CN213326288U - Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure - Google Patents

Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure Download PDF

Info

Publication number
CN213326288U
CN213326288U CN202021481856.2U CN202021481856U CN213326288U CN 213326288 U CN213326288 U CN 213326288U CN 202021481856 U CN202021481856 U CN 202021481856U CN 213326288 U CN213326288 U CN 213326288U
Authority
CN
China
Prior art keywords
roof beam
frame
beam structure
top surface
threaded hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021481856.2U
Other languages
Chinese (zh)
Inventor
李处嘎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Yuqing Construction Technology Co ltd
Original Assignee
Henan Yuqing Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Yuqing Construction Technology Co ltd filed Critical Henan Yuqing Construction Technology Co ltd
Priority to CN202021481856.2U priority Critical patent/CN213326288U/en
Application granted granted Critical
Publication of CN213326288U publication Critical patent/CN213326288U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of building lifting device, especially, be an assembled building prefabricated wall hoist and mount shoulder pole roof beam, including the roof beam structure, the equal rigid coupling in left and right sides face of roof beam structure has vertical baffle, the bottom mounting welding of vertical baffle has buffer, the equal fixed welding in both ends has rings about the roof beam structure top surface, the lower part of hanging frame has been cup jointed in both ends activity about the roof beam structure surface, the fixed transverse baffle that has cup jointed in middle part of lower part hanging frame inner wall. The utility model discloses a setting of frame is hung to the lower part, utilizes roof beam structure and the direct bolted connection of lower part hanging frame, can let the lower part hang the frame and carry out the transform of position at the surface of roof beam structure for the hoist and mount operation of the prefabricated wall of reply equidimension not, and through the interact between horizontal baffle, locating plate and the picture peg, can let the lower part hang the frame joint at the surface of roof beam structure, break away from between lower part hanging frame and the roof beam structure can not appear, thereby improved the practicality of this shoulder pole roof beam.

Description

Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure
Technical Field
The utility model relates to a building lifting device technical field especially relates to an assembly type structure prefabricated wall hoist and mount shoulder pole roof beam.
Background
The prefabricated building is a building which directly installs prefabricated components such as a floor slab, a wallboard, a stair tread, a balcony and the like in a hoisting mode, mainly comprises a prefabricated concrete structure, a steel structure, a modern wood structure building and the like, and is a representative of a modern industrial production mode due to the adoption of standardized design, factory production, assembly construction, information management and intelligent application.
However, in the prior art, because the prefabricated part can not be directly connected with the tower crane through the hoisting rope in the hoisting process, the prefabricated part is damaged due to uneven stress, the shoulder pole beam is required to be used for indirect connection in the hoisting operation, the upward acting force of the tower crane acting on the prefabricated part is balanced, but the existing shoulder pole beam is mostly an I-shaped steel and can not be suitable for hoisting the prefabricated part with all sizes, the limitation of the prefabricated part is large in use, the prefabricated part is directly placed on the ground through the tower crane after being generally used, hard collision can be generated when the prefabricated part is in contact with the bottom surface, and the prefabricated wall hoisting shoulder pole beam of the prefabricated building can be damaged to a certain extent.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing an assembly type construction precast wall hoisting carrying pole beam.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the utility model provides an assembled building precast wall hoist and mount shoulder pole roof beam, includes the roof beam structure, the equal gim peg in the left and right sides face of roof beam structure has vertical baffle, the bottom mounting welding of vertical baffle has buffer, the equal fixedly welded in both ends has rings about the roof beam structure top surface, the lower part of having cup jointed about both ends is hung the frame all movable, the lower part is hung the fixed transverse baffle that has cup jointed in middle part of frame inner wall, the tip of transverse baffle runs through the inner wall that the frame was hung to the lower part and extends to the outside and the fixed welding of hanging the frame of lower part and have the locating plate, the fixed cover in top surface of locating plate has the picture peg, the top surface of locating plate is run through and extends to the outside bottom of locating plate in the bottom of picture peg, the top and the bottom of picture.
Preferably, buffer includes first buffering lagging, the top surface of first buffering lagging and the fixed welding in bottom surface of vertical baffle, second buffering lagging has been cup jointed in the bottom activity of first buffering lagging, the bottom of first buffering lagging runs through the top surface of second buffering lagging and extends to the inside of second buffering lagging and fixed welding has the limiting plate, the fixed welding in bottom surface of limiting plate has buffer spring, buffer spring's bottom and the fixed bolt in bottom surface of second buffering lagging inner chamber.
Preferably, a first threaded hole is formed in the middle of the top surface of the lower hanging frame, a second threaded hole is formed in the middle of the top surface of the transverse baffle, and the size, position and shape of the first threaded hole are matched with those of the second threaded hole.
Preferably, the front surface of the beam frame is provided with a main threaded hole, and the size and the shape of the main threaded hole are matched with those of the first threaded hole.
Preferably, the top surface of the positioning plate is provided with a locking hole, and the size and the shape of the locking hole are matched with those of the inserting plate.
Preferably, the middle part of the front face of the beam frame is provided with a sliding groove, the sliding groove penetrates through the front face and the back face of the beam frame, and the transverse baffle is located inside the sliding groove.
Compared with the prior art, the beneficial effects of the utility model are that: firstly, the device utilizes the roof beam structure and the direct bolted connection of lower part hanging frame through the setting of lower part hanging frame, can let the lower part hanging frame carry out the transform of position at the surface of roof beam structure for the hoist and mount operation of the prefabricated wall of reply equidimension not, and through the interact between horizontal baffle, locating plate and the picture peg, can let the lower part hanging frame joint at the surface of roof beam structure, the breaking away from between lower part hanging frame and the roof beam structure can not appear, thereby has improved the practicality of this shoulder pole roof beam.
The utility model discloses a buffer can provide the cushioning effect when this shoulder pole roof beam hoist and mount finishes placing on ground, utilize mutually supporting between first buffering lagging, second buffering lagging, limiting plate and the buffer spring, let buffer spring can change the relative position between first buffering lagging and the second buffering lagging through elastic deformation for the decurrent effort of direction that this shoulder pole roof beam produced because of the dead weight of buffering, thereby improved the suitability of this shoulder pole roof beam.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a top view of the external structure of the present invention;
FIG. 3 is a side view of the structure of the present invention;
fig. 4 is a schematic view of a partial structure of the present invention;
FIG. 5 is an enlarged view of the structure at A in FIG. 1;
fig. 6 is a schematic view of a partial structure of the present invention.
In the figure: 1. a beam frame; 2. a vertical baffle; 3. a buffer device; 31. a first cushion collar plate; 32. a second buffer sleeve plate; 33. a limiting plate; 34. a buffer spring; 4. a hoisting ring; 5. a lower hanging frame; 6. a transverse baffle; 7. positioning a plate; 8. and (4) inserting plates.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution: a prefabricated wall hoisting carrying pole beam of an assembly type building comprises a beam frame 1, wherein the front surface of the beam frame 1 is provided with a main threaded hole, the size and the shape of the main threaded hole are matched with those of a first threaded hole, the main threaded hole, the first threaded hole and a second threaded hole are arranged so as to be capable of fixedly connecting the beam frame 1 and a lower hoisting frame 5 by using bolts, the beam frame 1 and the lower hoisting frame 5 can be integrated to improve the stability and the safety of hoisting operation, the middle part of the front surface of the beam frame 1 is provided with a sliding groove, the sliding groove penetrates through the front surface and the back surface of the beam frame 1, a transverse baffle 6 is positioned inside the sliding groove, the sliding groove is arranged so as to enable the lower hoisting frame 5 to slide left and right on the outer surface of the beam frame 1, rapid adjustment is carried out along with the difference of the length of a hoisting wall body, the left side surface and the right side surface of the beam frame 1 are fixedly, the buffer device 3 comprises a first buffer sleeve plate 31, the top surface of the first buffer sleeve plate 31 is fixedly welded with the bottom surface of the vertical baffle 2, a second buffer sleeve plate 32 is movably sleeved at the bottom end of the first buffer sleeve plate 31, the bottom end of the first buffer sleeve plate 31 penetrates through the top surface of the second buffer sleeve plate 32 and extends to the inside of the second buffer sleeve plate 32, a limit plate 33 is fixedly welded at the bottom surface of the limit plate 33, a buffer spring 34 is fixedly welded at the bottom surface of the limit plate 33, the bottom end of the buffer spring 34 is fixedly bolted with the bottom surface of the inner cavity of the second buffer sleeve plate 32, when the shoulder pole beam is placed after use, a buffering acting force is provided for the shoulder pole beam when the shoulder pole beam contacts the ground, the damage of the components of the shoulder pole beam caused by hard collision is avoided, hanging rings 4 are fixedly welded at the left end and the right end of the top surface of the beam frame 1, lower hanging frames 5 are movably sleeved at the left end and the right end of the, the middle part of the top surface of the transverse baffle 6 is provided with a second threaded hole, the size, the position and the shape of the first threaded hole are the same as those of the second threaded hole, position and shape looks adaptation, the fixed horizontal baffle 6 that has cup jointed in middle part of lower part hanging frame 5 inner wall, the tip of horizontal baffle 6 runs through the inner wall of lower part hanging frame 5 and extends to the outside and the fixed welding of lower part hanging frame 5 has locating plate 7, the locking hole has been seted up to the top surface of locating plate 7, the size and the shape of locking hole and the size and the shape looks adaptation of picture peg 8, the setting of locking hole can let horizontal baffle 6 and lower part hang being connected between the frame 5 more stable, let the lower part hang frame 5 at the gliding more steady of surface of roof beam structure 1, picture peg 8 has been cup jointed to the top surface of locating plate 7 is fixed, the bottom of picture peg 8 runs through the top surface of locating plate 7 and extends to the outside bottom of locating plate 7, the top and the bottom of picture peg 8 respectively with the positive top of lower part hanging frame.
The working principle is as follows: during the use, operating personnel at first carries out the adjustment in the position to lower part hoisting frame 5 according to the length of prefabricated wall body, treat that lower part hoisting frame 5 adjusts to the position of needs after, pass first screw hole, main screw hole and second screw hole in proper order through the bolt, let the position of lower part hoisting frame 5 can be fixed at the surface of roof beam structure 1, then be connected between couple and rings 4 of tower crane, let the couple can pass rings 4, the rethread hoisting rope is connected the bottom of lower part hoisting frame 5 and prefabricated wall body, then alright lift by crane, hang prefabricated wall body to the region that needs the installation.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an assembled building prefabricated wall hoist and mount shoulder pole roof beam, includes roof beam structure (1), its characterized in that: the left side surface and the right side surface of the beam frame (1) are fixedly bolted with vertical baffles (2), the bottom end of the vertical baffle (2) is fixedly welded with a buffer device (3), the left end and the right end of the top surface of the beam frame (1) are fixedly welded with lifting rings (4), the left end and the right end of the outer surface of the beam frame (1) are movably sleeved with a lower hanging frame (5), the middle part of the inner wall of the lower hanging frame (5) is fixedly sleeved with a transverse baffle (6), the end part of the transverse baffle (6) penetrates through the inner wall of the lower hanging frame (5) and extends to the outside of the lower hanging frame (5) and is fixedly welded with a positioning plate (7), the top surface of the positioning plate (7) is fixedly sleeved with an inserting plate (8), the bottom end of the inserting plate (8) penetrates through the top surface of the positioning plate (7) and extends to the bottom end outside the positioning plate (7), the top end and the bottom end of the inserting plate (8) are fixedly bolted with the top and the bottom of the front surface of the lower hanging frame (5) respectively.
2. The prefabricated wall hoisting carrying pole beam for the prefabricated building as claimed in claim 1, wherein: buffer (3) are including first buffering lagging (31), the top surface of first buffering lagging (31) and the bottom surface fixed weld of vertical baffle (2), second buffering lagging (32) have been cup jointed in the bottom activity of first buffering lagging (31), the bottom of first buffering lagging (31) runs through the top surface of second buffering lagging (32) and extends to the inside and the fixed welding of second buffering lagging (32) and has limiting plate (33), the fixed welding in bottom surface of limiting plate (33) has buffer spring (34), the bottom of buffer spring (34) and the bottom surface fixed bolt of second buffering lagging (32) inner chamber.
3. The prefabricated wall hoisting carrying pole beam for the prefabricated building as claimed in claim 1, wherein: the middle part of the top surface of the lower hanging frame (5) is provided with a first threaded hole, the middle part of the top surface of the transverse baffle (6) is provided with a second threaded hole, and the size, position and shape of the first threaded hole are matched with those of the second threaded hole.
4. The prefabricated wall hoisting carrying pole beam for the prefabricated building as claimed in claim 1, wherein: the front surface of the beam frame (1) is provided with a main threaded hole, and the size and the shape of the main threaded hole are matched with those of the first threaded hole.
5. The prefabricated wall hoisting carrying pole beam for the prefabricated building as claimed in claim 1, wherein: the top surface of the positioning plate (7) is provided with a locking hole, and the size and the shape of the locking hole are matched with those of the inserting plate (8).
6. The prefabricated wall hoisting carrying pole beam for the prefabricated building as claimed in claim 1, wherein: the middle part of the front surface of the beam frame (1) is provided with a sliding groove, the sliding groove penetrates through the front surface and the back surface of the beam frame (1), and the transverse baffle (6) is positioned inside the sliding groove.
CN202021481856.2U 2020-07-24 2020-07-24 Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure Active CN213326288U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021481856.2U CN213326288U (en) 2020-07-24 2020-07-24 Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021481856.2U CN213326288U (en) 2020-07-24 2020-07-24 Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure

Publications (1)

Publication Number Publication Date
CN213326288U true CN213326288U (en) 2021-06-01

Family

ID=76090420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021481856.2U Active CN213326288U (en) 2020-07-24 2020-07-24 Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure

Country Status (1)

Country Link
CN (1) CN213326288U (en)

Similar Documents

Publication Publication Date Title
CN113152873A (en) Heightening hanging basket system
CN201864454U (en) Lifting appliance of centralized overhauling transportation system of electrolytic cell
CN201721597U (en) Flat deck track type marine hanging basket suspension
CN213326288U (en) Prefabricated wall hoist and mount shoulder pole roof beam of assembly type structure
CN205591529U (en) Attached lifting scaffold
CN204456816U (en) One can promote supporting leg type elevator hoistway construction platform
CN209855192U (en) Automatic lifting frame for shaped elevator shaft way
CN106481967B (en) A kind of installation method of rubber diaphragm gas chamber
CN209815490U (en) Hoisting device for rotor magnetic pole in hydraulic generator pit
CN209750913U (en) Multi-functional roofing belt cleaning device fixed knot constructs
CN210150541U (en) Special-shaped building construction elevator
CN216042530U (en) Heightening hanging basket system
CN212562404U (en) Overhanging scaffold
CN215974523U (en) Rocker arm hinge pin replacer
CN205687396U (en) A kind of rotary suspension hook of wind-power tower
CN213834250U (en) Auxiliary lifting device for manhole cover
CN210117167U (en) Bridge type swing arm crane
CN216038278U (en) Novel installation of bridge crane parallel operation connecting rod device
CN218560864U (en) Construction structure based on BIM in super high-rise building
CN219906752U (en) Hoisting device for anti-floating anchor rod
CN213539680U (en) Scaffold connecting piece latch fitting convenient to installation
CN214570279U (en) Climbing frame of tower crane and tower crane
CN209760032U (en) Bottom die of truss hanging basket
CN218754515U (en) Assembled stair lifting device
CN213682523U (en) Connecting device for building external hanging and building main body

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant