Prior art keywords
support
bridge
existing bridge
dismantling
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022185521.2U
Other languages
Chinese (zh)
Inventor
高珊
曹志枫
李丹
张帅阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Sixth Construction Group Co ltd
Original Assignee
Gansu Sixth Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Sixth Construction Group Co ltd filed Critical Gansu Sixth Construction Group Co ltd
Priority to CN202022185521.2U priority Critical patent/CN213538706U/en
Application granted granted Critical
Publication of CN213538706U publication Critical patent/CN213538706U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a movable protector that is used for existing bridge railing to demolish and resumes, including two slip tracks that are parallel to each other, the slip track sets up in the bridge upper surface along bridge length direction and is close to side wall department, install the support on the slip track, the support can be followed slip track length direction and removed, one side of support is fixed with the guard flap that is the arc structure, guard flap's lower extreme pastes and leans on the lower border department in the bridge side wall outside, guard flap can remove along with the support. The utility model discloses: the protective baffle is arranged close to the lower edge of the outer side of the bridge, so that concrete blocks or other impurities are prevented from falling below the bridge in the dismantling process of guardrails on two sides of the bridge, safety accidents are effectively prevented, and the surrounding environment is protected; the sliding rail is arranged, so that the support can move conveniently, and the use mode is simple and convenient; the construction personnel are not affected in the using process.

Description

Movable protection device for dismantling and recovering existing bridge guardrail
Technical Field
The utility model belongs to the technical field of the bridge construction, a movable protector that is used for existing bridge railing to demolish and resume is related to.
Background
When carrying out bridge both sides guardrail and demolish, the easy phenomenon that takes place to mix earth piece and other impurity and drop from the bridge both sides causes the potential safety hazard to bridge below personnel, or pollutes ecological environment around the bridge very easily, so when bridge both sides guardrail is demolishd, need set up protector in the bridge outside in order to prevent, impurity such as concrete piece drops to under the bridge.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to solve the problem that prior art exists, provide a movable protector that is used for existing bridge railing to demolish and resume.
Therefore, the utility model adopts the following technical scheme:
the utility model provides a movable protector that is used for existing bridge railing to demolish and resume, includes two slip tracks that are parallel to each other, the slip track sets up in the bridge upper surface near side wall department along bridge length direction, install the support on the slip track, the support can be followed slip track length direction and removed, one side of support is fixed with the guard flap that is the arc structure, guard flap's lower extreme pastes and leans on in the lower border department in the bridge side wall outside, guard flap can remove along with the support.
Furthermore, the cross section of the sliding track is of an I-shaped structure, the bottom end of the support is provided with a clamping groove matched with the cross section of the support, and the clamping groove is installed on the sliding track.
Further, the outside of draw-in groove is equipped with the screw, install the bolt in the screw.
Furthermore, a pulley is arranged in the clamping groove and is abutted against the upper surface of the sliding rail.
Further, a plurality of supporting rods are fixed to the top of the support, the supporting rods are located above the side walls of the bridge, connecting rods are fixed to the ends, far away from the support, of the supporting rods, and the bottom ends of the connecting rods are fixed to the protective baffle.
Furthermore, the lower part of support is equipped with the balancing weight fixed slot, install the balancing weight in the balancing weight fixed slot.
Further, the protective baffle is made of stainless steel.
The beneficial effects of the utility model reside in that: the protective baffle is arranged close to the lower edge of the outer side of the bridge, so that concrete blocks or other impurities are prevented from falling below the bridge in the dismantling process of guardrails on two sides of the bridge, safety accidents are effectively prevented, and the surrounding environment is protected; the sliding rail is arranged, so that the support can move conveniently, and the use mode is simple and convenient; the construction personnel are not affected in the using process.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic structural diagram of the novel card slot;
in the figure, 1-sliding rail, 2-bracket, 3-clamping groove, 4-screw hole, 5-bolt, 6-protective baffle, 7-supporting rod, 8-connecting rod, 9-counterweight block fixing groove, 10-counterweight block, 11-pulley, 12-bridge, 13-side wall and 14-guardrail.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention clearer and clearer, the present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1 and 2, a movable protection device for dismantling and recovering an existing bridge guardrail comprises two mutually parallel sliding rails 1, wherein the sliding rails 1 are arranged on the upper surface of a bridge 12 close to a side wall 13 along the length direction of the bridge 12, a support 2 is mounted on each sliding rail 1, the support 2 can move along the length direction of each sliding rail 1, specifically, the cross section of each sliding rail 1 is in an i-shaped structure, a clamping groove 3 matched with the cross section of each support is formed in the bottom end of each support 2, each clamping groove 3 is mounted on each sliding rail 1, when the movable protection device is used, a worker pushes each support 2 to move on each sliding rail 1 under the action of external force, a screw hole 4 is formed in the outer side of each clamping groove 3, a bolt 5 is mounted in each screw hole 4, and the support 2 can be fixed on the corresponding sliding rail 1 after the bolt 5 is tightened; in order to facilitate the movement of the bracket 2, a pulley 11 is arranged in the clamping groove 3, and the pulley 11 is abutted against the upper surface of the sliding rail 1, so that the friction force between the clamping groove 3 and the sliding rail 1 can be reduced during the movement.
A protective baffle 6 in an arc structure is fixed on one side of a support 2, the protective baffle 6 is made of stainless steel, the lower end of the protective baffle 6 is attached to the lower edge of the outer side of a side wall 13 of a bridge 12, the protective baffle 6 can move along with the support 2, specifically, a plurality of support rods 7 are fixed on the top of the support 2, the support rods 7 are positioned above the side wall of the bridge, one ends of the support rods 7, far away from the support 2, extend out of the side wall of the bridge and are fixed with connecting rods 8, the bottom ends of the connecting rods 8 are fixed with the protective baffle 6 in a welding mode, the protective baffle 6 is fixed in the mode, the structure of the protective baffle can prevent operators from being obstructed in dismantling operation engineering, and the working efficiency of the operators,
in order to keep the device stable in the using process, the lower part of the bracket 2 is provided with a balancing weight fixing groove 9, and a balancing weight 10 is installed in the balancing weight fixing groove 9.
The utility model discloses a work is made and the principle as follows:
before the bridge guardrail is dismantled, the sliding rail 1 is fixedly arranged on the upper surface of the bridge 12 close to the side wall 13, one end of the support 2 from the sliding rail 1 is arranged on the sliding rail 1, specifically, the clamping groove 3 is aligned to the outer end of the sliding rail 1 and then slides into the sliding rail 1, after the installation is finished, the lower end of the protective baffle 6 is close to the lower edge of the outer side of the side wall 13 of the bridge 12, then a worker pushes the support 2 to move the support 2 to an operation area where the guardrail 14 needs to be dismantled, then the counterweight 10 is arranged in the counterweight fixing groove 9 to improve the stability of the support 2, the bolt 5 is screwed tightly to prevent the support 2 from sliding on the sliding rail 1, after the installation is finished, the guardrail dismantling 14 operation can be carried out, cement blocks or other impurities falling from the outer side of the side wall 13 in the dismantling process fall onto the protective baffle 6, so that safety accidents or the surrounding environment around the bridge 12 cannot, after the guardrail is disassembled and constructed, the cement blocks or other impurities on the protective baffle 6 are cleared, then the balancing weight 10 is taken down, the bolt 5 is unscrewed, and the support 2 is pushed to another construction position.

Claims (7)

1. The utility model provides a movable protector that is used for existing bridge railing to demolish and resume, a serial communication port, including two slip tracks that are parallel to each other, the slip track sets up in the bridge upper surface and is close to side wall department along bridge length direction, install the support on the slip track, the support can be followed slip track length direction and removed, one side of support is fixed with the guard flap that is the arc structure, guard flap's lower extreme pastes the lower border department in the bridge side wall outside, guard flap can remove along with the support.
2. The movable protection device for dismantling and recovering an existing bridge guardrail as claimed in claim 1, wherein the cross section of the sliding rail is in an I-shaped structure, a clamping groove matched with the cross section of the support is formed in the bottom end of the support, and the clamping groove is installed on the sliding rail.
3. The movable protection device for dismantling and recovering an existing bridge guardrail as claimed in claim 2, wherein a screw hole is formed in the outer side of the clamping groove, and a bolt is installed in the screw hole.
4. The removable guard for demolition and restoration of an existing bridge railing according to claim 2, wherein a pulley is provided in the slot, the pulley abutting against the upper surface of the sliding track.
5. The movable protection device for dismantling and recovering an existing bridge guardrail as claimed in claim 1, wherein a plurality of support rods are fixed to the top of the support, the support rods are located above the side wall of the bridge, a connecting rod is fixed to one end, away from the support, of each support rod, and the bottom end of each connecting rod is fixed to the protection baffle.
6. The movable protection device for demolishing and recovering an existing bridge guardrail according to claim 1, wherein the lower portion of the bracket is provided with a counterweight fixing groove, and a counterweight is installed in the counterweight fixing groove.
7. The removable guard for demolition and restoration of an existing bridge railing according to claim 1, wherein the guard fence is made of stainless steel.
CN202022185521.2U 2020-09-29 2020-09-29 Movable protection device for dismantling and recovering existing bridge guardrail Active CN213538706U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022185521.2U CN213538706U (en) 2020-09-29 2020-09-29 Movable protection device for dismantling and recovering existing bridge guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022185521.2U CN213538706U (en) 2020-09-29 2020-09-29 Movable protection device for dismantling and recovering existing bridge guardrail

Publications (1)

Publication Number Publication Date
CN213538706U true CN213538706U (en) 2021-06-25

Family

ID=76495409

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022185521.2U Active CN213538706U (en) 2020-09-29 2020-09-29 Movable protection device for dismantling and recovering existing bridge guardrail

Country Status (1)

Country Link
CN (1) CN213538706U (en)

Similar Documents

Publication Publication Date Title
CN213538706U (en) Movable protection device for dismantling and recovering existing bridge guardrail
CN212247882U (en) Protection machine for road and bridge site operation
CN219138453U (en) A face limit protection device for construction
CN111648581A (en) Construction is with novel scaffold frame that has safeguard function
CN204663021U (en) Detachablely face limit early warning movable rail device
CN201106280Y (en) Hanging outrigger scaffold post-anchorage piece
CN213742223U (en) Elevator shaft operating frame
CN219034133U (en) Bridge pier pad stone construction safety device
CN220434299U (en) Device for protecting steel structure roof operation
CN213509955U (en) Safety device is used in building engineering construction
CN214362889U (en) Light-duty bridge electromechanical construction hangs hanging flower basket
CN216276882U (en) Super high-rise building core section of thick bamboo frog type creeping formwork device
CN212359331U (en) Movable protective fence for building construction
CN221645586U (en) Bridge support pad stone operation protector
CN218116158U (en) Pier hanging flower basket installation operation platform
CN221742105U (en) Elevartor shaft protection system device
CN211114923U (en) Fixing seat for upright post of edge guard rail
CN214245375U (en) Detachable pier body construction work platform
CN218322383U (en) Safety protection device
CN212176822U (en) Municipal construction is with rail guard convenient to transport
CN212671259U (en) Movable disassembly-free type edge opening protection device
CN210508462U (en) Fixing device for wall column of edge protection facility
CN214365440U (en) Height-adjustable assembled guardrail
CN221442305U (en) Rail guard for building engineering
CN215431334U (en) Underground steel wire rope chopping tool

Legal Events