CN214144023U - Assembled inspection shaft connection structure - Google Patents

Assembled inspection shaft connection structure Download PDF

Info

Publication number
CN214144023U
CN214144023U CN202023332490.5U CN202023332490U CN214144023U CN 214144023 U CN214144023 U CN 214144023U CN 202023332490 U CN202023332490 U CN 202023332490U CN 214144023 U CN214144023 U CN 214144023U
Authority
CN
China
Prior art keywords
butt joint
pipe
annular
drain pipe
joint pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023332490.5U
Other languages
Chinese (zh)
Inventor
贾新阳
王亚东
曹爱清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Miyun Cement Products Co ltd
Original Assignee
Beijing Miyun Cement Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Miyun Cement Products Co ltd filed Critical Beijing Miyun Cement Products Co ltd
Priority to CN202023332490.5U priority Critical patent/CN214144023U/en
Application granted granted Critical
Publication of CN214144023U publication Critical patent/CN214144023U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model relates to an assembled inspection shaft connection structure in underground drainage pipe field, it includes the well body and sets up the drain pipe around the well body, the global butt joint pipe that communicates each other with the internal portion of well that is provided with of well, the diameter of drain pipe outer peripheral face equals the diameter of butt joint inside pipe wall, in the tip of drain pipe is closely pegged graft and is docked intraductally, a plurality of annular has been seted up with drain pipe laminating department to the butt joint inside pipe wall, sets up the injecting glue mouth that a plurality of and every annular communicate each other, every to the butt joint outside pipe peripheral face the annular is internal to inject into there is sealed glue. This application has improved the sealing performance between drain pipe and the butt joint pipe, and the difficult condition that causes leaks takes place, and then the difficult soil horizon that causes around the well body appears collapsing.

Description

Assembled inspection shaft connection structure
Technical Field
The application relates to the field of underground drainage pipes, in particular to an assembly type inspection well connecting structure.
Background
The inspection well is used for maintaining power supply, water drainage, pollution discharge, communication cable television, gas pipes, street lamp lines and the like of urban underground infrastructure, and is convenient to install. It is usually installed at the intersection of pipelines, turning, where the pipe diameter or slope changes, and at certain intervals on straight pipeline sections, and is convenient for regular inspection of the attached structures.
A common inspection well for drainage type comprises a vertically arranged well body and drainage pipes which are arranged on the peripheral surface of the well body and are communicated with the inside of the well body. The periphery of the well body is provided with a water through hole, the conventional connection mode of the well body and the drain pipe is that a socket of the drain pipe is inserted into the water through hole of the well body, then the connection position of the drain pipe and the water through hole is subjected to water closing treatment, and the water closing treatment is mainly to coat cement mortar on a gap between the drain pipe and the inner wall of the water through hole for plugging, so that the drain pipe and the well body are connected and fixed.
After the inspection well is used for a long time, the connecting gap of the drain pipe and the well body is often washed away by a water source, and when the water pressure in the well body is large, the acting force along the extending direction of the drain pipe can be applied to the connecting gap of the drain pipe and the well body, so that the cement mortar is easily broken and separated, and the water leakage is caused. The water source leaks around the well body and contacts with the soil layer, so that the soil layer is easy to sink, and the bottom surface of the peripheral surface of the inspection well sinks.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an assembled inspection shaft connection structure, its advantage is that the condition of leaking of the well body and drain pipe connection gap has been reduced takes place, is difficult for causing sinking of inspection shaft.
The application provides a fabricated inspection well connection structure adopts following technical scheme:
the utility model provides an assembled inspection shaft connection structure, includes the well body and sets up the drain pipe around the well body, the global butt joint pipe that communicates each other with the internal portion of well that is provided with of well, the diameter of drain pipe outer peripheral face equals the diameter of butt joint inside pipe wall, the tip of drain pipe is closely pegged graft in the butt joint pipe, a plurality of annular has been seted up with drain pipe laminating department to butt joint inside pipe wall, sets up the injecting glue mouth that a plurality of and every annular communicate each other, every to the pipe outer peripheral face the annular internal injection has sealed glue.
Through adopting above-mentioned technical scheme, when assembling the inspection shaft, insert into the butt joint pipe of well body one side with the tip of drain pipe in, then through the injecting glue mouth, in will sealing glue pours into the annular into, the annular is located the region that butt joint pipe overlaps with butt joint pipe for sealed glue can fill the gap between drain pipe and the butt joint pipe, thereby improved the sealing performance between drain pipe and the butt joint pipe, the difficult condition that causes leaks takes place, and then the difficult soil horizon that causes around the well body appears collapsing.
Preferably, a plurality of partition plates are arranged in each annular groove, so that the annular grooves form a plurality of compartments, the number of the glue injection openings corresponds to the number of the compartments, and the glue injection openings are communicated with the compartments.
By adopting the technical scheme, the ring groove is divided into the plurality of compartments by the partition plate, so that when glue liquid is filled, the glue liquid can be filled into each compartment more fully, a plurality of glue injection ports are arranged, the glue liquid is distributed more uniformly in the ring groove, and a glue liquid gap is not formed between the drain pipe and the butt joint pipe easily.
Preferably, a sleeve is arranged in the butt joint pipe, the diameter of the inner circumferential surface of the sleeve is equal to that of the inner wall of the butt joint pipe, and the annular groove and the partition plate are arranged on the inner circumferential surface of the sleeve.
Through adopting above-mentioned technical scheme, the setting of sleeve pipe need not to carry out operations such as grooving in the butt joint pipe, has reduced the loaded down with trivial details operation of grooving, has improved the preparation efficiency of the well body.
Preferably, one side of each partition plate, which faces the water discharge pipe, is provided with a plurality of gaps for glue solution circulation.
By adopting the technical scheme, the opening of the notch enables the glue solution to flow into the adjacent separating chambers through the notch when the glue solution is injected, so that the gap between the partition plate and the peripheral surface of the butt joint pipe is reduced, and the sealing performance between the butt joint pipe and the drain pipe is improved.
Preferably, the partition plates in the adjacent ring grooves are arranged in a staggered mode.
Through adopting above-mentioned technical scheme, because the baffle sets up in the crisscross way for along the difficult formation straight line of the axis baffle of butt joint pipe, even there is the clearance between baffle and the drain pipe, also can remedy to sealing performance through the staggered arrangement of baffle.
Preferably, the outer peripheral surface of the drain pipe is provided with an annular sealing plate, and the annular sealing plate is connected with the end face bolt of the butt joint pipe.
Through adopting above-mentioned technical scheme, after the drain pipe pegged graft each other with the butt joint pipe, the annular shrouding pastes and leans on the terminal surface of butt joint pipe, and the rethread bolt is to annular shrouding and the reciprocal anchorage of butt joint pipe, has increased the stability fixed with the drain pipe mushroom to the butt joint pipe.
Preferably, the end face of the butt joint pipe is embedded with a matching pipe, and an internal thread in threaded connection with the bolt is formed in the matching pipe.
Through adopting above-mentioned technical scheme, through the prefabrication of cooperation pipe, reduced the loaded down with trivial details of direct trompil operation on the butt joint pipe, through prefabricated mode, improved the intensity and the preparation efficiency of butt joint pipe greatly.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the sealing performance between the butt joint pipe and the drain pipe is improved; the sealing glue is poured into the annular groove through the glue injection port, the annular groove is located in the overlapped area of the butt joint pipe and the butt joint pipe, so that the sealing glue can fill a gap between the drain pipe and the butt joint pipe, the sealing performance between the drain pipe and the butt joint pipe is improved, the water leakage is not easily caused, and the soil layer around the well body is not easily caused to collapse;
2. the preparation efficiency of the well body is improved, and the sleeve is prefabricated in the butt joint pipe, so that the complexity of operations such as directly slotting in the butt joint pipe is reduced, and the preparation efficiency of the well body is improved.
Drawings
FIG. 1 is a schematic view of the overall construction of an inspection well;
FIG. 2 is an enlarged detail view at A of FIG. 1;
FIG. 3 is an exploded view showing the connection structure of the well body and the water discharge pipe;
fig. 4 is a schematic diagram showing the structure of the inner sleeve of the butt joint pipe.
Description of reference numerals: 1. a well body; 11. caulking grooves; 12. looping; 2. a drain pipe; 21. an annular seal plate; 22. a bolt; 3. butt-joint pipes; 31. a mating tube; 4. a sleeve; 42. a ring groove; 43. a partition plate; 44. a compartment; 45. and (6) a glue injection port.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
An assembled inspection well connecting structure, as shown in fig. 1, comprises a well body 1 and drain pipes 2 arranged on the peripheral surface of the well body 1 and mutually installed with the well body 1.
As shown in fig. 2, the well body 1 is a concrete pipe, the lower end of the well body 1 is arranged for sealing, the well body 1 is vertically arranged underground, three caulking grooves 11 are uniformly formed in the upper end face of the well body 1 by taking the central line of the well body 1 as an axis, a lapping ring 12 is arranged in each caulking groove 11, the lapping ring 12 is welded and fixed with the reinforcing steel bars inside the well body 1, and the lapping ring 12 does not protrude out of the surface of the caulking groove 11, so that workers can fix the lapping ring 12 with each other through a rope, and then hoist the well body 1, thereby improving the convenience of hoisting the well body 1, and the lapping ring 12 does not protrude out of the surface of the caulking groove 11, and the longitudinal building of the well body 1 cannot be influenced.
As shown in fig. 3, a plurality of butt joint pipes 3 are horizontally arranged on the circumferential surface of the well body 1 (the number of butt joint pipes 3 in this embodiment is taken as an example), the axial lines of the butt joint pipes 3 are perpendicular to the axial line of the well body 1, and the butt joint pipes 3 and the well body 1 are prefabricated integrally.
As shown in fig. 3, the drain pipe 2 is a prefabricated pipe fitting made of concrete, the diameter of the outer peripheral surface of the drain pipe 2 is equal to the diameter of the inner wall of the butt joint pipe 3, and when the drain pipe 2 and the butt joint pipe 3 are mutually inserted, one end of the drain pipe 2 is inserted into the butt joint pipe 3, so that the outer wall of the drain pipe 2 is tightly attached to the inner wall of the butt joint pipe 3. The outer peripheral surface of the drain pipe 2 is also provided with an annular sealing plate 21, the plane of the annular sealing plate 21 is perpendicular to the central line of the drain pipe 2, and the annular sealing plate 21 is welded with the steel bars inside the drain pipe 2 when the drain pipe 2 is prefabricated, so that the annular sealing plate 21 protrudes out of the outer peripheral surface of the drain pipe 2 after concrete is poured and solidified. Annular shrouding 21 leaves the distance with drain pipe 2 grafting one end for behind drain pipe 2 and the mutual grafting of butt joint pipe 3, butt joint pipe 3 terminal surface supports and leans on one side at annular shrouding 21. A plurality of bolts 22 are arranged on the annular closing plate 21 in a penetrating way, and the bolts 22 are uniformly distributed along the outline of the annular closing plate 21. And the end surface of the butt joint pipe 3 is provided with a matching pipe 31 at the position corresponding to each bolt 22, the matching pipe 31 is prefabricated in the butt joint pipe 3, and the axis of the matching pipe 31 is parallel to the axis of the butt joint pipe 3. The bolt 22 is matched with the bolt 22 of the matching pipe 31, so that the drainage pipe 2 and the butt joint pipe 3 are fixed with each other more firmly.
As shown in fig. 4, a sleeve 4 is prefabricated on the inner wall of the port of the butt joint pipe 3, the axis of the sleeve 4 is coincident with the axis of the butt joint pipe 3, the diameter of the inner wall of the sleeve 4 is equal to that of the inner wall of the butt joint pipe 3, and one end face of the sleeve 4 is flush with the end face of the butt joint pipe 3. When the drain pipe 2 and the butt joint pipe 3 are inserted into each other, the sleeve 4 is attached to the outer peripheral surface of the drain pipe 2. Three ring grooves 42 are formed in the inner circumferential surface of the sleeve 4 along the axial direction of the sleeve 4, a plurality of partition plates 43 are respectively arranged in each ring groove 42 at intervals along the annular direction of the ring groove 42, and the edge of each partition plate 43 is fixedly connected with the inner wall of the ring groove 42, so that the ring grooves 42 are divided into a plurality of separation chambers 44 with the same size. The peripheral surface of the butt joint pipe 3 is provided with a plurality of glue injection ports 45 which are mutually communicated with the ring grooves 42, and the number of the glue injection ports 45 corresponds to the proper amount of the separation chambers 44 one by one.
After drain pipe 2 and butt joint pipe 3 pegged graft each other, one edge of baffle 43 and drain pipe 2 outer wall are leaned on each other, the staff pours into every compartment 44 sealed glue through every injecting glue mouth 45, because the space of compartment 44 inside is far less than the size of annular 42, make sealed glue can be abundant fill in into compartment 44, sealed glue is the waterproof sealed glue of purchasing now on the market, form the sealing layer in the gap to pipe 3 and drain pipe 2 after sealed glue solidifies, thereby greatly increased the sealing performance between drain pipe 2 and the butt joint pipe 3, the difficult condition of leaking takes place, and then the difficult soil horizon around causing the well body 1 appears collapsing.
As shown in fig. 4, the number of the partition plates 43 in each ring groove 42 is the same, but the fixing positions are different, so that even if liquid enters a gap between the partition plate 43 and the drain pipe 2, the liquid cannot smoothly pass through each ring groove 42 due to the distribution positions of the partition plates 43, and the leakage of the liquid is greatly hindered. And 3 gaps are respectively arranged on the edge of each clapboard 43 facing the drain pipe 2. When the sealant is injected into each compartment 44, the redundant glue flows into the adjacent compartments 44 through the gap, so that the gap between the partition plate 43 and the drain pipe 2 is filled, and the sealing performance between the drain pipe 2 and the butt joint pipe 3 is greatly improved.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (7)

1. The utility model provides an assembled inspection shaft connection structure, includes well body (1) and sets up drain pipe (2) around well body (1), its characterized in that: global of the well body (1) be provided with the well body (1) inside butt joint pipe (3) that communicates each other, the diameter of drain pipe (2) outer peripheral face equals the diameter to butt joint pipe (3) inner wall, the tip of drain pipe (2) is closely pegged graft in butt joint pipe (3), a plurality of annular (42) have been seted up with drain pipe (2) laminating department to butt joint pipe (3) inner wall, and the injecting glue mouth (45) that communicate each other of a plurality of and every annular (42) are seted up to butt joint pipe (3) outer peripheral face, every the injection has sealed glue in annular (42).
2. The fabricated manhole connecting structure according to claim 1, wherein: every be provided with a plurality of baffle (43) in annular (42), make annular (42) form a plurality of divider room (44), the quantity that injecting glue mouth (45) was seted up corresponds with divider room (44) quantity, injecting glue mouth (45) and divider room (44) intercommunication each other.
3. The fabricated manhole connecting structure according to claim 2, wherein: the butt joint pipe (3) is internally provided with a sleeve (4), the diameter of the inner peripheral surface of the sleeve (4) is equal to that of the inner wall of the butt joint pipe (3), and the annular groove (42) and the partition plate (43) are arranged on the inner peripheral surface of the sleeve (4).
4. The fabricated manhole connecting structure according to claim 3, wherein: one side of each partition plate (43) facing the water discharge pipe (2) is provided with a plurality of gaps for glue solution circulation.
5. The fabricated manhole connecting structure according to claim 3, wherein: the clapboards (43) in the adjacent ring grooves (42) are arranged in a staggered mode.
6. The fabricated manhole connecting structure according to claim 1, wherein: the outer peripheral surface of the drain pipe (2) is provided with an annular sealing plate (21), and the annular sealing plate (21) is connected with an end face bolt (22) of the butt joint pipe (3).
7. The fabricated manhole connecting structure according to claim 6, wherein: the end face of the butt joint pipe (3) is embedded with a matching pipe (31), and an internal thread in threaded connection with the bolt (22) is arranged in the matching pipe (31).
CN202023332490.5U 2020-12-31 2020-12-31 Assembled inspection shaft connection structure Active CN214144023U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023332490.5U CN214144023U (en) 2020-12-31 2020-12-31 Assembled inspection shaft connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023332490.5U CN214144023U (en) 2020-12-31 2020-12-31 Assembled inspection shaft connection structure

Publications (1)

Publication Number Publication Date
CN214144023U true CN214144023U (en) 2021-09-07

Family

ID=77545435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023332490.5U Active CN214144023U (en) 2020-12-31 2020-12-31 Assembled inspection shaft connection structure

Country Status (1)

Country Link
CN (1) CN214144023U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351830A (en) * 2022-01-29 2022-04-15 浙江汇博水泥制品有限公司 Impervious reinforced concrete drain pipe and production process thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351830A (en) * 2022-01-29 2022-04-15 浙江汇博水泥制品有限公司 Impervious reinforced concrete drain pipe and production process thereof

Similar Documents

Publication Publication Date Title
CN201883454U (en) Prefabricated reinforced-concrete assembly-type combined inspection well chamber
CN108166993B (en) A kind of portable slip casting casing bit and application method suitable for grouting behind shaft or drift lining
CN214144023U (en) Assembled inspection shaft connection structure
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
CN213979046U (en) Inspection well assembly
KR100411659B1 (en) Precast Culvert Including a Grout Tube and Connecting Method Precast Culverts by Filling Mortar in the Female and Male Shearing Key
CN205894103U (en) Prefabricated parabola type utility tunnel
CN212001932U (en) Full grout sleeve and have this telescopic precast beam connection structure
CN203284803U (en) Combined type multifunctional comprehensive inspection well chamber
CN214116915U (en) Novel assembled inspection shaft connection structure
CN111764435A (en) Prefabricated grout of concrete seals assembled inspection shaft
CN215053224U (en) Basement waterproof structure
KR101817712B1 (en) A Culvert and method for constructing the culvert
CN208136954U (en) Precast splice type Pipe rack
CN216664218U (en) Prefabricated open caisson well section of stagnant water
CN214116913U (en) Assembled inspection shaft
CN205976057U (en) Side fascia installation node
CN212582739U (en) Prefabricated grout of concrete seals assembled inspection shaft
CN211257228U (en) Novel assembled inspection shaft
CN209817036U (en) Fabricated drop well suitable for urban drainage pipe network
CN214116914U (en) Assembly structure of inspection well
CN219862942U (en) Prefabricated piping lane of assembled
KR101396514B1 (en) Coupling structure of leading pipe for underwater prefabricating intake tower
CN220581900U (en) Socket joint formula cement culvert pipe convenient to installation
CN221723634U (en) Municipal pipeline junction leak protection water gomphosis structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant