CN213268825U - Processing device for climbing frame attachment support meeting small beam - Google Patents

Processing device for climbing frame attachment support meeting small beam Download PDF

Info

Publication number
CN213268825U
CN213268825U CN202021603055.9U CN202021603055U CN213268825U CN 213268825 U CN213268825 U CN 213268825U CN 202021603055 U CN202021603055 U CN 202021603055U CN 213268825 U CN213268825 U CN 213268825U
Authority
CN
China
Prior art keywords
atress
pipe
extension
stress tube
climbing frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021603055.9U
Other languages
Chinese (zh)
Inventor
周健芝
李忠鹏
刘睿智
李威震
秦洪伟
王鹏
李明信
岳晓洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202021603055.9U priority Critical patent/CN213268825U/en
Application granted granted Critical
Publication of CN213268825U publication Critical patent/CN213268825U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a climb a processing apparatus that attaches support and meet trabecula, including floor body and balcony roof beam, the top of balcony roof beam is provided with extension atress platform, the right side fixedly connected with at extension atress platform top climbs a support of attaching, the both sides at extension atress platform top all run through and are provided with the atress pipe, the inner chamber of atress pipe is provided with straining device, straining device is including the pulling post that is located the atress inside pipe chamber, annular groove has been seted up to the bottom on pulling post surface, annular groove's inner chamber annular is provided with three rotation and supports the piece. The utility model discloses a run through the inner chamber to pre-buried pipe fitting with the atress pipe for the bottom of atress pipe extends to the bottom of floor body, uses through the cooperation of straining device and thread bush afterwards, makes floor body and extension atress platform can the centre gripping fixed, can reach the installation effectiveness height and demolish convenient purpose.

Description

Processing device for climbing frame attachment support meeting small beam
Technical Field
The utility model belongs to the technical field of the construction, especially, relate to a climb frame and adhere to processing apparatus that support meets trabecula.
Background
The climbing frame is also called a lifting frame, can be divided into hydraulic type, electric type, manual pull type and other main types according to the power source, is a novel scaffold system developed in recent years, is mainly applied to high-rise shear wall type floors, can ascend or descend along a building, and completely improves the scaffold technology by the system, namely, the scaffold does not need to be turned over, and the scaffold is not required to be disassembled and assembled (the scaffold is used till the construction is finished after one-time assembly), is not limited by the height of the building, greatly saves manpower and materials, has larger improvement on the traditional scaffold in the safety angle, and has great development advantages in high-rise buildings.
When climbing the frame and adhering to the support and meeting the high balcony roof beam of minitude, the support height is greater than the roof beam height, if consider to adhere to on the roof beam, because of being restricted to fall the board and wear the necessary high unable installation and atress requirement of satisfying of screw rod, and the connected mode of traditional bolt screw, in the use of reality, need the user to push away floor top and bottom simultaneously and carry out the concurrent operation, run through the floor with the screw rod, again by the user nut on the bottom of the floor is to the screw rod cover, the mode of this kind of installation, the construction degree of difficulty is great, the process of construction is comparatively loaded down with trivial details, the installation effectiveness is.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a climb a processing apparatus who adheres to support and meet trabecula, have the installation effectiveness height and demolish convenient advantage, solved and climbed a attached to support and met when the high balcony roof beam of minimus, the support height is greater than the roof beam height, if consider to adhere to on the roof beam, because of being under the control of falling the board and wearing the necessary unable installation and the atress requirement of highly satisfying of screw rod, and the connected mode of traditional bolt screw rod, in the use of reality, it carries out the concurrent operation to need the user to push away floor top and bottom simultaneously, run through the floor with the screw rod, cap nut on the screw rod cover bottom the floor by the user again, the mode of this kind of installation, the construction degree of difficulty is great, the process of construction is comparatively loaded down with trivial details, the lower problem of.
The utility model provides an above-mentioned technical problem's technical scheme as follows: a processing device for a climbing frame attachment support meeting a small beam comprises a floor slab body and a balcony beam, wherein the top of the balcony beam is provided with an extension stress platform, the right side of the top of the extended stress platform is fixedly connected with a climbing frame attachment support, stress pipes are arranged on both sides of the top of the extended stress platform in a penetrating way, the inner cavity of the stress tube is provided with a tensioning mechanism, the tensioning mechanism comprises a pulling column positioned in the inner cavity of the stress tube, the bottom of the surface of the pulling column is provided with an annular groove, the inner cavity of the annular groove is annularly provided with three rotating resisting blocks, the bottom of the surface of the stress tube is annularly provided with a rectangular through hole matched with the rotary resisting block, the rotary resisting block is rotationally connected with the inner wall of the rectangular through hole, the surface of the stress tube is rotatably connected with a threaded sleeve, and the top of the surface of the stress tube is provided with an external thread matched with the threaded sleeve.
The utility model discloses a processing apparatus for a trawling frame adheres to support and meets trabecula, further: spacing through-holes are formed in the top of the surface of the pulling column and the top of the surface of the stress tube, and a spacing column penetrates through the top of the right side of the stress tube.
The utility model discloses a processing apparatus for a trawling frame adheres to support and meets trabecula, further: the bottom of the inner cavity of the stress tube is welded with a spring, and the top of the spring is welded with the bottom of the pulling column.
The utility model discloses a processing apparatus for a trawling frame adheres to support and meets trabecula, further: the surface of the pulling column is fixedly connected with a limiting ring, and the inner wall of the stress tube is provided with an annular limiting groove matched with the limiting ring.
The utility model discloses a processing apparatus for a trawling frame adheres to support and meets trabecula, further: the surface cover of atress pipe is equipped with pre-buried pipe fitting, pre-buried pipe fitting's top and bottom laminate mutually with the bottom of extension atress platform and the top of floor body respectively.
The utility model has the advantages that:
1. the utility model has the advantages that the stress tube is penetrated to the inner cavity of the embedded pipe fitting, the bottom of the stress tube is extended to the bottom of the floor slab body, then the floor slab body and the extension stress platform are clamped and fixed by the matching of the tensioning mechanism and the thread sleeve, the purposes of high installation efficiency and convenient disassembly can be achieved, the problems that when the climbing frame attachment support meets a small-height balcony beam, the height of the support is larger than the height of the beam, if the attachment on the beam is considered, the installation and stress requirements can not be met due to the necessary height of the descending plate and the threaded rod can be solved, in the connection mode of the traditional bolt and the screw rod, in the actual use process, a user needs to push the top and the bottom of the floor slab simultaneously to operate, the threaded rod penetrates through the floor slab, and then the nut is sleeved on the bottom of the floor slab by the user, the installation mode has large construction difficulty and complicated, the installation efficiency is lower.
2. The utility model discloses a cooperation of spacing through-hole and spacing post is used, and when the top of pulling post and the top of atress pipe are neat at ordinary times, can penetrate the inner chamber of two spacing through-holes with spacing post, carry on spacingly to the pulling post for the spring can not upwards promote the pulling post.
3. The utility model discloses a setting of spring plays the effect that upwards promotes to the pulling post for the pulling post drives three rotation and supports the piece and take place the rotation, makes then to rotate and supports the inner chamber that the piece breaks away from the atress pipe.
4. The utility model discloses a cooperation of spacing ring and annular spacing groove is used, has played spacing effect to the pulling post, supports the piece to rotating then and carries on spacingly, has avoided rotating to support the piece excessively rotatory.
Drawings
The above and/or other aspects and advantages of the present invention will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are given by way of illustration only and not by way of limitation, wherein:
fig. 1 is a schematic front sectional view of an embodiment of the present invention;
FIG. 2 is an enlarged view of a portion of point A of FIG. 1 according to the present invention;
FIG. 3 is an enlarged view of a portion of point B in FIG. 1 according to the present invention;
fig. 4 is a schematic perspective view of the stress tube, the tightening mechanism and the thread bushing of the present invention.
In the drawings, the components represented by the respective reference numerals are listed below:
1. floor body, 2, balcony roof beam, 3, climb a frame and adhere to the support, 4, extension atress platform, 5, atress pipe, 6, straining device, 61, pulling post, 62, annular groove, 63, rotate and support the piece, 64, rectangle through-hole, 7, thread bush, 8, spring, 9, spacing through-hole, 10, spacing post, 11, spacing ring, 12, annular spacing groove, 13, pre-buried pipe fitting.
Detailed Description
Hereinafter, an embodiment of the present invention of a processing apparatus for a scaffold attachment support encountering a trabecula will be described with reference to the accompanying drawings.
The embodiments described herein are specific embodiments of the present invention, and are intended to be illustrative of the concepts of the present invention, which are intended to be illustrative and exemplary, and should not be construed as limiting the scope of the embodiments of the present invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
The drawings in the present specification are schematic views to assist in explaining the concept of the present invention, and schematically show the shapes of the respective portions and the mutual relationships thereof. It should be noted that for the sake of clarity in showing the structures of the various components of the embodiments of the present invention, the drawings are not drawn to the same scale. Like reference numerals are used to denote like parts.
FIGS. 1-4 show a device for processing a climbing frame attachment support encountered by a trabecula, which comprises a floor slab body 1 and a balcony beam 2, wherein the top of the balcony beam 2 is provided with an extension stress platform 4, the right side of the top of the extension stress platform 4 is fixedly connected with the climbing frame attachment support 3, two sides of the top of the extension stress platform 4 are respectively provided with a stress tube 5, the bottom of the inner cavity of the stress tube 5 is welded with a spring 8, the top of the spring 8 is welded with the bottom of a pulling column 61, the surface of the stress tube 5 is sleeved with a pre-embedded tube 13, the top and the bottom of the pre-embedded tube 13 are respectively attached to the bottom of the extension stress platform 4 and the top of the floor slab body 1, the inner cavity of the stress tube 5 is provided with a tensioning mechanism 6, the tensioning mechanism 6 comprises the pulling column 61 located in the inner cavity of the stress tube 5, the top of the surface of the pulling column 61 and the top of, the top on the right side of the stress tube 5 is provided with a limiting column 10 in a penetrating way, the limiting column 10 can penetrate into the inner cavities of the two limiting through holes 9 to limit the pulling column 61 through the matching use of the limiting through holes 9 and the limiting column 10 when the top of the pulling column 61 is level with the top of the stress tube 5, the spring 8 can not push the pulling column 61 upwards, the pulling column 61 is pushed upwards through the arrangement of the spring 8, the pulling column 61 drives the three rotation resisting blocks 63 to rotate, the rotation resisting blocks 63 are separated from the inner cavity of the stress tube 5, the surface of the pulling column 61 is fixedly connected with a limiting ring 11, the inner wall of the stress tube 5 is provided with an annular limiting groove 12 matched with the limiting ring 11, the pulling column 61 is limited through the matching use of the limiting ring 11 and the annular limiting groove 12, the rotation resisting blocks 63 are limited, and the excessive rotation resisting blocks 63 are avoided, the bottom on pulling post 61 surface has seted up annular groove 62, and the inner chamber annular of annular groove 62 is provided with three and rotates and supports piece 63, and the bottom annular on atress pipe 5 surface is seted up and is supported the rectangle through-hole 64 that piece 63 looks adaptation with rotating, rotates and supports the inner wall rotation connection of piece 63 and rectangle through-hole 64, and the surface rotation of atress pipe 5 is connected with thread bush 7, and the top on atress pipe 5 surface is provided with the external screw thread with thread bush 7 looks adaptation.
The working principle is as follows: the utility model discloses when using, the user is through running through the inner chamber to pre-buried pipe fitting 13 with atress pipe 5, make the bottom of atress pipe 5 remove to the bottom of floor body 1, take out spacing post 10 afterwards, pulling post 61 removes spacingly this moment, spring 8 expands rapidly and promotes pulling post 61 and upwards moves in the inner chamber of atress pipe 5, pulling post 61 is in the in-process of upward movement, it rotates to drive to rotate and supports piece 63 to take place rotatoryly through annular groove 62, make to rotate and support piece 63 and break away from the inner chamber of atress pipe 5, the user rotates thread bush 7 afterwards, under the combined action of the screw thread of inner wall and atress pipe 5 surface external screw thread, make atress pipe 5 upward movement, until the top that rotates and supports piece 63 closely laminates with the bottom of floor body 1, and can when thread bush 7 can's unable rotation;
when the floor slab is disassembled, a user reversely rotates the threaded sleeve 7 to enable the rotary resisting blocks 63 to be separated from the bottom of the floor slab body 1, then the pulling columns 61 are pressed downwards, the pulling columns 61 move downwards, the three rotary resisting blocks 63 are retracted to the inner cavity of the stress tube 5, the limiting columns 10 are inserted into the inner cavity of the limiting through hole 9 again, the position of the pulling columns 61 is limited, and the stress tube 5 is pulled out upwards;
through the operation of above step, can reach the purpose that the installation effectiveness is high and demolish convenient.
In summary, the following steps: the processing device for the climbing frame attachment support meeting the small beam is characterized in that the stress tube 5 penetrates into the inner cavity of the embedded pipe fitting 13, so that the bottom of the stress tube 5 extends to the bottom of the floor slab body 1, then the floor slab body 1 and the extension stress platform 4 are clamped and fixed through the matching use of the tensioning mechanism 6 and the thread sleeve 7, the purposes of high installation efficiency and convenient and fast removal can be achieved, the problem that when the climbing frame attachment support meets the small-height balcony beam, the support height is larger than the beam height, if the attachment on the beam is considered, the installation and stress requirements cannot be met due to the necessary height of a descending plate and a threaded rod is penetrated is solved, in the actual use process, a user needs to push the top and the bottom of the floor slab simultaneously to operate, the threaded rod penetrates through the floor slab, and then the nut is sleeved on the threaded rod at the bottom of the floor slab by the user, and the installation mode is achieved, the construction difficulty is great, the construction process is relatively complicated, and the installation efficiency is lower
The technical features disclosed above are not limited to the combinations with other features disclosed, and other combinations between the technical features can be performed by those skilled in the art according to the purpose of the invention to achieve the aim of the invention.

Claims (6)

1. The utility model provides a climb a processing apparatus that attaches support and meet trabecula, its characterized in that, includes floor body (1) and balcony roof beam (2), the top of balcony roof beam (2) is provided with extension atress platform (4), the right side fixedly connected with at extension atress platform (4) top climbs a frame and attaches support (3), the both sides at extension atress platform (4) top are all run through and are provided with atress pipe (5), the inner chamber of atress pipe (5) is provided with straining device (6), straining device (6) are including pulling post (61) that are located atress pipe (5) inner chamber, annular groove (62) have been seted up to the bottom on pulling post (61) surface, the inner chamber annular of annular groove (62) is provided with three rotation and supports piece (63), the bottom annular on atress pipe (5) surface is seted up with rotation and supports rectangle through-hole (64) that piece (63) adapted, the rotary supporting block (63) is rotatably connected with the inner wall of the rectangular through hole (64), the surface of the stress tube (5) is rotatably connected with the threaded sleeve (7), and the top of the surface of the stress tube (5) is provided with an external thread matched with the threaded sleeve (7).
2. The processing device for the attachment support of the climbing frame to meet the trabecula as claimed in claim 1, wherein the top of the surface of the pulling column (61) and the top of the surface of the stress tube (5) are both provided with a limiting through hole (9), and the top of the right side of the stress tube (5) is provided with a limiting column (10) in a penetrating way.
3. The handling device of the attachment support of the climbing frame to the trabecula as claimed in claim 1, characterized in that the spring (8) is welded to the bottom of the inner cavity of the stress tube (5), and the top of the spring (8) is welded to the bottom of the pulling column (61).
4. The processing device for the trawl meeting of the attachment support of the climbing frame according to claim 1, wherein a limiting ring (11) is fixedly connected to the surface of the pulling column (61), and an annular limiting groove (12) matched with the limiting ring (11) is formed in the inner wall of the stress tube (5).
5. The processing device for the climbing frame attachment support encountering the trabecula as claimed in claim 1, wherein the surface of the stress tube (5) is sleeved with an embedded pipe (13), and the top and the bottom of the embedded pipe (13) are respectively attached to the bottom of the extension stress platform (4) and the top of the floor slab body (1).
6. The handling device for the trawl met by the attachment seat of the climbing frame according to claim 1, wherein a plurality of handles are fixedly connected to the surface of the threaded sleeve (7) in a ring shape.
CN202021603055.9U 2020-08-05 2020-08-05 Processing device for climbing frame attachment support meeting small beam Active CN213268825U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021603055.9U CN213268825U (en) 2020-08-05 2020-08-05 Processing device for climbing frame attachment support meeting small beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021603055.9U CN213268825U (en) 2020-08-05 2020-08-05 Processing device for climbing frame attachment support meeting small beam

Publications (1)

Publication Number Publication Date
CN213268825U true CN213268825U (en) 2021-05-25

Family

ID=75969562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021603055.9U Active CN213268825U (en) 2020-08-05 2020-08-05 Processing device for climbing frame attachment support meeting small beam

Country Status (1)

Country Link
CN (1) CN213268825U (en)

Similar Documents

Publication Publication Date Title
CN106241679B (en) A kind of mechanical platform being mostly used extensible automatic control lifting
CN201544357U (en) Portable dedicated device for suspended ceiling drilling
CN213268825U (en) Processing device for climbing frame attachment support meeting small beam
CN201103235Y (en) Connection device between wall and scaffold
CN106351441B (en) Chimney climbing formwork for construction device and construction method
CN112727074A (en) Building machine and building construction method
CN201571545U (en) Structural frame ascending operation shoes
CN203846740U (en) Boring support for ceiling
CN207553558U (en) A kind of assembly scaffold
CN110644787A (en) Convenient form removal instrument of secondary prefabricated construction timber formwork loss prevention of building construction floor
KR101349598B1 (en) Working Platform Movable on the Deck
CN111617405B (en) A fire control unit for forest zone
CN214220576U (en) Supporting structure of attached lifting scaffold
CN210519519U (en) Gardens of using with dolly combination are cut
CN210009541U (en) Fire water monitor
CN219451444U (en) Building climbing frame
CN215760616U (en) Fixing device capable of quickly fixing climbing net
CN107717846B (en) Special jig for disassembling cutter
CN206129130U (en) Power maintenance ladder convenient to climbing
CN215631531U (en) Outer climbing frame protection device for building construction
CN216239629U (en) Scaffold for building engineering
CN216552990U (en) Steel rope fastening structure for aerial work hanging basket
CN216042535U (en) Climbing frame for building construction
CN219622215U (en) Integrated structure of decoration double-layer construction platform
CN210947647U (en) Detachable portable scaffold for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant