CN212609147U - Wind cable anchoring system of cable crane tower - Google Patents

Wind cable anchoring system of cable crane tower Download PDF

Info

Publication number
CN212609147U
CN212609147U CN202021853581.0U CN202021853581U CN212609147U CN 212609147 U CN212609147 U CN 212609147U CN 202021853581 U CN202021853581 U CN 202021853581U CN 212609147 U CN212609147 U CN 212609147U
Authority
CN
China
Prior art keywords
cable
tower
anchor
fixed
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202021853581.0U
Other languages
Chinese (zh)
Inventor
庞庆
武彦杰
单晓东
姜大威
罗永华
李磊
张美佳
牛晓鹏
姚东旭
刘恒宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd, CCCC Fourth Highway Engineering Co Ltd filed Critical Sixth Engineering Co Ltd Of Cccc Fourth Highway Engineering Co ltd
Priority to CN202021853581.0U priority Critical patent/CN212609147U/en
Application granted granted Critical
Publication of CN212609147U publication Critical patent/CN212609147U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a cable tower wind cable anchoring system, the sidespan side of both sides cable tower sets up an anchorage respectively, and every cable tower top is provided with the anchor roof beam, is connected with back wind cable between anchorage and anchor roof beam, and the midspan of two cable towers is connected with the ventilation cable between the side, and ventilation cable one end snap-on is on the anchor roof beam at a cable tower top, and the other end is fixed through the top of the tower anchor roof beam of cable coaster with another cable tower. The utility model discloses a cable is transferred to unilateral anchor, single-ended, and construction speed is fast, has shortened and has transferred the cable time, has practiced thrift construction cost by a wide margin, receives construction site environmental restriction little, and the anchor dependable performance, can satisfy the site operation requirement.

Description

Wind cable anchoring system of cable crane tower
Technical Field
The utility model belongs to the technical field of the bridge construction, concretely relates to adopt cable crane to carry out anchor structure of cable tower wind cable when long span construction for the straightness adjustment of hanging down of cable tower and keep the cable tower stable.
Background
The construction of the large-span steel structure bridge usually adopts a cable crane to hoist the steel truss. The cable of cable loop wheel machine operation supports on the cable tower of both sides, and cable tower height is higher, will bear great wind-load, can exert great horizontal pulling force to the cable tower when cable loop wheel machine operation simultaneously, for keeping the stability and the straightness that hangs down of cable tower, needs effectively to fix the cable tower with cable wind cable. Usually, wind cables are arranged on two sides of a cable tower, one end of each wind cable is anchored on the cable tower, and the other end of each wind cable is anchored on a ground anchor. The ground anchor generally adopts gravity type anchorage, because bulky, area is big, and cable tower both sides all set up the anchorage and not only can receive the construction site limitation sometimes, and construction cost is high moreover, and the accent cable is long for a time, influences the construction progress.
SUMMERY OF THE UTILITY MODEL
The utility model aims at the above-mentioned problem, a system and construction method that cable crane cable tower wind cable carries out the anchor is provided, can anchor the wind cable fast, adjust the cable tower straightness that hangs down to reduce construction cost as far as possible.
The utility model discloses a cable hanger cable tower wind cable anchoring system, the sidespan side of both sides cable tower sets up an anchorage respectively, and every cable tower top is provided with the anchor roof beam, is connected with back wind cable, its characterized in that between anchorage and anchor roof beam: and one end of the ventilation cable is directly fixed on the anchoring beam at the top of one cable tower, and the other end of the ventilation cable is fixed with the tower top anchoring beam of the other cable tower through a cable pulley.
The utility model discloses set up the anchorage in the side of striding of every cable tower, the side of striding of two cable towers adopts the ventilation cable taut, saves two anchorages than current anchor system, and the advantage is unilateral anchor, single-ended accent cable, and construction speed is fast, has shortened and has transferred the cable time, has practiced thrift construction cost by a wide margin, receives construction site environmental constraint little, and the anchor dependable performance, and the security is high, can satisfy the site operation requirement.
Drawings
Fig. 1 is an elevation view of the anchoring system of the present invention;
fig. 2 is a plan view of the anchoring system of the present invention;
FIG. 3 is a schematic view of the configuration of the vent cable connected to the overhead anchor beam by the cable block;
fig. 4 is a schematic structural view of the direct connection of the ventilation cable and the tower top anchoring beam.
Detailed Description
As shown in fig. 1 and 2, the utility model discloses a cable tower wind cable anchor system sets up an anchorage 2 respectively in the sidespan side of both sides cable tower 1, and every cable tower top is provided with anchor beam 3, and anchorage 2 is connected with back wind cable 4 with anchor beam 3 within a definite time, is connected with between the midspan side of two cable towers and leads to wind cable 5, lead to wind cable 5 one end snap-on the anchor beam at a cable tower top, the other end is fixed through the top of the tower anchor beam of cable coaster 6 with another cable tower.
The rear wind cable is made of steel stranded wires, and the ventilation cable is made of steel wire ropes.
As shown in fig. 3 and 4, the cable adjusting pulley 6 comprises a first fixed pulley 61 and a second fixed pulley 62 connected through a connecting plate, and a first movable pulley 63 and a second movable pulley 64 connected through a connecting plate, wherein the first fixed pulley 61 is connected with the anchoring beam 3 at the top of the cable tower through a fixed steel cable 65, and the second fixed pulley 62 is connected with the second movable pulley 64 through a cable adjusting steel cable 66; one end of the ventilation cable 5 directly fixed with the anchoring beam is fixed by a rope clamp 7 after passing around the tower top anchoring beam, and the other end of the ventilation cable 5 is fixed by the rope clamp 7 after passing around a first movable pulley 63 of the cable adjusting pulley.
The concrete construction method of the wind cable anchoring system of the cable crane tower comprises the following steps:
(1) anchors 2 are respectively arranged on the side span sides of cable towers 1 at two sides, an anchoring beam 3 is arranged at the top of each cable tower, a rear wind cable 4 is connected between the anchor 2 and the anchoring beam 3 at the top of the tower, one end of the rear wind cable 4 is permanently anchored with the anchor, and the other end of the rear wind cable is temporarily anchored with the anchoring beam at the top of the tower;
(2) connecting a cable adjusting pulley 6 on an anchoring beam at the top of a cable tower, wherein the cable adjusting pulley 6 comprises a first fixed pulley 61 and a second fixed pulley 62 which are connected through a connecting plate, and a first movable pulley 62 and a second movable pulley 64 which are connected through the connecting plate, the first fixed pulley is connected with the anchoring beam at the top of the cable tower through a fixed steel wire rope 65, and the second fixed pulley is connected with the second movable pulley through a cable adjusting steel wire rope 66;
(3) one end of the ventilation cable 5 is wound around the anchoring beam at the top of the other cable tower and is fixed by a rope clamp 7; the other end of the ventilation cable is pulled to the top of a cable tower provided with a cable adjusting pulley 6 by a traction cable, and the ventilation cable is fixed by a rope clamp 7 after passing through a first movable pulley 63 of the cable adjusting pulley;
(4) synchronously tensioning the rear wind cables 3 of the two cable towers by adopting a hydraulic jack at the tops of the two cable towers 1, and adjusting the distance between the second fixed pulley 62 and the second movable pulley 64 by tightening a cable adjusting steel wire rope 66 on the cable adjusting pulley 6 while tensioning the rear wind cables, thereby tensioning the ventilation cable 5; and adjusting the verticality of the wind cable and the ventilation cable to meet the design requirement, enabling the two sides of the cable tower to be stressed consistently, and keeping balance and verticality.

Claims (2)

1. The utility model provides a cable crane cable tower wind cable anchor system, the sidespan side of both sides cable tower sets up an anchorage respectively, and every cable tower top is provided with the anchor roof beam, is connected with back wind cable, its characterized in that between anchorage and anchor roof beam: and one end of the ventilation cable is directly fixed on the anchoring beam at the top of one cable tower, and the other end of the ventilation cable is fixed with the tower top anchoring beam of the other cable tower through a cable pulley.
2. The cable hoist tower cable anchoring system of claim 1, wherein: the cable adjusting pulley comprises a first fixed pulley and a second fixed pulley which are connected through a connecting plate, and a first movable pulley and a second movable pulley which are connected through a connecting plate, wherein the first fixed pulley is connected with an anchoring beam at the top of the cable tower through a fixed steel wire rope, and the second fixed pulley is connected with the second movable pulley through a cable adjusting steel wire rope; one end of the ventilation cable, which is directly fixed with the anchor beam, winds around the tower top anchor beam and then is fixed by a rope clamp, and the other end of the ventilation cable winds around the first movable pulley of the cable adjusting pulley and then is fixed by the rope clamp.
CN202021853581.0U 2020-08-30 2020-08-30 Wind cable anchoring system of cable crane tower Expired - Fee Related CN212609147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021853581.0U CN212609147U (en) 2020-08-30 2020-08-30 Wind cable anchoring system of cable crane tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021853581.0U CN212609147U (en) 2020-08-30 2020-08-30 Wind cable anchoring system of cable crane tower

Publications (1)

Publication Number Publication Date
CN212609147U true CN212609147U (en) 2021-02-26

Family

ID=74705703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021853581.0U Expired - Fee Related CN212609147U (en) 2020-08-30 2020-08-30 Wind cable anchoring system of cable crane tower

Country Status (1)

Country Link
CN (1) CN212609147U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111924720A (en) * 2020-08-30 2020-11-13 中交第四公路工程局有限公司 Wind cable anchoring system of cable crane tower and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111924720A (en) * 2020-08-30 2020-11-13 中交第四公路工程局有限公司 Wind cable anchoring system of cable crane tower and construction method

Similar Documents

Publication Publication Date Title
CN111924720A (en) Wind cable anchoring system of cable crane tower and construction method
CN102444086B (en) Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge
CN100543235C (en) The method and system of erecting steel trusses by stay cable auxiliary complete cantilever
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN101224856A (en) Long-span load-carrying cable lifting machine and mounting method therefor
CN104060540B (en) A kind of cable of space cable suspension bridge false stull and construction method for hanging thereof
CN201172597Y (en) Wide span heavy-load cable hoisting machine
CN106758767B (en) A kind of suspension bridge segmented cat road and its construction method
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN212670303U (en) Stay cable beam end mounting structure
CN220283391U (en) Cable hanging system
CN212609147U (en) Wind cable anchoring system of cable crane tower
CN110939069B (en) Construction method of suspension bridge catwalk
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN201330377Y (en) Suspension rope towing device
CN209779465U (en) main tower erects cable-stay bridge's string cable construction system that changes
CN114104989B (en) Cable buckle integrated tower wind cable system of large-span cable crane and construction method
CN209128888U (en) Anchor head traction device after a kind of suspension bridge dorsal funciculus
CN107673239B (en) Cable crane tower self-balancing system and installation method thereof
CN106968178B (en) Construction method for main beam of cable-stayed suspension bridge
CN212358014U (en) Single-span cable hoisting device for hoisting suspension bridge girder
CN211498489U (en) Mountain area highway bridge bent cap prestressed steel strand stretch-draw construction operation rack
CN219508376U (en) Device for erecting super-long and super-heavy stay cable
CN109113354B (en) Whole-course cableway type windproof real-time pulled cable wind system and construction method thereof
CN209619862U (en) A kind of hoist cable arch rib installation support frame big suitable for environmental restrictions

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210226