CN211396757U - Steel module integrated house with integral bathroom - Google Patents

Steel module integrated house with integral bathroom Download PDF

Info

Publication number
CN211396757U
CN211396757U CN201921592291.2U CN201921592291U CN211396757U CN 211396757 U CN211396757 U CN 211396757U CN 201921592291 U CN201921592291 U CN 201921592291U CN 211396757 U CN211396757 U CN 211396757U
Authority
CN
China
Prior art keywords
bathroom
module
integral
integral bathroom
integrated house
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921592291.2U
Other languages
Chinese (zh)
Inventor
王金丽
范志富
刘济铖
屈旭满
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
MCC Tiangong Tianjin Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd, MCC Tiangong Tianjin Equipment Manufacturing Co Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201921592291.2U priority Critical patent/CN211396757U/en
Application granted granted Critical
Publication of CN211396757U publication Critical patent/CN211396757U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a steel module integrated house with an integral bathroom, which firstly carries out integral sinking of a keel at the lower part of the integral bathroom module in the steel module integrated house according to the size of the integral bathroom to ensure that the ground of the bathroom is not higher than the indoor ground; reserving a structural vent port at the top of the steel module integrated house structure; and in the decoration stage, a water supply pipe joint and a water discharge pipe joint are reserved near the bathroom, and after the integral bathroom is integrally installed, a water supply and discharge pipeline, a ventilation pipeline, an electric pipeline and equipment are connected. The utility model has the advantages that: the application of the integral bathroom module in the steel module integrated house reduces the field construction, improves the efficiency, reduces the secondary pollution of the field construction, and the water supply, drainage, ventilation and electric pipelines are hidden between the integral bathroom module and the inner wall plate, thereby being convenient to overhaul, neat and beautiful, and simultaneously reducing the cost of actual installation.

Description

Steel module integrated house with integral bathroom
Technical Field
The utility model belongs to the technical field of assembled steel construction module integrated house, especially, relate to a steel module integrated house with integral bathroom.
Background
The assembly type building is a great change to the construction mode, the development of the assembly type building is beneficial to saving resource and energy, reducing construction pollution and improving labor production efficiency and quality safety level, and the assembly rate and the integration level of the steel module integrated house are higher than those of the assembly type building. The quality and installation speed of the bathroom, which are indispensable parts in the building, directly restrict the overall manufacturing efficiency.
The bathroom in the existing steel module integrated house adopts a split type installation method, the ground, the wall surface and the like are firstly installed during installation, a water closing test is carried out after the installation is finished, sanitary appliances and pipeline ventilation electric appliances can be installed after the test is qualified, and the process is complex and tedious; the integral bathroom refers to a factory fully-prefabricated integral unit formed by an integrated chassis, a wallboard, a top plate, built-in bathroom facilities, toileting facilities, washing facilities and the like, and the application of the integral bathroom in a modular building can reduce projects such as a water-closing test, electrical installation, pipeline installation and the like during field installation, improve the working efficiency and shorten the construction period.
The existing steel module integrated house adopts the same-layer drainage technology, a toilet bowl installed in the traditional bathroom is suitable for adopting a side drainage mode due to large pipe diameter, the type of the toilet bowl is single, the relative installation difficulty is high, and the appearance of the toilet bowl is influenced by an open-mounted pipeline; in addition, a water closing test needs to be carried out when a common bathroom is installed, and the time is long; the installation involves a plurality of professional cross constructions such as pipelines, ventilation, electricity and the like, and the working procedure is complex; from design to purchase construction, a plurality of professional materials are involved, and the cost is high.
Disclosure of Invention
In order to solve the technical problem, the utility model provides a steel module integrated house with integral bathroom.
The utility model adopts the technical proposal that: a steel module integrated house with an integral bathroom comprises module outer wall corrugated plates, a bottom keel and an integral bathroom module, wherein the bottom keel comprises a common keel and an integral bathroom lower keel, the integral bathroom lower keel is arranged at the lower part of the integral bathroom module, and the height of the integral bathroom lower keel is lower than that of the common keel; the integral bathroom module comprises a bathroom waterproof chassis and an inner wall plate, and the inner wall plate and the module outer wall corrugated plate form a bathroom space.
Preferably, the bathroom waterproof chassis is provided with a water discharge pipe interface, and the inner wall plate on one side is provided with a water supply pipe interface.
Preferably, the module outer wall corrugated plate in the bathroom space is provided with a ventilation pipe connector.
Preferably, the vent tube opening is higher than the inner panel height.
Preferably, the sanitary waterproof chassis is connected with the integral sanitary lower keel through a bearing screw.
The utility model has the advantages and positive effects that: the application of the integral bathroom module in the steel module integrated house reduces the field construction, improves the efficiency, reduces the secondary pollution of the field construction, and the water supply, drainage, ventilation and electric pipelines are hidden between the integral bathroom module and the inner wall plate, thereby being convenient to overhaul, neat and beautiful, and simultaneously reducing the cost of actual installation.
Drawings
Fig. 1 is a schematic view illustrating an installation of an integrated sanitary module according to an embodiment of the present invention;
fig. 2 is a schematic view of the arrangement of the structural keels of one embodiment of the present invention;
FIG. 3 is a schematic view of a vent prefabrication according to one embodiment of the present invention;
fig. 4 is an installation schematic view of a waterproof bathroom chassis according to an embodiment of the present invention.
In the figure:
1. drain pipe connector 2, ventilation pipe connector 3 and water supply pipe connector
4. Integral bathroom 5, interior wallboard 6, ordinary fossil fragments
7. Integral bathroom lower part fossil fragments 8, module outer wall buckled plate 9, waterproof chassis of bathroom
10. Bearing bolt 11, ground
Detailed Description
An embodiment of the present invention is described below with reference to the drawings.
As shown in fig. 1-4, the utility model relates to a steel module integrated house with integral bathroom, including module outer wall buckled plate, end fossil fragments and integral bathroom module, module outer wall buckled plate encloses end keel and forms steel module integrated house, and adjacent module outer wall buckled plate in integral bathroom module one side sets up, and end keel includes ordinary fossil fragments and integral bathroom lower part fossil fragments, and integral bathroom lower part fossil fragments set up in integral bathroom module lower part, and other positions are equipped with ordinary fossil fragments, and integral bathroom lower part fossil fragments height is less than ordinary fossil fragments, guarantees that bathroom bottom surface is not higher than indoor ground.
The integral bathroom module comprises a bathroom waterproof chassis and an inner wall plate, the bathroom waterproof chassis is connected with an integral bathroom lower keel through a bearing screw rod, the inner wall plate and a module outer wall corrugated plate form a bathroom space, a drainage pipe joint is arranged on the bathroom waterproof chassis, a water supply pipe joint is arranged on the inner wall plate on one side, a ventilation pipe joint is arranged on the module outer wall corrugated plate in the bathroom space, and the ventilation pipe joint is higher than the inner wall plate. The suspended ceiling in the integral bathroom module is arranged on the upper side of the inner wall plate, and the ventilation pipe is arranged on the upper portion of the suspended ceiling and used for the ventilation function of the whole integral bathroom module.
A method for installing an integral bathroom in a steel module integrated house solves the problem of installation of the integral bathroom in the steel module integrated house in the prior art, and integrally sinks a keel at the lower part of the integral bathroom module in the steel module integrated house according to the size of the integral bathroom to ensure that the ground of the bathroom is not higher than the indoor ground; reserving a structural vent port at the top of the steel module integrated house structure; and in the decoration stage, a water supply pipe joint and a water discharge pipe joint are reserved near the bathroom, and after the integral bathroom is integrally installed, a water supply and discharge pipeline, a ventilation pipeline, an electric pipeline and equipment are connected. The specific installation steps are as follows:
step one, a steel module integrated house structure manufacturing stage, setting the position of a bottom keel to be installed with an integrated bathroom module as an integrated bathroom lower keel, sinking the integrated bathroom lower keel to be lower than a common keel, and arranging the integrated bathroom lower keel according to the position of a bottom bearing screw rod of the integrated bathroom module and the direction of a drainage pipeline as shown in figure 2;
secondly, welding a structure ventilation pipe on the module outer wall corrugated plate in the bathroom space range to form a ventilation pipe interface, wherein the height of the ventilation pipe interface is higher than that of the inner wall plate and higher than that of the suspended ceiling as shown in FIG. 3;
thirdly, after the steel module integrated house structure is manufactured, the installation of the common keel, the heat-preservation water and electricity pipeline and the decorative plate is finished before the installation of the integral bathroom module, and the bottom plate and the wallboard are not installed at the corresponding repairing positions of the integral bathroom module;
fourthly, as shown in fig. 4, installing a bathroom waterproof chassis, welding a bearing screw rod on a lower beam of the bathroom waterproof chassis, and correspondingly placing the bathroom waterproof chassis with the integral bathroom lower keel through the bearing screw rod;
fifthly, assembling functional components in the integral bathroom module, and connecting the reserved ventilation opening, water supply and drainage port and electrical equipment outside;
and sixthly, installing the upper suspended ceiling on the light steel keels and the inner wall plate on the side surface of the integral bathroom after the detection is qualified.
The working process of the example is as follows:
a method for installing an integral bathroom in a steel module integrated house comprises the following specific steps:
1) a steel module integrated house structure manufacturing stage, reserving a sinking space in advance according to the size of the integral bathroom, and arranging integral bathroom lower keels according to the position of a bottom bearing screw rod of the integral bathroom and the direction of a drainage pipeline;
2) a ventilation pipe is welded on a corrugated plate of a module outer wall of the steel module integrated house, and the height of the ventilation opening is higher than the total height of the integrated bathroom;
3) after the steel module integrated house structure is manufactured, before the whole bathroom is installed, the installation of the module body keel, the heat preservation, the water and electricity pipeline and the decorative plate is completed, but the corresponding part of the bathroom is not provided with a floor and a wallboard, and the synchronous water and electricity pipeline is reserved with an interface of the whole bathroom;
4) installing an integral sanitary waterproof chassis, welding and connecting peripheral bearing screw rods and integral sanitary lower beams, adjusting and placing middle part bearing screw rods on prearranged integral sanitary lower keels, and then assembling other components of the integral sanitary;
5) after the integral type bathroom module is installed, connecting equipment such as a reserved ventilation opening, a water supply and drainage opening and electric equipment outside and detecting whether the equipment is qualified or not;
6) and after the detection is qualified, installing the light steel keels and the inner wall boards on the side surfaces of the integral bathroom module, and installing the upper suspended ceiling.
While one embodiment of the present invention has been described in detail, the description is only a preferred embodiment of the present invention, and should not be considered as limiting the scope of the present invention. All the equivalent changes and improvements made according to the application scope of the present invention should still fall within the patent coverage of the present invention.

Claims (5)

1. The utility model provides a steel module integrated house with integral bathroom which characterized in that: the integrated bathroom module comprises a module outer wall corrugated plate, a bottom keel and an integrated bathroom module, wherein the bottom keel comprises a common keel and an integrated bathroom lower keel, the integrated bathroom lower keel is arranged at the lower part of the integrated bathroom module, and the height of the integrated bathroom lower keel is lower than that of the common keel; the integral bathroom module comprises a bathroom waterproof chassis and an inner wall plate, and the inner wall plate and the module outer wall corrugated plate form a bathroom space.
2. The steel module integrated house with integral bathroom of claim 1, characterized in that: a water discharge pipe connector is arranged on the bathroom waterproof chassis, and a water supply pipe connector is arranged on the inner wall plate on one side.
3. The steel module integrated house with integral bathroom of claim 2, characterized in that: and a ventilation pipe connector is arranged on the module outer wall corrugated plate in the bathroom space.
4. The steel module integrated house with integral bathroom of claim 3, characterized in that: the ventilating pipe orifice is higher than the height of the inner wallboard.
5. The steel module integrated house with integral bathroom of claim 4, characterized in that: the bathroom waterproof chassis is connected with the integral bathroom lower keel through a bearing screw rod.
CN201921592291.2U 2019-09-24 2019-09-24 Steel module integrated house with integral bathroom Active CN211396757U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921592291.2U CN211396757U (en) 2019-09-24 2019-09-24 Steel module integrated house with integral bathroom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921592291.2U CN211396757U (en) 2019-09-24 2019-09-24 Steel module integrated house with integral bathroom

Publications (1)

Publication Number Publication Date
CN211396757U true CN211396757U (en) 2020-09-01

Family

ID=72217377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921592291.2U Active CN211396757U (en) 2019-09-24 2019-09-24 Steel module integrated house with integral bathroom

Country Status (1)

Country Link
CN (1) CN211396757U (en)

Similar Documents

Publication Publication Date Title
CN202117202U (en) Light steel keel partition wall structure adaptive to construction errors of building structure
CN205444458U (en) Integrated assembled steel construction building
CN102146706A (en) Lightgage steel joist partition wall adaptive to building error of building structural body and construction method thereof
CN106320521A (en) Pure part plate combined industrialized house assembling structure which can be rapidly erected
CN109518811A (en) A kind of easy-to-mount building structure
CN212613960U (en) Assembled bathroom system
CN106049903A (en) Assembled bathroom and construction method for same
CN211396757U (en) Steel module integrated house with integral bathroom
CN205369954U (en) Positioner is assembled to truss steel pipe
CN202125091U (en) Combined multifunctional toilet
CN103343573A (en) Modular building with high bearing performance and capable of being produced in industrialized mode and being dismantled and installed rapidly
CN206157903U (en) Pure part plate combination industrialization house assembly structure that can build fast
CN210622013U (en) Ribbed reinforced heat-preservation decorative integrated external wall panel connecting joint
CN204627039U (en) A kind of integral vacuum toilet
CN216380168U (en) Integrated double-layer aluminum plate heat insulation unit curtain wall
CN104389442A (en) Ecologic residential house building module
CN213868712U (en) Toilet wallboard
CN102635250B (en) Kiosk villa
CN108547423B (en) Be applicable to wall photovoltaic decorative board installing the system
CN219080545U (en) Clamping structure of assembled floor drain and ground waterproof layer
CN219240784U (en) Assembled single drainage floor drain suitable for overhead ground
CN112237394A (en) Embedded bathtub for assembled toilet and installation method thereof
CN205857814U (en) A kind of assembled toilet
CN201605695U (en) Unit assembled-type curved surface daylighting roof
CN212201437U (en) Photovoltaic assembly energy-saving environment-friendly integrated public toilet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210805

Address after: No.88, West 2nd Road, Airport Economic Zone, Dongli District, Tianjin 300308

Patentee after: MCC TIANGONG GROUP Corp.,Ltd.

Address before: No.88, West 2nd Road, Airport Economic Zone, Dongli District, Tianjin 300308

Patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: MCC TIANGONG (TIANJIN) EQUIPMENT MANUFACTURING Co.,Ltd.

TR01 Transfer of patent right