CN212982293U - Novel simple and easy lever hoist - Google Patents
Novel simple and easy lever hoist Download PDFInfo
- Publication number
- CN212982293U CN212982293U CN202021745975.4U CN202021745975U CN212982293U CN 212982293 U CN212982293 U CN 212982293U CN 202021745975 U CN202021745975 U CN 202021745975U CN 212982293 U CN212982293 U CN 212982293U
- Authority
- CN
- China
- Prior art keywords
- hoisting
- steel pipe
- rod
- base
- lifting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model discloses a novel simple lever sling, which comprises a base, a vertical supporting rod, a supporting piece, a hoisting cross rod, a lifting hook and a traction rope; the base can be additionally provided with a balance weight by using a soil bag according to the actual situation on site, so that the stability in the hoisting and rotating process is ensured; the bottom ends of the vertical supporting rods are arranged on the base through steel pipe fasteners; the supporting piece adopts three steel pipes to connect the vertical supporting rods with the base through steel pipe fasteners respectively, and the combination is in a triangular stable spatial structure; the hoisting cross rod is transversely arranged at the top end of the supporting vertical rod through the S-shaped steel bar hook, and the rigidity of the hoisting cross rod needs to meet the requirement of no deformation or bending in the hoisting process; the lifting hook and the traction rope are arranged below one end of the lifting cross rod together. The utility model discloses equipment is simple, simple to operate, with low costs, efficient superiority, and generally little medium-sized professional team all can be from the beginning to the beginning, can direct application on narrow construction platform such as side slope.
Description
Technical Field
The utility model belongs to the technical field of lifting device, concretely relates to novel simple and easy lever hoist.
Background
In the construction process of highway slope protection engineering, prefabricated parts are required to be installed on the slope in most of the time. On-site hoisting from top to bottom cannot be adopted due to the influence of the anchor rod, manual carrying and installation are not suitable for high-altitude platform-free operation, a large amount of physical power needs to be consumed, efficiency is low, and construction safety risk is large. In the prior art, if a hoisting crane is adopted for hoisting, although the hoisting radius and the hoisting height are large, the mechanization degree is higher, the labor amount of workers can be greatly reduced; but has the defects of high installation cost, low speed, crane resource waste, large rope hoisting swing, incapability of accurately hoisting in place, easy collision with high-altitude operation personnel and potential safety hazard. If adopt climing the mountain tiger material loading machine, though light in weight, vertical transport is fast, area is little, is the common vertical transport equipment in highway protection engineering, has the characteristics such as extension height, nevertheless to installing that the horizontal displacement of unit inner member is great, the operating condition of no power is not applicable, and the ann tears open inconveniently, needs the operation team to carry out the equipment investment. Generally, due to the limitation of a field, the number of installation components is large, the hoisting height is not large, and the methods can not meet the engineering requirements. Based on the technical scheme, the lever simple lifting appliance is provided, and the components are conveyed to the specified installation position on the side slope through the lever principle.
Disclosure of Invention
To the weak point among the prior art, the utility model provides a novel simple and easy lever hoist has solved hoist and mount prefabricated component waste hoisting machinery resource and the slow problem of progress on narrow construction platform, has simplified construction method, has improved the efficiency of construction, has reduced the construction risk, has created economic benefits.
In order to achieve the above purpose, the utility model discloses technical scheme as follows:
a novel simple lever lifting appliance comprises a base, a supporting vertical rod, a supporting piece, a lifting cross rod, a lifting hook and a traction rope;
the base is composed of five steel pipes, the four steel pipes are vertically connected end to end by steel pipe fasteners or welded to form a rectangular base, and the other steel pipe is arranged in the middle of the rectangular base to be used as a reinforcing rod, so that the balance weight can be increased by a soil bag according to the actual situation on site, and the stability in the hoisting and rotating process is ensured;
the bottom end of the vertical supporting rod is arranged on the base through a steel pipe fastener and falls on one end of the reinforcing rod, and the length of the vertical supporting rod is selected and arranged according to the height of the side slope;
the supporting piece adopts three steel pipes to respectively connect the vertical supporting rods with the base through steel pipe fasteners, the combination is in a triangular stable space structure, and the length of the supporting piece is selectively set according to the length of the vertical supporting rods;
the hoisting cross rod is transversely arranged at the top end of the supporting vertical rod through the S-shaped steel bar hook, a steel pipe with a proper length is selected according to the height of a field and a side slope, the rigidity of the steel pipe needs to meet the requirement that the steel pipe is not deformed or bent in the hoisting process, and the flexibility of the hoisting cross rod in the up-and-down and rotation process in the construction process is ensured and the steel pipe is not easy to deform;
the lifting hook and the traction rope are arranged below one end of the lifting cross rod together.
Furthermore, the lifting hook is a B-shaped lifting hook.
Furthermore, the haulage rope adopts ordinary string all can, and the toughness satisfies the afterbody and lifts up the in-process and not break, mainly as for the effect of supplementary steering and lifting hook pushing down.
Furthermore, in order to avoid that an operator cannot reach the tail of the hoisting cross rod after the object is hoisted by the lifting hook due to too large hoisting height, the other end of the hoisting cross rod is also provided with a hoisting rope; the sling is made of a thick rope with high flexibility and good comfort, the toughness meets the requirement of no breakage in the process of hoisting a heavy object, and the length meets the requirement that the lifting hook can hoist the heavy object.
Has the advantages that: the utility model discloses equipment is simple, simple to operate, with low costs, efficient superiority, and generally little medium-sized professional team all can be from the beginning to the beginning, can direct application on narrow construction platform such as side slope. In particular, the method comprises the following steps of,
(1) the construction cost is saved: the waste of crane resources is saved, the investment of equipment and electric power of a project is reduced, and in addition, the cost for building a platform is saved;
(2) the construction progress is accelerated: by adopting the traditional construction scheme of climbing tigers for hoisting and manual carrying, the construction period is long, the times of equipment carrying and dismounting are more, the construction progress is slow, the visual nodes of the project cannot be met, and after the lever simple hoisting tool is adopted, the component hoisting is accurate and in place, a large amount of carrying time is saved, the construction efficiency is improved by 50 percent, and the originally planned construction period of 13.5 days is finished in only 6 days;
(3) the safety risk is reduced: the risk that operating personnel walk in the high altitude in the transverse precast block in the vertical hoisting process of the traditional creeper is avoided, the risk that the operating personnel collide with the hoisting personnel due to overlarge cable swing in the hoisting process of the crane is avoided, and the construction safety is ensured.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
In the figure, 1-base, 2-supporting vertical rod, 3-supporting piece, 4-lifting cross rod, 5-lifting hook, 6-traction rope and 7-lifting rope.
Detailed Description
The present invention is described below with reference to specific examples. It will be understood by those skilled in the art that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention in any way.
A novel simple lever lifting appliance is shown in figure 1 and comprises a base 1, a supporting vertical rod 2, a supporting piece 3, a lifting cross rod 4, a lifting hook 5, a traction rope 6 and a lifting rope 7;
the base 1 consists of five steel pipes, the four steel pipes are vertically connected end to end by steel pipe fasteners or welded to form a rectangular base, and the other steel pipe is arranged in the middle of the rectangular base to be used as a reinforcing rod, so that the balance weight can be increased by a soil bag according to the actual situation on site, and the stability in the hoisting and rotating process is ensured;
the bottom end of the vertical supporting rod 2 is arranged on the base 1 through a steel pipe fastener and falls on one end of the reinforcing rod, and the length of the vertical supporting rod is selected and arranged according to the height of the side slope;
the supporting piece 3 is formed by connecting the supporting vertical rod 2 and the base 1 through three steel pipes respectively through steel pipe fasteners, the combination is in a triangular stable space structure, and the length of the supporting vertical rod is selected and set according to the length of the supporting vertical rod 2;
the hoisting cross rod 4 is transversely arranged at the top end of the supporting vertical rod 2 through an S-shaped steel bar hook, a steel pipe with a proper length is selected according to the height of a field and a side slope, the rigidity of the steel pipe needs to meet the requirement that the steel pipe is not deformed or bent in the hoisting process, and the flexibility of the hoisting cross rod in the up-and-down and rotation process is ensured and the steel pipe is not easy to deform in the construction process;
the lifting hook 5 and the traction rope 6 are arranged below one end part of the lifting cross rod 4 together, and the lifting hook 5 is a B-shaped lifting hook; the traction rope 6 can be a common thin rope, the toughness meets the requirement that the tail part is not broken in the lifting process, and the traction rope is mainly used for assisting steering and pressing down a lifting hook;
in order to avoid that an operator cannot reach the tail part of the lifting cross rod 4 after the lifting hook 5 lifts an object due to too large lifting height, the lifting sling 7 is arranged at the other end part of the lifting cross rod 4; the sling 7 is made of a thick rope with high flexibility and good comfort, the toughness meets the requirement of no breakage in the process of hoisting heavy objects, and the length meets the requirement that the lifting hook can hoist the objects.
Specifically, the specification of five steel pipes forming the base 1 is 1.5m, phi 50 and 4.5 mm;
the specification of the steel pipe of the supporting vertical rod 2 is phi 50-89 x 4.5 mm;
the specification of three steel pipes adopted by the supporting piece 3 is phi 40 x 4.5 mm;
the B-shaped hook of the hook 5 is made of phi 22 steel bars.
The utility model discloses a work flow:
(1) the equipment is in place: firstly, assembling a machine tool according to a drawing, then carrying out trial hoisting and rotation according to the weight of a hoisting piece and the target weight of 2.0 times, moving the machine tool to a stable operation field according to the installation position of a component after meeting the safety and stability performance, and reinforcing and balancing the base;
(2) the method comprises the following steps that (1) when a component is in place, the component to be installed is conveyed to a lifting range;
(3) and (5) hoisting and installing. According to the field requirement, the target member is lifted by an operator and then rotated to the installation position, and then the target member is installed by other personnel in the next step.
Claims (4)
1. The utility model provides a novel simple and easy lever hoist, its characterized in that: comprises a base, a supporting vertical rod, a supporting piece, a lifting cross rod, a lifting hook and a traction rope;
the base is composed of five steel pipes, the four steel pipes are vertically connected end to end by steel pipe fasteners or welded to form a rectangular base, and the other steel pipe is arranged in the middle of the rectangular base to be used as a reinforcing rod, so that the balance weight can be increased by a soil bag according to the actual situation on site, and the stability in the hoisting and rotating process is ensured;
the bottom end of the vertical supporting rod is arranged on the base through a steel pipe fastener and falls on one end of the reinforcing rod, and the length of the vertical supporting rod is selected and arranged according to the height of the side slope;
the supporting piece adopts three steel pipes to respectively connect the vertical supporting rods with the base through steel pipe fasteners, the combination is in a triangular stable space structure, and the length of the supporting piece is selectively set according to the length of the vertical supporting rods;
the hoisting cross rod is transversely arranged at the top end of the supporting vertical rod through the S-shaped steel bar hook, a steel pipe with a proper length is selected according to the height of a field and a side slope, the rigidity of the steel pipe needs to meet the requirement that the steel pipe is not deformed or bent in the hoisting process, and the flexibility of the hoisting cross rod in the up-and-down and rotation process in the construction process is ensured and the steel pipe is not easy to deform;
the lifting hook and the traction rope are arranged below one end of the lifting cross rod together.
2. The new simple lever hanger of claim 1, wherein said hook is a sigmoid hook.
3. The novel simple lever hanger according to claim 1, wherein the pulling rope is a common thin rope, and the toughness of the pulling rope is sufficient for the tail part not to break during lifting, and is mainly used for assisting steering and pressing down the lifting hook.
4. The novel simple lever sling according to claim 1 wherein a sling is further provided at the other end of the lifting cross-bar; the sling is made of a thick rope with high flexibility and good comfort, the toughness meets the requirement of no breakage in the process of hoisting a heavy object, and the length meets the requirement that the lifting hook can hoist the heavy object.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021745975.4U CN212982293U (en) | 2020-08-20 | 2020-08-20 | Novel simple and easy lever hoist |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021745975.4U CN212982293U (en) | 2020-08-20 | 2020-08-20 | Novel simple and easy lever hoist |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212982293U true CN212982293U (en) | 2021-04-16 |
Family
ID=75434497
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021745975.4U Active CN212982293U (en) | 2020-08-20 | 2020-08-20 | Novel simple and easy lever hoist |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212982293U (en) |
-
2020
- 2020-08-20 CN CN202021745975.4U patent/CN212982293U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101284628B (en) | Hoisting method for framework of large tonnage pressing machine | |
CN204199721U (en) | A kind of erecting device for factory building construction high and medium structure | |
CN206692235U (en) | A kind of steel structure dome lifts by crane erecting device | |
CN108979131B (en) | Integral lifting platform device for high-rise building construction steel formwork and operation frame | |
CN110759222A (en) | Take quick hoist device of PC wallboard of counter weight | |
CN203834373U (en) | Lifting movement mold carriage trolley for box culvert side wall formwork | |
CN103993739B (en) | The construction method of granulation tower spraying layer stiff beam | |
CN206753105U (en) | A kind of skyscraper tears building machine open | |
CN101818563B (en) | Jack-up integral lifting mobile platform and using method | |
CN212982293U (en) | Novel simple and easy lever hoist | |
CN210483094U (en) | Inverted triangular pipe truss lifting device | |
CN217400394U (en) | High-altitude manual hoisting profiled steel sheet construction device | |
CN113668401B (en) | Hoisting process based on installation and transportation platform on long-span bridge pier | |
CN215291319U (en) | Multi-point elevator shaft construction lifting platform | |
CN210763974U (en) | Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material | |
CN210505201U (en) | Equipment for hoisting reinforcing steel bars in batches | |
CN212405472U (en) | Cross node connection structure of assembled frame structure | |
CN110606435B (en) | Suspension type electric hoist suitable for reverse construction method soil taking port transferring materials | |
CN211169496U (en) | Take quick hoist device of PC wallboard of counter weight | |
CN107059654A (en) | The compound overlength Hanging basket on front support of single cable plane and its installation method | |
CN204185146U (en) | Construction of Steel Structure overhang crane between skyscraper two tall buildings | |
CN103015323B (en) | Beam body hoisting device | |
CN105113426A (en) | Cable connector and steel truss arch bridge cable connecting method | |
CN206256382U (en) | It is a kind of to suspend purlin car in midair for the triangle that Wavelike steel webplate is installed | |
CN221479293U (en) | Cable tower main cable saddle grid reaction frame bolt lifting appliance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |