CN211456489U - Multi-functional protective cradle that hangs of interim cable of construction - Google Patents

Multi-functional protective cradle that hangs of interim cable of construction Download PDF

Info

Publication number
CN211456489U
CN211456489U CN202020227052.3U CN202020227052U CN211456489U CN 211456489 U CN211456489 U CN 211456489U CN 202020227052 U CN202020227052 U CN 202020227052U CN 211456489 U CN211456489 U CN 211456489U
Authority
CN
China
Prior art keywords
cable
inserted bar
hanging
cable hook
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020227052.3U
Other languages
Chinese (zh)
Inventor
钟恩
李天隆
王朝龙
卢建文
郑少星
区建峰
陆波
邱威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau South China Co Ltd
Original Assignee
China Construction Eighth Bureau South China Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Bureau South China Co Ltd filed Critical China Construction Eighth Bureau South China Co Ltd
Priority to CN202020227052.3U priority Critical patent/CN211456489U/en
Application granted granted Critical
Publication of CN211456489U publication Critical patent/CN211456489U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a multi-functional protective cradle that hangs of interim cable of construction, including sleeve pipe, end plate, hang inserted bar, cable hook, end plate fixed mounting hangs the inserted bar and passes through the hinge and install in sheathed tube one side at the sheathed tube top, hangs the inserted bar and can overturn to the direction on sheathed tube top, and the biggest open angle of hinge is 90, and the cable hook rigid coupling is at sheathed tube opposite side. The beneficial effects are that: 1. inserting the hanging inserted bar into the jack drilled on the wall body, hanging the support on the wall body, and then hanging the cable on the cable hook; 2. the sleeve is sleeved at the tail end of the steel bar, so that the support is hung on the steel bar, and then the cable is hung on the cable hook; 3. the cable hook is hung on a scaffold, the hanging inserted bar is turned to be vertical to the central shaft of the sleeve, and then the cable is hung on the hanging inserted bar; the phenomena of dragging the cable to the ground, soaking water, twisting, rolling and treading by personnel can be avoided.

Description

Multi-functional protective cradle that hangs of interim cable of construction
Technical Field
The utility model relates to a construction technical field especially relates to a multi-functional protective cradle that hangs of interim cable of construction.
Background
Temporary electricity safety management is the most common safety management on a construction site. The temporary cable generally refers to a power supply line for ensuring the on-site installation of machinery, work, and the like at a construction site. At present, in the construction process of building engineering, the laying and protection of temporary cables are the most basic daily work, and various construction operators, mechanical operators and the like need to use temporary power to carry out construction operation and the like. However, some parts are limited by sites, temporary cables cannot be effectively protected in an overhead mode, and the like, and the cables are partially laid on a construction floor, an external scaffold and a shear wall.
Conventionally, cables are erected by using brackets, and binding tapes are directly tied to places such as steel bars and steel pipe frames for laying, or are directly placed on plate surfaces. When the conventional support frame erecting method is used for plate surface construction, the support frame is easy to damage, influences walking of field operation personnel, a trolley and the like, and is easy to collide and damage in operation. When the cable is directly tied to the steel bar, the steel pipe frame and the like for use, the cable is easy to wear and tear and has safety risks such as electric leakage.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome the above problem that prior art exists, provide a multi-functional protective cradle that hangs of interim cable of construction.
For realizing above-mentioned technical purpose, reach above-mentioned technological effect, the utility model discloses a following technical scheme realizes:
the utility model provides a multi-functional protective cradle that hangs of interim cable of construction, includes sleeve pipe, end plate, hangs inserted bar, cable hook, end plate fixed mounting is on sheathed tube top, hang the inserted bar and pass through the hinge and install in sheathed tube one side, hang the direction upset that the inserted bar can be to the sleeve pipe top, the biggest open angle of hinge is 90, the cable hook rigid coupling is at sheathed tube opposite side.
Wherein, a layer of insulating leather hose is respectively sleeved on the hanging inserted bar and the cable hook.
Wherein the length of the hanging insertion rod is more than or equal to 200 mm.
Wherein the radius of the curved arc of the cable hook is more than or equal to 24 mm.
Wherein, the sleeve is formed by cutting and processing a steel pipe with the diameter of 40mm and the wall thickness of 3 mm.
Wherein, hang the inserted bar and adopt C16 reinforcing bar waste material cutting to form.
The cable hook is formed by cutting and bending C16 steel bar waste.
The utility model has the advantages that: 1. inserting the hanging inserted bar into the jack drilled on the wall body, hanging the support on the wall body, and then hanging the cable on the cable hook; 2. the sleeve is sleeved at the tail end of the steel bar, so that the support is hung on the steel bar, and then the cable is hung on the cable hook; 3. the cable hook is hung on a scaffold, the hanging inserted bar is turned to be vertical to the central shaft of the sleeve, and then the cable is hung on the hanging inserted bar; the phenomena of dragging the cable to the ground, soaking water, twisting, rolling and treading by personnel can be avoided.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the invention without undue limitation to the invention. In the drawings:
fig. 1 is a schematic structural view of a suspension inserted link in a closed state according to an embodiment of the present invention;
fig. 2 is a schematic structural view of the embodiment of the present invention in which the suspension inserted link is in the unfolded state;
fig. 3 is a schematic structural diagram of a first embodiment of the present invention;
fig. 4 is a schematic structural diagram of a second embodiment of the present invention;
fig. 5 is a schematic structural diagram of a third embodiment of the present invention.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
As shown in fig. 1 and 2, the multifunctional hanging protection support for the temporary cable for construction comprises a sleeve 1, an end plate 2, a hanging inserted bar 3 and a cable hook 4, wherein the end plate 2 is fixedly installed at the top end of the sleeve 1, the hanging inserted bar 3 is installed on one side of the sleeve 1 through a hinge 5, the hanging inserted bar 3 can turn over towards the top end of the sleeve 1, the maximum opening angle of the hinge 5 is 90 degrees, and the cable hook 4 is fixedly connected to the other side of the sleeve 1.
The hanging inserted bar 3 and the cable hook 4 are respectively sleeved with a layer of insulating leather hose to avoid friction between the cable and the hanging inserted bar 3 and the cable hook 4. The length of the hanging inserted bar 3 is more than or equal to 200mm, and the hanging inserted bar 3 is ensured not to be separated from the jack when being inserted into the jack arranged on the wall body.
As shown in fig. 1 to fig. 3, a multifunctional hanging protection bracket for temporary cables in construction comprises a sleeve 1, an end plate 2, a hanging inserted link 3 and a cable hook 4, wherein the end plate 2 is fixedly mounted on the top end of the sleeve 1, the hanging inserted link 3 is mounted on one side of the sleeve 1 through a hinge 5, the hanging inserted link 3 can be turned over towards the top end of the sleeve 1, the maximum opening angle of the hinge 5 is 90 degrees, and the cable hook 4 is fixedly connected to the other side of the sleeve 1.
The length of the hanging inserted bar 3 is more than or equal to 200mm, and the hanging inserted bar 3 is ensured not to be separated from the jack when being inserted into the jack arranged on the wall body.
The radius of the curved arc of the cable hook 4 is more than or equal to 24 mm. The sleeve pipe 1 is formed by cutting and processing a steel pipe with the diameter of 40mm and the wall thickness of 3mm, the hanging inserted bar 3 is formed by cutting C16 steel bar waste, and the cable hook 4 is formed by bending the C16 steel bar waste after cutting.
The embodiment utilizes the hanging inserted bar 3 to be inserted into the jack drilled on the wall body, the bracket is hung on the wall body 6, and then the cable is hung on the cable hook 4.
As shown in fig. 1, 2 and 4, the second embodiment of the temporary cable hanging protection bracket for construction comprises a sleeve 1, an end plate 2, a hanging inserted bar 3 and a cable hook 4, wherein the end plate 2 is fixedly installed at the top end of the sleeve 1, the hanging inserted bar 3 is installed on one side of the sleeve 1 through a hinge 5, the hanging inserted bar 3 can be turned over towards the top end of the sleeve 1, the maximum opening angle of the hinge 5 is 90 degrees, and the cable hook 4 is fixedly connected to the other side of the sleeve 1.
The length of the hanging inserted bar 3 is more than or equal to 200mm, and the hanging inserted bar 3 is ensured not to be separated from the jack when being inserted into the jack arranged on the wall body.
The radius of the curved arc of the cable hook 4 is more than or equal to 24 mm. The sleeve pipe 1 is formed by cutting and processing a steel pipe with the diameter of 40mm and the wall thickness of 3mm, the hanging inserted bar 3 is formed by cutting C16 steel bar waste, and the cable hook 4 is formed by bending the C16 steel bar waste after cutting.
In this embodiment, the sleeve 1 is sleeved on the end of the steel bar 7, so that the bracket is hung on the steel bar, and then the cable is hung on the cable hook 4.
As shown in fig. 1, 2 and 5, the third embodiment of the temporary cable hanging protection support for construction comprises a sleeve 1, an end plate 2, a hanging inserted bar 3 and a cable hook 4, wherein the end plate 2 is fixedly installed at the top end of the sleeve 1, the hanging inserted bar 3 is installed on one side of the sleeve 1 through a hinge 5, the hanging inserted bar 3 can be turned over towards the top end of the sleeve 1, the maximum opening angle of the hinge 5 is 90 degrees, and the cable hook 4 is fixedly connected to the other side of the sleeve 1.
The length of the hanging inserted bar 3 is more than or equal to 200mm, and the hanging inserted bar 3 is ensured not to be separated from the jack when being inserted into the jack arranged on the wall body.
The radius of the curved arc of the cable hook 4 is more than or equal to 24 mm. The sleeve pipe 1 is formed by cutting and processing a steel pipe with the diameter of 40mm and the wall thickness of 3mm, the hanging inserted bar 3 is formed by cutting C16 steel bar waste, and the cable hook 4 is formed by bending the C16 steel bar waste after cutting.
In the present embodiment, the cable hook 4 is hung on the scaffold 8, the hanging insertion rod 3 is turned over to be perpendicular to the central axis of the casing 1, and then the cable is hung on the hanging insertion rod 3.
The foregoing shows and describes the general principles, essential features, and advantages of the invention. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention.

Claims (7)

1. The utility model provides a multi-functional protective cradle that hangs of interim cable of construction which characterized in that: including sleeve pipe, end plate, suspension inserted bar, cable hook, end plate fixed mounting is on sheathed tube top, hang the inserted bar and pass through the hinge and install in sheathed tube one side, hang the inserted bar and can overturn to the direction on sleeve pipe top, the biggest open angle of hinge is 90, the cable hook rigid coupling is at sheathed tube opposite side.
2. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: and the suspension inserted bar and the cable hook are respectively sleeved with a layer of insulating leather hose.
3. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: the length of the hanging insertion rod is more than or equal to 200 mm.
4. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: the radius of the curved arc of the cable hook is more than or equal to 24 mm.
5. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: the sleeve is formed by cutting and processing a steel pipe with the diameter of 40mm and the wall thickness of 3 mm.
6. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: the hanging inserted bar is formed by cutting C16 steel bar waste.
7. The multifunctional hanging protection bracket for construction temporary cables as claimed in claim 1, wherein: the cable hook is formed by cutting and bending C16 steel bar waste.
CN202020227052.3U 2020-02-28 2020-02-28 Multi-functional protective cradle that hangs of interim cable of construction Active CN211456489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020227052.3U CN211456489U (en) 2020-02-28 2020-02-28 Multi-functional protective cradle that hangs of interim cable of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020227052.3U CN211456489U (en) 2020-02-28 2020-02-28 Multi-functional protective cradle that hangs of interim cable of construction

Publications (1)

Publication Number Publication Date
CN211456489U true CN211456489U (en) 2020-09-08

Family

ID=72297995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020227052.3U Active CN211456489U (en) 2020-02-28 2020-02-28 Multi-functional protective cradle that hangs of interim cable of construction

Country Status (1)

Country Link
CN (1) CN211456489U (en)

Similar Documents

Publication Publication Date Title
CN110158937B (en) Cradle hanging structure without support and counterweight and construction method thereof
CN211449900U (en) High-efficient installation device of exhaust pipe
CN210286447U (en) Lifting hook device for lifting cement pipeline
CN211456489U (en) Multi-functional protective cradle that hangs of interim cable of construction
CN105126272A (en) Safety belt suspension device
CN205442567U (en) Steel -pipe pole operation platform
CN217417897U (en) Pipeline hoisting auxiliary tool and pipeline hoisting equipment
CN204675726U (en) Purlin lifting auxiliary device
CN110359674A (en) A kind of vertical duct well casing pipeline construction method of skyscraper small space
CN206237100U (en) Cable hanging unit
CN205123133U (en) Dismantled and assembled construction cable support
CN210140398U (en) Multifunctional suspension equipment for mechanical engineering
CN206396757U (en) New Anchor Cable removes machine
CN215120004U (en) Cable insulation hook
CN201247925Y (en) Safety hanging stair for maintaining cable terminal
CN201490634U (en) Trolley for casing
CN201623405U (en) Simple and convenient electric shock prevention temporary cable supporting frame
CN212387615U (en) Portable movable mast hoisting device in pipe shaft
CN211239271U (en) Mining cable pit is from scalable cable couple device of takeing root
CN212033684U (en) Insulated wire hook device for hanging cable
CN106436711A (en) Novel anchor cable removing machine
CN201256266Y (en) Multifunctional electric cable safety hook for simple construction
CN210461928U (en) Lifting auxiliary device for mounting flexible pipe cable
CN216699401U (en) Assembled pipeline that engineering construction used
CN219106919U (en) Underground pipe gallery hoisting type cable laying auxiliary device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant