CN212198198U - Pipeline installation device in crane beam - Google Patents

Pipeline installation device in crane beam Download PDF

Info

Publication number
CN212198198U
CN212198198U CN202021073233.1U CN202021073233U CN212198198U CN 212198198 U CN212198198 U CN 212198198U CN 202021073233 U CN202021073233 U CN 202021073233U CN 212198198 U CN212198198 U CN 212198198U
Authority
CN
China
Prior art keywords
pipeline
crane beam
fixed pulley
flexible body
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021073233.1U
Other languages
Chinese (zh)
Inventor
曲德文
滕德志
曹磊
陈耀武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202021073233.1U priority Critical patent/CN212198198U/en
Application granted granted Critical
Publication of CN212198198U publication Critical patent/CN212198198U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a pipeline installation device in crane beam, including the flexible body, fix the fixed pulley on the long span of crane beam leads to and fix the cylinder in the long direction one end of crane beam, flexible body one end hookup passes the pipeline and colludes on the pipeline through the couple, and the other end cooperates with the fixed pulley, walks around the fixed pulley pivot after to the ground that hangs down. The utility model discloses simple structure makes the fixed pulley roll through ground personnel pulling flexible body, and is more laborsaving when making the pipeline get into the crane beam inside with the help of the cylinder, uses the flexible body to improve the adaptability to different supporting structures moreover.

Description

Pipeline installation device in crane beam
Technical Field
The utility model belongs to high altitude pipe installation operation field particularly, relates to a pipeline installation device in crane beam for realize high altitude pipe installation in the factory building.
Background
In recent years, in the construction of medium pipeline installation systems, particularly in the process of installing high-altitude pipelines, the construction progress is required to be accelerated, and the construction safety is required to be ensured. The common construction method is that a part of a crane beam brake plate or an auxiliary truss which obstructs the pipeline from entering the crane beam is manually dismantled, the medium pipeline is slowly lifted to the pipeline installation height in a chain-reversing hand-pulling mode, and the medium pipeline is slowly moved to the installation position in the pipeline installation height range in the chain-reversing hand-pulling mode. The method has low construction operation efficiency, short chain-reversing distance, manpower waste and inconvenient overhead operation.
SUMMERY OF THE UTILITY MODEL
To the technical problem, the utility model provides a pipeline installation device in crane beam solves the big problem of the construction degree of difficulty that arouses because of crane beam system inner structure is complicated, pipeline overlength etc. has compromise the requirement of safety, quality, progress and the economy of whole installation pipeline work progress simultaneously.
The utility model adopts the following technical scheme:
the utility model provides a pipeline installation device in crane beam, includes the flexible body, still includes the fixed pulley of fixing on the long span of crane beam leads to and fix the cylinder at crane beam leads to length direction one end, and flexible body one end coupling hook passes the pipeline and colludes on the pipeline through the couple, and the other end cooperates with the fixed pulley.
Compared with the prior art, the utility model has the advantages of, make the fixed pulley roll through ground personnel pulling flexible body, it is more laborsaving when making the pipeline get into inside the crane beam with the help of the cylinder, improved the adaptability to different supporting structures through using flexible body moreover.
Furthermore, rollers are respectively fixed at two ends of the crane beam in the overall length direction, and two fixed pulleys or a fixed pulley group consisting of the two fixed pulleys are fixed in the middle of the overall length span of the crane beam.
Further, the flexible body is a steel wire rope.
Drawings
Fig. 1 is a schematic view of the state of use of the pipeline installation device in a crane beam of the present invention;
FIG. 2 is a side view of the pipeline installation in a crane beam;
in the figure: 1-crane beam; 2-a fixed pulley group; 3-a pipeline; 4-a roller; 5-a steel wire rope; 6-hooking; 7-overhead workers; 8-ground operator; 9-a roller bracket; 10-a crane.
Detailed Description
The invention will be further described with reference to the accompanying drawings and specific embodiments. It is to be understood that the following description is only for purposes of clearly illustrating the present invention and is not to be taken in a limiting sense.
Referring to fig. 1 and 2, an installation device for a pipeline in a crane beam is composed of a crown block 2, a roller 3, a wire rope 5, a hook 6 and the like, and is used for transporting the pipeline 3 to an installation position inside the crane beam 1 through cooperation of an aerial worker 7 and a ground worker 8.
The fixed pulley block 2 consists of two M100 fixed pulleys with the same specification, and is fixed in the middle of the full-length span of the crane beam through welding, and the full-length span of the crane beam is very large and can reach hundreds of meters. The two ends of the crane beam in the full-length direction are respectively provided with a roller bracket 9 perpendicular to the full-length direction, and the rollers 4 are sleeved on the roller brackets 9 and fixed at the two ends of the crane beam in the full-length direction through the roller brackets 9. Set up two wire rope 5 altogether, every wire rope one end is equipped with couple 6, and the one end that has couple 6 is passed behind pipeline 3 and is colluded on pipeline 3, and the other end is the free end, walks around the fixed pulley pivot and then hangs down subaerial, is by the pulling of ground operation personnel 8, drives pipeline 3 and removes. When the pipeline 3 moves, rolling friction is generated between the pipeline and the roller 4, and the rolling friction force is smaller than the friction force generated by direct contact, so that labor is saved when the pipeline is pulled.
A method for installing a pipeline in a crane beam is implemented by the following steps:
s1: the fixed pulley block 2 is fixed in the middle of the direction of the full length span of the crane beam in a welding mode, correspondingly, two rollers 4 are arranged at two ends of the direction of the full length of the crane beam respectively, the installation positions of the fixed pulley block 2 and the rollers 4 are lower than the installation position of the pipeline 3 respectively, the fixed pulley block 2 is composed of two M100 fixed pulleys, two steel wire ropes 5 are provided simultaneously, one end of each steel wire rope 5 is a free end, the other end of each steel wire rope is connected with a hook 6, the free end of each steel wire rope 5 penetrates through the fixed pulleys and falls to the ground to be pulled by ground operating personnel 8, and one end of each connecting hook 6 is temporarily hung at an. The fixed pulley group 2 in the S1 can also be directly replaced by two M100 fixed pulleys arranged in the middle of the full-length span of the crane beam.
S2: the two groups of cranes 10 respectively hoist the pipeline 3 from two ends of the through length direction of the crane beam, each end is provided with an aerial worker 7, one end of the pipeline 3 is placed on the roller 4, the aerial worker 7 assists in preventing the pipeline 3 from colliding with the crane beam system when entering the crane beam 1, the aerial worker 7 enables one end of the steel wire rope 5 with the hook 6 to penetrate through the pipeline 3, the hook 6 is hooked on the pipeline 3, and the other end of the steel wire rope penetrates through the fixed pulley and falls to the ground. Each section of pipeline 3 is obtained by pre-assembling two single sections of pipelines with the length of 12m on the terrace.
S3: two groups of ground operating personnel 8 hold the steel wire rope 5 below the fixed pulley block, pull the steel wire rope 5 from different directions to make the fixed pulley roll, pull the pipeline 3 to advance towards the inside of the crane beam, the roller also starts to roll, reduce the force required for pulling the pipeline, in the process, the high-altitude operating personnel prevent the pipeline 3 from touching the crane beam system through auxiliary operation, when the pipeline 3 exceeds the roller by more than half of the length, the hoisting of the pipeline 3 by the crane 10 is released.
S4: when the pipeline 3 approaches the pipeline bracket inside the crane beam, the high-altitude operator 7 lifts one end of the pipeline to enable the lifted end to abut against the pipeline bracket at the installation height.
S5: the ground operator 8 continues to pull the steel wire rope 5, so that the pipeline 3 is completely moved from the roller 4 to the pipeline bracket 7; and then the pipeline 3 moves along the pipeline bracket, in the moving process, the high-altitude operation personnel 7 continuously cooperate with the pipeline bracket, under the condition that the advancing of the pipeline is blocked, the pipeline is lifted to the position where the pipeline can pass through smoothly, and after the pipeline reaches the specified installation position, welding is carried out by welding personnel.
Through the utility model discloses an installation device and installation method, can rotate the pulling force of applying operating personnel through wire rope with the help of the fixed pulley and use the pipeline on, the roll through the cylinder reduces frictional resistance to save the manpower, accelerated the construction progress, avoid the pipeline to touch crane beam system through industry control operation personnel's assistance, improved the piping erection quality.
The above description is only the preferred embodiment of the present invention. Various modifications and equivalent changes may be made by those skilled in the art without departing from the spirit and scope of the present invention, and such modifications and changes are intended to be included within the scope of the present invention.

Claims (3)

1. The utility model provides a pipeline installation device in crane beam, includes the flexible body, its characterized in that still includes the fixed pulley of fixing on the long span of crane beam leads to and fix the cylinder at crane beam leads to length direction one end, and flexible body one end connects the couple, passes the pipeline and colludes on the pipeline through the couple, and the other end cooperates with the fixed pulley.
2. The installation device for pipeline in crane beam as claimed in claim 1, wherein rollers are fixed at both ends of the crane beam in the longitudinal direction, and two fixed pulleys are fixed in the middle of the crane beam in the longitudinal span, or a fixed pulley group consisting of two fixed pulleys.
3. The crane in-beam conduit installation apparatus of claim 1 wherein the flexible body is a wire rope.
CN202021073233.1U 2020-06-12 2020-06-12 Pipeline installation device in crane beam Active CN212198198U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021073233.1U CN212198198U (en) 2020-06-12 2020-06-12 Pipeline installation device in crane beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021073233.1U CN212198198U (en) 2020-06-12 2020-06-12 Pipeline installation device in crane beam

Publications (1)

Publication Number Publication Date
CN212198198U true CN212198198U (en) 2020-12-22

Family

ID=73809061

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021073233.1U Active CN212198198U (en) 2020-06-12 2020-06-12 Pipeline installation device in crane beam

Country Status (1)

Country Link
CN (1) CN212198198U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111620237A (en) * 2020-06-12 2020-09-04 中国二十二冶集团有限公司 Device and method for installing pipeline in crane beam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111620237A (en) * 2020-06-12 2020-09-04 中国二十二冶集团有限公司 Device and method for installing pipeline in crane beam
CN111620237B (en) * 2020-06-12 2024-05-24 中国二十二冶集团有限公司 Crane beam inner pipeline installation device and installation method

Similar Documents

Publication Publication Date Title
CN206722429U (en) A kind of roofing color corrugated sheet steel transportation system
CN212198198U (en) Pipeline installation device in crane beam
CN104196255A (en) Mobile safety net hanging method for plant roof installation
CN102602834B (en) Platform-free lifting method and system of installing large rectangular devices to high-rise buildings
CN211034762U (en) Cable winding and unwinding and hoisting integrated combined vehicle
CN203794533U (en) Light portable mobile lifting equipment
CN104818858A (en) Indoor heavy electric cabinet lifting method
CN212251443U (en) Special pipeline of old factory building dust removal pipeline transformation installation removes hoist device
CN111620237A (en) Device and method for installing pipeline in crane beam
CN213015280U (en) Movable material loading platform
CN104150393B (en) A kind of micro power power equipment rotary hoisting device
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN111711131A (en) Cable guiding device in bridge and cable laying method
CN217555687U (en) Hoisting accessory is changed to cladding material workshop electric block part
CN105776092A (en) Stretching type basket device and construction method thereof
CN212050425U (en) Special hanging flower basket of cable crane haulage rope blind area maintenance
CN206000178U (en) A kind of mounting tool of roof large span large-diameter pipeline
CN112377672A (en) Old factory dust removal pipeline reconstruction and installation method and special pipeline moving and hoisting device thereof
CN212769534U (en) Rotatable simple and easy hoist device
CN219116989U (en) Rail sliding device for hoisting high-rise building surface
CN212799441U (en) Horizontal air pipe lifting device
CN204456689U (en) A kind of work high above the ground sliding platform
CN212924215U (en) Electric winch support that intensity is high
CN214734060U (en) Major diameter pipeline poling construction structures based on steel construction gallows
CN218520918U (en) Real abdomen formula steel crane roof beam installation device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant