CN214402722U - Civil engineering construction is with pouring template - Google Patents
Civil engineering construction is with pouring template Download PDFInfo
- Publication number
- CN214402722U CN214402722U CN202120242528.5U CN202120242528U CN214402722U CN 214402722 U CN214402722 U CN 214402722U CN 202120242528 U CN202120242528 U CN 202120242528U CN 214402722 U CN214402722 U CN 214402722U
- Authority
- CN
- China
- Prior art keywords
- template
- formwork
- wall
- civil engineering
- engineering construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 26
- 239000002390 adhesive tape Substances 0.000 claims description 10
- 230000007246 mechanism Effects 0.000 claims description 6
- 238000009415 formwork Methods 0.000 claims 20
- 238000009434 installation Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 239000000853 adhesive Substances 0.000 description 2
- 230000001070 adhesive effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005381 potential energy Methods 0.000 description 2
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000000452 restraining effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Abstract
The utility model provides a civil engineering construction is with pouring template. The pouring template for civil engineering construction comprises a first template; the second template is arranged on one side of the first template; the two fixing plates are respectively fixedly arranged on the outer wall of one side, far away from the first template and the second template; the two mounting grooves are respectively formed in the tops of the two fixing plates; the two threaded rods are rotatably arranged on the inner walls of the two mounting grooves respectively, and the ends, far away from each other, of the two threaded rods extend out of the two mounting grooves respectively and are fixedly provided with handles; and the two thread blocks are respectively sleeved on the two threaded rods in a threaded manner. The utility model provides a civil engineering construction is with pouring template has easy operation, and convenient to use improves work efficiency, prevents to take place the advantage of empting.
Description
Technical Field
The utility model relates to a civil engineering technical field especially relates to a civil engineering construction is with pouring template.
Background
Civil engineering is a general term for scientific technology for building various land engineering facilities. It refers to both the materials, equipment used and the technical activities carried out such as surveying, designing, construction, maintenance, repair, etc., as well as the objects of engineering construction. I.e. various engineering facilities such as houses, roads, railways, pipelines, tunnels, bridges, canals, dams, ports, power stations, airports, ocean platforms, water supply and drainage and protection projects, which are built on or under the ground, on land and directly or indirectly serve human life, production, military affairs and scientific research. When concrete pouring is carried out, the template is needed to be used for restraining the poured concrete space until the poured concrete is solidified and formed, and then the template is detached.
However, when the traditional pouring template is used, a plurality of templates are usually fixed by a large number of bolts, and then the built templates are supported by a plurality of support rods, so that more manpower and time are wasted during installation, and the bolts are also required to be removed one by one when the templates need to be removed, so that the working efficiency is reduced, and the stability is poor.
Therefore, there is a need to provide a new pouring form for civil engineering construction to solve the above technical problems.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem provide an easy operation, convenient to use improves work efficiency, prevents to take place the civil engineering construction of empting with pouring the template.
For solving the technical problem, the utility model provides a civil engineering construction is with pouring template includes: a first template; the second template is arranged on one side of the first template; the two fixing plates are respectively fixedly arranged on the outer wall of one side, far away from the first template and the second template; the two mounting grooves are respectively formed in the tops of the two fixing plates; the two threaded rods are rotatably arranged on the inner walls of the two mounting grooves respectively, and the ends, far away from each other, of the two threaded rods extend out of the two mounting grooves respectively and are fixedly provided with handles; the two thread blocks are respectively sleeved on the two threaded rods in a threaded manner; the two supporting plates are respectively hinged to the tops of the two fixing plates; the two support rods are respectively hinged to the tops of the two thread blocks, and one ends of the two support rods, which are far away from the two thread blocks, are respectively hinged to the outer walls of one sides of the two support plates; and the two mounting mechanisms are respectively arranged on the first template and the second template.
Preferably, the mounting mechanism comprises a cavity, a first clamping rod, a push rod, a spring, a connecting plate, a clamping groove and a second clamping rod, the cavity is arranged on the first template, the first clamping rod is fixedly arranged on the outer wall of one side of the second template close to the first template, the first clamping rod extends into the cavity and is provided with a first arc surface, the push rod is slidably arranged on the inner wall of the cavity, the push rod extends out of the cavity and is fixedly provided with a push block, the spring is movably sleeved on the push rod, one end of the spring is fixedly connected with the outer wall of one side of the first template, the other end of the spring is fixedly connected with the outer wall of one side of the push block, the connecting plate is fixedly arranged on the push rod, the clamping groove is arranged on the outer wall of the first clamping rod, the second clamping rod is fixedly arranged on the outer wall of one side of the connecting plate, the second clamping rod extends into the clamping groove and is provided with a second arc surface, and the second arc surface is matched with the first arc surface.
Preferably, a first sliding hole is formed in the outer wall of one side, close to the second template, of the first template, and the first clamping rod penetrates through the first sliding hole and is in sliding connection with the inner wall of the first sliding hole.
Preferably, a second sliding hole is formed in the outer wall of one side of the first template, and the push rod penetrates through the second sliding hole and is in sliding connection with the inner wall of the second sliding hole.
Preferably, two limiting grooves are formed in the inner walls of the mounting grooves respectively, the bottoms of the thread blocks are fixedly provided with limiting blocks respectively, and the bottoms of the limiting blocks extend into the limiting blocks and are connected with the inner walls of the limiting blocks in a sliding mode.
Preferably, the top of the first template and the top of the second template are respectively and fixedly provided with an inserted bar, the bottom of the first template and the bottom of the second template are respectively provided with a slot, and the two inserted bars are respectively matched with the two inserted bars.
Preferably, the top of the first template and the top of the second template are both provided with a first double faced adhesive tape, and the outer wall of one side of the second template, which is close to the first template, is provided with a second double faced adhesive tape.
Compared with the prior art, the utility model provides a civil engineering construction is with pouring template has following beneficial effect:
the utility model provides a civil engineering construction is with pouring template, first template and second template through setting up can carry out quick concatenation work, time saving and labor saving, improve work efficiency, under the effect of first double faced adhesive tape and second double faced adhesive tape, make first template and second template form an airtight space, prevent to take place outflow when concreting, can build not co-altitude template as required through the slot and the inserted bar that set up, therefore, the clothes hanger is strong in practicability, can play the supporting role to a plurality of first templates and a plurality of second template through the backup pad that sets up, prevent that it from taking place to empty.
Drawings
Fig. 1 is a schematic structural view of a preferred embodiment of a pouring template for civil engineering construction provided by the present invention;
FIG. 2 is a schematic top view of the first and second mold plates shown in FIG. 1;
fig. 3 is an enlarged view of the portion a shown in fig. 2.
Reference numbers in the figures: 1. a first template; 2. a second template; 3. a fixing plate; 4. mounting grooves; 5. a threaded rod; 6. a thread block; 7. a support plate; 8. a support bar; 9. a cavity; 10. a first clamping rod; 11. a push rod; 12. a spring; 13. a connecting plate; 14. a card slot; 15. and a second clamping rod.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and embodiments.
Please refer to fig. 1-3, wherein fig. 1 is a schematic structural diagram of a pouring form for civil engineering construction according to a preferred embodiment of the present invention; FIG. 2 is a schematic top view of the first and second mold plates shown in FIG. 1; fig. 3 is an enlarged view of the portion a shown in fig. 2. Civil engineering construction includes with pouring the template: a first template 1; the second template 2 is arranged on one side of the first template 1; the two fixing plates 3 are respectively fixedly arranged on the outer wall of one side, far away from each other, of the first template 1 and the second template 2; the two mounting grooves 4 are respectively formed in the tops of the two fixing plates 3; the two threaded rods 5 are respectively rotatably installed on the inner walls of the two installation grooves 4, and the ends, far away from each other, of the two threaded rods 5 respectively extend out of the two installation grooves 4 and are fixedly provided with handles; the two thread blocks 6 are respectively sleeved on the two threaded rods 5 in a threaded manner; the two supporting plates 7 are respectively hinged to the tops of the two fixing plates 3; the two support rods 8 are respectively hinged to the tops of the two thread blocks 6, and one ends of the two support rods 8, which are far away from the two thread blocks 6, are respectively hinged to the outer walls of one sides of the two support plates 7; and the two installation mechanisms are respectively arranged on the first template 1 and the second template 2.
The installation mechanism comprises a cavity 9, a first clamping rod 10, a push rod 11, a spring 12, a connecting plate 13, a clamping groove 14 and a second clamping rod 15, wherein the cavity 9 is arranged on the first template 1, the first clamping rod 10 is fixedly arranged on the outer wall of one side of the second template 2 close to the first template 1, the first clamping rod 10 extends into the cavity 9 and is provided with a first arc surface, the push rod 11 is slidably arranged on the inner wall of the cavity 9, the push rod 11 extends out of the cavity 9 and is fixedly provided with a push block, the spring 12 is movably sleeved on the push rod 11, one end of the spring 12 is fixedly connected with the outer wall of one side of the first template 1, the other end of the spring 12 is fixedly connected with the outer wall of one side of the push block, the connecting plate 13 is fixedly arranged on the push rod 11, the clamping groove 14 is arranged on the outer wall of the first clamping rod 10, the second clamping rod 15 is fixedly installed on the outer wall of one side of the connecting plate 13, the second clamping rod 15 extends into the clamping groove 14 and is provided with a second arc surface, and the second arc surface is matched with the first arc surface.
A first sliding hole is formed in the outer wall of one side, close to the second template 2, of the first template 1, and the first clamping rod 10 penetrates through the first sliding hole and is connected with the inner wall of the first sliding hole in a sliding mode.
A second sliding hole is formed in the outer wall of one side of the first template 1, and the push rod 11 penetrates through the second sliding hole and is connected with the inner wall of the second sliding hole in a sliding mode.
Two limiting grooves are respectively formed in the inner wall of the mounting groove 4, two limiting blocks are respectively fixedly mounted at the bottoms of the thread blocks 6, and the bottoms of the limiting blocks respectively extend to the two limiting blocks and are connected with the inner walls of the limiting blocks in a sliding mode.
The top of the first template 1 and the top of the second template 2 are respectively and fixedly provided with an inserted bar, the bottom of the first template 1 and the bottom of the second template 2 are respectively provided with a slot, and the two inserted bars are respectively matched with the two inserted bars.
The top of the first template 1 and the top of the second template 2 are both provided with a first double faced adhesive tape, and the outer wall of one side of the second template 2 close to the first template 1 is provided with a second double faced adhesive tape.
The utility model provides a civil engineering construction is with the theory of operation of pouring the template as follows:
when the template is used, the two fixing plates 3 are placed on the ground, then the first template 1 and the second template 2 are connected, the first clamping rod 10 on the second template 2 is inserted into the cavity 9, further, a first arc surface in the first clamping rod 10 is tangent to a second arc surface on the second clamping rod 15, the first clamping rod 10 drives the second clamping rod 15 to move, the second clamping rod 15 drives the connecting plate 13 and the push rod 11 to slide in the second sliding hole and enable the spring 12 to be in a compressed state, certain elastic potential energy is stored, when the clamping groove 14 on the first clamping rod 10 moves to the position of the second clamping rod 15, the second clamping rod 15 is clamped into the clamping groove 14 under the elastic action of the spring 12, the second clamping rod 15 limits the first clamping rod 10, further, the second double-sided adhesive on the second template 2 is bonded with the first template 1 to prevent the first clamping rod from generating gaps, and accordingly, the connection of the first template 1 and the second template 2 is completed, then continuously accumulating the first template 1 and the second template 2, inserting slots at the bottoms of the first template 1 and the second template 2 on the upper layer into the inserted rods, further bonding the first template 1 and the second template 2 on the upper layer by first double-faced adhesive at the top of the first template 1 and the second template 2 on the bottom layer, building to a certain height, rotating the handle, driving the threaded rod 5 to rotate by the handle, driving the limit block on the threaded block 6 to slide in the limit slot by the threaded rod 5, driving the support rod 8 by the threaded block 6 to support the support plate 7, enabling the support plate 7 to be in contact with the built first template 1 and the built second template 2, supporting the first template 1 and the built second template 2 to prevent the first template 1 and the second template 2 from falling down, pouring concrete into the first template 1 and the second template 2, dismantling the plurality of first templates 1 and the plurality of second templates 2 after the first template 1 and the plurality of second templates 2 are molded to a certain degree, and pressing the push block, the ejector pad drives the motion of push rod 11, spring 12 is compression state this moment, save certain elastic potential energy, push rod 11 drives connecting plate 13 and the motion of second kelly 15 simultaneously, make second kelly 15 withdraw from in draw-in groove 14, thereby first kelly 10 loses the injecing of second kelly 15, thereby can demolish first template 1 and second template 2, then lift first template 1 and the second template 2 of superiors upwards earlier and get, make slot on first template 1 and the second template 2 break away from the inserted bar of bottom, then reverse the handle, make the handle drive backup pad 7 keep away from first template 1 and second template 2, thereby accomplish to its dismantlement work, time saving and labor saving, and the work efficiency is improved.
Compared with the prior art, the utility model provides a civil engineering construction is with pouring template has following beneficial effect:
the utility model provides a civil engineering construction is with pouring template, first template 1 and second template 2 through setting up can carry out quick concatenation work, time saving and labor saving, improve work efficiency, glue under the effect of first double faced adhesive tape and second double faced adhesive tape, make first template 1 and second template 2 form an airtight space, prevent to take place the outflow when concreting, can build the not template of co-altitude as required through the slot that sets up and inserted bar, therefore, the clothes hanger is strong in practicability, backup pad 7 through setting up can play the supporting role to a plurality of first templates 1 and a plurality of second template 2, prevent that it from taking place to empty.
The above only is the embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent processes of the present invention are used in the specification and the attached drawings, or directly or indirectly applied to other related technical fields, and the same principle is included in the protection scope of the present invention.
Claims (7)
1. The utility model provides a civil engineering construction is with pouring template which characterized in that includes:
a first template;
the second template is arranged on one side of the first template;
the two fixing plates are respectively fixedly arranged on the outer wall of one side, far away from the first template and the second template;
the two mounting grooves are respectively formed in the tops of the two fixing plates;
the two threaded rods are rotatably arranged on the inner walls of the two mounting grooves respectively, and the ends, far away from each other, of the two threaded rods extend out of the two mounting grooves respectively and are fixedly provided with handles;
the two thread blocks are respectively sleeved on the two threaded rods in a threaded manner;
the two supporting plates are respectively hinged to the tops of the two fixing plates;
the two support rods are respectively hinged to the tops of the two thread blocks, and one ends of the two support rods, which are far away from the two thread blocks, are respectively hinged to the outer walls of one sides of the two support plates;
and the two mounting mechanisms are respectively arranged on the first template and the second template.
2. The pouring formwork for civil engineering construction according to claim 1, wherein the mounting mechanism comprises a cavity, a first clamping bar, a push bar, a spring, a connecting plate, a clamping groove and a second clamping bar, the cavity is opened on the first formwork, the first clamping bar is fixedly mounted on the outer wall of one side of the second formwork close to the first formwork, the first clamping bar extends into the cavity and is provided with a first arc surface, the push bar is slidably mounted on the inner wall of the cavity, the push bar extends out of the cavity and is fixedly mounted with a push block, the spring is movably sleeved on the push bar, one end of the spring is fixedly connected with the outer wall of one side of the first formwork, the other end of the spring is fixedly connected with the outer wall of one side of the push block, the connecting plate is fixedly mounted on the push bar, the clamping groove is opened on the outer wall of the first clamping bar, the second clamping rod is fixedly installed on the outer wall of one side of the connecting plate, extends into the clamping groove and is provided with a second cambered surface, and the second cambered surface is matched with the first cambered surface.
3. The pouring formwork for civil engineering construction according to claim 2, wherein a first sliding hole is formed in an outer wall of the first formwork on a side close to the second formwork, and the first clamping rod penetrates through the first sliding hole and is connected with an inner wall of the first sliding hole in a sliding manner.
4. The pouring formwork for civil engineering construction according to claim 2, wherein a second slide hole is formed in an outer wall of one side of the first formwork, and the push rod penetrates through the second slide hole and is connected with an inner wall of the second slide hole in a sliding manner.
5. The pouring template for civil engineering construction according to claim 1, wherein the inner walls of the two mounting grooves are respectively provided with a limiting groove, the bottoms of the two thread blocks are respectively fixedly provided with a limiting block, and the bottoms of the two limiting blocks respectively extend into the two limiting blocks and are connected with the inner walls of the two limiting blocks in a sliding manner.
6. The pouring formwork for civil engineering construction according to claim 1, wherein the top of the first formwork and the top of the second formwork are respectively fixedly provided with an inserting rod, the bottom of the first formwork and the bottom of the second formwork are respectively provided with a slot, and the two inserting rods are respectively matched with the two inserting rods.
7. The pouring formwork for civil engineering construction according to claim 1, wherein the first formwork and the second formwork are provided with a first double faced adhesive tape on the top, and a second double faced adhesive tape is provided on the outer wall of the second formwork on the side close to the first formwork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120242528.5U CN214402722U (en) | 2021-01-28 | 2021-01-28 | Civil engineering construction is with pouring template |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120242528.5U CN214402722U (en) | 2021-01-28 | 2021-01-28 | Civil engineering construction is with pouring template |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214402722U true CN214402722U (en) | 2021-10-15 |
Family
ID=78019232
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120242528.5U Expired - Fee Related CN214402722U (en) | 2021-01-28 | 2021-01-28 | Civil engineering construction is with pouring template |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214402722U (en) |
-
2021
- 2021-01-28 CN CN202120242528.5U patent/CN214402722U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN214272905U (en) | Concrete building template for civil engineering | |
CN112049407B (en) | Concrete building template for civil engineering | |
CN214402722U (en) | Civil engineering construction is with pouring template | |
CN113622555B (en) | Assembled hollow partition wall based on BIM technology and construction method thereof | |
CN214695434U (en) | Temporary support device is built to ecological bank protection of water conservancy | |
CN206053965U (en) | A kind of tunnel ditch cable trough construction trolley | |
CN210066800U (en) | Prefabricated cushion cap mould structure of instrument formula | |
CN206035501U (en) | Tunnel water ditch die carrier device | |
CN212294717U (en) | Civil engineering fundamental mode mounting fixture | |
CN204221941U (en) | A kind of combined type sycon cable duct mould | |
CN106607986A (en) | Automatic mold releasing device for foam concrete | |
CN206703279U (en) | A kind of pre-embedded bolt fixing device | |
CN207277821U (en) | A kind of non-dismantling self-heat-insulation template and its production equipment | |
CN213391111U (en) | Suspended ceiling supporting device for building construction | |
CN213868917U (en) | Concrete building template for mountain wind power civil engineering | |
CN216341185U (en) | Civil engineering supports with roof beam board and uses strengthening mechanism | |
CN220421408U (en) | Plugging device of power cable protection tube | |
CN215859062U (en) | Building foundation cement column watering device convenient to dismantle | |
CN215511539U (en) | Semidry gypsum block forming equipment | |
CN214561753U (en) | Die for assembly type building wallboard and discharging assembly of die | |
CN203904945U (en) | Integrated outside concrete formwork | |
CN216194862U (en) | Fair-faced concrete foundation chamfering tool for electric power construction | |
CN217581310U (en) | Reinforced concrete prefabricated frame for building | |
CN213774519U (en) | Basement outer wall unilateral steel form support system of easily assembling | |
CN217105077U (en) | Emergency piling device for yellow river water utilization |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211015 |
|