is located the top of curing chamber body, the both ends of scraper blade respectively with the lateral wall sliding connection of curing chamber body, the scraper blade with curing chamber body top butt, scraper blade length direction sets up along the direction of curing chamber body top slope, the water receiving tank is located respectively the both sides of scraper blade, and follow the scraper blade length direction sets up, the notch of water receiving tank up, the lower one end of water receiving tank stretches into in the collecting vat, drive assembly is used for ordering about the scraper blade is followed curing chamber body top reciprocating motion.
Through adopting above-mentioned technical scheme, at the in-process that clears up the water droplet at this internal top of curing room, order about the scraper blade through drive assembly and remove along the curing room top, at the in-process that the scraper blade removed, the in-process of scraping the water droplet at top through the scraper blade, make the water droplet flow in to the collecting tank along the water receiving tank of scraper blade both sides, continuously order about scraper blade reciprocating motion through drive assembly, the water droplet that condenses the curing room body top clears up, the direct drop of the water droplet grow of avoiding condensing is on the concrete test block, and then realize the cleaning effect to curing room body top water droplet.
Optionally, the driving assembly comprises a screw rod and a motor, the screw rod is horizontally connected with the curing chamber body in a rotating mode, the screw rod penetrates through the scraper plate and the scraper plate in a threaded connection mode, the axial direction of the screw rod is perpendicular to the scraper plate, one end of the screw rod extends out of the curing chamber body, the motor is arranged outside the curing chamber body, and the motor is used for driving the screw rod to rotate.
Through adopting above-mentioned technical scheme, carrying out the in-process of clearing up to the drop of water, order about the lead screw through the motor and rotate, because threaded connection between lead screw and scraper blade, the lead screw pivoted in-process orders about the scraper blade and removes, realizes the clearance effect to the drop of water at curing chamber body top, and the motor through setting up is outside the curing chamber body, because humidity is great in the curing chamber, when the motor is in the curing chamber, because great humidity in the curing chamber influences the life of motor.
Optionally, the curing chamber body side wall close to the two ends of the scraper is provided with a support plate, the support plate is arranged along the length direction of the curing chamber body side wall, the two ends of the scraper are provided with rollers, and the rollers are connected to the top of the support plate in a rolling manner.
Through adopting above-mentioned technical scheme, play the direction supporting role through the backup pad that sets up for the gyro wheel at scraper blade both ends rolls along the backup pad, and then makes the removal of scraper blade more smooth and easy, and it is more stable to remove.
Optionally, the curing room further comprises a sewer pipe and a water tank, the water tank is arranged at the bottom in the curing room body, and the bottom of the collecting tank is communicated with the water tank through the sewer pipe.
Through adopting above-mentioned technical scheme, collect the back through the collecting vat to the water after the clearance, enter into the water tank through the downcomer in, and then the convenience is retrieved water and is recycled, and then the effectual water resource of having practiced thrift, the waste of reduction water.
Optionally, a flexible strip is arranged on the contact surface of the scraper and the top of the curing chamber body, and the flexible strip is abutted to the top of the curing chamber body.
Through adopting above-mentioned technical scheme, through setting up flexible strip on the scraper blade, moving the in-process that carries out the clearance to the drop of water at maintenance room body top through the scraper blade, through flexible strip maintenance room body top direct contact, avoid because long-time in-process to maintenance room body top clearance, cause the damage to maintenance room body top surface, and effectively improve the clearance effect to the drop of water.
Optionally, the flexible strip is detachably connected to the scraper.
Through adopting above-mentioned technical scheme, can dismantle between flexible strip and the scraper blade through setting up and be connected, after long-time practicality, when flexible strip wearing and tearing are serious, the convenience is changed flexible strip.
Optionally, a guide rod is arranged at the top in the curing chamber body, the guide rod penetrates through the scraper and is in sliding connection with the scraper, and the guide rod is perpendicular to the scraper.
Through adopting above-mentioned technical scheme, through the guide bar that sets up, play direction and limiting displacement to the removal of scraper blade for the removal of scraper blade is more stable.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the top of the curing room body is obliquely arranged, and water drops on the top in the curing room body are cleaned through the cleaning mechanism, so that the phenomenon that water drops on the top are condensed too much and directly fall on a belt test block is avoided, and the surface of the concrete test block is prevented from being damaged;
2. the cleaning mechanism comprises a scraper plate, water receiving grooves and a driving assembly, the driving assembly drives the scraper plate to move along the top of the curing chamber, and in the process of moving the scraper plate, water drops on the top are scraped by the scraper plate, so that the water drops flow into the collecting grooves along the water receiving grooves on the two sides of the scraper plate, and the condensed water drops on the top of the curing chamber body are cleaned;
3. through the flexible strip of detachable that sets up on the scraper blade, not only can improve the drop of water clearance effect to the curing room body top, can prevent effectively moreover that the scraper blade from causing the damage to curing room body top.
Drawings
FIG. 1 is a schematic structural view of a concrete curing room according to an embodiment of the present invention.
FIG. 2 is a schematic structural view of a concrete curing room hiding the top of the curing room body according to an embodiment of the present application.
Fig. 3 is an enlarged schematic view of a portion a in fig. 2.
Reference numerals: 1. a curing chamber body; 11. an entrance and exit door; 2. collecting tank; 3. a cleaning mechanism; 31. a squeegee; 311. a flexible strip; 312. mounting grooves; 32. a water receiving tank; 33. a drive assembly; 331. a lead screw; 332. a motor; 34. a support plate; 35. a roller; 36. a guide bar; 4. a water pipe; 5. a water tank.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses a concrete curing room. Referring to fig. 1 and 2, the concrete curing room includes curing room body 1, collecting vat 2 and cleaning mechanism 3, top slope in the curing room body 1 sets up, an access door 11 is installed to one side lateral wall of curing room body 1, collecting vat 2 is installed at the lateral wall top in curing room body 1, collecting vat 2 is located the lower one side in curing room body 1 top, the notch of collecting vat 2 up, collecting vat 2 sets up along the length direction of curing room body 1 lateral wall, collect the water that condenses to curing room body 1 roof through collecting vat 2, still include downcomer 4 and water tank 5, water tank 5 places the bottom in curing room body 1, communicate through downcomer 4 between collecting vat 2 bottom and water tank 5, the water that collecting vat 2 collected collects is through downcomer 4 and is carried out reuse in collecting water tank 5, reduce the waste of water resource.
Referring to fig. 2 and 3, the cleaning mechanism 3 is used to clean water condensed on the top of the curing chamber body 1 into the collection tub 2. Cleaning mechanism 3 includes scraper blade 31, water receiving tank 32 and drive assembly 33, scraper blade 31 installs in the top of curing chamber body 1, scraper blade 31's both ends respectively with curing chamber body 1's lateral wall sliding connection, scraper blade 31 and curing chamber body 1 top butt, the direction setting of 1 top slope of curing chamber body is followed to scraper blade 31 length direction, water receiving tank 32 welds respectively in scraper blade 31's both sides, and set up along scraper blade 31 length direction, the notch of water receiving tank 32 up, the lower one end of water receiving tank 32 stretches into in the collecting vat 2, scraper blade 31 removes along curing chamber body 1 top, at the in-process that scraper blade 31 removed, the in-process of scraping the water droplet at top through scraper blade 31, make water flow into in to collecting vat 2 along the water receiving tank 32 of scraper blade 31 both sides.
Referring to fig. 2 and 3, the driving assembly 33 is used to drive the scraper 31 to reciprocate along the top of the chamber body 1. The driving assembly 33 comprises a screw 331 and a motor 332, the screw 331 is horizontally connected with the inside of the curing chamber body 1 in a rotating manner, the screw 331 penetrates through the scraper 31 and is in threaded connection with the scraper 31, the axial direction of the screw 331 is perpendicular to the scraper 31, one end of the screw 331 extends out of the curing chamber body 1, the motor 332 is installed outside the curing chamber body 1 through a motor shell, the motor 332 is used for driving the screw 331 to rotate, the output shaft of the motor 332 is coaxially connected with the screw 331, the motor 332 drives the screw 331 to rotate, due to the threaded connection between the screw 331 and the scraper 31, the scraper 31 is driven to move in the rotating process of the screw 331, and water drops on the top of the curing chamber body 1 are cleaned.
Referring to fig. 2 and 3, be close to respectively that the maintenance room body 1 lateral wall at scraper blade 31 both ends goes up horizontal installation and has backup pad 34, and backup pad 34 sets up along the length direction of maintenance room body 1 lateral wall, and gyro wheel 35 is all installed at scraper blade 31's both ends, and gyro wheel 35 roll connection is in backup pad 34 top, and gyro wheel 35 can roll along backup pad 34 length direction for scraper blade 31's removal is more smooth and easy, removes more stably. Guide bar 36 is installed at the top in the curing chamber body 1, the both ends of guide bar 36 all with the lateral wall fixed connection of curing chamber body 1, guide bar 36 passes scraper 31 and scraper 31 sliding connection, guide bar 36 is perpendicular with scraper 31, at the in-process that scraper 31 removed, scraper 31 slides along guide bar 36, guide bar 36 plays direction and limiting displacement to scraper 31's removal for scraper 31's removal is more stable.
Referring to fig. 2 and 3, the flexible strip 311 is installed on the contact surface between the scraper 31 and the top of the curing chamber body 1, and the top of the curing chamber body 1 is directly contacted through the flexible strip 311, so that the damage to the top surface of the curing chamber body 1 caused by long-time cleaning of the top of the curing chamber body 1 is avoided. The flexible strip 311 is abutted against the top of the curing chamber body 1, and the flexible strip 311 is detachably connected to the scraper 31. Mounting groove 312 has been seted up along length direction at scraper blade 31 top, and flexible strip 311 is installed in mounting groove 312, when flexible strip 311 wearing and tearing are serious, conveniently changes flexible strip 311.
The implementation principle of a concrete curing room of the embodiment of the application is as follows: in-process of carrying out the maintenance to the concrete test block, order about lead screw 331 through motor 332 and rotate, because threaded connection between lead screw 331 and scraper blade 31, lead screw 331 pivoted in-process orders about scraper blade 31 and removes, the in-process that scraper blade 31 removed, scraper blade 31 drives flexible strip 311 and removes, the in-process of scraping the water droplet at curing chamber body 1 top through flexible strip 311, make water flow into to collection tank 2 along the water receiving tank 32 of scraper blade 31 both sides, in collecting water tank 5 through downcomer 4, through ordering about scraper blade 31 along curing chamber body 1 top reciprocating continuous motion to the drop of water that condenses, avoid the top water droplet to condense and directly drop on the belt test block and be destroyed the concrete test block surface.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. A concrete curing room is characterized in that: including maintenance room body (1), collecting vat (2) and clearance mechanism (3), top slope in maintenance room body (1) sets up, collecting vat (2) are located lateral wall top in maintenance room body (1), collecting vat (2) are located the lower one side in maintenance room body (1) top, collecting vat (2) set up along the length direction of maintenance room body (1) lateral wall, clearance mechanism (3) are used for clearing up the water that condenses at maintenance room body (1) top to the collecting vat (2).
2. A concrete curing room as defined in claim 1, wherein: clearance mechanism (3) are including scraper blade (31), water receiving tank (32) and drive assembly (33), scraper blade (31) are located the top of maintenance room body (1), the both ends of scraper blade (31) respectively with the lateral wall sliding connection of maintenance room body (1), scraper blade (31) with maintenance room body (1) top butt, scraper blade (31) length direction sets up along the direction of maintenance room body (1) top slope, water receiving tank (32) are located respectively the both sides of scraper blade (31), just follow scraper blade (31) length direction sets up, the notch of water receiving tank (32) up, the lower one end of water receiving tank (32) stretches into in collecting vat (2), drive assembly (33) are used for ordering about scraper blade (31) are followed maintenance room body (1) top reciprocating motion.
3. A concrete curing room as defined in claim 2, wherein: the drive assembly (33) comprises a lead screw (331) and a motor (332), the lead screw (331) is horizontally connected with the inside of the curing chamber body (1) in a rotating mode, the lead screw (331) penetrates through the scraper (31) and the scraper (31) in a threaded mode, the axial direction of the lead screw (331) is perpendicular to the scraper (31), one end of the lead screw (331) extends out of the curing chamber body (1), the motor (332) is arranged outside the curing chamber body (1), and the motor (332) is used for driving the lead screw (331) to rotate.
4. A concrete curing room as defined in claim 2, wherein: be close to respectively scraper blade (31) both ends be equipped with backup pad (34) on curing chamber body (1) lateral wall, backup pad (34) set up along the length direction of curing chamber body (1) lateral wall, the both ends of scraper blade (31) all are equipped with gyro wheel (35), gyro wheel (35) roll connection in backup pad (34) top.
5. A concrete curing room as defined in claim 1, wherein: the maintenance room is characterized by further comprising a sewer pipe (4) and a water tank (5), wherein the water tank (5) is arranged at the bottom inside the maintenance room body (1), and the bottom of the collecting tank (2) is communicated with the water tank (5) through the sewer pipe (4).
6. A concrete curing room as defined in claim 2, wherein: the flexible maintenance room is characterized in that a flexible strip (311) is arranged on the contact surface of the scraper (31) and the top of the maintenance room body (1), and the flexible strip (311) is abutted to the top of the maintenance room body (1).
7. A concrete curing room as defined in claim 6, wherein: the flexible strip (311) is detachably connected to the scraper (31).
8. A concrete curing room as defined in claim 7, wherein: the top is equipped with guide bar (36) in curing chamber body (1), guide bar (36) pass scraper blade (31) and scraper blade (31) sliding connection, guide bar (36) are perpendicular with scraper blade (31).
CN202120819107.4U 2021-04-20 2021-04-20 Concrete curing room Active CN214819511U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120819107.4U CN214819511U (en) 2021-04-20 2021-04-20 Concrete curing room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120819107.4U CN214819511U (en) 2021-04-20 2021-04-20 Concrete curing room

Publications (1)

Publication Number Publication Date
CN214819511U true CN214819511U (en) 2021-11-23

Family

ID=78765282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120819107.4U Active CN214819511U (en) 2021-04-20 2021-04-20 Concrete curing room

Country Status (1)

Country Link
CN (1) CN214819511U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114102826A (en) * 2021-12-27 2022-03-01 嘉兴市通程塑业有限公司 Precast concrete pile is with evaporating foster system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114102826A (en) * 2021-12-27 2022-03-01 嘉兴市通程塑业有限公司 Precast concrete pile is with evaporating foster system

Similar Documents

Publication Publication Date Title
CN214819511U (en) Concrete curing room
CN207073095U (en) A kind of bridge beam gap residue remove device with dust exhaust apparatus
CN219504451U (en) Rust removal cleaning structure
CN110354590A (en) A kind of metal screen air cleaning unit using steam self-cleaning technology
CN108894527A (en) A kind of cleaning device of high-altitude metope
CN211726690U (en) Cleaning equipment for punching machining of bearing bush
CN212818331U (en) Slag scraping pool for sewage treatment
CN114232386A (en) Special paper processing is with rubber coating device
CN214004679U (en) Energy-saving roll-type leather staking equipment
CN216474767U (en) Building construction working face sprays dust fall heat sink
CN220376416U (en) Waste water drying device
CN220011566U (en) Material guiding machine
CN217912046U (en) Cleaning equipment for glass processing
CN215031622U (en) Automobile brake detection platform
CN220878018U (en) Pickling waste acid treatment device
CN214862199U (en) Special wet dust collector of slag production line
CN220038518U (en) Electricity generation waste heat recovery device
CN216152839U (en) Epoxy steel band cooling arrangement
CN219091545U (en) Wet dust collector for sand blasting workshop
CN215562980U (en) Green water circulating system that plants of municipal administration
CN216572244U (en) Electromechanical engineering workshop environmental protection dust collector
CN220610607U (en) Organic fertilizer rolls and breaks up device
CN214862297U (en) Dust collector for highway construction
CN220771207U (en) Hydraulic decoupler with dirt removing function
CN213294900U (en) Leather processing sewage treatment plant

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A concrete curing room

Effective date of registration: 20221101

Granted publication date: 20211123

Pledgee: Xi'an innovation financing Company limited by guarantee

Pledgor: SHAANXI FENGDONG XINCHENG CONCRETE CO.,LTD.

Registration number: Y2022610000693