CN212200088U - Be used for prefabricated T roof beam diaphragm construction equipment - Google Patents

Be used for prefabricated T roof beam diaphragm construction equipment Download PDF

Info

Publication number
CN212200088U
CN212200088U CN202020512340.3U CN202020512340U CN212200088U CN 212200088 U CN212200088 U CN 212200088U CN 202020512340 U CN202020512340 U CN 202020512340U CN 212200088 U CN212200088 U CN 212200088U
Authority
CN
China
Prior art keywords
ladder
prefabricated
hanging
diaphragm plate
shaped beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020512340.3U
Other languages
Chinese (zh)
Inventor
李文杰
杨爽
胡俊
吕露
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN202020512340.3U priority Critical patent/CN212200088U/en
Application granted granted Critical
Publication of CN212200088U publication Critical patent/CN212200088U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a construction device for prefabricating a diaphragm plate of a T-shaped beam, which comprises two ladder frames, the ladder stand comprises a first ladder stand and a second ladder stand, a scaffold board is arranged between the first ladder stand and the second ladder stand, two ends of the scaffold board are hinged with one end of the first ladder stand and one end of the second ladder stand, two sides of the ladder stand are provided with guardrails, one end of the guardrail is hinged with the first ladder, the other end is clamped with the second ladder, a fixed rod is arranged between the scaffold board and the ladder stand, the other end of the ladder stand frame is provided with a hanging piece which is used for hanging on the external leakage steel bar of the T-shaped beam, the first ladder stand and the second ladder stand are hinged with the scaffold, wherein the guardrail also adopts articulated mode with the cat ladder frame, just can fold whole string basket, convenient transportation, simple structure, design benefit shifts the convenience, provides reliable support for the construction of prefabricated T roof beam diaphragm.

Description

Be used for prefabricated T roof beam diaphragm construction equipment
Technical Field
The utility model belongs to the technical field of prefabricated T roof beam diaphragm construction and specifically relates to a be used for prefabricated T roof beam diaphragm construction equipment.
Background
In the field of bridge construction, after the prefabricated T-beam is erected, a constructor lacks an operable platform in the diaphragm plate construction process, and after the prefabricated T-beam is erected, the gap is narrow, so that hanging basket operation cannot be adopted; if a ladder stand with hooks on one side is adopted, the danger is high. Therefore, a simple device is needed, which is light and convenient and can be operated by one person, and a platform for construction at the diaphragm plate is provided for operators under the condition of ensuring the safety of construction operation.
Chinese patent CN 208023417U "a self-control hanging basket" relates to a self-control hanging basket, includes: hanging flower basket and top cap, the bottom of hanging flower basket is equipped with the scaffold board, four avris of hanging flower basket all are equipped with the guardrail owner post, four guardrail owner posts loop through two guardrail bar connections, guardrail bar's top is equipped with the guardrail railing, four guardrail owner post's top is all articulated through the one end of pin with the connecting rod, the other end of four connecting rods respectively with four corner fixed connection of top cap bottom, the both sides of hanging flower basket all are equipped with three guardrail auxiliary column, the other both sides of hanging flower basket all are equipped with two guardrail auxiliary column, the bottom on hanging flower basket surface is equipped with the fender foot board, this kind of self-control formula hanging flower basket can not be folded, do not install well between comparatively constrictive prefabricated T roof beam structure, and can not fold.
Chinese patent CN 208844429U "a suspended hanging basket assembly for construction operation of a T-beam diaphragm plate template" relates to a suspended hanging basket assembly for construction operation of a T-beam diaphragm plate template, the T-beam diaphragm plate template construction operation platform assembly is composed of an installation fixing piece and a hanging basket body, wherein the hanging basket body is arranged on the installation fixing piece in a penetrating and sleeving manner, ladder stands are symmetrically arranged on any two opposite side surfaces of the hanging basket body upwards, and the top ends of the ladder stands are provided with circular hanging rings in a connected structure in an extending manner; guard rails and foot stopping plates are respectively arranged on the other two opposite side surfaces of the hanging basket body upwards; the inside of the hanging basket body is also provided with a tool placing box with an open top and a closed bottom and periphery. The structure is unstable in hoisting, easy to act and shake, incapable of being folded and occupied in transportation.
SUMMERY OF THE UTILITY MODEL
The utility model mainly aims at providing a construction device for prefabricating a diaphragm plate of a T-shaped beam, which solves the problems that after the prefabricating of the T-shaped beam is completed, the gap is narrow and the hanging basket operation cannot be adopted; if a ladder stand with hooks on one side is adopted, the danger is high.
In order to solve the technical problem, the utility model discloses the technical scheme who adopts is: a construction device for prefabricating a T-beam diaphragm plate comprises two ladder frames, wherein each ladder frame comprises a first ladder and a second ladder, a scaffold board is arranged between the first ladder and the second ladder, two ends of the scaffold board are hinged with one end of the first ladder and one end of the second ladder, guardrails are arranged on two sides of each ladder frame, one end of each guardrail is hinged with the first ladder, the other end of each guardrail is clamped with the second ladder, and a fixing rod is arranged between each scaffold board and each ladder frame;
the other end of the ladder stand is provided with a hanging piece, and the hanging piece is used for being hung on the outer leakage steel bar of the T-shaped beam.
In the preferred scheme, the hanging piece is a hook, and the hook is rotatably connected with the end part of the ladder stand.
In the preferred scheme, the pendant is the link, and the link includes horizontal pole and a plurality of rings, rings are established at the fixed ladder frame of climbing ladder frame tip, the horizontal pole passes rings and outer fixed ladder frame of leaking the reinforcing bar.
In the preferred scheme, be equipped with a plurality of first anti-skidding grooves on the horizontal pole, the rings inboard is equipped with third prevention spout, third prevention spout and first anti-skidding groove joint.
In the preferred scheme, a clamping piece is further arranged, an inner groove of the clamping piece is clamped with the cross rod, and the end part of the clamping piece is clamped on the outer leakage steel bar.
In the preferred scheme, a plurality of second anti-skidding grooves are formed in the cross rod, and the clamping piece inner grooves are formed in the second anti-skidding grooves of the cross rod.
In the preferred scheme, first cat ladder one side is equipped with the stationary dog, the guardrail tip is equipped with the fixed slot, the fixed slot card is on the stationary dog.
In the preferred scheme, a fixing bolt is arranged and penetrates through the fixing claw, and the guardrail is arranged between the fixing bolt and the fixing claw.
In the preferred scheme, the fixed claw is arranged on one side of the first ladder stand, and the guardrail is hinged to the other side of the first ladder stand.
In the preferred scheme, a plurality of fixing columns are arranged on the scaffold board, one end of the fixing rod is hinged to the ladder stand, and a clamping groove is formed in the other end of the fixing rod and clamped on the fixing columns.
The utility model provides a be used for prefabricated T roof beam diaphragm construction equipment lacks the movable platform that can operate in narrow and small space to the construction of T roof beam diaphragm, provides a device that is used for prefabricated T roof beam diaphragm to be under construction, and simple and easy, light, but one man operation solve the phenomenon that the construction of T roof beam diaphragm lacks the platform, simple structure, design benefit shifts conveniently, provides reliable support for the construction of prefabricated T roof beam diaphragm.
Drawings
The invention will be further explained with reference to the following figures and examples:
FIG. 1 is a general block diagram of the present invention;
FIG. 2 is a structural view of the installation position of the present invention;
FIG. 3 is a general structural view of a preferred embodiment of the present invention;
FIG. 4 is a structural view of the installation position of the preferred embodiment of the present invention;
fig. 5 is a left view structure diagram of the preferred embodiment of the present invention:
FIG. 6 is a disassembled structure view of the preferred embodiment of the present invention;
FIG. 7 is a view of the structure of the slot position of the present invention;
FIG. 8 is a drawing showing a structure of the slot clamp connection disassembly of the present invention;
FIG. 9 is a block diagram of the guard bar and the fixing rod of the present invention;
FIG. 10 is a general folding structure of the present invention;
in the figure: a T-beam 1; leaking steel bars 101; a hook 2; a ladder frame 3; a first ladder 301; a second ladder 302; a guardrail (4); a fixing groove 401; a fixing rod 5; a card slot 501; a scaffold board 6; a fixed column 601; a fixing bolt 7; a fixed jaw 8; a hanging ring 9; a cross bar 901; a lifting ring 902; a fastener 903; a first anti-slip groove 904; a second anti-slip slot 905; a third prevention slide groove 906.
Detailed Description
As shown in fig. 1-10, a be used for prefabricated T roof beam diaphragm plate construction equipment, including two ladder frames 3, ladder frame 3 includes first cat ladder 301 and second cat ladder 302, be equipped with scaffold board 6 between first cat ladder 301 and the second cat ladder 302, scaffold board 6 both ends are articulated with first cat ladder 301 and second cat ladder 302 one end, ladder frame 3 both sides are equipped with guardrail 4, 4 one ends of guardrail are articulated with first cat ladder 301, and the other end and second cat ladder 302 joint, be equipped with dead lever 5 between scaffold board 6 and the ladder frame 3, the ladder frame 3 other end is equipped with the pendant, the pendant is used for hanging on the outer reinforcing bar 101 that leaks of T roof beam 1. From this structure, as the structure shown in fig. 1~3 and fig. 10, wherein first cat ladder 301 and second cat ladder 302 and scaffold board 6 are articulated, wherein guardrail 4 also adopts articulated mode with cat ladder frame 3, just can fold whole string basket, convenient transportation, owing to can fold, also can carry out effectual installation and use this string basket in narrow and small position, for making construction equipment more stable, adopt first cat ladder 301 and the second cat ladder 302 of dead lever 5 and cat ladder frame 3 to assemble into triangular structure, make whole structure more stable.
In the preferred scheme, the hanging piece is a hook 2, and the hook 2 is rotatably connected with the end part of the ladder stand 3. With the structure, as shown in figures 1-2, the device is simple and convenient to install.
In a preferable scheme, the hanging part is a hanging ring 9, the hanging ring 9 comprises a cross rod 901 and a plurality of hanging rings 902, the hanging rings 902 are arranged at the end parts of the climbing ladder frame 3, and the cross rod 901 penetrates through the hanging rings 902 and the outer leakage steel bars 101 to fix the climbing ladder frame 3. From this structure, the structure that 3~9 show adopts comparatively stable structure link 9, and horizontal pole 901 is used for placing on outer hourglass reinforcing bar 101, adopts rings 902 to hang on horizontal pole 901 again, and this kind of structure is comparatively stable, and the installation is also comparatively convenient.
In a preferable scheme, a plurality of first anti-slip grooves 904 are formed in the cross bar 901, a third anti-slip groove 906 is formed in the inner side of the hanging ring 902, and the third anti-slip groove 906 is connected with the first anti-slip grooves 904 in a clamping mode. From this structure, first antiskid groove 904 cooperates with third prevention slide groove 906 on rings 902, makes whole structure in the work progress, can not make rings 902 effect slide on horizontal pole 901, plays the effect of fixed rings 902 position.
In the preferred scheme, a clamping piece 903 is further arranged, an inner groove of the clamping piece 903 is clamped with the cross bar 901, and the end part of the clamping piece 903 is clamped on the outer leakage steel bar 101. With the structure, as shown in fig. 5-8, the clamping piece 903 is used for clamping the cross bar 901 on the external leakage steel bar 101, so that the cross bar 901 is prevented from sliding left and right on the external leakage steel bar 101 in the construction process.
In a preferable scheme, a plurality of second anti-slip grooves 905 are formed in the cross bar 901, and the clamping piece 903 is arranged in the groove in the second anti-slip groove 905 of the cross bar 901. From this structure, second antiskid groove 905 is used for fixing fastener 903 on horizontal pole 901, and second antiskid groove 905 uses with fastener 903 cooperation, prevents horizontal pole 901 horizontal slip on leaking reinforcing bar 101 in the work progress.
In a preferable scheme, a fixing claw 8 is arranged on one side of the first ladder 301, a fixing groove 401 is arranged at the end of the guardrail 4, and the fixing groove 401 is clamped on the fixing claw 8. With this structure, the guard rail 4 is caught by the fixing jaw 8 to play a stabilizing role as shown in fig. 9.
In a preferable scheme, a fixing bolt 7 is arranged, the fixing bolt 7 penetrates through a fixing claw 8, and the guardrail 4 is arranged between the fixing bolt 7 and the fixing claw 8. With this structure, the guard rail 4 is fixed to the fixing claws 8 by the fixing bolts 7. The guard rail 4 is prevented from falling off the fixing jaw 8 by the fixing bolt 7.
In a preferable scheme, the fixing claw 8 is arranged on one side of the first ladder stand 301, and the guardrail 4 is hinged with the other side of the first ladder stand 301. With this arrangement, as shown in the figures 3-9, the first ladder 301 and the second ladder 302 are identical in structure, so that the ladder is convenient to manufacture, and during installation, the identical first ladder 301 and the identical second ladder 302 are oppositely installed, and the guardrails 4 on the first ladder 301 and the second ladder 302 are oppositely and reversely installed.
In a preferable scheme, a plurality of fixing columns 601 are arranged on the scaffold board 6, one end of the fixing rod 5 is hinged to the ladder stand 3, a clamping groove 501 is formed in the other end of the fixing rod 5, and the clamping groove 501 is clamped on the fixing columns 601. By this structure, for making construction equipment more stable, adopt dead lever 5 and the first cat ladder 301 and the second cat ladder 302 of cat ladder frame 3 in assemble into the triangle-shaped structure, make whole structure more stable, and dead lever 5 tip is installed fixedly through draw-in groove 501 and fixed column 601, simple structure, simple to operate.
The above-mentioned embodiments are merely preferred embodiments of the present invention, and should not be considered as limitations of the present invention, and the protection scope of the present invention should be defined by the technical solutions described in the claims, and includes equivalent alternatives of technical features in the technical solutions described in the claims. Namely, equivalent alterations and modifications within the scope of the invention are also within the scope of the invention.

Claims (10)

1. The utility model provides a be used for prefabricated T roof beam diaphragm construction equipment, characterized by: the ladder comprises two ladder frames (3), wherein each ladder frame (3) comprises a first ladder (301) and a second ladder (302), a scaffold board (6) is arranged between the first ladder (301) and the second ladder (302), two ends of each scaffold board (6) are hinged to one end of each first ladder (301) and one end of each second ladder (302), guardrails (4) are arranged on two sides of each ladder frame (3), one end of each guardrail (4) is hinged to the corresponding first ladder (301), the other end of each guardrail (4) is clamped to the corresponding second ladder (302), and a fixing rod (5) is arranged between each scaffold board (6) and each ladder frame (3);
the other end of the ladder climbing frame (3) is provided with a hanging piece, and the hanging piece is used for being hung on an outer leakage reinforcing steel bar (101) of the T-shaped beam (1).
2. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 1, wherein: the hanging piece is a hook (2), and the hook (2) is rotatably connected with the end part of the ladder stand (3).
3. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 1, wherein: the hanging piece is a hanging ring (9), the hanging ring (9) comprises a cross rod (901) and a plurality of hanging rings (902), the hanging rings (902) are arranged at the end part of the ladder climbing frame (3), and the cross rod (901) penetrates through the hanging rings (902) and the outer leakage reinforcing steel bars (101) to fix the ladder climbing frame (3).
4. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 3, wherein: the anti-skidding lifting ring is characterized in that a plurality of first anti-skidding grooves (904) are formed in the cross bar (901), a third anti-skidding groove (906) is formed in the inner side of the lifting ring (902), and the third anti-skidding groove (906) is connected with the first anti-skidding grooves (904) in a clamped mode.
5. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 3, wherein: the steel bar leakage-proof device is further provided with a clamping piece (903), an inner groove of the clamping piece (903) is clamped with the cross bar (901), and the end part of the clamping piece is clamped on the steel bar leakage-proof steel bar (101).
6. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 5, wherein: a plurality of second anti-skidding grooves (905) are formed in the cross rod (901), and the clamping piece (903) is arranged in the second anti-skidding grooves (905) of the cross rod (901) in an inner groove mode.
7. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 1, wherein: first cat ladder (301) one side is equipped with stationary dog (8), guardrail (4) tip is equipped with fixed slot (401), fixed slot (401) card is on stationary dog (8).
8. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 7, wherein: be equipped with fixing bolt (7), fixing bolt (7) pass stationary dog (8), and establish between fixing bolt (7) and stationary dog (8) guardrail (4).
9. The apparatus as claimed in claim 8, wherein the apparatus for constructing the diaphragm plate of the prefabricated T-beam comprises: the fixed claw (8) is arranged on one side of the first ladder stand (301), and the guardrail (4) is hinged to the other side of the first ladder stand (301).
10. The device for constructing the diaphragm plate of the prefabricated T-shaped beam as claimed in claim 1, wherein: the scaffold board (6) is provided with a plurality of fixing columns (601), one end of the fixing rod (5) is hinged to the stair climbing frame (3), the other end of the fixing rod (5) is provided with a clamping groove (501), and the clamping groove (501) is clamped on the fixing columns (601).
CN202020512340.3U 2020-04-09 2020-04-09 Be used for prefabricated T roof beam diaphragm construction equipment Active CN212200088U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020512340.3U CN212200088U (en) 2020-04-09 2020-04-09 Be used for prefabricated T roof beam diaphragm construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020512340.3U CN212200088U (en) 2020-04-09 2020-04-09 Be used for prefabricated T roof beam diaphragm construction equipment

Publications (1)

Publication Number Publication Date
CN212200088U true CN212200088U (en) 2020-12-22

Family

ID=73828945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020512340.3U Active CN212200088U (en) 2020-04-09 2020-04-09 Be used for prefabricated T roof beam diaphragm construction equipment

Country Status (1)

Country Link
CN (1) CN212200088U (en)

Similar Documents

Publication Publication Date Title
US8245816B2 (en) Integral safety system which can be used for construction
CN208056596U (en) A kind of Novel engineering exterior wall scaffold
CN205188839U (en) Movably -assembled anti -collision bridge wall construction hanging basket
CN212200088U (en) Be used for prefabricated T roof beam diaphragm construction equipment
CN110863641A (en) Ultrahigh floor type boarding scaffold in hyperbolic cooling tower and erection method thereof
CN218815057U (en) Construction scaffold for building
CN206801072U (en) A kind of foundation ditch temporary guard rail
CN110847051B (en) Hogging moment construction hanging basket in limited space of middle beam of T-shaped beam and using method
CN214785753U (en) Scaffold convenient to dismantle installation
CN109537868B (en) Portable operation platform for hoisting assembled main beams
CN211447727U (en) Hogging moment construction hanging basket in T roof beam center sill finite space
CN204038917U (en) Dismountable external hanging service platform
CN111997383A (en) Construction is with platform of unloading
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN215368654U (en) Building outrigger safety protective guard
CN218406331U (en) Anti-tilting scaffold
CN216587881U (en) Interim steel stair of turnover use
CN111945583A (en) Edge protection construction method and device for hanging basket end of cantilever grouting beam
IE20090645A1 (en) A method and apparatus for erecting a mobile scaffold tower
CN218261678U (en) Tower top limited space large cantilever hoisting falsework
CN211472213U (en) Deck type railway steel truss bridge construction hanging basket
CN212406014U (en) Multifunctional scaffold for road and bridge construction
CN209990148U (en) Construction is with platform of unloading
CN212980496U (en) Inclined plane operation scaffold tool platform
CN219118704U (en) Foldable step scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant