CN205976057U - Side fascia installation node - Google Patents

Side fascia installation node Download PDF

Info

Publication number
CN205976057U
CN205976057U CN201620518977.7U CN201620518977U CN205976057U CN 205976057 U CN205976057 U CN 205976057U CN 201620518977 U CN201620518977 U CN 201620518977U CN 205976057 U CN205976057 U CN 205976057U
Authority
CN
China
Prior art keywords
side fascia
lower side
upper side
fascia
notch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620518977.7U
Other languages
Chinese (zh)
Inventor
陈定球
李昌州
俞大有
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mingsheng Drawin Technology Investment Co Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201620518977.7U priority Critical patent/CN205976057U/en
Application granted granted Critical
Publication of CN205976057U publication Critical patent/CN205976057U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model belongs to the building structure field specifically discloses a side fascia installation node, including last side fascia, lower side fascia and floor, the floor is set up under on the side fascia, cast -in -place layer has been pour at the side fascia top down, go up side fascia and side fascia adoption grout sleeve connection down, the vertical muscle of lower side fascia passes cast -in -place layer and stretches into in the grout sleeve of last side fascia thick liquids formation steel bar butt joint's thick liquid anchor attach fitting injects among the grout sleeve, it is equipped with the notch to go up the bottom of side fascia and the top of lower side fascia, go up the side fascia and/or down the side fascia be equipped with the injected hole, through the injected hole is in waterproof slurry has been poured into during the concatenation is stitched and in the notch. The utility model provides a for outer waterproof wall panel provides the reliable assurance, and construction convenience, water -proof effects good, improved production efficiency and building quality.

Description

Node installed by a kind of Side fascia
Technical field
The utility model belongs to building structure field and in particular to node installed by a kind of Side fascia.
Background technology
In assembled architecture industry, Side fascia carries out factorial praluction by the way of prefabricated, then Assembling, thus Enable to standardize, and quality controllable, efficient quick.At present, adopt shear wall structure as external wall panel structure system more, but It is that the external wall panel structure system productivity ratio of current shear wall structure is relatively low, artificial input is larger, and the labour intensity of workman is larger, And traditional waterproof type typically breaks marine glue in seam crossing, the workload not only constructed is big, and marine glue is over time Occur aging for a long time, finally result in the generation of drainage, the water resistance of impact assembled architecture and construction quality.
In sum, need badly and develop a kind of easy construction, node installed by the Side fascia of good water-proof effect.
Utility model content
The purpose of this utility model is that node installed by the Side fascia providing a kind of easy construction, good water-proof effect.
Above-mentioned purpose is to be achieved through the following technical solutions:Node installed by a kind of Side fascia, including upper Side fascia, lower exterior wall Plate and floor, described floor rides upon on lower Side fascia, and described lower Side fascia top has poured in-situ layer, described upper Side fascia and Lower Side fascia adopts grout sleeve to connect, and the vertical muscle of described lower Side fascia passes through in-situ layer and stretches into the grouting of described upper Side fascia In sleeve, described grout sleeve pours into the slurry anchor connection joint that slurry forms steel reinforcement abutting joints;The bottom of described upper Side fascia It is provided with notch with the top of lower Side fascia, described upper Side fascia and/or lower Side fascia are provided with injected hole, exist by described injected hole In described splicing seams and it is perfused with waterproofing slurry in notch.Described floor can be precast floor slab, may also be laminated floor slab, also may be used To be cast-in-place making entirely, when floor is for laminated floor slab, the above-mentioned in-situ layer pouring at lower Side fascia top is laminated floor slab In-situ layer.In the assembling process of wallboard, the vertical muscle of described lower Side fascia stretches into the grouting of described upper Side fascia through in-situ layer In sleeve, then it is in the milk in grout sleeve and the vertical muscle in insertion grout sleeve is carried out starching anchor.When upper Side fascia and lower exterior wall After the completion of plate assembling, water resistant solution is perfused with described notch by the injected hole being arranged in upper Side fascia or lower Side fascia Material, forms one layer of vertical waterproof layer, can effectively stop outdoor rain from leaking out to interior, there is provided reliable waterproof ensures, this reality Tongue and groove or other waterproof constructions need not be designed with new in the prefabrication process of Side fascia, simplify mould, be also convenient for Side fascia Transport, is damaged in transportation without having to worry about flashing member, improves production efficiency and the building matter of assembled architecture Amount.Described notch can be reserved during upper Side fascia is prefabricated or installation process in open up, outer for insulation Wallboard, described notch is preferably provided at heat-insulation layer, only needs the top of upper Side fascia bottom and lower Side fascia in such assembling process The heat-insulation layer in portion is dug up part and can be formed notch, simplifies operational procedure, reduces difficulty of construction simultaneously.After the completion of assembling, in order to Improve waterproof effect, marine glue can be adopted to block in the medial and lateral of upper Side fascia and the junction of lower Side fascia.Above-mentioned waterproof side Formula is not only suitable for the close spelling structure between Side fascia and lower Side fascia, is also applied between Side fascia and lower Side fascia reserved The structure of splicing seams, when using second structure, is preferably equipped with seal in the inner side and outer side of described splicing seams, it is to avoid Waterproofing slurry leaks along splicing seams.
Further, described Side fascia is thermal insulation external wall panel, and described thermal insulation external wall panel at least includes heat-insulation layer.It is arranged such, It is beneficial to the insulation of Side fascia, and as described above, portion can be dug up in the heat-insulation layer of upper Side fascia bottom and the top of lower Side fascia Divide and can form notch, simplify operational procedure, reduce difficulty of construction simultaneously.
Further, described notch extends to heat-insulation layer by the end face of Side fascia, and described waterproofing slurry is foam mortar or bubble Foam concrete.Be arranged such it is ensured that in node of the present utility model Side fascia hot bridge cut-off function, it is to avoid reduce Side fascia Heat insulation function.
Further, it is reserved with splicing seams, the inner side and outer side of described splicing seams between described upper Side fascia and lower Side fascia It is equipped with seal, waterproofing slurry is perfused with described splicing seams by described injected hole.Described upper Side fascia and lower exterior wall Between plate, reserved splicing seams are enclosed by seal, after the completion of upper Side fascia assembly, by being arranged on upper Side fascia or lower exterior wall Injected hole in plate is perfused with waterproofing slurry in described splicing seams, forms the waterproof layer of one layer of level, stops outdoor rain from being oozed Leak to interior, improve waterproof effect.
Further, described upper Side fascia and/or lower Side fascia are provided with plural injected hole.Because Side fascia has Certain width, on the one hand only one injected hole of setting is difficult to be filled up completely with the splicing seams between upper Side fascia and lower Side fascia Closely knit, on the other hand arrange multiple holes can slip casting simultaneously, improve efficiency of construction.It should be noted that described injected hole can be The grout hole of grouting sleeve or setting in the prefabrication process of upper Side fascia and/or lower Side fascia.
Further, described upper Side fascia and/or lower Side fascia are provided with steam vent.It is arranged such, favourable during slip casting The discharge of air in splicing seams.
Further, described seal bottom is coated with adhesive or is provided with double faced adhesive tape.It is arranged such, be conducive to seal solid It is scheduled on lower Side fascia, it is to avoid during cornice sheathing dropping place, seal position changes, thus affecting the sealing of seal Property.
Further, described seal is rectangle mount structure, and four sides of described seal are matched with the top surface of lower Side fascia. It is arranged such, easy construction, the surrounding of splicing seams is all enclosed simultaneously, improve sealing.
Further, the top surface of the bottom surface of described upper Side fascia and lower Side fascia is matsurface.Be arranged such, waterproofing slurry with The top of the bottom of upper Side fascia and lower Side fascia connects even closer.
Further, described wainscot sheathing top is provided with least one blind hole.It is arranged such, during slip casting, described blind Be perfused with slurry in hole, so, in splicing seams formed waterproof layer be connected on lower external wall panel structure more firm.
Further, described injected hole is hollow hole or pre-buried hollow bushing.In the prefabrication process of described hollow hole wallboard Core pulling is formed, and injected hole is preferably formed by way of pre-buried hollow bushing, and shaping is more easy.
Brief description
The accompanying drawing constituting a part of the present utility model is used for providing further understanding to of the present utility model, and this practicality is new The schematic description and description of type is used for explaining the utility model, does not constitute to improper restriction of the present utility model.
Fig. 1 is the sectional view of the Side fascia installation node involved by a kind of embodiment of the utility model;
Fig. 2 is the stereochemical structure sectional view that node installed by involved Side fascia in Fig. 1.
In figure:
2 times Side fascias of Side fascia, 3 seal 4 injected hole on 1
5 vertical waterproof layer 20 heat-insulation layers of horizontal waterproof layer 9 notch 10
21 structure sheaf 22 grout sleeve 23 indulges muscle 24 floor
25 in-situ layers
Specific embodiment
Below in conjunction with the accompanying drawings the utility model is described in detail, the description of this part is only exemplary and explanatory, Should not there is any restriction effect to protection domain of the present utility model.Additionally, those skilled in the art's retouching according to presents State, respective combination can be carried out to the feature in embodiment in presents and in different embodiment.
The utility model embodiment is as follows, sees figures.1.and.2, and node installed by a kind of Side fascia, include going up Side fascia 1, under Side fascia 2 and floor 24, described floor 24 rides upon on lower Side fascia 2, and described lower Side fascia 2 top has poured in-situ layer 25, Described upper Side fascia 1 and lower Side fascia 2 are connected using grout sleeve 22, and the vertical muscle 23 of described lower Side fascia 2 passes through in-situ layer 25 And stretch in the grout sleeve 22 of described upper Side fascia 1, described grout sleeve 22 pours into the slurry that slurry forms steel reinforcement abutting joints Anchor jointing;The top of the bottom of described upper Side fascia 1 and lower Side fascia 2 is provided with notch 9, described upper Side fascia 1 and/or under Side fascia 2 is provided with injected hole 4, and is perfused with waterproofing slurry in notch 9 by described injected hole 4 in described splicing seams.Described Floor 24 can be precast floor slab, may also be laminated floor slab or cast-in-place making entirely, when floor 24 is laminated floor slab, The above-mentioned in-situ layer 25 pouring at lower Side fascia 2 top is the in-situ layer of laminated floor slab.In the assembling process of wallboard, when upper outer After wallboard 1 and lower Side fascia 2 dropping place, the vertical muscle 23 of described lower Side fascia 2 stretches into the filling of described upper Side fascia 1 through in-situ layer 25 In slurry sleeve 22, then in grout sleeve 22, grouting carries out starching anchor to the vertical muscle 23 in insertion grout sleeve 22.When upper exterior wall After the completion of plate 1 and the assembling of lower Side fascia 2, by the injected hole 4 that is arranged in upper Side fascia 1 or lower Side fascia 2 in described notch 9 In be perfused with waterproofing slurry, form one layer of vertical waterproof layer 10, can effectively stop outdoor rain from leaking out to interior, there is provided reliably Waterproof ensure, the utility model need not design tongue and groove or other waterproof constructions in the prefabrication process of Side fascia, simplify mould, It is also convenient for the transport of Side fascia, is damaged in transportation without having to worry about flashing member, improve the life of assembled architecture Produce efficiency and construction quality.Described notch 9 can be reserved during upper Side fascia 1 is prefabricated or installation process In open up, for thermal insulation external wall panel, described notch 9 is preferably provided at heat-insulation layer 20, only needs upper exterior wall in such assembling process The heat-insulation layer 20 at the top of plate 1 bottom and lower Side fascia 2 is dug up part and can be formed notch 9, simplifies operational procedure, reduces simultaneously Difficulty of construction.After the completion of assembling, in order to improve waterproof effect, can be inside and outside in the junction of upper Side fascia 1 and lower Side fascia 2 Side adopts marine glue to block.Above-mentioned waterproof type is not only suitable for the close spelling structure between Side fascia 1 and lower Side fascia 2, also fits For the structure of splicing seams reserved between upper Side fascia 1 and lower Side fascia 2, when using second structure, preferably in described spelling The inner side and outer side of seam is equipped with seal 3, it is to avoid waterproofing slurry leaks along splicing seams.Described waterproofing slurry can be swollen Buckle slurry or expansive concrete or foam mortar or foam concrete, are not limited to above-mentioned waterproof material certainly, Should be understood to arbitrarily go for waterproof material of the present utility model.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1, described Side fascia is that insulation is outer Wallboard, described thermal insulation external wall panel at least includes heat-insulation layer 20.It is arranged such, be beneficial to the insulation of Side fascia, and as described above, can Heat-insulation layer 20 in upper Side fascia 1 bottom and the top of lower Side fascia 2 is dug up part and can be formed notch 9, simplifies operational procedure, Reduce difficulty of construction simultaneously.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1 and Fig. 2, described notch 9 is by outer The end face of wallboard extends to heat-insulation layer 20, and described waterproofing slurry is foam mortar or foam concrete.Be arranged such it is ensured that this The hot bridge cut-off function of Side fascia in the node of utility model, it is to avoid reduce the heat insulation function of Side fascia.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1 and Fig. 2, described upper Side fascia 1 It is reserved with splicing seams and lower Side fascia 2 between, the inner side and outer side of described splicing seams is equipped with seal 3, by described slip casting Hole 4 is perfused with waterproofing slurry in described splicing seams.Between described upper Side fascia 1 and lower Side fascia 2, reserved splicing seams are by close Sealing 3 encloses, after the completion of the assembly of upper Side fascia 1, by the injected hole 4 that is arranged in upper Side fascia 1 or lower Side fascia 2 described It is perfused with waterproofing slurry in splicing seams, forms one layer of horizontal waterproof layer 5, stop outdoor rain from leaking out to interior, improve waterproof effect Really.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2, described upper Side fascia 1 and/or Lower Side fascia 2 is provided with plural injected hole 4.Because Side fascia has certain width, on the one hand only setting one is noted Slurry hole 4 is difficult to be filled up completely with the splicing seams between upper Side fascia 1 and lower Side fascia 2 closely knit, and on the other hand arranging multiple holes can Slip casting simultaneously, improves efficiency of construction.
On the basis of above-described embodiment, in another embodiment of the utility model, described upper Side fascia 1 and/or lower exterior wall Plate 2 is provided with steam vent.It is arranged such, the discharge of air in favourable splicing seams during slip casting.
On the basis of above-described embodiment, in another embodiment of the utility model, described seal 3 bottom is coated with gluing Agent or be provided with double faced adhesive tape.It is arranged such, be conducive to seal 3 to be fixed on lower Side fascia 2, it is to avoid during cornice sheathing dropping place Seal 3 position changes, thus affecting the sealing of seal 3.
On the basis of above-described embodiment, in another embodiment of the utility model, described seal 3 is rectangle mount structure, Four sides of described seal 3 are matched with the top surface of lower Side fascia 2.It is arranged such, easy construction, simultaneously by the surrounding of splicing seams All enclose, improve sealing.
On the basis of above-described embodiment, in another embodiment of the utility model, the bottom surface of described upper Side fascia 1 and lower outer The top surface of wallboard 2 is matsurface.It is arranged such, waterproofing slurry is connected more with the bottom of upper Side fascia 1 and the top of lower Side fascia 2 Step up close.
On the basis of above-described embodiment, in another embodiment of the utility model, described wainscot sheathing top is provided with least one Individual blind hole.It is arranged such, during slip casting, in described blind hole, is perfused with slurry, so, the level being formed in splicing seams is prevented Water layer 5 be connected in lower Side fascia 2 structure more firm.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1, described injected hole 4 is hollow hole Or pre-buried hollow bushing.Core pulling in the prefabrication process of described hollow hole wallboard is formed, and injected hole 4 preferably passes through pre-buried hollow sleeve The mode of pipe is formed, and shaping is more easy.
On the basis of above-described embodiment, in another embodiment of the utility model, the inwall of described grout sleeve 22 is provided with Steel lobe.The setting of the utility model steel lobe increases grout sleeve 22 integral rigidity, on the premise of meeting rigidity, can suitably subtract Few grout sleeve 22 wall thickness, material-saving.Reducing wall thickness in the case of external diameter identical simultaneously, increased grouting material so that filling Slurry is more closely knit, and reinforcing bar is higher with the adhesive property of grout sleeve 22 entirety.Additionally, the slurry pouring into shape in grout sleeve 22 Become the lock solid structure matching with sky in sleeve and steel lobe, the anchorage reliability of reinforcing bar is greatly improved.
On the basis of above-described embodiment, in another embodiment of the utility model, described steel lobe opened up slurry hole or led Stock tank.Cross to starch hole or lead arranging of stock tank and have enough flowing spaces when on the one hand ensureing that grouting material flows to connection end, enrich Grouting material in gap between steel lobe can be connected integral simultaneously, increase grout sleeve 22 and grouting by whole grout sleeve Adhesion between material, the globality of grouting material is higher, and then is effectively increased the bond stress to reinforcing bar for the grouting material.
On the basis of above-described embodiment, in another embodiment of the utility model, described cross slurry hole or lead stock tank along grouting Sleeve 22 circumferentially disposed.So, by cross slurry hole or lead stock tank by between steel lobe gap connect.
The above is only preferred embodiment of the present utility model it is noted that common skill for the art For art personnel, on the premise of without departing from the utility model principle, some improvements and modifications can also be made, these improve and Retouching also should be regarded as protection domain of the present utility model.

Claims (10)

1. node installed by a kind of Side fascia, and including upper Side fascia, lower Side fascia and floor, described floor rides upon lower Side fascia On, described lower Side fascia top has poured in-situ layer, and described upper Side fascia and lower Side fascia adopt grout sleeve to connect, its feature It is, the vertical muscle of described lower Side fascia passes through in-situ layer and stretches in the grout sleeve of described upper Side fascia, in described grouting set The slurry anchor connection joint that slurry forms steel reinforcement abutting joints is poured in cylinder;The top of the bottom of described upper Side fascia and lower Side fascia is provided with Notch, described upper Side fascia and/or lower Side fascia are provided with injected hole, are irrigated in splicing seams and in notch by described injected hole There is waterproofing slurry.
2. Side fascia according to claim 1 installs node it is characterised in that described Side fascia is thermal insulation external wall panel, institute State thermal insulation external wall panel and at least include heat-insulation layer.
3. Side fascia according to claim 2 installs node it is characterised in that described notch is extended by the end face of Side fascia To heat-insulation layer, described waterproofing slurry is foam mortar or foam concrete.
4. Side fascia according to claim 2 installs node it is characterised in that between described upper Side fascia and lower Side fascia It is reserved with splicing seams, the inner side and outer side of described splicing seams is equipped with seal, by described injected hole in described splicing seams It is perfused with waterproofing slurry.
5. Side fascia according to claim 3 or 4 installs node it is characterised in that described upper Side fascia and/or lower exterior wall Plate is provided with plural injected hole.
6. Side fascia according to claim 3 or 4 installs node it is characterised in that described upper Side fascia and/or lower exterior wall Plate is provided with steam vent.
7. Side fascia according to claim 4 installs node it is characterised in that described seal bottom is coated with adhesive Or it is provided with double faced adhesive tape.
8. Side fascia according to claim 7 installs node it is characterised in that described seal is rectangle mount structure, institute State four sides of seal and the top surface of lower Side fascia matches.
9. Side fascia according to claim 8 installs node it is characterised in that the bottom surface of described upper Side fascia and lower exterior wall The top surface of plate is matsurface.
10. Side fascia according to claim 9 installs node it is characterised in that described lower Side fascia top is provided with least One blind hole.
CN201620518977.7U 2016-05-31 2016-05-31 Side fascia installation node Active CN205976057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620518977.7U CN205976057U (en) 2016-05-31 2016-05-31 Side fascia installation node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620518977.7U CN205976057U (en) 2016-05-31 2016-05-31 Side fascia installation node

Publications (1)

Publication Number Publication Date
CN205976057U true CN205976057U (en) 2017-02-22

Family

ID=58020053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620518977.7U Active CN205976057U (en) 2016-05-31 2016-05-31 Side fascia installation node

Country Status (1)

Country Link
CN (1) CN205976057U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863103A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wallboard mounting node
CN111764520A (en) * 2020-06-30 2020-10-13 北新绿色住宅有限公司 Fiber cement external wall panel lap joint seal structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863103A (en) * 2016-05-31 2016-08-17 中民筑友科技投资有限公司 Outer wallboard mounting node
CN111764520A (en) * 2020-06-30 2020-10-13 北新绿色住宅有限公司 Fiber cement external wall panel lap joint seal structure

Similar Documents

Publication Publication Date Title
CN206034677U (en) Side fascia installation node
CN205976143U (en) Side fascia installation node
CN206189870U (en) Improves construction quality,
CN105863103A (en) Outer wallboard mounting node
CN110761322B (en) Cast-in-place pipe gallery side wall horizontal construction joint reinforcing structure and construction method thereof
CN108678279A (en) Based on the built-in assembled architecture and its construction method for leading to high bellows prefabricated panel
CN208981531U (en) A kind of prefabricated assembled parapet connection structure
CN206189455U (en) Piping lane
CN105908878A (en) External wall panel mounting joint
CN209339466U (en) A kind of assembled parapet constructing structure
CN205894390U (en) Compound incubation exterior sheathing and take wall body of compound incubation exterior sheathing
CN107806349A (en) A kind of steel FRP complex waves card tunnel secondary liner structure and its apply method
CN108301466A (en) Integral prefabricated caisson of toilet and caisson of toilet construction and its construction method
CN205976057U (en) Side fascia installation node
CN105971154A (en) Installation joint for outer wallboards
CN205917937U (en) Side fascia installation node
CN207348239U (en) Connecting node waterproof construction
CN105863085A (en) External wall panel waterproof joint
CN210263453U (en) Precast concrete externally-hung wallboard structure bottom drainage structures
CN206189676U (en) Side fascia installation node
CN206034702U (en) Outer waterproof wall panel node
CN205975951U (en) Side fascia installation node
CN107035027A (en) A kind of assembled steel reinforced concrete structure light wt compound external wall panel
CN105863135A (en) Mounting node for external wall panel
CN205976150U (en) Side fascia installation node

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant