CN212866952U - Low-rise floor is protector for concrete placement - Google Patents
Low-rise floor is protector for concrete placement Download PDFInfo
- Publication number
- CN212866952U CN212866952U CN202021318636.8U CN202021318636U CN212866952U CN 212866952 U CN212866952 U CN 212866952U CN 202021318636 U CN202021318636 U CN 202021318636U CN 212866952 U CN212866952 U CN 212866952U
- Authority
- CN
- China
- Prior art keywords
- fixed
- operation platform
- fixed mounting
- mounting
- low
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a protective device for concrete pouring of low-rise floors, which relates to the technical field of building construction; mounting panel bottom edge fixed mounting has the several support column, the bottom center fixed mounting of mounting panel has the motor, the output and the rotation axis fixed connection of motor, operation platform mechanism fixed mounting is on the rotation axis, and it is through the flexible and horizontal direction's of operation platform mechanism in length direction rotation, and its effectual operating range that has enlarged operating personnel has reduced intensity of labour, has improved efficiency to concrete after pouring has played fine guard action.
Description
Technical Field
The utility model belongs to the technical field of the construction, concretely relates to low floor surface protector for concrete placement.
Background
The concrete pouring refers to a process of pouring concrete into a mold until the concrete is plasticized, the concrete on the upper surface of a poured floor slab needs to be protected, and other operations and personnel can be performed on the concrete surface after the strength of the concrete meets the design requirement.
However, after concrete is poured, defects such as honeycombs, holes, exposed ribs, gaps, slag inclusion and the like often occur in a curing period, a protective wood board is built above the poured concrete in the existing treatment measures, and an operator stands on the protective wood board to repair the defects of the poured concrete, so that the operation is complicated and the efficiency is low.
SUMMERY OF THE UTILITY MODEL
Aiming at solving the problems of the defects and the shortcomings of the prior art; an object of the utility model is to provide a simple structure, reasonable in design, convenient to use's low floor concrete placement uses protector, and it is flexible and the rotation of horizontal direction at length direction through operation platform mechanism, its effectual operating range that has enlarged operating personnel has reduced intensity of labour, has improved efficiency to concrete after pouring has played fine guard action.
In order to achieve the above object, the utility model adopts the following technical scheme: the device comprises a mounting plate, a support column, a motor, a rotating shaft and an operation platform mechanism; mounting panel bottom edge fixed mounting has the several support column, the bottom center fixed mounting of mounting panel has the motor, the output and the rotation axis fixed connection of motor, operation platform mechanism fixed mounting is on the rotation axis.
Preferably, the operation platform mechanism consists of a fixed operation platform, a lengthened operation platform, an upright post and a steel wire rope; the fixed operation platform passes through the mounting hole fixed mounting of right-hand member on the rotation axis, the left end inner chamber activity joint of fixed operation platform is fixed with extension operation platform, the equal fixed mounting in upper end of fixed operation platform and extension operation platform has the several stand, the upper end fixed mounting of stand has wire rope.
Preferably, the length of the steel wire rope can be adjusted movably in the middle section of the steel wire rope.
Preferably, the right side of the fixed operation platform is fixedly provided with a balancing weight, and the left end of the fixed operation platform is fixedly provided with a locking bolt.
Preferably, the upper end surfaces of the fixed operation platform and the lengthened operation platform are both provided with anti-skid layers.
Preferably, a plurality of reinforcing rods are fixedly installed at the bottom ends of the supporting columns.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses an operation platform mechanism is at length direction's flexible and horizontal direction's rotation, and its effectual operating range that has enlarged operating personnel has reduced intensity of labour, has improved efficiency to concrete after pouring has played fine guard action.
Drawings
For ease of illustration, the invention is described in detail by the following detailed description and accompanying drawings.
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural diagram of the middle working platform mechanism 5 of the present invention.
In the figure: mounting panel 1, support column 2, motor 3, rotation axis 4, operation platform mechanism 5
Fixed work platform 51, lengthened work platform 52, upright column 53 and steel wire rope 54
A balancing weight 511, a locking bolt 512 and an adjusting steel wire rope 541.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described below with reference to specific embodiments shown in the accompanying drawings. It should be understood that the description is intended to be illustrative only and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
It should also be noted that, in order to avoid obscuring the invention with unnecessary details, only the structures and/or process steps that are closely related to the solution according to the invention are shown in the drawings, while other details that are not relevant to the invention are omitted.
As shown in fig. 1 and 2, the following technical solutions are adopted in the present embodiment: the device comprises a mounting plate 1, a support column 2, a motor 3, a rotating shaft 4 and an operation platform mechanism 5; 1 bottom edge fixed mounting of mounting panel has several support column 2, the bottom center fixed mounting of mounting panel 1 has motor 3, motor 3's output and 4 fixed connection of rotation axis, 5 fixed mounting of operation platform mechanism are on rotation axis 4.
The working platform mechanism 5 consists of a fixed working platform 51, a lengthened working platform 52, a stand column 53 and a steel wire rope 54; fixed work platform 51 is on rotation axis 4 through the mounting hole fixed mounting of right-hand member, the left end inner chamber activity joint of fixed work platform 51 is fixed with extension work platform 52, the equal fixed mounting in upper end of fixed work platform 51 and extension work platform 52 has several stand 53, the upper end fixed mounting of stand 53 has wire rope 54, the mobile regulation of the length of adjusting wire rope 541 in wire rope 54 interlude, the right side fixed mounting of fixed work platform 51 have balancing weight 511, the left end fixed mounting of fixed work platform 51 has locking bolt 512, the up end of fixed work platform 51 and extension work platform 52 all be provided with the skid resistant course, the bottom fixed mounting of support column 2 have several stiffeners.
The working principle of the specific embodiment is as follows: when the poured concrete has defects and needs to be repaired, the position of the lengthened operation platform 52 on the fixed operation platform 51 is adjusted according to requirements, the lengthened operation platform 52 is tightly supported and fixed through the locking bolt 512, the length of the steel wire rope 541 is adjusted, an operator can stand on the operation platform mechanism 5 to repair the defects of the concrete, the motor 3 drives the operation platform mechanism 5 to rotate horizontally, the operation range of the operator is effectively expanded, and the poured concrete is well protected.
In addition, the occupied space can be effectively reduced by inserting the lengthened operation platform 52 into the inner cavity of the fixed operation platform 51 during storage at ordinary times.
The beneficial effects of the embodiment are as follows: the utility model discloses an operation platform mechanism is at length direction's flexible and horizontal direction's rotation, and its effectual operating range that has enlarged operating personnel has reduced intensity of labour, has improved efficiency to concrete after pouring has played fine guard action.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (6)
1. The utility model provides a low floor is protector for concrete placement which characterized in that: the device comprises a mounting plate (1), a support column (2), a motor (3), a rotating shaft (4) and an operation platform mechanism (5); mounting panel (1) bottom edge fixed mounting has several support column (2), the bottom center fixed mounting of mounting panel (1) has motor (3), the output and rotation axis (4) fixed connection of motor (3), operation platform mechanism (5) fixed mounting is on rotation axis (4).
2. The protective device for concrete pouring of low-rise floors as claimed in claim 1, wherein: the operation platform mechanism (5) consists of a fixed operation platform (51), a lengthened operation platform (52), an upright post (53) and a steel wire rope (54); fixed work platform (51) are through the mounting hole fixed mounting of right-hand member on rotation axis (4), the left end inner chamber activity joint of fixed work platform (51) is fixed with extension work platform (52), the equal fixed mounting in upper end of fixed work platform (51) and extension work platform (52) has several stand (53), the upper end fixed mounting of stand (53) has wire rope (54).
3. The protective device for concrete pouring of low-rise floors as claimed in claim 2, wherein: the length of the adjusting steel wire rope (541) in the middle section of the steel wire rope (54) can be movably adjusted.
4. The protective device for concrete pouring of low-rise floors as claimed in claim 2, wherein: the right side fixed mounting of fixed work platform (51) have balancing weight (511), the left end fixed mounting of fixed work platform (51) has locking bolt (512).
5. The protective device for concrete pouring of low-rise floors as claimed in claim 2, wherein: the upper end surfaces of the fixed operation platform (51) and the lengthened operation platform (52) are provided with anti-skid layers.
6. The protective device for concrete pouring of low-rise floors as claimed in claim 1, wherein: the bottom end of the supporting column (2) is fixedly provided with a plurality of reinforcing rods.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021318636.8U CN212866952U (en) | 2020-07-08 | 2020-07-08 | Low-rise floor is protector for concrete placement |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202021318636.8U CN212866952U (en) | 2020-07-08 | 2020-07-08 | Low-rise floor is protector for concrete placement |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212866952U true CN212866952U (en) | 2021-04-02 |
Family
ID=75213445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202021318636.8U Active CN212866952U (en) | 2020-07-08 | 2020-07-08 | Low-rise floor is protector for concrete placement |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212866952U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565303A (en) * | 2021-08-09 | 2021-10-29 | 山东滕建建设集团有限公司 | Adjustable that construction was used bears frame structure |
-
2020
- 2020-07-08 CN CN202021318636.8U patent/CN212866952U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565303A (en) * | 2021-08-09 | 2021-10-29 | 山东滕建建设集团有限公司 | Adjustable that construction was used bears frame structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202830776U (en) | Bridge variable cross-section rectangular high pier cantilever creeping formwork construction device | |
CN211286622U (en) | Hoop type lead screw creeping formwork system for cylindrical pier construction | |
CN105839543A (en) | Construction process for self-lifting outer frame turnover formwork of bridge high pier | |
CN212866952U (en) | Low-rise floor is protector for concrete placement | |
CN210659228U (en) | Movable single-side formwork system for subway construction | |
CN212957538U (en) | Roof flower frame beam and outer wall decoration construction movable operation platform | |
CN209568688U (en) | A kind of elevating construction platform | |
CN204850469U (en) | Commercial mansion system that builds | |
CN216662305U (en) | Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform | |
CN212866926U (en) | Movable supporting beam dismounting device | |
CN210369893U (en) | Light-duty creeping formwork system of lead screw promotion | |
CN205100543U (en) | Novel construction system of commercial mansion | |
CN106088564A (en) | Track climbing type monolithic architecture construction scaffolding | |
CN114427307A (en) | Anti-toppling structure and method in building demolition process | |
CN211257769U (en) | Truss bridging based on attached lifting platform | |
CN209874468U (en) | Construction hydraulic pressure template climbing device | |
CN208039787U (en) | High-altitude edge-facing operation assembly operation platform | |
CN221276336U (en) | Inner frame operation platform suitable for hollow pier steel bar and formwork installation | |
CN105003074A (en) | Commercial building construction system and construction method thereof | |
CN215167838U (en) | Movable overhung suspension type operating platform | |
CN212176822U (en) | Municipal construction is with rail guard convenient to transport | |
CN218842867U (en) | Movable bridge arch rib support frame | |
CN216112499U (en) | Portable console mode pipeline support | |
CN109944430A (en) | A kind of electric lifting platform construction method for special-shaped exterior walls of buildings operation | |
CN214658643U (en) | Mobile platform for multi-use architecture construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |