CN201106280Y - Hanging outrigger scaffold post-anchorage piece - Google Patents
Hanging outrigger scaffold post-anchorage piece Download PDFInfo
- Publication number
- CN201106280Y CN201106280Y CNU2007201846516U CN200720184651U CN201106280Y CN 201106280 Y CN201106280 Y CN 201106280Y CN U2007201846516 U CNU2007201846516 U CN U2007201846516U CN 200720184651 U CN200720184651 U CN 200720184651U CN 201106280 Y CN201106280 Y CN 201106280Y
- Authority
- CN
- China
- Prior art keywords
- builder
- fixed mount
- building
- post
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The technical problem needs to be solved by the utility model is to provide an overhanging scaffolding post-installed fastener which has convenient installation and dismantlement, has certain protective effect on building surfaces, and causes no damages to buildings. The post-installed fastener is safe in use, thus guaranteeing the personnel safety of builders. In order to achieve the purpose, the technical proposal adopted by the post-installed fastener is that: the overhanging scaffolding post-installed fastener which comprises a mounting bracket inbuilt in the building is provided; steel bars are arranged at the top end of the mounting bracket, and the steel bar and the mounting bracket are connected by bolts.
Description
Technical field
The utility model relates to a kind of building implements, relates in particular to a kind of builder's jack rear anchor piece.
Background technology
It mainly is the architectural builder's jack that is provided with that relies on part to build up that scaffold is set up in present building site.As shown in Figure 1, present builder's jack is after what a semiorbicular fixed mount is set I-steel to be inserted, and is inserted into timber wedge then and fixes.Gu Ding shortcoming clearly fixes that to insert i shaped steel behind the fixed mount very inconvenient like this, insertions that need be close to the ground, and effort very, the while damages building surface easily.Squeeze into timber wedge and waste time and energy after inserting well, the back dismounting of finishing using is also very inconvenient.And timber wedge in use also is easy to become flexible, and brings hidden danger for workman's personal safety.Such structure in use also can cause damage to the surface of building.
The utility model content
Technical problem to be solved in the utility model just provides a kind of builder's jack rear anchor piece, and is easy for installation, dismantles also easily, simultaneously for building surface certain protection arranged, and can not cause damage.More secure when used, make that constructor's personal safety is guaranteed.
In order to solve the problems of the technologies described above, the utility model adopts following technical scheme: a kind of builder's jack rear anchor piece, comprise the fixed mount of burying underground under construction, and described fixed mount top is provided with the bar steel, and the bar steel is connected by bolt with fixed mount.
Preferred described fixed mount lower end is provided with cushion block near Architectural Services Department.Can protect building surface like this, simultaneously when construction, when carrying out certain buffering when painstaking as the I-steel of scaffold.
Preferably, fixed mount quantity is no less than 2 groups in each builder's jack rear anchor piece.Can further guarantee the safety factor of scaffold like this.
The utility model is owing to adopted technique scheme, and the fixed mount top is not sealed when mounted, and I-steel can be laid from top to bottom by crane, lay put in place after, with bolt setting strip steel I-steel is fixed, easy for installation quick, can not damage simultaneously building surface.As long as carry out inverse operation during dismounting.
Description of drawings
The utility model is described in further detail below in conjunction with accompanying drawing:
Fig. 1 is the structural representation of existing builder's jack.
Fig. 2 is the structural representation that has used the builder's jack of a kind of builder's jack rear anchor piece of the utility model.
Fig. 3 is a cross sectional view of having used the builder's jack of a kind of builder's jack rear anchor piece of the utility model.
The specific embodiment
Shown in Fig. 2,3, a kind of builder's jack rear anchor piece, comprise the fixed mount 4 that is embedded in the building 1, the I-steel 2 that generally will be needed to fix by crane during installation is placed in the fixed mount 4, use bolt 32 that fixed mount 4 tops are added bar steel 31 then, bar steel 31 and fixed mount 4 are firmly fixing with I-steel 2 together.I-steel 2 just can use as scaffold like this.Because it is painstaking that I-steel 2 is often wanted when in use, therefore, we are provided with cushion block 33 in described fixed mount 4 lower ends near building 1 place in use.Cushion block generally uses plank to get final product, and can the certain protection effect be arranged for building 1 surface like this.In order to guarantee constructor's safety, fixed mount 4 quantity are no less than 2 groups in each builder's jack rear anchor piece, can improve the safety factor of whole builder's jack so greatly.
As shown in Figure 1, original builder's jack dismounting is a big problem, because timber wedge 5 is difficult to complete taking-up, therefore each construction all will consume a large amount of timber wedge 5.Even so, still be easy to damage fixed mount 4 upper parts.And I-steel 2 can only extract, and so also will overcome and build the friction on 1 surface, more may damage the surface of building 1.And use the utility model builder's jack rear anchor piece now, and when dismounting, only need to use earlier crane regular worker Zee bar steel Z 2, open bolt 32 then, take off bar steel 31 and get final product.The all parts of builder's jack rear anchor piece can be reused, for construction work can be saved a lot of funds.
Claims (3)
1, a kind of builder's jack rear anchor piece comprises the fixed mount (4) that is embedded in the building (1), it is characterized in that: described fixed mount (4) top is provided with bar steel (31), and bar steel (31) is connected by bolt (32) with fixed mount (4).
2, builder's jack rear anchor piece according to claim 1 is characterized in that: cushion block (33) is located to be provided with near building (1) in described fixed mount (4) lower end.
3, builder's jack rear anchor piece according to claim 1 is characterized in that: fixed mount (4) quantity is no less than 2 groups in each builder's jack rear anchor piece.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007201846516U CN201106280Y (en) | 2007-10-17 | 2007-10-17 | Hanging outrigger scaffold post-anchorage piece |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2007201846516U CN201106280Y (en) | 2007-10-17 | 2007-10-17 | Hanging outrigger scaffold post-anchorage piece |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201106280Y true CN201106280Y (en) | 2008-08-27 |
Family
ID=39958081
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2007201846516U Expired - Fee Related CN201106280Y (en) | 2007-10-17 | 2007-10-17 | Hanging outrigger scaffold post-anchorage piece |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201106280Y (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296798A (en) * | 2011-06-14 | 2011-12-28 | 中国建筑第五工程局有限公司 | Bracket bearing structure at external corner part of segmented erection type scaffold |
CN102650149A (en) * | 2012-05-04 | 2012-08-29 | 中天建设集团有限公司 | I steel reinforcement and hoop fixing structure |
CN102653956A (en) * | 2012-05-04 | 2012-09-05 | 中天建设集团有限公司 | Cantilever beam support structure |
CN103306473A (en) * | 2012-03-09 | 2013-09-18 | 张全胜 | Tool type anchoring part for overhanging scaffold |
-
2007
- 2007-10-17 CN CNU2007201846516U patent/CN201106280Y/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296798A (en) * | 2011-06-14 | 2011-12-28 | 中国建筑第五工程局有限公司 | Bracket bearing structure at external corner part of segmented erection type scaffold |
CN103306473A (en) * | 2012-03-09 | 2013-09-18 | 张全胜 | Tool type anchoring part for overhanging scaffold |
CN102650149A (en) * | 2012-05-04 | 2012-08-29 | 中天建设集团有限公司 | I steel reinforcement and hoop fixing structure |
CN102653956A (en) * | 2012-05-04 | 2012-09-05 | 中天建设集团有限公司 | Cantilever beam support structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
CN203768803U (en) | Bridge wet joint formwork lifting device | |
CN201106280Y (en) | Hanging outrigger scaffold post-anchorage piece | |
CN203961238U (en) | Bolt anchor slab adjustable tool formula builder's jack | |
CN201953005U (en) | Detachable protective railing | |
CN202577960U (en) | Suspension outer bearing type combination steel formwork applied in roller compacted concrete (RCC) construction | |
CN202596148U (en) | Reusable cantilever scaffold anchoring compression ring | |
CN205153515U (en) | Overhanging bearing frame makes up positioner | |
CN203145488U (en) | Limb protective railings of foundation pit and for building construction | |
CN202194395U (en) | Tool type edge protector rack | |
CN208056519U (en) | A kind of detachable edge protection column | |
CN204126290U (en) | Elevator shaft horizontal protective device | |
CN203499234U (en) | Anchoring tool for overhanging scaffold | |
CN201710847U (en) | Safety protection device | |
CN205348815U (en) | Face limit protector and pole setting thereof | |
CN204850515U (en) | Steel construction faces limit protector | |
CN205348816U (en) | Face limit protector and pole setting thereof | |
CN203583906U (en) | Disassembling-free floor edge guardrail in decoration stage | |
CN204343647U (en) | A kind of the shaped steel suspension scaffolding bracing frame | |
CN209145185U (en) | A kind of staircase external angle protective device and constructing device | |
CN201495788U (en) | Safety protecting net system | |
CN201261947Y (en) | Assembled safety channel | |
CN203361676U (en) | Temporary protective guard for building construction | |
CN208456185U (en) | A kind of tower crane wall-connecting piece safe walkway | |
CN205445641U (en) | Hydraulic prop prevents down fixing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |