CN212336763U - Curtain wall installation guide rail device fixed on roof flower frame beam - Google Patents

Curtain wall installation guide rail device fixed on roof flower frame beam Download PDF

Info

Publication number
CN212336763U
CN212336763U CN202020862142.XU CN202020862142U CN212336763U CN 212336763 U CN212336763 U CN 212336763U CN 202020862142 U CN202020862142 U CN 202020862142U CN 212336763 U CN212336763 U CN 212336763U
Authority
CN
China
Prior art keywords
guide rail
steel
roof
horizontal cantilever
curtain wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020862142.XU
Other languages
Chinese (zh)
Inventor
王敬
夏天
张卫平
李博
沈国军
李利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau South China Co Ltd
Original Assignee
China Construction Eighth Bureau South China Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Bureau South China Co Ltd filed Critical China Construction Eighth Bureau South China Co Ltd
Priority to CN202020862142.XU priority Critical patent/CN212336763U/en
Application granted granted Critical
Publication of CN212336763U publication Critical patent/CN212336763U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Greenhouses (AREA)

Abstract

一种固定于屋面花架梁的幕墙安装导轨装置,包括至少一组导轨系统,每组导轨系统包括:导轨安装机构,包括两个置于屋面花架梁上方的水平悬臂支撑,以及至少一个导轨槽钢,导轨槽钢置于水平悬臂支撑的下方且相互固定,两个水平悬臂支撑通过钢方通固定连接;固定机构,每个水平悬臂支撑对应设有一个固定机构,固定机构包括钢立柱以及固定于屋面花架梁顶面的预埋钢板,钢立柱置于屋面花架梁的顶部,钢立柱的一端与预埋钢板固定连接,另一端与对应的水平悬臂支撑连接;水平行走装置,水平行走装置置于导轨槽钢内,且能沿导轨槽钢移动。本实用新型安装安全,提高了整体安装效率,安装方便,节约空间。

Figure 202020862142

A curtain wall installation guide rail device fixed on roof planter beams, comprising at least one set of guide rail systems, each set of guide rail systems comprising: a guide rail installation mechanism, including two horizontal cantilever supports placed above the roof planter beams, and at least one guide rail channel steel , the guide rail channel steel is placed under the horizontal cantilever support and fixed to each other, and the two horizontal cantilever supports are fixedly connected through steel squares; the fixing mechanism, each horizontal cantilever support is provided with a corresponding fixing mechanism, and the fixing mechanism includes a steel column and a fixed The pre-embedded steel plate on the top surface of the roof trellis beam, the steel column is placed on the top of the roof trellis beam, one end of the steel column is fixedly connected with the embedded steel plate, and the other end is connected with the corresponding horizontal cantilever support; Inside the channel steel of the guide rail, and can move along the channel steel of the guide rail. The utility model has the advantages of safe installation, improved overall installation efficiency, convenient installation and space saving.

Figure 202020862142

Description

Curtain wall installation guide rail device fixed on roof flower frame beam
Technical Field
The utility model relates to a building technical field, concretely relates to be fixed in curtain installation guide rail device of roofing flower frame roof beam.
Background
In some projects, roof covering upper portion often can design some flower frame roof beams and increase the whole effect of building, and conventional curtain installation adopts the roof covering to set up hoisting device, is difficult to satisfy roofing structure top curtain installation, often assists the installation with the tower crane to the life cycle of tower crane has been prolonged, and is difficult to guarantee the safety in the installation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a can the full coverage curtain plate installation facade scope, the curtain installation guide rail device who is fixed in roofing flower frame roof beam that has improved whole installation effectiveness.
The utility model discloses a following technical scheme realizes:
the utility model provides a curtain installation guide rail device who is fixed in roofing flower frame roof beam, includes at least a set of guide rail system, and every group guide rail system includes:
the guide rail mounting mechanism comprises two horizontal cantilever supports arranged above the roof flower shelf beam and at least one guide rail channel steel, the guide rail channel steel is arranged below the horizontal cantilever supports and fixed with each other, and the two horizontal cantilever supports are fixedly connected through a steel square tube;
each horizontal cantilever support is correspondingly provided with one fixing mechanism, each fixing mechanism comprises a steel stand column and an embedded steel plate fixed on the top surface of the roof flower shelf beam, the steel stand column is arranged at the top of the roof flower shelf beam, one end of each steel stand column is fixedly connected with the embedded steel plate, and the other end of each steel stand column is connected with the corresponding horizontal cantilever support;
and the horizontal traveling device is arranged in the guide rail channel steel and can move along the guide rail channel steel.
Further, fixed establishment still includes the steel bracing, steel bracing one end with horizontal cantilever supports and is connected, the other end with the steel stand is connected.
Further, fixed establishment still includes supplementary fixing device, supplementary fixing device is including arranging in the steel member of hanging of horizontal cantilever support bottom, the hangers board that is fixed in the roofing structural layer, hang the steel member with the hangers board passes through wire rope and connects.
Further, the bottom that the horizontal cantilever supported is equipped with the steel sheet, and every guide rail channel-section steel corresponds and is equipped with one the steel sheet, and the guide rail channel-section steel with the steel sheet is articulated.
Further, one side that horizontal cantilever support was provided with the steel bracing is equipped with the guide rail channel-section steel, the opposite side is equipped with hang the steel member.
Preferably, the number of the guide rail channel steels is two, the guide rail channel steel on the inner side is used for hoisting the curtain wall plate, and the guide rail channel steel on the outer side is used for assisting the installation of the curtain wall plate by the operating platform.
The utility model discloses have following advantage:
1. the auxiliary installation of the tower crane is not needed, so that the service cycle of the tower crane is prolonged, and the safety in the installation process is ensured.
2. The vertical face range of the curtain wall plate installation can be fully covered, and the overall installation efficiency is improved.
3. The installation is convenient, the space is saved, the coverage is wide, the construction is flexible and efficient, and the input cost is low.
4. The curtain wall is suitable for high-rise buildings with curtain walls on the outer vertical surfaces.
Description of the drawings:
FIG. 1 is a top view of the curtain wall mounting rail assembly of the present invention secured to a roof truss beam;
fig. 2 is a side view of the curtain wall mounting rail device fixed on the roof truss beam.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and specific embodiments.
Referring to fig. 1-2, a curtain installation guide rail device who is fixed in roofing flower frame roof beam includes at least two sets of guide rail system, and every group guide rail system includes:
the guide rail installation mechanism comprises two horizontal cantilever supports 11 arranged above a roof truss beam 10 and two guide rail channel steel 12, wherein the guide rail channel steel 12 is arranged below the horizontal cantilever supports 11 and is fixed with each other, the two horizontal cantilever supports 11 are fixedly connected through a steel square tube 13, and the adjacent horizontal cantilever supports 11 in each section are connected into a whole through the steel square tube 13, so that the overall stability and the stress effect are improved;
each horizontal cantilever support is correspondingly provided with a fixing mechanism, each fixing mechanism comprises a steel upright post 21 and an embedded steel plate 22 fixed on the top surface of the roof flower frame beam 10, the steel upright post 21 is arranged on the top of the roof flower frame beam 10, one end of each steel upright post 21 is fixedly connected with the embedded steel plate 22, and the other end of each steel upright post 21 is connected with the corresponding horizontal cantilever support 11; fixing mechanism still includes steel bracing 23, and 23 one end of steel bracing is connected with horizontal cantilever support 11, and the other end is connected with steel stand 21 increase steel bracing 23 on the steel stand 21, wherein, one side that horizontal cantilever support 11 was provided with steel bracing 23 is equipped with two guide rail channel-section steels 12, and inboard guide rail channel-section steel is used for hoist and mount curtain plate, and outside track channel-section steel sets up the supplementary curtain plate installation of operation platform and can improve curtain plate installation effectiveness like this.
Every section of vertical adoption single bracing of fixed establishment, steel stand 21 is as main supporting mechanism promptly, and can set up according to actual conditions is nimble, can practice thrift the space like this, promotes the bulk rigidity through setting up steel bracing 23, increases stability. In order to improve the rigidity of the mechanism, a steel plate 111 is arranged at the bottom of the horizontal cantilever support 11, the steel plate 111 is welded with the horizontal cantilever support 11, one steel plate 111 is correspondingly arranged on each guide rail channel steel 12, and the guide rail channel steel 12 is hinged to the steel plate 111.
In addition, the fixing mechanism further comprises an auxiliary fixing device, the auxiliary fixing device comprises a hanging steel member 24 and a hanging lug plate 25, the hanging steel member 24 is arranged at the bottom of the horizontal cantilever support 11 and is fixed on the roof structure layer 4, the hanging steel member 24 is connected with the hanging lug plate 25 through a steel wire rope 26, and the hanging steel member 24 is arranged on the other side of the horizontal cantilever support 11.
The horizontal traveling device 3 is arranged in the guide rail channel steel 12 and can move along the guide rail channel steel 12, and the horizontal traveling device can move in the whole vertical face in the guide rail channel steel 12 and can meet the requirements of material lifting and installation.
A construction method of a curtain wall installation guide rail device fixed on a roof truss beam comprises the following steps:
s1, embedding a steel plate on the top surface of the roof flower rack beam to serve as a support of the curtain wall mounting guide rail;
s2, sequentially mounting a support steel upright post, a cantilever horizontal support channel steel, a steel inclined strut and an auxiliary fixing device;
s3, installing a horizontal steel square tube, and connecting adjacent horizontal cantilever supports into a whole;
s4, sequentially welding two steel plates on the outer side of the horizontal cantilever support;
and S5, installing a guide rail channel steel and a horizontal walking device, wherein the guide rail channel steel is hinged with the upper steel plate.
The utility model discloses construction method is simple, only needs at the pre-buried steel sheet of roofing pergola roof beam top face, as the support of curtain installation guide rail, and erection bracing steel stand, cantilever horizontal support channel-section steel, steel bracing, horizontal steel square tube connect into stable whole with each section support in proper order, improve support rigidity and atress effect, horizontal cantilever supports inboard installation off-load wire rope, and the bottom is fixed in the roofing structural layer. Cantilever horizontal stay outside end welded fastening twice steel sheet, installation guide rail and horizontal running gear, inboard guide rail are used for hoist and mount curtain plate, and the outside guide rail is used for installing the installation of operation platform auxiliary curtain plate, improves curtain plate installation effectiveness.
The present invention has been described in detail with reference to the drawings and the embodiments, and those skilled in the art can make various changes to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the present invention, as modifications of the materials of construction, specifications of materials, specific dimensions, manner of connection, etc. should be considered within the scope of the claims. The scope of the invention is to be determined by the appended claims.

Claims (6)

1.一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,包括至少一组导轨系统,每组导轨系统包括:1. a kind of curtain wall installation guide rail device being fixed on roof planter beam, is characterized in that, comprises at least one group of guide rail systems, and each group of guide rail systems comprises: 导轨安装机构,包括两个置于所述屋面花架梁上方的水平悬臂支撑,以及至少一个导轨槽钢,所述导轨槽钢置于所述水平悬臂支撑的下方且相互固定,两个水平悬臂支撑通过钢方通固定连接;The guide rail installation mechanism includes two horizontal cantilever supports placed above the roof planter beams, and at least one guide channel steel, the guide channel steel is placed under the horizontal cantilever support and fixed to each other, and the two horizontal cantilever supports Fixed connection through steel square pass; 固定机构,每个所述水平悬臂支撑对应设有一个所述固定机构,所述固定机构包括钢立柱以及固定于屋面花架梁顶面的预埋钢板,所述钢立柱置于所述屋面花架梁的顶部,所述钢立柱的一端与所述预埋钢板固定连接,另一端与对应的水平悬臂支撑连接;Fixing mechanism, each of the horizontal cantilever supports is provided with a corresponding fixing mechanism, and the fixing mechanism includes a steel column and a pre-embedded steel plate fixed on the top surface of the roof trellis beam, and the steel column is placed on the roof trellis beam. One end of the steel column is fixedly connected to the embedded steel plate, and the other end is connected to the corresponding horizontal cantilever support; 水平行走装置,所述水平行走装置置于所述导轨槽钢内,且能沿导轨槽钢移动。The horizontal walking device is placed in the guide channel steel and can move along the guide channel steel. 2.根据权利要求1所述的一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,所述固定机构还包括钢斜撑,所述钢斜撑一端与所述水平悬臂支撑连接,另一端与所述钢立柱连接。2. a kind of curtain wall installation guide rail device being fixed on the roof planter beam according to claim 1, is characterized in that, described fixing mechanism also comprises steel diagonal bracing, and one end of described steel diagonal bracing is connected with described horizontal cantilever support, The other end is connected with the steel column. 3.根据权利要求2所述的一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,所述固定机构还包括辅助固定装置,所述辅助固定装置包括置于所述水平悬臂支撑底部的吊挂钢构件、固定于屋面结构层的挂耳板,所述吊挂钢构件与所述挂耳板通过钢丝绳连接。3. a kind of curtain wall installation guide rail device fixed on the roof planter beam according to claim 2, is characterized in that, described fixing mechanism also comprises auxiliary fixing device, and described auxiliary fixing device comprises being placed at the bottom of described horizontal cantilever support The hanging steel member and the hanging lug plate fixed on the roof structure layer, the hanging steel member and the hanging lug plate are connected by wire ropes. 4.根据权利要求3所述的一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,所述水平悬臂支撑的底部设有钢板,每个导轨槽钢对应设有一个所述钢板,且导轨槽钢与所述钢板铰接。4. a kind of curtain wall installation guide rail device fixed on the roof flower frame beam according to claim 3 is characterized in that, the bottom of described horizontal cantilever support is provided with steel plate, and each guide rail channel steel is correspondingly provided with a described steel plate, And the guide rail channel steel is hinged with the steel plate. 5.根据权利要求4所述的一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,所述水平悬臂支撑设置有钢斜撑的一侧设有所述导轨槽钢,另一侧设有所述吊挂钢构件。5. a kind of curtain wall installation guide rail device fixed on the roof planter beam according to claim 4, it is characterized in that, the side that described horizontal cantilever support is provided with steel diagonal brace is provided with described guide rail channel steel, the other side is provided with described guide rail channel steel The hanging steel member is provided. 6.根据权利要求1所述的一种固定于屋面花架梁的幕墙安装导轨装置,其特征在于,所述导轨槽钢设有两个,内侧导轨槽钢用于吊装幕墙板块,外侧导轨槽钢用于操作平台辅助幕墙板块安装。6. a kind of curtain wall installation guide rail device fixed on the roof planter beam according to claim 1, is characterized in that, described guide rail channel steel is provided with two, inner guide rail channel steel is used for hoisting curtain wall plate, outer guide rail channel steel It is used to operate the platform to assist the installation of curtain wall panels.
CN202020862142.XU 2020-05-21 2020-05-21 Curtain wall installation guide rail device fixed on roof flower frame beam Expired - Fee Related CN212336763U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020862142.XU CN212336763U (en) 2020-05-21 2020-05-21 Curtain wall installation guide rail device fixed on roof flower frame beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020862142.XU CN212336763U (en) 2020-05-21 2020-05-21 Curtain wall installation guide rail device fixed on roof flower frame beam

Publications (1)

Publication Number Publication Date
CN212336763U true CN212336763U (en) 2021-01-12

Family

ID=74083701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020862142.XU Expired - Fee Related CN212336763U (en) 2020-05-21 2020-05-21 Curtain wall installation guide rail device fixed on roof flower frame beam

Country Status (1)

Country Link
CN (1) CN212336763U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519914A (en) * 2020-05-21 2020-08-11 中建八局华南建设有限公司 Curtain wall installation guide rail device and construction method fixed on roof planter beams

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111519914A (en) * 2020-05-21 2020-08-11 中建八局华南建设有限公司 Curtain wall installation guide rail device and construction method fixed on roof planter beams

Similar Documents

Publication Publication Date Title
CN215803108U (en) Attached beam type hanging basket
CN106065661A (en) Large span unsettled steel corridor construction engineering method
CN105484502B (en) A kind of industrial premises steel structural roof purlin and support bar combined installation method
CN106759909B (en) A lower hanging and upper bearing structure system and its construction method
CN217028004U (en) Annular hanging basket suspension device for curtain wall construction of super high-rise building
CN207268073U (en) Novel flexible formwork bearing frame
CN211923476U (en) Electric hoist lifting system attached to lifting scaffold
CN109296192B (en) Lifting frame for assembled building
CN210084736U (en) A portable lifting hook for installation of people's air defense door
CN210316599U (en) A curtain wall annular track for roof frame beams
CN213014697U (en) Corner cantilever structure and building structure
CN211714403U (en) Mounting device for modular metal cornice elements
CN221810709U (en) A hanging basket exterior wall construction device
CN218623252U (en) Hanging basket installation fixing system at framework
CN220014395U (en) Can have enough to meet need mounting bracket by intelligent integrated platform system bailey frame of equipping
CN219031629U (en) Lifting equipment for indoor plate installation
CN218088703U (en) Steel bar truss building carrier plate installation device
CN117027352A (en) Large-span high altitude vestibule curtain wall construction operation platform
CN211949527U (en) A combined hanging basket for the construction of overhanging eaves of high-rise buildings
CN215484552U (en) Construction hanging basket structure of roof frame structure
CN205955156U (en) Elevartor shaft steel platform
CN214302804U (en) Double-layer hanging basket of riding horse type
CN209780229U (en) Jacking platform system of integrated tower crane
CN223032914U (en) Track hoisting device
CN111519914A (en) Curtain wall installation guide rail device and construction method fixed on roof planter beams

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210112