CN209990148U - Construction is with platform of unloading - Google Patents
Construction is with platform of unloading Download PDFInfo
- Publication number
- CN209990148U CN209990148U CN201920487620.0U CN201920487620U CN209990148U CN 209990148 U CN209990148 U CN 209990148U CN 201920487620 U CN201920487620 U CN 201920487620U CN 209990148 U CN209990148 U CN 209990148U
- Authority
- CN
- China
- Prior art keywords
- building
- fixed
- bottom plate
- cross beam
- discharging platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title description 7
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 44
- 239000010959 steel Substances 0.000 claims abstract description 44
- 238000007599 discharging Methods 0.000 claims abstract description 23
- 238000009435 building construction Methods 0.000 claims abstract description 11
- 238000009826 distribution Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 description 6
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses an unloading platform for building construction, which comprises a U-shaped girder, a first building crossbeam, a second building crossbeam and a third building crossbeam, wherein the position of the first building crossbeam is positioned between the second building crossbeam and the third building crossbeam, both ends of the U-shaped girder are fixed at the top end of the first building crossbeam through two first steel bar embedded parts, the middle parts of both ends of the U-shaped girder are respectively and alternately connected with two vertical beams, and the outer side of the second building crossbeam and the outer side of the third building crossbeam are respectively and fixedly connected with the top ends and the bottom ends of the vertical beams through the second steel bar embedded parts, the stability and the safety of the U-shaped main beam can be further improved through the steel ropes and the steel diagonal braces which are connected with the vertical beams, and the vertical beam, the steel rope and the steel diagonal brace are convenient to mount and dismount, so that the mounting and dismounting of the discharging platform are not influenced while the stability and the safety of the discharging platform are improved.
Description
Technical Field
The utility model relates to a platform of unloading, in particular to platform of unloading for construction.
Background
The unloading platform is a temporary operation platform and an operation frame which are usually erected on a construction site and are generally used for material turnover. The discharging platform is divided into a movable discharging platform, a floor type discharging platform and an overhanging type discharging platform.
At present, the formula of encorbelmenting platform of unloading needs the manual work to carry the material, needs constructor to stand on the platform of unloading, and the current formula of encorbelmenting platform of unloading has following shortcoming: 1. the existing overhanging type unloading platform is generally fixed on a cross beam through a steel bar embedded part, is poor in stability, has poor safety if the steel bar embedded part is loosened after being used for a long time, and has high safety when being not convenient to install and disassemble, and the unloading platform is difficult to install and disassemble if the safety is greatly improved; 2. the existing overhanging type discharging platform is not convenient for adjusting the length of the platform, so that a longer material cannot use the discharging platform, and the construction efficiency is influenced.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a construction is with platform of unloading to current overhanging type that proposes in solving above-mentioned background art possesses the problem of high security and be not convenient for adjust platform length when unable installation and the dismantlement of being convenient for of platform of unloading.
In order to achieve the above object, the utility model provides a following technical scheme: an unloading platform for building construction comprises a U-shaped main beam, a first building cross beam, a second building cross beam and a third building cross beam, the first building beam is positioned between the second building beam and the third building beam, two ends of the U-shaped main beam are fixed at the top end of the first building beam through two first steel bar embedded parts, the middle parts of two ends of the U-shaped main beam are respectively inserted and connected with two vertical beams, the outer side of the second building cross beam and the outer side of the third building cross beam are respectively fixedly connected with the top ends and the bottom ends of the vertical beams through second steel bar embedded parts, a first bottom plate is fixedly arranged in the middle of the inner wall of the U-shaped main beam, two sliding grooves are respectively arranged on two sides of the inner wall of the U-shaped main beam and are respectively connected with two sides of a second bottom plate in a sliding manner, the bottom of the side of the first bottom plate is fixedly connected with the bottom of the side of the second bottom plate through a plurality of electric cylinders.
As a preferred technical scheme of the utility model, every the middle part of erecting the roof beam both sides all articulates there are two pairs of fixed plates, every is every the fixed plate all presss from both sides the top and the bottom of establishing at U type girder, every is every the fixed plate all runs through U type girder and U type girder fixed connection through first locking bolt.
As a preferred technical scheme of the utility model, the both sides of U type girder bottom and the fixed four pairs of U type hinges that are equipped with of bottom symmetry on one side of two perpendicular roof beams, it is four right U type hinge all through second locking bolt respectively with the both ends fixed connection of four steel sprags.
As a preferred technical scheme of the utility model, the fixed four first links that are equipped with in both sides of U type girder outer wall, two the top of erecting roof beam one side is fixed and is equipped with two second links, every the second link all through the steel cable with be in with two first link fixed connection of one side.
As a preferred technical scheme of the utility model, the fixed picture peg that is equipped with in top of first bottom plate avris, the top of second bottom plate avris is seted up with picture peg matched with fluting, a plurality of screw rod hole has evenly been seted up at the middle part of picture peg, the middle part on second bottom plate top passes one of them screw rod hole and picture peg fixed connection through locking screw.
As a preferred technical scheme of the utility model, the top of first bottom plate and the top of second bottom plate are the fixed C type guard plate that is equipped with two symmetric distributions respectively, two the both ends of C type guard plate are all through a plurality of telescopic link fixed connection, the telescopic link includes outer tube, inner tube and telescopic link fixer, a pot head of outer tube is established in the outside of inner tube one end, the one end at the outer tube is established to the fixed cover of telescopic link fixer, the other end of outer tube and the other end of inner tube respectively with the both ends fixed connection of two C type guard plates.
As a preferred technical scheme of the utility model, one of them the fixed control button, a plurality of that is equipped with in the outside of C type guard plate electronic jar all is through control button and external power supply electric connection.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model relates to a construction is with platform of unloading has following beneficial effect:
1) when the unloading platform is built on a certain floor, the stability and the safety of the U-shaped girder can be improved by fixing the vertical beam through the second steel bar embedded parts, meanwhile, the stability and the safety of the U-shaped girder can be further improved through the steel ropes and the steel diagonal braces which are connected with the vertical beam, and the vertical beam, the steel ropes and the steel diagonal braces are convenient to mount and dismount, so that the mounting and the dismounting of the unloading platform are not influenced while the stability and the safety of the unloading platform are improved;
2) the second bottom plate can be pushed to slide in the U-shaped main beam through the electric cylinders, then the splicing length of the first bottom plate and the second bottom plate is adjusted, the length of the discharging platform is convenient to adjust, and the discharging platform is suitable for materials with different lengths in a certain range.
Drawings
FIG. 1 is a schematic front view of the present invention;
fig. 2 is a schematic sectional structure of the present invention;
FIG. 3 is an enlarged schematic view of part A of FIG. 2 according to the present invention;
FIG. 4 is an enlarged schematic view of a portion B of FIG. 2 according to the present invention;
fig. 5 is a schematic view of the top view structure of the U-shaped main beam of the present invention.
In the figure: 1. a U-shaped main beam; 2. a first building beam; 3. a second building beam; 4. a third building beam; 5. a first steel bar embedded part; 6. erecting a beam; 7. a fixing plate; 8. a first locking bolt; 9. a second steel bar embedded part; 10. a U-shaped hinge; 11. a second locking bolt; 12. a steel diagonal brace; 13. a first suspension loop; 14. a second suspension loop; 15. a steel cord; 16. a chute; 17. a first base plate; 18. a second base plate; 19. a C-shaped protection plate; 20. an electric cylinder; 21. inserting plates; 22. grooving; 23. locking the screw rod; 24. a screw hole; 25. a control button; 26. a telescopic rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the utility model provides a discharging platform for building construction, comprising a U-shaped main beam 1, a first building beam 2, a second building beam 3 and a third building beam 4, wherein the position of the first building beam 2 is between the second building beam 3 and the third building beam 4, both ends of the U-shaped main beam 1 are fixed on the top end of the first building beam 2 through two first steel embedded parts 5, the middle parts of both ends of the U-shaped main beam 1 are respectively connected with two vertical beams 6 in an inserting way, both the outer side of the second building beam 3 and the outer side of the third building beam 4 are respectively connected with the top end and the bottom end of the vertical beam 6 through a second steel embedded part 9, a first bottom plate 17 is fixed on the middle part of the inner wall of the U-shaped main beam 1, two sliding grooves 16 are respectively arranged on both sides of the inner wall of the U-shaped main beam 1, the two sliding grooves 16 are respectively connected with both sides of the second bottom plate, the bottom of the first bottom plate 17 is fixedly connected with the bottom of the second bottom plate 18 through a plurality of electric cylinders 20.
Preferably, every middle part of erecting 6 both sides of roof beam all articulates there are two pairs of fixed plates 7, every top and bottom at U type girder 1 are all pressed from both sides to fixed plate 7, every pair of fixed plate 7 all runs through U type girder 1 and U type girder 1 fixed connection through first locking bolt 8, run through U type girder 1 through first locking bolt 8 and will every 7 fixed connection of fixed plate get up, can play the purpose of location to erecting 6 roof beams, improve the stability of erecting 6 roof beams, the dismantlement of being convenient for simultaneously erecting 6 roof beams.
Preferably, the both sides of 1 bottom of U type girder and the bottom symmetry of two vertical beams 6 one sides are fixed and are equipped with four pairs of U type hinge 10, and four pairs of U type hinge 10 all through second locking bolt 11 respectively with four steel bracing 12's both ends fixed connection, can further improve the stability and the security of U type girder 1 through steel bracing 12, and steel bracing 12 is convenient for install and dismantle simultaneously, does not influence the convenience of U type girder 1.
Preferably, two sides of the outer wall of the U-shaped main beam 1 are fixedly provided with four first hanging rings 13, the top of one side of each of the two vertical beams 6 is fixedly provided with two second hanging rings 14, each second hanging ring 14 is fixedly connected with the two first hanging rings 13 on the same side through a steel rope 15, and the stability and the safety of the U-shaped main beam 1 can be further improved through the steel rope 15.
Preferably, an inserting plate 21 is fixedly arranged at the top of the side of the first bottom plate 17, a slot 22 matched with the inserting plate 21 is formed in the top of the side of the second bottom plate 18, a plurality of screw holes 24 are uniformly formed in the middle of the inserting plate 21, the middle of the top end of the second bottom plate 18 penetrates through one of the screw holes 24 through a locking screw 23 and is fixedly connected with the inserting plate 21, the inserting plate 21 can be positioned through the locking screw 23, the stability of connection between the first bottom plate 17 and the second bottom plate 18 is improved, and meanwhile the electric cylinder 20 can be prevented from being damaged by materials.
Preferably, the top of first bottom plate 17 and the top of second bottom plate 18 are fixed respectively and are equipped with the C type guard plate 19 of two symmetric distributions, a plurality of telescopic link 26 fixed connection is all passed through at the both ends of two C type guard plates 19, telescopic link 26 includes the outer tube, inner tube and telescopic link fixer, a pot head of outer tube is established in the outside of inner tube one end, the fixed cover of telescopic link fixer is established in the one end of outer tube, the other end of outer tube and the other end of inner tube respectively with the both ends fixed connection of two C type guard plates 19, can avoid clearance between two C type guard plates 19 to endanger staff's safety through telescopic link 26.
Preferably, the control button 25 is fixedly arranged on the outer side of one of the C-shaped protection plates 19, the electric cylinders 20 are electrically connected with an external power supply through the control button 25, the length of the discharging platform is convenient to adjust through the control button 25, and the operation is simple and convenient.
When the discharging platform is used specifically, the utility model relates to a discharging platform for building construction, firstly, the vertical beams 6 are inserted and connected with the U-shaped main beams 1, then each pair of fixed plates 7 are fixedly connected to position the vertical beams 6 by penetrating the U-shaped main beams 1 through the first locking bolts 8, the stability of the connection between the vertical beams 6 and the U-shaped main beams 1 is improved, then the steel inclined strut 12 is fixedly arranged between each pair of U-shaped hinges 10 through the second locking bolts 11, then the steel rope 15 is fixedly connected with the first hanging ring 13 and the second hanging ring 14 which are arranged at the same side, then the two ends of the U-shaped main beams 1 are fixedly arranged on the first building cross beam 2 at a proper floor through the first steel bar embedded part 5, then the top end and the bottom end of the vertical beams 6 are respectively fixedly connected with the outer sides of the upper layer and the lower layer at an installation floor through the second steel bar embedded part 9, the stability and the safety of the U-shaped main beams 1 can be improved by fixing the vertical beams 6 through, meanwhile, the stability and the safety of the U-shaped main beam 1 can be further improved through the steel ropes 15 and the steel diagonal braces 12 connected with the vertical beam 6, the vertical beam 6, the steel rope 15 and the steel diagonal brace 12 are convenient to mount and dismount, so that the mounting and dismounting of the discharging platform are not influenced while the stability and the safety of the discharging platform are improved, when a single first steel bar embedded part 5 or a single second steel bar embedded part 9 is used for a long time and is loosened, the rest first steel bar embedded parts 5 and the rest second steel bar embedded parts 9 can still play a role in fixing, the stability and the safety of the unloading platform are not influenced, when the length of the unloading platform needs to be adjusted, control a plurality of electronic jar 20 through control button 25 and promote second bottom plate 18 and slide in the inside of U type girder 1, adjust the concatenation length of first bottom plate 17 and second bottom plate 18 then, be convenient for adjust the length of platform of unloading, make the platform of unloading be applicable to the material of different length in certain extent.
In the description of the present invention, it should be understood that the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the indicated device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus should not be construed as limiting the present invention.
In the present invention, unless otherwise explicitly specified or limited, for example, it may be fixedly connected, detachably connected, or integrated; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (7)
1. The discharging platform for building construction comprises a U-shaped main beam (1), a first building cross beam (2), a second building cross beam (3) and a third building cross beam (4), and is characterized in that the position of the first building cross beam (2) is located between the second building cross beam (3) and the third building cross beam (4), two ends of the U-shaped main beam (1) are fixed at the top end of the first building cross beam (2) through two first steel bar embedded parts (5), the middle parts of the two ends of the U-shaped main beam (1) are respectively and alternately connected with two vertical beams (6), the outer side of the second building cross beam (3) and the outer side of the third building cross beam (4) are respectively and fixedly connected with the top end and the bottom end of the vertical beams (6) through second steel bar embedded parts (9), a first bottom plate (17) is fixedly arranged in the middle part of the inner wall of the U-shaped main beam (1), two sliding grooves (16) are respectively arranged on two sides of the inner wall of the U-shaped main beam (1, two spout (16) respectively with the both sides sliding connection of second bottom plate (18), the bottom of first bottom plate (17) avris is through the bottom fixed connection of a plurality of electronic jar (20) and second bottom plate (18) avris.
2. The discharging platform for building construction according to claim 1, wherein: every the middle part of erecting roof beam (6) both sides all articulates there are two pairs of fixed plates (7), every is every fixed plate (7) all press from both sides and establish the top and the bottom at U type girder (1), every is every fixed plate (7) all run through U type girder (1) and U type girder (1) fixed connection through first locking bolt (8).
3. The discharging platform for building construction according to claim 1, wherein: the two sides of the bottom of the U-shaped main beam (1) and the bottoms of the two vertical beams (6) are symmetrically and fixedly provided with four pairs of U-shaped hinges (10), and the four pairs of U-shaped hinges (10) are fixedly connected with the two ends of the four steel inclined struts (12) respectively through second locking bolts (11).
4. The discharging platform for building construction according to claim 1, wherein: the fixed four first link (13) that are equipped with in both sides of U type girder (1) outer wall, two the top of erecting roof beam (6) one side is fixed and is equipped with two second link (14), every second link (14) all through steel cable (15) with be in two first link (13) fixed connection with one side.
5. The discharging platform for building construction according to claim 1, wherein: the fixed picture peg (21) that is equipped with in top of first bottom plate (17) avris, fluting (22) with picture peg (21) matched with have been seted up at the top of second bottom plate (18) avris, a plurality of screw rod hole (24) have evenly been seted up at the middle part of picture peg (21), the middle part on second bottom plate (18) top passes one of them screw rod hole (24) and picture peg (21) fixed connection through locking screw (23).
6. The discharging platform for building construction according to claim 1, wherein: the top of first bottom plate (17) and the top of second bottom plate (18) are fixed C type guard plate (19) that are equipped with two symmetric distributions respectively, two the both ends of C type guard plate (19) are all through a plurality of telescopic link (26) fixed connection, telescopic link (26) include outer tube, inner tube and telescopic link fixer, a pot head of outer tube is established in the outside of inner tube one end, the fixed cover of telescopic link fixer is established in the one end of outer tube, the other end of outer tube and the other end of inner tube respectively with the both ends fixed connection of two C type guard plates (19).
7. The discharging platform for building construction according to claim 6, wherein: the outer side of one of the C-shaped protection plates (19) is fixedly provided with a control button (25), and the electric cylinders (20) are electrically connected with an external power supply through the control button (25).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920487620.0U CN209990148U (en) | 2019-04-11 | 2019-04-11 | Construction is with platform of unloading |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920487620.0U CN209990148U (en) | 2019-04-11 | 2019-04-11 | Construction is with platform of unloading |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209990148U true CN209990148U (en) | 2020-01-24 |
Family
ID=69291250
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920487620.0U Expired - Fee Related CN209990148U (en) | 2019-04-11 | 2019-04-11 | Construction is with platform of unloading |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209990148U (en) |
-
2019
- 2019-04-11 CN CN201920487620.0U patent/CN209990148U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN214831957U (en) | Assembled multi-high-rise steel column butt joint operation platform | |
CN209990148U (en) | Construction is with platform of unloading | |
CN111997383A (en) | Construction is with platform of unloading | |
CN212246007U (en) | Be used for tower crane bracket welded portable platform | |
CN213626818U (en) | Frame type safety ladder cage | |
CN211470603U (en) | Telescopic tower crane passageway | |
CN211689948U (en) | Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge | |
CN218563117U (en) | Steel construction engineering girder steel safety device | |
CN204024104U (en) | Fast-assembling modularization winding staircase | |
CN110259097A (en) | A kind of attachment type raise scaffold protective device | |
CN216190208U (en) | People goods ladder protection platform | |
CN211421793U (en) | Design steel operation platform | |
CN110171766B (en) | Steel bar transportation lifting appliance | |
CN205894662U (en) | Modular triangle steel truss template | |
CN215857308U (en) | Bridge stay cable stretching brace device | |
CN206829587U (en) | A kind of hydraulic climbing formwork wall-attached frame | |
CN221442199U (en) | Adjustable safety channel | |
CN216007855U (en) | But height-adjusting is discharge table for construction | |
CN216810841U (en) | High formwork in house construction civil engineering | |
CN215588296U (en) | Operation platform for field welding of section steel column | |
CN217054263U (en) | Draw scaffold frame of encorbelmenting to one side | |
CN218714961U (en) | Integral hoisting platform with adjustable spacing | |
CN219100689U (en) | Attachment structure suitable for super high floor attached lifting scaffold | |
CN217923103U (en) | Outer construction platform device of suspension cable tower | |
CN212200088U (en) | Be used for prefabricated T roof beam diaphragm construction equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200124 Termination date: 20210411 |
|
CF01 | Termination of patent right due to non-payment of annual fee |