CN203977903U - The on-the-spot environment-friendly type building garbage chamber of a kind of construction project - Google Patents

The on-the-spot environment-friendly type building garbage chamber of a kind of construction project Download PDF

Info

Publication number
CN203977903U
CN203977903U CN201420401298.2U CN201420401298U CN203977903U CN 203977903 U CN203977903 U CN 203977903U CN 201420401298 U CN201420401298 U CN 201420401298U CN 203977903 U CN203977903 U CN 203977903U
Authority
CN
China
Prior art keywords
room body
garbage chamber
friendly type
construction project
type building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420401298.2U
Other languages
Chinese (zh)
Inventor
唐华
胡革宇
程震
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420401298.2U priority Critical patent/CN203977903U/en
Application granted granted Critical
Publication of CN203977903U publication Critical patent/CN203977903U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses the on-the-spot environment-friendly type building garbage chamber of a kind of construction project, comprise room body (1), door (2), is characterized in that: described room body is provided with roller (3); Described room body (1) interior You Obstinate enclosure wall processed (5); At described room body, (Nei 1), Obstinate enclosure wall processed (5) outside is provided with support (13), interconnective blower fan water pump control cabinet (12), water tank (7), atomizing water spraying device, and described atomizing water spraying device is located on described support (13).The utility model integral body can be opened wide in translation, is convenient to machinery and topples over and load and transport rubbish, improves construction efficiency.Eliminated Secondary Transport, reduced and had bad luck the dust pollution that rubbish produces.Quick disassembled and the fast-assembling of changing places, has improved the recycling rate of waterused of installations and facilities, and by water smoke blower fan depositing dust, water smoke area coverage is large, it is far away to spray, and alleviates environment pollution, a tractor serves several purposes.The utility model water-saving result highly significant.

Description

The on-the-spot environment-friendly type building garbage chamber of a kind of construction project
Technical field
The utility model relates to the on-the-spot building waste of engineering construction to be cleared and memory device, relates in particular to the on-the-spot environment-friendly type building garbage chamber of a kind of construction project, for the environmental improvement of dust pollution, is a kind of novel environment friendly sealing garbage chamber.
Background technology
Current, the improvement of air quality is highly expected by the whole society.Engineering construction dust pollution is to cause one of bad key factor of quality of air environment.In work progress, often use tower crane and hopper by under the refuse collection of the building scope of operation, rubbish is poured directly into outside the fixed refuse door of interim construction, then through manually proceeding in garbage chamber, therefore topples over transport process and produce dust pollution.When rubbish that cleaning, outward transport pile with in garbage chamber, no matter be people's fixture vehicle or use loader entrucking, all cause reentrainment of dust.So the Dust Improvement of construction site construction waste needs a kind of environmental protection and more efficient cleaning to clear measure.
Utility model content
The utility model relates to the on-the-spot building waste of engineering construction to be cleared and memory device, relates in particular to the on-the-spot environment-friendly type building garbage chamber of a kind of construction project, for the environmental improvement of dust pollution, is a kind of novel environment friendly sealing garbage chamber.
Technical problem to be solved in the utility model is achieved through the following technical solutions:
The on-the-spot environment-friendly type building garbage chamber of construction project, comprises room body, door, and described room body is provided with roller, and described roller can slide in orbit; You Obstinate enclosure wall processed in described room body; Nei described room body, Obstinate enclosure wall processed outside is provided with support, interconnective blower fan water pump control cabinet, water tank, atomizing water spraying device, and described atomizing water spraying device is located on described support.
In described water tank, be provided with submersible pump.
The porous pulverizing nozzle that described atomizing water spraying device comprises blower fan, connects by pulverizing nozzle upper hose; Described pulverizing nozzle upper hose is connected with described submersible pump.
Described room body is spliced steel room body; Described door is opposite opened gate.
Described water tank is spliced stainless steel water tank; Described blower fan is pipe type fan.
Between described blower fan and support, universal joint is set.
The openings of Suo Shu Obstinate enclosure wall processed is consistent with described door.
Described track is formed by fixedly connecting by pre-buried angle steel, channel-section steel.
The structure explanation that the utility model is above-mentioned:
1. house basic structure: the stock that this garbage chamber adopts is angle steel and metal sheet, by connecting and composing body of wall, gate and roof with bolt, the integral house of composition after boring.Ground under two side walls of garbage chamber, pre-buried angle steel or channel-section steel, as track, are respectively installed roller under the body of wall of both sides, and seat is on track.In garbage chamber, with concrete casting, build up three enclosure walls, form garbage pool.
2. atomizing de-dusting equipment forms: pin-connected panel water tank is installed on the ground after the rear wall of described enclosure of concrete and garbage chamber steel between wall, offers retaining mouth on water tank, installs submersible pump in water tank.By steel bracket is installed on enclosure wall after concrete, steel bracket is installed water smoke blower fan, between water smoke blower fan and support, universal joint is set, make blower fan can degree of switching under manual operation, elevation-depression angle.On rear enclosure wall, mount variable frequency control case, blower fan, water pump are controlled.
3. water smoke blower fan: metal conduit formula blower fan.Porous atomizing water nozzle is housed in fan outlet section, on fan outlet flange, annular header is installed, uniform some atomizing water nozzles on collector.The water inlet pipe of porous atomizing water nozzle and annular header is connected with submersible pump with pressure-bearing flexible pipe by galvanized pipe.
The utility model adopts technique scheme to have following beneficial effect:
1. garbage chamber integral body can be opened wide in translation, is convenient to machinery and topples over and load and transport rubbish, improves construction efficiency.
2. eliminated the Secondary Transport of tower crane after garbage chamber is dumped rubbish outward, both reduced manpower consumption, reduced again and had bad luck the dust pollution that rubbish produces.
3. no matter be garbage chamber wall body structure, or equal quick disassembled and fast-assembling of changing places such as water tank, water pump, blower fan, improved the recycling rate of waterused of installations and facilities, significantly reduced the solid waste discharge of the building producing when old-fashioned fixedly garbage chamber is removed.
4. to topple over and clear be by water smoke blower fan depositing dust to rubbish, and water smoke area coverage is large, it is far away to spray, and alleviates environment pollution.
5. a complete set of equipment such as water smoke blower fan, water pump and controller thereof also can be used for the job site earthwork and digs the airborne dust operations such as fortune, old building dismounting, realizes a tractor serves several purposes.
6. blower and water pump, can be different according to airborne dust situation by professional Frequency Converter Control, regulate water smoke range and area coverage, realize good dust-laying effect.
7. the utility model adopts water mist dust fall, has changed job site and has used traditionally the injection of giant and (operating) water nozzle to press dust collecting method, water-saving result highly significant.
Accompanying drawing explanation
Fig. 1 is the utility model garbage chamber lateral view
Fig. 2 is the utility model garbage chamber plan structure schematic diagram
Fig. 3 is the utility model water smoke blower fan work theory structure schematic diagram
Wherein, the spliced steel of 1-moves garbage chamber, 2-garbage chamber opposite opened gate, 3-garbage chamber side wall roller, 4-steel track, 5-Obstinate enclosure wall processed, 6-submersible pump, the spliced stainless steel water tank of 7-, 8-blower fan, 9-porous pulverizing nozzle, 10-universal joint, 11-pulverizing nozzle upper hose, 12-blower fan water pump control cabinet, 13-support
The specific embodiment
The on-the-spot environment-friendly type building garbage chamber of a kind of construction project shown in Fig. 1, Fig. 2, Fig. 3, comprises spliced steel room body 1, opposite opened gate 2, and roller 3, described roller 3 can slide on track 4; The interior You Obstinate of described room body 1 enclosure wall 5 processed; Suo Shu Obstinate enclosure wall is provided with support 13, and described support 13 is provided with pipe type fan 8, and 13, described blower fan 8 and support arrange universal joint 10; Obstinate enclosure wall processed 5 outsides are provided with blower fan water pump control cabinet 12, spliced stainless steel water tank 7, atomizing water spraying device; In described water tank 7, be provided with submersible pump 6; Described atomizing water spraying device comprises blower fan 8, the porous pulverizing nozzle 9 connecting by pulverizing nozzle upper hose 11;
The utility model atomizing de-dusting operation: when using construction on-the-spot use tower crane and hopper to dump rubbish, first open garbage chamber gate 2, manually to pusher garbage chamber, make it along track 4 translation backward, garbage pool 5 and water tank 7, water smoke blower fan 8 etc. are completely unlimited, and tower crane is directly positioned over hopper and in garbage pool, lays down building waste.While dumping rubbish, open described water smoke blower and water pump, the water smoke under wind-force is swept along sprays to garbage pool, and airborne dust is subject to nebulization and landing fast, pollutes and is suppressed.
Removing, in outward transport room during rubbish, no matter machinery or manually shovel load garbage, also can cause airborne dust, and same open water mist blower and water pump, regulates blower fan angle and electric machine frequency, makes jet length, angle directly to airborne dust source point, reaches best anti-dust effect.Topple over, load and transport after rubbish completing, manually retract garbage chamber body of wall, make it to get back to original position, close gate, keep on-the-spot clean and tidy looks.

Claims (8)

1. the on-the-spot environment-friendly type building garbage chamber of construction project, comprises room body (1), and door (2), is characterized in that: described room body is provided with roller (3); Described room body (1) interior You Obstinate enclosure wall processed (5); At described room body, (Nei 1), Obstinate enclosure wall processed (5) outside is provided with support (13), interconnective blower fan water pump control cabinet (12), water tank (7), atomizing water spraying device, and described atomizing water spraying device is located on described support (13).
2. the on-the-spot environment-friendly type building garbage chamber of construction project according to claim 1, is characterized in that: in described water tank (7), be provided with submersible pump (6).
3. the on-the-spot environment-friendly type building garbage chamber of construction project according to claim 2, is characterized in that: described atomizing water spraying device comprises blower fan (8), the porous pulverizing nozzle (9) connecting by pulverizing nozzle upper hose (11); Described pulverizing nozzle upper hose (11) is connected with described submersible pump (6).
4. according to the on-the-spot environment-friendly type building garbage chamber of the construction project described in claim 1,2 or 3, it is characterized in that: described room body (1) is spliced steel room body; Described door (2) is opposite opened gate.
5. according to the on-the-spot environment-friendly type building garbage chamber of the construction project described in claim 1,2 or 3, it is characterized in that: described water tank (7) is spliced stainless steel water tank; Described blower fan (8) is pipe type fan.
6. according to the on-the-spot environment-friendly type building garbage chamber of the construction project described in claim 1,2 or 3, it is characterized in that: between described blower fan (8) and support (13), universal joint (10) is set.
7. according to the on-the-spot environment-friendly type building garbage chamber of the construction project described in claim 1,2 or 3, it is characterized in that the openings of: Suo Shu Obstinate enclosure wall processed (5) is consistent with described door (2).
8. according to the on-the-spot environment-friendly type building garbage chamber of the construction project described in claim 1,2 or 3, it is characterized in that: it is upper that described room body (1) is located at steel track (4), and described steel track (4) is formed by fixedly connecting by pre-buried angle steel, channel-section steel.
CN201420401298.2U 2014-07-21 2014-07-21 The on-the-spot environment-friendly type building garbage chamber of a kind of construction project Expired - Fee Related CN203977903U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420401298.2U CN203977903U (en) 2014-07-21 2014-07-21 The on-the-spot environment-friendly type building garbage chamber of a kind of construction project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420401298.2U CN203977903U (en) 2014-07-21 2014-07-21 The on-the-spot environment-friendly type building garbage chamber of a kind of construction project

Publications (1)

Publication Number Publication Date
CN203977903U true CN203977903U (en) 2014-12-03

Family

ID=51975362

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420401298.2U Expired - Fee Related CN203977903U (en) 2014-07-21 2014-07-21 The on-the-spot environment-friendly type building garbage chamber of a kind of construction project

Country Status (1)

Country Link
CN (1) CN203977903U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013863A (en) * 2016-07-14 2016-10-12 吴义坡 Fireproof waste storehouse
CN106088674A (en) * 2016-07-14 2016-11-09 吴义坡 A kind of portable taste removal waste product storehouse
CN108910369A (en) * 2018-09-14 2018-11-30 北京城建五建设集团有限公司 One kind pushing and pulling closed atomizing refuse depot and its construction method entirely
CN110630048A (en) * 2019-10-14 2019-12-31 中国恩菲工程技术有限公司 Garbage house
CN113477059A (en) * 2021-07-02 2021-10-08 深圳市锦明环保科技有限公司 Intelligent garbage room air quality automatic management device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013863A (en) * 2016-07-14 2016-10-12 吴义坡 Fireproof waste storehouse
CN106088674A (en) * 2016-07-14 2016-11-09 吴义坡 A kind of portable taste removal waste product storehouse
CN108910369A (en) * 2018-09-14 2018-11-30 北京城建五建设集团有限公司 One kind pushing and pulling closed atomizing refuse depot and its construction method entirely
CN108910369B (en) * 2018-09-14 2024-03-26 北京城建五建设集团有限公司 Full-push-pull closed spray type garbage station and construction method thereof
CN110630048A (en) * 2019-10-14 2019-12-31 中国恩菲工程技术有限公司 Garbage house
CN113477059A (en) * 2021-07-02 2021-10-08 深圳市锦明环保科技有限公司 Intelligent garbage room air quality automatic management device

Similar Documents

Publication Publication Date Title
CN203977903U (en) The on-the-spot environment-friendly type building garbage chamber of a kind of construction project
CN111375461B (en) Building garbage collection device for building engineering
CN205361725U (en) Device is administered to simple and easy raise dust
CN206655263U (en) A kind of level land mechanism of land leveller
CN104912016A (en) Multifunctional electric garbage clearance car
CN209934364U (en) Building concrete production dust fall pipeline
CN206143697U (en) Environmental protection dust removing vehicle
CN106193647B (en) A kind of high-strength energy-saving building
CN107034830A (en) It is a kind of can convenient cleaning roads traffic indication board spray truck
CN207727494U (en) A kind of Construction of Civil Engineering dedusting machinery drenching dust-settling technology based on water
CN108708344A (en) A kind of bridge construction sprinkling truck and its application method
CN104773536A (en) Dust suppression system for dust silo
CN213051016U (en) Garbage transfer device for construction
CN212075212U (en) Building engineering garbage collection device
CN211253893U (en) Garbage disposal equipment with deodorization air channel
CN210507287U (en) Green energy-concerving and environment-protective spraying apparatus for construction
CN208213831U (en) A kind of dust exhaust apparatus
CN214883324U (en) Civil engineering is with intelligent dustproof device
CN216125889U (en) Spray set is used in waterproofing membrane processing
CN218774518U (en) Intelligent spraying device of building construction site
CN211190568U (en) Spraying system for crawler-type environment-friendly construction waste mobile crusher
CN213527842U (en) Building engineering construction dust collector
CN215916824U (en) Dust removal device of loader
CN210613210U (en) A dust pelletizing system for grit storage feed bin
CN213836473U (en) Cleaning device is used in highway construction convenient to unload

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141203

Termination date: 20150721

EXPY Termination of patent right or utility model