CN204185146U - Construction of Steel Structure overhang crane between skyscraper two tall buildings - Google Patents
Construction of Steel Structure overhang crane between skyscraper two tall buildings Download PDFInfo
- Publication number
- CN204185146U CN204185146U CN201420447851.6U CN201420447851U CN204185146U CN 204185146 U CN204185146 U CN 204185146U CN 201420447851 U CN201420447851 U CN 201420447851U CN 204185146 U CN204185146 U CN 204185146U
- Authority
- CN
- China
- Prior art keywords
- truss
- crane
- track
- construction
- crane truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种高层建筑双塔楼间钢结构施工用悬挂起重机,包括吊车桁架上弦、吊车桁架下弦、工字钢、连接件、电动葫芦,其特征在于:吊车桁架上弦和吊车桁架下弦通过吊车桁架腹杆和缀条连接组合而成空间格构式桁架,吊车桁架上弦两端为桁架端头,搁置并固定在砼梁上;吊车桁架下弦的下翼缘上设置连接件,连接件与轨道工字钢上翼缘采用螺栓连接,吊车桁架下弦与轨道工字钢在竖直面上平行,轨道工字钢的两端用橡胶块或角钢与轨道工字钢腹板螺栓连接设置成车挡;电动葫芦通过行走装置安装在轨道工字钢上;手拉葫芦的挂钩和吊钩分别用钢丝绳捆绑于砼柱和桁架端头上。起重的能力大,施工效率高,同时不长期占用公用的起重设备,保证各专业施工的同步进行。
A suspension crane for steel structure construction between two towers of a high-rise building, including the upper chord of the crane truss, the lower chord of the crane truss, I-beam, connectors, and electric hoist, characterized in that: the upper chord of the crane truss and the lower chord of the crane truss pass through the web of the crane truss and the The two ends of the upper chord of the crane truss are truss ends, which are shelved and fixed on the concrete beam; the lower flange of the lower chord of the crane truss is provided with a connecting piece, and the connecting piece is connected to the track I-beam. The flange is connected by bolts, the lower chord of the crane truss is parallel to the I-beam of the track on the vertical plane, and the two ends of the I-beam of the track are connected by rubber blocks or angle steel to the web of the I-beam of the track to form a car block; the electric hoist passes through The walking device is installed on the track I-beam; the hook and hook of the chain hoist are respectively tied to the concrete column and the end of the truss with a steel wire rope. The lifting capacity is large, the construction efficiency is high, and at the same time, the public lifting equipment is not occupied for a long time, which ensures the simultaneous progress of various professional constructions.
Description
所属技术领域 Technical field
本实用新型涉及一种建筑施工用起重设备,更具体涉及一种高层建筑双塔楼间钢结构施工用悬挂起重机。用于高层建筑双塔楼间,钢结构施工时能够吊装大型钢构件,且可纵向运输的悬挂式起重设备。 The utility model relates to a hoisting device for building construction, in particular to a suspension crane for steel structure construction between double towers of a high-rise building. Suspension-type hoisting equipment that can hoist large-scale steel components during steel structure construction and can be transported longitudinally between the twin towers of high-rise buildings.
背景技术 Background technique
目前,建筑工地常用的起重设备有固定式起重机(例如固定式塔式起重机等)、移动式起重机(例如汽车起重机、履带式起重机等)。对于以钢筋混凝土结构为主,钢结构为辅助或点缀的双塔楼高层公共建筑,往往塔式起重机的选型都比较小,而且可移动重机无法驶入建筑内部作业,或由于移动式起重机作业半径大、高度大等原因,导致无法吊装,或者吊臂与塔楼建筑相碰撞等安全问题,此种情况对钢结构大型构件的吊装有很大的影响。如果将大型钢构件进行再分段,变为重量较小的构件,往往钢构件会变得很零碎,一来可能无法满足设计及规范要求,二来增加工地的作业量(例如吊装、拼装、焊接等),降低施工效率,加长工期,甚至增加辅助措施等成本。再者如果钢结构施工长时间占用塔式起重机,则会影响土建等相关其它专业的施工进度。 At present, the commonly used lifting equipment on construction sites includes fixed cranes (such as fixed tower cranes, etc.), mobile cranes (such as truck cranes, crawler cranes, etc.). For high-rise public buildings with double towers mainly composed of reinforced concrete structures and steel structures as auxiliary or embellishment, the selection of tower cranes is often relatively small, and the mobile cranes cannot drive into the building to work, or due to the mobile cranes operating Large radius, high height and other reasons lead to safety problems such as failure to hoist, or collision between the boom and the tower building. This situation has a great impact on the hoisting of large steel structure components. If the large steel components are subdivided into smaller components, the steel components will often become very fragmented, which may not meet the design and specification requirements, and increase the workload on the construction site (such as hoisting, assembling, Welding, etc.), reducing construction efficiency, lengthening the construction period, and even increasing the cost of auxiliary measures. Furthermore, if the steel structure construction occupies the tower crane for a long time, it will affect the construction progress of other related disciplines such as civil engineering.
此外,工厂车间用的桥式起重机(吊车)(详见《钢结构设计手册(上册)》(第三版)P901~P914)须安装平行的工字钢轨道,且最大的吊车跨度为31.5m,对于条件相对复杂多变的建筑工地就不适用,例如,间距大于31.5m的双塔楼,或者塔楼上搁置吊车的梁(轨道)不平行等,桥式起重机均不适用。再者,电动单梁悬挂起重机的轨道梁最大跨度仅为9m,适用性就更小了。龙门起重机对自身轨道基础要求较高,并且支腿高度、横梁跨度一般都不满足高层建筑的施工需求。 In addition, the bridge cranes (cranes) used in the factory workshop (see "Steel Structure Design Manual (Volume 1)" (Third Edition) P901~P914 for details) must be installed with parallel I-shaped steel tracks, and the maximum span of the crane is 31.5m , It is not applicable to construction sites with relatively complex and changeable conditions, for example, double towers with a distance greater than 31.5m, or the beams (rails) of the cranes on the towers are not parallel, etc., bridge cranes are not applicable. Furthermore, the maximum span of the track beam of the electric single-girder suspension crane is only 9m, and the applicability is even smaller. Gantry cranes have high requirements on their own track foundations, and the height of outriggers and spans of beams generally do not meet the construction requirements of high-rise buildings.
综上所述,建筑工地常用的起重机、工厂车间用的桥式起重机、电动单梁悬挂起重机、龙门起重机均不能满足双塔楼高层建筑内部的重型钢结构施工。 To sum up, the cranes commonly used on construction sites, bridge cranes used in factory workshops, electric single-girder suspension cranes, and gantry cranes cannot meet the heavy steel structure construction inside a double-tower high-rise building.
发明内容 Contents of the invention
为了克服建筑钢结构施工中,塔式起重机无法完全吊装所有钢构件,且移动式起重机无法作业或作业时安全风险大的不足,本实用新型提供一种起重机——高层建筑双塔楼间钢结构施工用悬挂起重机,既能高层建筑双塔楼间满足大型钢构件的吊装,减少钢结构的工地作业量,又能不用长时间占用的塔式起重机,各专业共同施工配合,提高施工效率,降低成本。 In order to overcome the shortcomings that the tower crane cannot completely hoist all the steel components in the construction of the building steel structure, and the mobile crane cannot work or the safety risk is high during operation, the utility model provides a kind of crane-steel structure construction between double towers of high-rise buildings The use of suspension cranes can not only meet the hoisting of large steel components between the two towers of high-rise buildings, reduce the workload of steel structures on the site, but also eliminate the need for long-term occupation of tower cranes, and cooperate with each professional to improve construction efficiency and reduce costs.
本实用新型解决其技术问题所采用的技术方案是: The technical scheme that the utility model solves its technical problem adopts is:
吊车桁架上弦和吊车桁架下弦通过吊车桁架腹杆和缀条连接组合而成空间格构式桁架,吊车桁架上弦两端为桁架端头,搁置并固定在砼梁上。 The upper chord of the crane truss and the lower chord of the crane truss are combined through the connection of the web of the crane truss and the strips to form a space lattice truss.
吊车桁架上弦和吊车桁架下弦的桁架材质为Q235B或Q345B,桁架的截面规格为H钢或圆管或方管。 The truss material of the upper chord of the crane truss and the lower chord of the crane truss is Q235B or Q345B, and the section specification of the truss is H steel or round tube or square tube.
吊车桁架下弦的下翼缘上设置连接件,连接件与轨道工字钢上翼缘采用螺栓连接,吊车桁架下弦与轨道工字钢在竖直面上平行,轨道工字钢的两端用橡胶块或角钢与轨道工字钢腹板螺栓连接设置成车挡。 The lower flange of the lower chord of the crane truss is provided with a connecting piece, which is connected with the upper flange of the track I-beam by bolts. The lower chord of the crane truss is parallel to the track I-beam on the vertical plane, and rubber The block or angle steel is connected with the track I-beam web bolts to form a car block.
橡胶块规格为100mm(厚)X100mm(长)X100mm(宽),角钢规格为L80x10。 The specification of the rubber block is 100mm (thickness) X100mm (length) X100mm (width), and the specification of the angle steel is L80x10.
电动葫芦通过行走装置安装在轨道工字钢上。 The electric hoist is installed on the track I-beam through the traveling device.
手拉葫芦的挂钩和吊钩分别用钢丝绳捆绑于砼柱和桁架端头上。 The hook and hook of the chain hoist are respectively bound to the concrete column and the end of the truss with a steel wire rope.
本实用新型的优点是解决建筑钢结构施工中,塔式起重机无法完全吊装所有钢构件,且移动式起重机无法作业或作业时安全风险大的难题,起重量明显大于常规塔吊,覆盖范围广,在建筑施工中不占用公用的起重设备,吊车桁架的材料普通,结构简单,电动葫芦的成本低,整套起重机系统安拆方便,操作简单,可重复使用。 The utility model has the advantage of solving the problem that the tower crane cannot completely hoist all the steel components in the construction of the building steel structure, and the mobile crane cannot work or the safety risk is high during operation. The lifting capacity is obviously larger than that of the conventional tower crane, and the coverage is wide. No public hoisting equipment is occupied during the building construction. The material of the crane truss is common, the structure is simple, the cost of the electric hoist is low, the whole crane system is easy to install and dismantle, easy to operate, and can be reused.
附图说明 Description of drawings
下面结合附图和实施例对本实用新型进一步说明。 Below in conjunction with accompanying drawing and embodiment the utility model is further described.
图1是本实用新型的立面图及节点详图。 Fig. 1 is the elevation view of the utility model and the detailed diagram of node.
图2是本实用新型的俯视图。 Fig. 2 is a top view of the utility model.
图3是本实用新型的应用实例。 Fig. 3 is the application example of the utility model.
图中,1-吊车桁架上弦,2-吊车桁架腹杆,3-吊车桁架下弦,4-桁架端头,5-轨道工字钢,6-连接件,7-车挡,8-电动葫芦,9-吊钩,10-行走装置,11-滑道,12-砼柱,13-砼梁,14-缀条,15-手动葫芦,16-砼次梁,17-高层建筑塔楼,18-吊车桁架,19-大型钢构件,20-已起重拼装完成的钢结构。 In the figure, 1- the upper chord of the crane truss, 2- the web of the crane truss, 3- the lower chord of the crane truss, 4- the end of the truss, 5- the track I-beam, 6- the connector, 7- the car stop, 8- the electric hoist, 9-hook, 10-traveling device, 11-slide, 12-concrete column, 13-concrete beam, 14-strip, 15-manual hoist, 16-concrete secondary beam, 17-high-rise building tower, 18-crane Truss, 19-large steel components, 20-steel structures that have been hoisted and assembled.
具体实施方式 Detailed ways
下面结合附图详述本实用新型的具体实施方式: The specific embodiment of the utility model is described in detail below in conjunction with accompanying drawing:
在高层建筑两塔楼之间,钢结构的施工平台上方,安装高层建筑双塔楼间钢结构施工用悬挂起重机,将建筑内部大型钢构件的吊起,将其沿道轨道运送到指定位置落钩安装。此起重机主要包括吊车桁架18、轨道工字钢5、电动葫芦8、手动葫芦15四大部分。 Between the two towers of the high-rise building, above the construction platform of the steel structure, install a suspension crane for the construction of the steel structure between the two towers of the high-rise building, lift the large steel components inside the building, transport them along the track to the designated location, and drop the hook for installation. The crane mainly includes four parts: crane truss 18, track I-beam 5, electric hoist 8, and manual hoist 15.
吊车桁架18:两榀相同的平面桁架用缀条连接组合而成空间格构式桁架,有利提高平面外刚度,保证侧向稳定,同时,根据需要,灵活在其任何一榀或两榀平面桁架下安装轨道工字5和电动葫芦8。吊车桁架的材质一般为Q235B或Q345B,桁架的高度一般为跨度的1/10~1/20,桁架的截面规格一般为H钢、圆管、方管等。具体的做法由恒载,以及吊重、检修等活荷载,根据现行《钢结构设计规范》(GB50017-2003)的计算结果以及实际情况需要而定。桁架的两端4搁置在高层建筑两塔楼17的砼梁13上,砼梁13与吊车桁架端头4接触面之间,放置-10mm(厚)x300mm(宽)的钢板,一方面作为吊车桁架横梁移动的滑道11。另一方面,保护成品砼梁13。若计算结果有要求,须对相应的砼梁13进行局部加固。桁架端头一般伸入塔楼内不小于500mm。 Crane truss 18: Two identical planar trusses are connected by dowels to form a spatial lattice truss, which is beneficial to improve out-of-plane rigidity and ensure lateral stability. Install track I-shaped 5 and electric hoist 8 below. The material of the crane truss is generally Q235B or Q345B, the height of the truss is generally 1/10 to 1/20 of the span, and the cross-sectional specification of the truss is generally H steel, round tube, square tube, etc. The specific method depends on the dead load, live load such as hoisting and maintenance, according to the calculation results of the current "Code for Design of Steel Structures" (GB50017-2003) and the actual situation. The two ends 4 of the truss are placed on the concrete beams 13 of the two towers 17 of the high-rise building. Between the concrete beam 13 and the contact surface of the end 4 of the crane truss, a steel plate of -10mm (thickness) x 300mm (width) is placed, on the one hand as a crane truss The slideway 11 that crossbeam moves. On the other hand, the finished concrete beam 13 is protected. If the calculation result requires, the corresponding concrete beam 13 must be partially reinforced. The end of the truss generally extends into the tower by not less than 500mm.
轨道工字钢5:选自《热轧工字钢尺寸、外形、重量及允许偏差》(GB/T 706-1988),由Q235B钢轧制而成。其型号由电动葫芦8的型号而定。在吊车桁架下弦3的下翼缘上设置连接件6,连接件6与轨道工字钢5上翼缘采用螺栓连接,吊车桁架下弦3与轨道工字钢5在竖直面上平行。轨道工字钢的两端用100mm(厚)X100mm(长)X100mm(宽)的橡胶块或L80x10的角钢与轨道工字钢腹板螺栓连接设置成车挡7。 Track I-beam 5: selected from "Hot-rolled I-beam size, shape, weight and allowable deviation" (GB/T 706-1988), rolled from Q235B steel. Its model is decided by the model of electric hoist 8. A connector 6 is arranged on the lower flange of the lower chord 3 of the crane truss, and the connector 6 is connected with the upper flange of the track I-beam 5 by bolts, and the lower chord 3 of the crane truss is parallel to the track I-beam 5 on the vertical plane. The two ends of the track I-beam are connected with the track I-beam web bolts with 100mm (thick) X100mm (long) X100mm (wide) rubber block or L80x10 angle steel to form a car block 7 .
电动葫芦8:根据工程的需要(例如起重量、起升高度等)确定其型号,可以成品定制采购,其行走系统安装在轨道工字钢下翼缘上,沿着轨道来回运行移动。一般情况下,电动葫芦的吨位为0.5T/1T/2T/3T/5T/10T/16T/20T/32T,起升高度为6m/9m/12m/18m/24m/30m,起升速度为8m/min,运行速度为20m/min。对电动葫芦的控制一般采用无线遥控器。 Electric hoist 8: Its model is determined according to the needs of the project (such as lifting capacity, lifting height, etc.), and the finished product can be customized and purchased. Its walking system is installed on the lower flange of the track I-beam and moves back and forth along the track. In general, the tonnage of the electric hoist is 0.5T/1T/2T/3T/5T/10T/16T/20T/32T, the lifting height is 6m/9m/12m/18m/24m/30m, and the lifting speed is 8m/ min, the running speed is 20m/min. The control of the electric hoist generally uses a wireless remote control.
手动葫芦15:用于悬挂起重机空载时,水平横向牵引吊车桁架,更换吊装起重地点,其型号根据牵引力大小而定。 Manual hoist 15: used to suspend the crane when it is unloaded, to pull the crane truss horizontally and horizontally, and to change the hoisting location. Its model depends on the size of the traction force.
在需要使用此实用新型的高层建筑施工中,根据工程实际情况,对此实用新型进行设计,尤其是吊车桁架18的结构设计;或者对重复使用此实用新型的吊车桁架进行结构验算(可根据工程实际需要改变吊车桁架的跨度)通过后施工可实施。 In the construction of high-rise buildings that need to use this utility model, according to the actual situation of the project, design this utility model, especially the structural design of the crane truss 18; The actual need to change the span of the crane truss) can be implemented after passing the construction.
用塔式起重机将工厂分段制作好的吊车桁架转运至两塔楼间的施工作业面上,然后将其将拼装成格构式空间吊车桁架18。在吊车桁架下弦3安装连接件6,轨道工字钢5再与连接件6进行螺栓连接,方便安拆,重复使用。连接件的大小、间距以及轨道工字钢5型号的选择根据计算结果而定,也可参照《悬挂运输设备轨道设计计算》06CG08。吊车桁架18及轨道工字钢6的对接焊接须为一级全熔透焊缝,轨道工字钢6的下翼缘为电动葫芦行走装置10的运行轨迹,因此其焊接检测合格,须对焊缝磨平处理。 Use the tower crane to transfer the crane truss manufactured in sections by the factory to the construction work surface between the two towers, and then assemble it into a lattice space crane truss 18 . The connecting piece 6 is installed on the lower chord 3 of the crane truss, and the track I-beam 5 is bolted to the connecting piece 6, which is convenient for installation and disassembly, and can be reused. The size and spacing of the connectors and the selection of the I-beam 5 type of the track are determined according to the calculation results, and can also refer to "Design and Calculation of Tracks for Suspension Transportation Equipment" 06CG08. The butt welding of the crane truss 18 and the track I-beam 6 must be a first-class full-penetration weld. The lower flange of the track I-beam 6 is the running track of the electric hoist traveling device 10, so its welding inspection is qualified and must be butt welded. Seam smoothing.
此实用新型在安装时,须检查所有零部件是否安全到位,不可出现漏装,错装,例如电源线的错接,电动葫芦8的限位器、限重器的漏装。安装到位后,进行空载试运行。 When this utility model is installed, it is necessary to check whether all parts are in place safely, and there must be no missing or wrong installation, such as the wrong connection of the power cord, the missing installation of the limiter and weight limiter of the electric hoist 8. After the installation is in place, conduct a no-load test run.
试运行成功后,在高层建筑两塔楼上设置吊点,用两台卷扬机将此实用新型同步提升至安装位置,然后安装吊车桁架端头(4)。 After the trial operation is successful, set the lifting points on the two towers of the high-rise building, use two winches to lift the utility model to the installation position synchronously, and then install the crane truss end (4).
此实用新型重新接入电源,进行满载试运行,经相关部门验收合格后投入使用。起重工须经过培训,持证上岗,具体操作遵守现行的《建筑施工起重吊装工程安全技术规范》JGJ276-2012。 This utility model is re-connected to the power supply, carries out a full-load test run, and is put into use after passing the acceptance by relevant departments. Lifting workers must undergo training and work with certificates, and the specific operations must comply with the current "Safety Technical Code for Hoisting and Hoisting Engineering in Construction Construction" JGJ276-2012.
此实用新型的拆除顺序与安装顺序好相反,拆除过程中避免随意、野蛮切割,影响其重复使用。 The dismantling sequence of this utility model is opposite to the installation sequence, and random and brutal cutting should be avoided during the dismantling process, which will affect its repeated use.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420447851.6U CN204185146U (en) | 2014-08-10 | 2014-08-10 | Construction of Steel Structure overhang crane between skyscraper two tall buildings |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420447851.6U CN204185146U (en) | 2014-08-10 | 2014-08-10 | Construction of Steel Structure overhang crane between skyscraper two tall buildings |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204185146U true CN204185146U (en) | 2015-03-04 |
Family
ID=52617159
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420447851.6U Expired - Fee Related CN204185146U (en) | 2014-08-10 | 2014-08-10 | Construction of Steel Structure overhang crane between skyscraper two tall buildings |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204185146U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105540446A (en) * | 2016-01-15 | 2016-05-04 | 北京市建筑工程研究院有限责任公司 | Interior-climbing type lifting platform |
| CN108163723A (en) * | 2017-11-16 | 2018-06-15 | 上海二十冶建设有限公司 | A kind of bulilt-up area tower crane installing and dismounting device and its application method |
| CN113879963A (en) * | 2021-11-09 | 2022-01-04 | 中国二十二冶集团有限公司 | Indoor track beam push type installation construction device and method |
-
2014
- 2014-08-10 CN CN201420447851.6U patent/CN204185146U/en not_active Expired - Fee Related
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105540446A (en) * | 2016-01-15 | 2016-05-04 | 北京市建筑工程研究院有限责任公司 | Interior-climbing type lifting platform |
| CN108163723A (en) * | 2017-11-16 | 2018-06-15 | 上海二十冶建设有限公司 | A kind of bulilt-up area tower crane installing and dismounting device and its application method |
| CN108163723B (en) * | 2017-11-16 | 2019-07-23 | 上海二十冶建设有限公司 | A kind of bulilt-up area tower crane installing and dismounting device and its application method |
| CN113879963A (en) * | 2021-11-09 | 2022-01-04 | 中国二十二冶集团有限公司 | Indoor track beam push type installation construction device and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101514586B (en) | Hanger rail type electric hanging boat and construction method thereof | |
| CN105421249A (en) | Novel dragging- hoisting combined type hanging basket structure and construction method | |
| CN103291076A (en) | Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame | |
| CN102251483B (en) | Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane | |
| CN106592962A (en) | Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus | |
| CN208122371U (en) | On across the high-speed rail safe guarding shed fast dismounting device of operation line | |
| CN108049666B (en) | A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction | |
| CN204185146U (en) | Construction of Steel Structure overhang crane between skyscraper two tall buildings | |
| CN205205685U (en) | Span wire pier is function portal device at most | |
| CN204754249U (en) | A transporting device that is used for indoor big flue to install | |
| CN102587678B (en) | Device for slipping node of steel structure | |
| CN103967263B (en) | Hydraulic automatic jumping discharging platform | |
| CN202482772U (en) | Collapse-proof stop block mounting system for railway bridge | |
| CN105544406A (en) | Sliding-type Bailey beam dismantling device and dismantling method thereof | |
| CN204662929U (en) | A kind of cross-line walking fence operation device | |
| CN208071235U (en) | A kind of bearing and lifting system of steel truss frame integral hoisting | |
| CN203947758U (en) | Novel hydraulic automatic climbing discharging platform | |
| CN203159027U (en) | A prefabricated iron tower foundation spreader | |
| CN201952736U (en) | Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder | |
| CN209816682U (en) | Bridge steel box girder aerial working operation platform | |
| CN203782619U (en) | Construction trolley | |
| CN203794505U (en) | Internal climbing steel beam conveying device of internal climbing movable arm tower crane | |
| CN102733612B (en) | Mounting method of electric hoist orbit | |
| CN203334186U (en) | A wheel type device for cable-stayed bridge floor press anchoring | |
| CN206438420U (en) | The assembled equipment of fixed asymmetric bridge girder cantilever |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150304 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |