CN216131506U - Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure - Google Patents

Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure Download PDF

Info

Publication number
CN216131506U
CN216131506U CN202122826647.8U CN202122826647U CN216131506U CN 216131506 U CN216131506 U CN 216131506U CN 202122826647 U CN202122826647 U CN 202122826647U CN 216131506 U CN216131506 U CN 216131506U
Authority
CN
China
Prior art keywords
drain pipe
pipe
prefabricated inspection
inspection well
connection structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122826647.8U
Other languages
Chinese (zh)
Inventor
张其稳
曾海青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122826647.8U priority Critical patent/CN216131506U/en
Application granted granted Critical
Publication of CN216131506U publication Critical patent/CN216131506U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a connection structure of a prefabricated inspection well and a drainage pipe in water conservancy engineering, which is used for solving the technical problem that a quick connection method is not available in the prior art. The preformed pipeline window of the prefabricated inspection well is fixedly provided with the adapter through secondary pouring of concrete, the port part of the drain pipe is fixedly provided with the plug connector, one end of the plug connector is inserted into the end opening of the drain pipe, the other end of the plug connector is inserted into the adapter, transition connection is realized, and a sealing ring is arranged in the plug connection matching of the plug connector and the adapter, so that the mechanical sealing effect is achieved. The utility model realizes factory manufacture and construction site assembly construction by a mode of fixedly mounting the adapting pipe on the prefabricated inspection well in advance, realizes quick mounting and quick construction by the mechanical seal of the rubber seal ring between the socket pipe and the plug, omits the process of curing and hardening in concrete wet construction, realizes the effect of backfilling after mounting, has extremely high process simplification effect and improves the construction efficiency.

Description

Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
Technical Field
The utility model relates to a prefabricated inspection shaft and drain pipe connection technical field.
Background
In the civil construction of drainage pipe networks such as water conservancy, municipal administration, roads, farmlands and the like, the laying of the drainage pipe network is generally involved, and inspection wells and ribbed spiral drainage pipes in the drainage pipe network are common combination modes. The ribbed spiral drainage pipe has high pressure resistance, and the inspection well is hoisted and assembled by adopting a concrete prefabricated inspection well.
Because the spiral drainage pipe is ribbed and the error between the spiral drainage pipe and the prefabricated inspection well in construction is caused, the existing connection mode is a wet operation mode, namely, a mode of reserving a large installation hole in the concrete inspection well is adopted for butt joint, wet operation is carried out in a mode of filling joints with mortar after butt joint, the wet operation needs maintenance, and the operation time is long.
For example, CN211312769U discloses a wet process, i.e. before the precast concrete manhole is installed, plastic pipes are inserted into the precast concrete manhole, building a brick wall layer and an arch brick wall layer on the outer side of the joint of the plastic pipe and the precast concrete inspection well, tightly filling gaps between the brick wall layer and the arch brick wall layer with 1:2 micro-expansion cement mortar, wrapping the buried plastic pipe in the brick wall, erecting a mold on the inner wall of the inspection well, concrete is poured into a gap between the inner wall of the inspection well and the plastic pipe for filling, the joint surface of the new concrete and the old concrete needs to be roughened in advance, after the mould is removed, and filling and compacting gaps between the arch brick wall layer and the periphery of the plastic pipe, between the concrete layer and the plastic pipe, and between the well wall of the concrete prefabricated inspection well and the concrete layer by using 1:2 micro-expansion cement mortar.
SUMMERY OF THE UTILITY MODEL
In order to solve the defects of the prior art, the utility model provides a prefabricated inspection well and drain pipe connecting structure which is used for solving the technical problem that a quick connecting method is not available in the prior art.
The technical scheme adopted by the utility model for solving the technical problems is as follows:
prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure, including prefabricated inspection shaft and drain pipe, wherein, the drain pipe is ribbed spiral drainage pipe, and ribbed structure has increased its installation and the antiseep degree of difficulty, its characterized in that:
the prefabricated inspection well is characterized in that the reserved pipeline window is fixedly provided with the adapter through secondary pouring of concrete, the port of the drain pipe is fixedly provided with the plug connector, one end of the plug connector is inserted into the port of the drain pipe, the other end of the plug connector is inserted into the adapter, transition connection is realized, and a sealing ring is arranged in the plug-in fit of the plug connector and the adapter, so that the prefabricated inspection well has a mechanical sealing effect.
The outside of the plug is provided with mounting grooves for positioning the sealing ring, and the number of the mounting grooves is at least two.
The sealing ring is preferably a common rubber sealing ring.
And the plug connector is connected with the drain pipe through hot melting and fusion welding.
The plug is a tubular PVC, PE or PP pipe.
And pre-burying a water stop plate or a water stop belt at the boundary position of the secondary pouring concrete and the reserved pipeline window.
Reinforcing ribs are arranged on the outer side of the bearing pipe.
The prefabricated inspection well is a reinforced concrete prefabricated part.
The adapting pipe is a PVC, PE or PP pipe.
And an embedded rib is arranged outside the bearing pipe and is positioned in the secondary pouring concrete.
The utility model has the beneficial effects that:
the utility model realizes factory manufacture and construction site assembly construction by a mode of fixedly mounting the adapting pipe on the prefabricated inspection well in advance, realizes quick mounting and quick construction by the mechanical seal of the rubber seal ring between the socket pipe and the plug, omits the process of curing and hardening in concrete wet construction, realizes the effect of backfilling after mounting, has extremely high process simplification effect and improves the construction efficiency.
Drawings
Fig. 1 is a partial cross-sectional view of the present invention.
Fig. 2 is a perspective view of the faucet tube.
Fig. 3 is a perspective view of a ribbed spiral drain pipe.
In the figure:
10 prefabricated inspection well, 11 secondary concreting, 12 water stop plate or water stop belt,
20 water discharge pipes are arranged on the upper surface of the water tank,
30 bearing pipes, 31 reinforcing ribs, 32 embedded ribs, 33 bearing openings,
40 of the connecting plug is connected with the connecting plug,
50 sealing rings.
Detailed Description
Prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure, this connection structure includes prefabricated inspection shaft 10 and drain pipe 20, and wherein, drain pipe 20 is PVC ribbed spiral drain pipe, has spiral helicine ribbed belt promptly in the outside of drain pipe, is provided with the steel band additional strengthening in the stiffening rib, because the outer ribbed belt of drain pipe, so be connected between it and the inspection shaft and have the difficulty.
The structure and implementation of the present embodiment will be described in detail with reference to fig. 1 to 3 of the specification.
The prefabricated inspection well 10 is a reinforced concrete prefabricated product and is provided with a well mouth and a reserved pipeline window, and the whole prefabricated inspection well is integrally formed by adopting a template. And fixedly installing the adapting pipe 30 at the reserved pipeline window by adopting a mode of fixing the secondary pouring concrete 11, wherein the adapting pipe is made of PVC material and adopts an injection molding process. From structural division, this adapting pipe 30 outside has two stiffening ribs 31 and an embedded rib 32, and embedded rib and stiffening rib all are annular structure, have the same structure, and the effect that the difference is played is different, and embedded rib 32 wherein is at the secondary fixed in-process of pouring, and the bonding strength of adapting pipe and secondary concreting 11 can be improved in the existence of this embedded rib 32, and simultaneously, the waterproof performance at adapting pipe position can be improved in the existence of this embedded rib, avoids producing the seepage along here.
Furthermore, in the forming process of the prefabricated inspection well, a water stop plate or a water stop belt 12 is embedded in the boundary position of the secondary pouring area and matched with the secondary pouring, so that one half of the water stop plate or the water stop belt is fixed in the secondary pouring area, and the other half of the water stop plate or the water stop belt is fixed in the prefabricated inspection well wall to form a waterproof structure.
After the adapting pipe 30 is fixed through the secondary pouring process, the reinforcing rib is positioned at the outer side of the prefabricated inspection well, and the adapting port 33 is correspondingly arranged in the adapting pipe at the position of the reinforcing rib.
The prefabricated inspection well is constructed, the prefabrication process, the secondary pouring process and the fixing process of the bearing pipe are all completed in advance in a factory and belong to a whole, the whole is transported to a construction site, and the whole is hoisted into a foundation pit by means of hoisting equipment to complete the primary positioning of the prefabricated inspection well.
The water drainage pipe 20 is characterized in that a plug-in connector 40 is fixedly installed at the port of the water drainage pipe through a hot melting welding technology, the plug-in connector is a tubular PVC, PE or PP pipe, wherein one half of the plug-in connector is inserted into the port of the water drainage pipe, the other half of the plug-in connector is exposed, a sealing ring installation groove is formed in the outer portion of the exposed plug-in connector, as shown in the figure, two installation grooves are formed, a sealing ring 50 is installed in each installation groove, and the sealing ring is preferably a common rubber sealing ring.
The construction process is that, progressively insert the accepting of prefabricated inspection shaft intraductal with the exposed section of bayonet joint, realize self sealedly between the two under the effect of sealing washer, all can accomplish the installation of whole structure, and the job site does not have concrete wet process operation, has saved the maintenance time, realizes installing promptly and backfills, has improved the efficiency of civil construction greatly.
The above-described embodiments are merely illustrative of the preferred embodiments of the present invention and do not limit the scope of the present invention, and various modifications and improvements of the present invention by those skilled in the art without departing from the spirit of the present invention are intended to fall within the scope of the present invention defined by the claims.

Claims (9)

1. Prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure, including prefabricated inspection shaft (10) and drain pipe (20), wherein, drain pipe (20) are ribbed spiral drain pipe, its characterized in that:
the prefabricated inspection well is characterized in that a reserved pipeline window of the prefabricated inspection well is fixedly provided with a bearing pipe (30) through secondary pouring concrete (11), a connector (40) is fixedly arranged at the port part of the drain pipe, one end of the connector is inserted into the drain pipe, the other end of the connector is inserted into the bearing pipe (30), and a sealing ring is arranged in the insertion fit of the connector and the bearing pipe.
2. The connection structure of the hydraulic engineering prefabricated inspection well and the drainage pipe as claimed in claim 1, wherein an embedded rib (32) is arranged outside the adapting pipe (30), and the embedded rib (32) is located in the secondary pouring concrete (11).
3. The prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure of claim 2, wherein reinforcing ribs are provided on the outer side of the adapting pipe.
4. The connection structure of the prefabricated inspection well and the drainage pipe of the hydraulic engineering according to claim 1, wherein a water stop plate or a water stop belt is embedded in the boundary position of the secondary pouring concrete and the reserved pipeline window.
5. The prefabricated inspection well and drain pipe connection structure of hydraulic engineering according to claim 1, wherein the plug connector is externally provided with at least two mounting grooves for positioning the sealing ring.
6. The prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure of claim 1, wherein the bayonet joint is connected with the drain pipe by hot melt welding.
7. The hydraulic engineering prefabricated inspection well and drain pipe connecting structure as claimed in claim 1, wherein the prefabricated inspection well (10) is a reinforced concrete prefabricated member.
8. The prefabricated inspection shaft of hydraulic engineering and drain pipe connection structure of claim 1, wherein the adapter is a PVC, PE or PP pipe.
9. The prefabricated inspection well and drain pipe connection structure of hydraulic engineering of claim 1, wherein the connector is a PVC, PE or PP pipe.
CN202122826647.8U 2021-11-18 2021-11-18 Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure Expired - Fee Related CN216131506U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122826647.8U CN216131506U (en) 2021-11-18 2021-11-18 Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122826647.8U CN216131506U (en) 2021-11-18 2021-11-18 Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure

Publications (1)

Publication Number Publication Date
CN216131506U true CN216131506U (en) 2022-03-25

Family

ID=80778500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122826647.8U Expired - Fee Related CN216131506U (en) 2021-11-18 2021-11-18 Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure

Country Status (1)

Country Link
CN (1) CN216131506U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030225A (en) * 2022-07-22 2022-09-09 康泰塑胶科技集团有限公司 Prefabricated sealing assembly concrete inspection well, pipeline connecting system and construction method
CN115110579A (en) * 2022-07-22 2022-09-27 康泰塑胶科技集团有限公司 Anti-leakage anti-deflection angle concrete inspection well, pipeline connecting system and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030225A (en) * 2022-07-22 2022-09-09 康泰塑胶科技集团有限公司 Prefabricated sealing assembly concrete inspection well, pipeline connecting system and construction method
CN115110579A (en) * 2022-07-22 2022-09-27 康泰塑胶科技集团有限公司 Anti-leakage anti-deflection angle concrete inspection well, pipeline connecting system and construction method

Similar Documents

Publication Publication Date Title
US5386669A (en) Corrosion resistant leakproof plastic manhole system
KR100743369B1 (en) Precast culvert assembly for both culvert and utility-pipe conduit
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
CN107859064B (en) Waterproof structure for connection of prefabricated pipe gallery and cast-in-situ pipe gallery and construction method
CN113293802A (en) Construction method of inspection well
CN108222220B (en) Construction method for connecting new sewage pipe and old sewage pipe in displacement transformation of sewage pipe
KR100411659B1 (en) Precast Culvert Including a Grout Tube and Connecting Method Precast Culverts by Filling Mortar in the Female and Male Shearing Key
CN211312769U (en) Connecting member of plastic pipe and concrete prefabricated inspection well
CN112555522A (en) Steel socket composite reinforced concrete lining glass fiber reinforced plastic drain pipe and preparation method thereof
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN110808564B (en) Concrete cable trench construction process
CN220318582U (en) Well wall construction template of municipal administration tube well
KR101965801B1 (en) Assembly manhole apparatus for connecting hume pipe and constructing method thereof
KR20190002743U (en) concrete complex manhole
CN110056071A (en) A kind of municipal administration storm sewer assembling module and construction method
CN107059944A (en) Basement seepage point gradually leak stopping structure and construction method
CN206667305U (en) Basement seepage point gradually leak stopping structure
KR100891617B1 (en) The steel box for the concrete filling type closed conduit construction
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
CN217053673U (en) Connecting structure for plastic pipeline and concrete prefabricated inspection well
CN109914569B (en) Cement water delivery pipe
KR200275363Y1 (en) The mold establishment necessit do not exist assembly road water pipe
KR100909111B1 (en) Connecting pipe for manhole and method of manufacturing concrete manhole using the same
CN218757839U (en) Modular concrete inspection well
KR100749580B1 (en) Lining concrete manhole blocks, manufacturing method and installation method of the chemical resin lining manhole blocks which uses the installation structure and this liner of the chemical resin liner

Legal Events

Date Code Title Description
GR01 Patent grant