CN212075212U - Building engineering garbage collection device - Google Patents

Building engineering garbage collection device Download PDF

Info

Publication number
CN212075212U
CN212075212U CN202020405660.9U CN202020405660U CN212075212U CN 212075212 U CN212075212 U CN 212075212U CN 202020405660 U CN202020405660 U CN 202020405660U CN 212075212 U CN212075212 U CN 212075212U
Authority
CN
China
Prior art keywords
wall
fixed
bolts
box
bolt fastening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020405660.9U
Other languages
Chinese (zh)
Inventor
崔璨
朱涛
曹奕珂
宋昊
宋昶汝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Xinkunming Construction Co ltd
Original Assignee
Jinling Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinling Institute of Technology filed Critical Jinling Institute of Technology
Priority to CN202020405660.9U priority Critical patent/CN212075212U/en
Application granted granted Critical
Publication of CN212075212U publication Critical patent/CN212075212U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model discloses a building engineering garbage collection device, the on-line screen storage device comprises a base, base top outer wall has the processing case through the bolt fastening, one side of base top outer wall has the switch board through the bolt fastening, processing roof portion outer wall has seted up the feed inlet, and the inner wall of feed inlet has the feeder hopper through the bolt fastening, processing bottom of the case portion outer wall has seted up the discharge gate, and the inner wall of discharge gate has the discharging pipe through the bolt fastening, one side outer wall of processing case has the collecting box through the bolt fastening, and one side outer wall of collecting box is provided with sealing door, the opposite side of base top outer wall passes through the bolt fastening and has the fan. The utility model discloses a cooperation between dust removal sack and the dust absorption head in the collecting box prevents that building rubbish from leading to the dust to raise when broken, sets up atomizer in the discharging pipe bottom again, prevents through atomizer in to collecting box water spray that the dust secondary from raising polluted air.

Description

Building engineering garbage collection device
Technical Field
The utility model relates to a building engineering technical field especially relates to a building engineering garbage collection device.
Background
The building engineering refers to an engineering entity formed by the construction of various building constructions and their auxiliary facilities and the installation of lines, pipelines and equipment matched with them. The house building is characterized by comprising a top cover, a beam column, a wall, a foundation and a project which can form an internal space and meet the requirements of people on production, living, study and public activities. Civil engineering, building environment and energy application engineering, water supply and drainage science and engineering, building electrical and intelligence, architecture, urban and rural planning, landscape and garden, engineering management and engineering cost, real estate development and management and property management 9 subject professional instruction committees (hereinafter referred to as professional instruction committees) are arranged under the civil engineering and teaching instruction committees, and correspond to 11 specialties of soil and wood, buildings, management science and engineering (parts) and industrial and commercial management (parts) in the higher school's bibliography of the subject specialty.
A large amount of garbage can be generated in the building construction process, the building garbage needs to be collected after being processed, and due to the fact that a large amount of dust exists in the building garbage, the existing collecting device causes the dust to raise the polluted air in the processing process.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a construction engineering garbage collection device.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a building engineering garbage collection device, includes the base, base top outer wall has the processing case through the bolt fastening, one side of base top outer wall has the switch board through the bolt fastening, the feed inlet has been seted up to processing case top outer wall, and the inner wall of feed inlet has the feeder hopper through the bolt fastening, processing bottom of the case outer wall has seted up the discharge gate, and the inner wall of discharge gate has the discharging pipe through the bolt fastening, one side outer wall of processing the case has the collecting box through the bolt fastening, and one side outer wall of collecting box is provided with sealing door, the opposite side of base top outer wall has the fan through the bolt fastening, and the delivery outlet of fan passes through the pipe connection on the collecting box, discharging pipe bottom outer wall all has the atomizing shower nozzle.
Preferably, the two sides of the outer wall of the top of the base are both fixed with sliding rails through bolts, and the inner walls of the two sliding rails are connected with the same collecting box in a sliding manner.
Preferably, the inner walls of the two sides of the treatment box are both fixed with crushing rollers through bolts, and the two crushing rollers are meshed with each other.
Preferably, the inner wall of one side of the treatment box is fixed with a dust collection head through a bolt, and the dust collection head is connected to the collection box through a pipeline.
Preferably, the inner walls of the two sides of the collecting box are clamped with the same cage, and the outer wall of the bottom of the cage is fixed with a dust removal cloth bag through bolts.
Preferably, the outer wall of the dust collection head is fixed with a filter screen through a bolt.
Preferably, the fan is connected with a switch through a wire, and the switch is connected with a power line through a wire.
The utility model has the advantages that:
this building engineering garbage collection device sets up the collecting box through handling case one side, through the dust removal sack in the collecting box and the cooperation between the dust absorption head, prevents that building rubbish from leading to the dust to raise when broken, sets up atomizer in the discharging pipe bottom again, prevents through atomizer to collecting the interior water spray of box that the dust secondary from raising the contaminated air.
Drawings
Fig. 1 is a schematic structural view of a construction engineering garbage collection device provided by the present invention;
fig. 2 is a schematic view of a cross-sectional structure of a treatment tank of the construction waste collection device provided by the present invention;
fig. 3 is the utility model provides a collection box structural schematic diagram of building engineering garbage collection device.
In the figure: the device comprises a base 1, a processing box 2, a control cabinet 3, a processing pipe 4, a feeding hopper 5, a collecting box 6, a sealing door 7, a fan 8, a collecting box 9, a dust collecting head 10, a crushing roller 11, an atomizing nozzle 12, a dust removing cloth bag 13 and a cage 14.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, a construction engineering garbage collecting device comprises a base 1, a processing box 2 is fixed on the outer wall of the top of the base 1 through bolts, a control cabinet 3 is fixed on one side of the outer wall of the top of the base 1 through bolts, a feeding port is arranged on the outer wall of the top of the processing box 2, a feeding hopper 5 is fixed on the inner wall of the feeding port through bolts, a discharging port is arranged on the outer wall of the bottom of the processing box 2, a discharging pipe 4 is fixed on the inner wall of the discharging port through bolts, a collecting box 6 is fixed on the outer wall of one side of the processing box 2 through bolts, a sealing door 7 is arranged on the outer wall of one side of the collecting box 6, a fan 8 is fixed on the other side of the outer wall of the top of the base 1 through bolts, the discharging port of the fan 8 is connected to the collecting, and the inner wall sliding connection of two slide rails has same collection box 9, the both sides inner wall of handling case 2 all has crushing roller 11 through the bolt fastening, and two crushing roller 11 intermeshing, the one side inner wall of handling case 2 has dust collection head 10 through the bolt fastening, and dust collection head 10 passes through the pipe connection on collecting box 6, the both sides inner wall joint of collecting box 6 has same cage 14, and cage 14 bottom outer wall has dust removal sack 13 through the bolt fastening, the outer wall of dust collection head 10 has the filter screen through the bolt fastening, fan 8 is connected with the switch through the wire, and the switch is connected with the power cord through the wire.
The working principle is as follows: during the use, start crushing roller 11 and fan 8 earlier, then pour into building rubbish into to feeder hopper 5 through the dolly, grind each other through two crushing rollers 11 and carry out the breakage with rubbish, in the dust of raising up during the breakage simultaneously by fan 8 through dust absorption head 10 suction collection box 6, filter the collection through dust removal sack 13 in collection box 6, handle 2 broken back kibbling rubbish of case and get into through unloading pipe 4 and collect box 9 in, rethread atomizer 12 sprays water smoke to collecting box 9 and places the dust and raise.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. A construction engineering garbage collection device comprises a base (1) and is characterized in that a treatment box (2) is fixed on the outer wall of the top of the base (1) through bolts, a control cabinet (3) is fixed on one side of the outer wall of the top of the base (1) through bolts, a feed inlet is formed in the outer wall of the top of the treatment box (2), a feed hopper (5) is fixed on the inner wall of the feed inlet through bolts, a discharge outlet is formed in the outer wall of the bottom of the treatment box (2), a discharge pipe (4) is fixed on the inner wall of the discharge outlet through bolts, a collection box (6) is fixed on the outer wall of one side of the treatment box (2) through bolts, a sealing door (7) is arranged on the outer wall of one side of the collection box (6), a fan (8) is fixed on the other side of the outer wall of the top of the base, the outer wall of the bottom of the discharge pipe (4) is fixed with an atomizing nozzle (12) through a bolt.
2. The constructional engineering waste collection device of claim 1, wherein the two sides of the outer wall of the top of the base (1) are both fixed with slide rails through bolts, and the inner walls of the two slide rails are slidably connected with the same collection box (9).
3. A construction waste collection device according to claim 2, wherein the treatment tank (2) is fixed with crushing rolls (11) on both inner walls by bolts, and the two crushing rolls (11) are engaged with each other.
4. A construction waste collecting device according to claim 3, wherein a dust suction head (10) is fixed on one side of the inner wall of the processing box (2) through bolts, and the dust suction head (10) is connected to the collecting box (6) through a pipeline.
5. The constructional engineering waste collection device of claim 4, wherein the inner walls of the two sides of the collection box (6) are clamped with a cage (14), and the outer wall of the bottom of the cage (14) is fixed with a dust removal cloth bag (13) through bolts.
6. The construction engineering waste collection device according to claim 5, wherein the outer wall of the dust collection head (10) is fixed with a filter screen through bolts.
7. The construction engineering waste collection device according to claim 6, wherein the fan (8) is connected with a switch through a wire, and the switch is connected with a power line through a wire.
CN202020405660.9U 2020-03-26 2020-03-26 Building engineering garbage collection device Active CN212075212U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020405660.9U CN212075212U (en) 2020-03-26 2020-03-26 Building engineering garbage collection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020405660.9U CN212075212U (en) 2020-03-26 2020-03-26 Building engineering garbage collection device

Publications (1)

Publication Number Publication Date
CN212075212U true CN212075212U (en) 2020-12-04

Family

ID=73563152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020405660.9U Active CN212075212U (en) 2020-03-26 2020-03-26 Building engineering garbage collection device

Country Status (1)

Country Link
CN (1) CN212075212U (en)

Similar Documents

Publication Publication Date Title
CN204021670U (en) Refuse transfer station environment is carried standard configuration cover system
CN203977903U (en) The on-the-spot environment-friendly type building garbage chamber of a kind of construction project
CN208346728U (en) A kind of building engineering construction environment-protection type floor cleaning device
CN107638139A (en) A kind of factory floor environmental friendly indoor robot
CN212524304U (en) Construction waste treatment device
CN107744867A (en) A kind of solid waste reducing mechanism of anti-dust
CN212075212U (en) Building engineering garbage collection device
CN206265669U (en) A kind of automatic dustfall open-type entirety garbage pool
CN210752895U (en) House building engineering construction refuse treatment device
CN210131670U (en) Civil engineering soil reducing mechanism
CN212314944U (en) Building engineering residue collection device
CN215506088U (en) Dust exhausting fan for construction engineering
CN220214386U (en) Raise dust processing apparatus for building engineering
CN214235491U (en) Dust collecting device for industrial dust removal
CN218516822U (en) Environment-friendly treatment facility that building rubbish was recycled
CN209791193U (en) Building construction dust collector
CN218113844U (en) Spraying dust suppression garbage pool structure
CN213527842U (en) Building engineering construction dust collector
CN215655345U (en) Be used for building material broken handle device
CN211801095U (en) Waste treatment device for building engineering
CN214398333U (en) Town road rubbish recovery unit
CN207242598U (en) A kind of emergency management and rescue case
CN216878472U (en) Raise dust processing apparatus for building engineering
CN216604590U (en) Building environmental protection dust collecting equipment
CN220633564U (en) Building engineering dust device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240131

Address after: No. 49, Group 1, Baifu, Yanping Town, Yunyang County, Chongqing, 404500

Patentee after: Lai Xiaojuan

Country or region after: China

Address before: No. 99 Jiangning Road, Nanjing District hirokage 211169 cities in Jiangsu Province

Patentee before: JINLING INSTITUTE OF TECHNOLOGY

Country or region before: China

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240204

Address after: No. 3, Baihechang Road, Huankeyuan, Xinjie Street, Yixing City, Wuxi City, Jiangsu Province, 214000

Patentee after: Jiangsu Xinkunming Construction Co.,Ltd.

Country or region after: China

Address before: No. 49, Group 1, Baifu, Yanping Town, Yunyang County, Chongqing, 404500

Patentee before: Lai Xiaojuan

Country or region before: China