CN211499706U - Prevent building construction climbing rack that rocks - Google Patents
Prevent building construction climbing rack that rocks Download PDFInfo
- Publication number
- CN211499706U CN211499706U CN201921702720.7U CN201921702720U CN211499706U CN 211499706 U CN211499706 U CN 211499706U CN 201921702720 U CN201921702720 U CN 201921702720U CN 211499706 U CN211499706 U CN 211499706U
- Authority
- CN
- China
- Prior art keywords
- rod
- bolt
- screens
- rack
- pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model belongs to the technical field of the attached form climbing frame technique and specifically relates to a prevent building construction climbing frame that rocks, include: the hack lever, go up the screens pole, screens pole down, the protection pull ring, the protection pole, the footboard, the connection piece, first bolt, branch, the bar rest, the antiskid groove, the second bolt, screens piece, the third bolt, the upper end of hack lever is equipped with screens pole, the lower extreme is equipped with screens pole down, it is an overall structure with the hack lever to go up screens pole, two upper and lower branches are connected with to one side of hack lever, branch intermediate junction has the bar rest, fixed mounting has the footboard between two hack levers, the higher authority of going up screens pole is equipped with the protection pull ring, upper and lower screens pole on the hack lever is respectively by screens piece fixed mounting on the wall, connect the rope lock on the protection pull ring, the rope is fixed to the roof and is protected.
Description
Technical Field
The utility model relates to a building climbing frame technical field, more specifically say, relate to a prevent building construction climbing frame that rocks.
Background
With the progress of the times, the places such as people's residence, work, entertainment and the like are buildings at present, and in order to save land, a plurality of buildings are high-rise buildings with dozens of floors, in order to be beautiful, tiles are attached or various colors are painted on the outer sides of the buildings, various drain pipes are distributed on the outer sides of the floors, as time goes on, the tiles and various pigments can be peeled off and faded, various drain pipes can be damaged, maintenance is needed, workers need to maintain the outer sides of the buildings during maintenance, particularly the middle parts of two floors are difficult to reach indoors, the climbing frame needs to be supported by the workers outside the wall, most of the existing climbing frames are mechanisms similar to lifting platforms, one side of the climbing frame body close to the building structure is fixedly connected with a guide rail on the climbing frame body through a horizontal wall piece, the climbing frame is lifted up and down on the guide rail, at higher levels, such a climbing frame is difficult to reach at such a height, and the movement of such a device is very inconvenient.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a building construction climbing frame that prevents to rock to solve current climbing frame and remove inconvenient and limited working range, fixed scheduling problem.
In order to achieve the above object, the present invention provides: a building construction climbing frame that prevents rocking, comprising: a frame rod, an upper clamping rod, a lower clamping rod, a protective pull ring, a protective rod, a pedal, a connecting sheet, a first bolt, a support rod, a grab bar, an anti-skid groove, a second bolt, a clamping piece and a third bolt, the upper end of the hack lever is provided with an upper clamping rod, the lower end of the hack lever is provided with a lower clamping rod, the upper clamping rod and the lower clamping rod are integrated with the hack lever, the upper end and the lower end of one side of the frame rod are fixedly provided with supporting rods, a grab bar is fixedly arranged between the two supporting rods, the grab rail and the support rod are fixedly arranged through a second bolt, a pedal is arranged between the two frame rods, the pedal and the frame rods are fixedly arranged through a connecting sheet and the first bolt, a protective rod is movably connected between the two upper clamping rods, the upper clamping rods and the clamping pieces are fixedly installed through third bolts, the lower clamping rod and the clamping piece are fixedly installed through a third bolt, and a protective pull ring is arranged on the upper surface of the upper clamping rod.
Preferably, the surface of the pedal is provided with an anti-slip groove.
Preferably, the pedal and the frame rod are fixedly installed through the connecting piece and the first bolt.
Preferably, the support rod is provided with a handrail rod.
Preferably, the upper clamping rod, the lower clamping rod and the clamping piece are fixedly installed through a third bolt.
Preferably, the upper surface of the upper clamping rod is provided with a protective pull ring.
Advantageous effects
1. The utility model provides a traditional floor climbing of climbing frame limit and low floor, and the problem that just can not be used when will solving the high-rise building, the utility model has the advantages of can be under construction and maintain at the outer wall of high-rise building, guaranteed constructor's safety.
2. And secondly, the upper and lower clamping rods can be connected and fixed with the wall through the clamping pieces and the third bolts.
3. Moreover, the surface of going up screens pole is equipped with the protection pull ring, and the protection pull ring is used for connecting the protection rope that is put down by the roof, connects the protection rope and is in order to prevent screens piece and wall connection insecure and meet accident.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Fig. 2 is a schematic structural diagram of fig. 1 according to the present invention.
Fig. 3 is a connecting structure diagram of the upper clamping rod and the wall body of the utility model.
Fig. 4 is a connecting structure diagram of the lower clamping rod and the wall body of the present invention.
In the drawings, the corresponding relationship between the component names and the reference numbers is as follows: hack lever 1, go up screens pole 2, lower screens pole 3, protection pull ring 4, guard bar 5, footboard 6, connection piece 7, first bolt 8, branch 9, bar 10, antiskid groove 11, second bolt 12, screens piece 13, third bolt 14.
Detailed Description
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "connected" and "connected" are to be interpreted broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Example (b):
as shown in fig. 1-4;
the embodiment provides a building construction climbing frame that prevents to rock, includes: the frame rod 1, an upper clamping rod 2, a lower clamping rod 3, a protective pull ring 4, a protective rod 5, a pedal 6, a connecting sheet 7, a first bolt 8, a support rod 9, a handrail rod 10, an anti-skid groove 11, a second bolt 12, a clamping piece 13 and a third bolt 14, wherein the upper clamping rod 2 is arranged at the upper end of the frame rod 1, the lower clamping rod 3 is arranged at the lower end of the frame rod 1, the upper clamping rod 2 and the lower clamping rod 3 are integrated with the frame rod 1, the support rod 9 is fixedly arranged at the upper end and the lower end of one side of the frame rod 1, the handrail rod 10 is fixedly arranged between the two support rods 9, the handrail rod 10 and the support rod 9 are fixedly arranged through the second bolt, the pedal 6 is arranged between the two frame rods 1, the pedal 6 and the frame rod 1 are fixedly arranged through the connecting sheet 7 and the first bolt 8, the protective rod 5 is movably connected between the two upper clamping rods 2, the upper clamping rod 2 and the clamping piece 13 are fixedly arranged through the third bolt 14, the lower, the upper surface of the upper clamping rod 2 is provided with a protective pull ring 4.
Wherein, the surface of footboard 6 is equipped with anti-skidding groove 11, sets up anti-skidding groove 11 and protects constructor not easy slipping when the operation, has guaranteed the safety of construction.
Wherein, footboard 6 passes through connection piece 7 and first bolt 8 fixed mounting with hack lever 1, prevents that footboard 6 from rocking from beginning to end and causing harm for the constructor.
Wherein, the support rod 9 is provided with a grab rail 10, and the grab rail 10 can have better protection effect for constructors.
Wherein, go up screens pole 2 and screens pole 3 down and screens piece 13 through third bolt 14 fixed mounting, fix on the wall screens pole 2 and screens pole 3 down through screens piece 13 and third bolt 14, prevent to climb the frame and take place to rock.
Wherein, go up screens pole 2 upper surface and be equipped with protection pull ring 4, protection pull ring 4 is the protection rope of connecting to put down by the roof, prevents the accident that the third bolted connection is bad and take place.
The working principle is as follows: in the using process, the frame rod 1 and the pedal 6 are fixedly installed through the connecting sheet 7 and the first bolt 8, the supporting rods 9 are fixedly connected with the frame rod 1, the grab bars 10 are fixedly installed between the supporting rods 9 through the second bolts 12, the upper clamping rod 2 and the lower clamping rod 3 are fixedly installed on a wall body needing to be constructed through the clamping pieces 13 and the third bolts 14 after the assembly is completed, and then the protection pull ring 4 is connected with a protection rope placed on the roof.
Claims (5)
1. A building construction climbing frame that prevents rocking, comprising: the multifunctional rack is characterized in that the upper end of the rack rod (1) is provided with an upper clamping rod (2), the lower clamping rod (3), a protective pull ring (4), a protective rod (5), a pedal (6), a connecting sheet (7), a first bolt (8), a support rod (9), a grab bar (10), an anti-skidding groove (11), a second bolt (12), a clamping part (13) and a third bolt (14), the multifunctional rack is characterized in that the upper clamping rod (2) is arranged at the upper end of the rack rod (1), the lower clamping rod (3) is arranged at the lower end of the rack rod, the upper clamping rod (2) and the lower clamping rod (3) are integrated with the rack rod (1), the support rods (9) are fixedly arranged at the upper end and the lower end of one side of the rack rod (1), the grab bar (10) is fixedly arranged between the two support rods (9), the grab bar (10) and the support rod (9) are fixedly arranged through the second bolt, the pedal (6) is arranged between the two rack rods (1), and the pedal (6) and the rack, two swing joint has protection pole (5) between last screens pole (2), go up screens pole (2) and screens piece (13) through third bolt (14) fixed mounting, lower screens pole (3) and screens piece (13) are through third bolt (14) fixed mounting, the upper surface of going up screens pole (2) is equipped with protection pull ring (4).
2. The building construction climbing frame preventing shaking according to claim 1, wherein the surface of the step plate (6) is provided with an anti-slip groove (11).
3. The building construction climbing frame preventing shaking according to claim 1, wherein the pedal (6) is fixedly installed with the frame rod (1) through a connecting piece (7) and a first bolt (8).
4. The anti-sway building construction climbing frame according to claim 1, wherein a grab bar (10) is provided on the support bar (9).
5. The climbing frame for preventing shaking in building construction according to claim 1, wherein the upper and lower position-retaining rods (2, 3) and the position-retaining member (13) are fixedly installed by a third bolt (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921702720.7U CN211499706U (en) | 2019-10-12 | 2019-10-12 | Prevent building construction climbing rack that rocks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921702720.7U CN211499706U (en) | 2019-10-12 | 2019-10-12 | Prevent building construction climbing rack that rocks |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211499706U true CN211499706U (en) | 2020-09-15 |
Family
ID=72406408
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921702720.7U Expired - Fee Related CN211499706U (en) | 2019-10-12 | 2019-10-12 | Prevent building construction climbing rack that rocks |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211499706U (en) |
-
2019
- 2019-10-12 CN CN201921702720.7U patent/CN211499706U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201506699U (en) | Electric lifting bridge rack for construction | |
CN101845883B (en) | Climbing scaffold system and construction method | |
CN103979383B (en) | Building operation multiple layer up-down plateform system | |
CN106088565A (en) | The method of tiltedly climbing of attachment type raise scaffold and attachment type raise scaffold | |
CN201826542U (en) | Self-climbing protective screening | |
CN106150057B (en) | A kind of split blade type hydraulic pressure lift climbing frame | |
CN113137054A (en) | Method for setting inverted hoisting power equipment in attached lifting scaffold | |
KR101345144B1 (en) | Safety rail climbing equipment | |
CN214658685U (en) | Combined anti-skidding climbing frame for constructional engineering | |
CN211499706U (en) | Prevent building construction climbing rack that rocks | |
CN107268971B (en) | Dual self-lifting type external climbing frame for super high-rise building and application method | |
CN205000656U (en) | From over -and -under type material cycling platform | |
CN101701492A (en) | Guide rail frame type adhering lifting scaffold | |
CN207845065U (en) | A kind of manned crane hanging basket | |
CN201190423Y (en) | Horizontal protection shed for tall building | |
CN206110636U (en) | Burst formula hydraulic lifting climbs frame | |
JP3950800B2 (en) | Suspension scaffold | |
CN211114767U (en) | PC bay window department climbs frame and attaches wall device | |
CN114809582A (en) | Counter weight-free hanging basket I-shaped steel suspension bracket and construction method | |
CN211007705U (en) | Discharging platform | |
CN211949696U (en) | Protection device for assembly type building construction | |
CN103225390B (en) | Hollow facade pulley guide attached-type lifting scaffold | |
CN208039793U (en) | Detachable operation platform for installing steel pipe truss string clamp | |
CN102745573B (en) | Elevator steel wire rope overhauling device and overhauling method thereof | |
CN207863444U (en) | Independent attached wall mounting column |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200915 Termination date: 20211012 |