CN211333866U - High-speed railway beam-making pedestal suitable for unfavorable geology - Google Patents

High-speed railway beam-making pedestal suitable for unfavorable geology Download PDF

Info

Publication number
CN211333866U
CN211333866U CN201921809090.3U CN201921809090U CN211333866U CN 211333866 U CN211333866 U CN 211333866U CN 201921809090 U CN201921809090 U CN 201921809090U CN 211333866 U CN211333866 U CN 211333866U
Authority
CN
China
Prior art keywords
honeycomb
pile
beams
standard section
speed railway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921809090.3U
Other languages
Chinese (zh)
Inventor
李义强
王博
陈叶
贾培基
高松
景娅星
许宏伟
陈士通
赵维刚
王新敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Tiedao University
Original Assignee
Shijiazhuang Tiedao University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Tiedao University filed Critical Shijiazhuang Tiedao University
Priority to CN201921809090.3U priority Critical patent/CN211333866U/en
Application granted granted Critical
Publication of CN211333866U publication Critical patent/CN211333866U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a high-speed railway system roof beam pedestal suitable for unfavorable geology belongs to civil engineering technical field, and system roof beam pedestal includes the tubular pile basis more than two rows, and every calandria pile basis includes the tubular pile that a plurality of intervals set up, all erects the honeycomb beam assembly who arranges side by side on every calandria pile basis, and multirow honeycomb beam assembly passes through the connecting piece and links to each other with the tubular pile, links to each other through the transverse connection roof beam between two liang of adjacent honeycomb beam assemblies. The utility model can be widely applied to geology with various adverse conditions, has good integrity, large structural rigidity and small dead weight, and can effectively control foundation settlement; the mechanical construction degree is high, and the construction quality is easy to control; the honeycomb beam assembly can be repeatedly utilized, the problem of field secondary tillage in the later period is solved, the environmental pollution is reduced, green construction is realized, and the investment and the labor investment of large-scale equipment in the earlier period are reduced; the method has the advantages of no need of digging a foundation pit on site, no pouring of concrete, neat site, low cost, short construction period and early completion and production.

Description

适用于不良地质的高速铁路制梁台座High-speed railway beam pedestal suitable for bad geology

技术领域technical field

本实用新型属于土木工程技术领域,尤其涉及一种适用于不良地质的高速铁路制梁台座。The utility model belongs to the technical field of civil engineering, in particular to a high-speed railway beam-making pedestal suitable for poor geology.

背景技术Background technique

高速铁路预制箱梁因其重量大、表观变形要求苛刻,相应的对制梁台座强度和刚度要求也很高。常规高速铁路制梁台座在桩基承台或扩大基础上设置三、四道钢筋混凝土条形梁或框架梁,在混凝土梁上安装预制箱梁钢模板,绑扎钢筋笼,浇筑混凝土箱梁。这种常规制作方法工期长,耗费大量钢筋和混凝土,极大影响了预制梁场的场建速度。箱梁预制完成后,场地要退耕还田,对制梁台座进行拆除,破拆工作量大,费用高昂,不能重复使用,造成资源大量浪费。The high-speed railway prefabricated box girder has high requirements on the strength and rigidity of the girder pedestal due to its heavy weight and strict apparent deformation requirements. For conventional high-speed railway beam-making pedestals, three or four reinforced concrete strip beams or frame beams are set on the pile foundation caps or enlarged foundations, prefabricated box girder steel formwork is installed on the concrete beams, reinforced cages are bound, and concrete box beams are poured. This conventional production method has a long construction period and consumes a lot of steel bars and concrete, which greatly affects the field construction speed of the prefabricated beam field. After the prefabrication of the box girder is completed, the site must be returned to the farmland, and the girder pedestal will be dismantled.

现在已有使用装配式工字钢钢结构代替常规制梁台座结构,采用工字钢和钢支撑代替条形梁基础,这种方法较常规方法有所改观,但需要大量的预制件,且在稳定计算较为复杂。At present, the prefabricated I-beam steel structure has been used to replace the conventional beam-making pedestal structure, and the I-beam and steel supports are used to replace the strip beam foundation. This method is improved compared with the conventional method, but requires a large number of prefabricated parts, and in Stability calculations are more complicated.

实用新型内容Utility model content

本实用新型的目的是提供一种适用于不良地质的高速铁路制梁台座,旨在解决上述现有技术中混凝土制梁台座工期长耗材多、完工后破拆费用高、资源浪费大,装配式钢结构制梁台座需要大量的预制件、且稳定计算较为复杂的技术问题。The purpose of this utility model is to provide a high-speed railway beam-making pedestal suitable for poor geology, aiming to solve the problems of the above-mentioned prior art concrete beam-making pedestal with long construction period and many consumables, high cost of dismantling after completion, and large waste of resources. The steel structure beam pedestal requires a large number of prefabricated parts, and the stability calculation is relatively complex technical problems.

为解决上述技术问题,本实用新型所采取的技术方案是:In order to solve the above-mentioned technical problems, the technical scheme adopted by the present utility model is:

一种适用于不良地质的高速铁路制梁台座,其特征在于:包括两排以上管桩基础,每排管桩基础包括多个间隔设置的管桩,每排管桩基础上均架设蜂窝梁组件,多排蜂窝梁组件并列布置、且通过连接件与管桩相连;两两相邻的蜂窝梁组件之间通过多个间隔设置的横向连接梁相连。A high-speed railway beam-making pedestal suitable for poor geology is characterized in that: it includes more than two rows of pipe pile foundations, each row of pipe pile foundations includes a plurality of pipe piles arranged at intervals, and honeycomb beam assemblies are erected on each row of pipe pile foundations , and multiple rows of honeycomb beam assemblies are arranged side by side and are connected with the pipe piles through connecting pieces; two adjacent honeycomb beam assemblies are connected by a plurality of horizontal connecting beams arranged at intervals.

优选的,所述蜂窝梁组件包括两端的端部蜂窝梁及中间依次相连的多个标准段蜂窝梁,所述端部蜂窝梁与标准段蜂窝梁的交界处、相邻标准段蜂窝梁的交界处均设置于管桩上,所述端部蜂窝梁与标准段蜂窝梁的端部均通过连接件与管桩固定相连。Preferably, the honeycomb beam assembly includes end honeycomb beams at both ends and a plurality of standard section honeycomb beams connected in sequence in the middle, the junction of the end honeycomb beams and the standard section honeycomb beams, and the junction of adjacent standard section honeycomb beams The end parts of the honeycomb beams and the ends of the standard section honeycomb beams are fixedly connected to the pipe piles through connecting pieces.

优选的,所述端部蜂窝梁包括上翼缘板、下翼缘板和两个腹板,两个腹板并列设置于上翼缘板与下翼缘板之间,两个腹板的中部均水平并列设有多边形孔洞;所述标准段蜂窝梁为工字型,所述标准段蜂窝梁包括上翼缘板、下翼缘板及设置于上翼缘板与下翼缘板之间的腹板,所述腹板的中部水平并列设有多边形孔洞。Preferably, the end honeycomb beam includes an upper flange plate, a lower flange plate and two web plates, the two web plates are arranged side by side between the upper flange plate and the lower flange plate, and the middle part of the two web plates Polygonal holes are arranged in parallel horizontally; the standard section honeycomb beam is I-shaped, and the standard section honeycomb beam includes an upper flange plate, a lower flange plate and a The middle of the web is horizontally juxtaposed with polygonal holes.

优选的,所述端部蜂窝梁与标准段蜂窝梁的腹板外侧间隔竖向设有肋板;所述端部蜂窝梁端部设置的肋板与其末端之间预留连接部,所述横向连接梁的两端与连接部及相邻的肋板配合。Preferably, ribs are arranged vertically at intervals between the end honeycomb beams and the outer sides of the webs of the standard section honeycomb beams; connecting parts are reserved between the ribs arranged at the ends of the end honeycomb beams and their ends, and the transverse Both ends of the connecting beam are matched with the connecting part and the adjacent rib plates.

优选的,所述端部蜂窝梁与标准段蜂窝梁及相邻标准段蜂窝梁间的纵向交界处两侧通过拼接板连接。Preferably, the two sides of the longitudinal junction between the end honeycomb beams, the standard section honeycomb beams and the adjacent standard section honeycomb beams are connected by splicing plates.

优选的,所述横向连接梁包括两排工字钢,两排工字钢上下并列布置在相邻端部蜂窝梁之间及相邻标准段蜂窝梁之间,所述工字钢与端部蜂窝梁及标准段蜂窝梁相互垂直。Preferably, the transverse connecting beams include two rows of I-beams, and the two rows of I-beams are arranged side by side between adjacent end honeycomb beams and between adjacent standard section honeycomb beams. The honeycomb beam and the standard section honeycomb beam are perpendicular to each other.

优选的,所述管桩为PHC管桩,所述PHC管桩分体式成型,所述PHC管桩包括桩身和用于与连接件相连的桩帽,所述桩身包括下节桩和上节桩,所述下节桩与上节桩的交界处距离地面为1±0.1米;所述下节桩与上节桩间通过垫铁焊接固定;所述桩帽设置于上节桩的桩头顶部。Preferably, the pipe piles are PHC pipe piles, the PHC pipe piles are formed in separate parts, the PHC pipe piles include a pile body and a pile cap for connecting with a connector, and the pile body includes a lower section pile and an upper section pile. Section piles, the junction of the lower section piles and the upper section piles is 1±0.1 meters from the ground; the lower section piles and the upper section piles are welded and fixed by a pad iron; the pile caps are arranged on the piles of the upper section piles top of the head.

优选的,所述桩帽为现浇钢筋混凝土;所述连接件包括钢垫板、螺栓和与之配合的螺帽,所述钢垫板预埋于桩帽内,所述螺栓预先贯穿钢垫板并与之焊接固定,所述螺栓的外露端与蜂窝梁组件相连、且与螺帽螺纹连接固定。Preferably, the pile cap is cast-in-place reinforced concrete; the connecting piece includes a steel backing plate, a bolt and a nut matched therewith, the steel backing plate is pre-buried in the pile cap, and the bolt pre-penetrates the steel backing The plate is welded and fixed with it, and the exposed ends of the bolts are connected with the honeycomb beam assembly and are screwed and fixed with the nut.

采用上述技术方案所产生的有益效果在于:与现有技术相比,本实用新型具有结构简单、操作方便快捷的优点;可广泛应用于多种不良条件地质,对持力层起伏变化大的地质条件也能很好适用;整体性好、结构刚度大,自重小,可有效控制基础沉降,确保了箱梁生产质量;机械化施工程度高,施工质量易于控制;蜂窝梁组件可重复利用,避免了拆除工作,从根本上解决了后期场地复耕问题,减少了环境污染,实现了绿色施工在施工前期可不建设混凝土搅拌站,减少前期大型设备的投入量和人工投入;现场不需开挖基坑、不浇筑混凝土、场地整洁、造价低、工期短,提前竣工投产,将产生巨大的经济效益和社会价值。The beneficial effects of adopting the above technical scheme are: compared with the prior art, the utility model has the advantages of simple structure and convenient and quick operation; it can be widely used in a variety of unfavorable geological conditions, and is suitable for geological conditions with large fluctuations in the bearing layer. The conditions can also be well applied; good integrity, high structural rigidity, and low self-weight can effectively control the foundation settlement and ensure the production quality of box girder; high degree of mechanized construction, easy to control construction quality; honeycomb beam components can be reused, avoiding the need for The demolition work fundamentally solves the problem of re-cultivation of the site in the later stage, reduces environmental pollution, and realizes green construction without building a concrete mixing plant in the early stage of construction, reducing the investment of large-scale equipment and manual investment in the early stage; the site does not need to excavate foundation pits , No concrete is poured, the site is clean, the cost is low, the construction period is short, and the construction is completed and put into production ahead of schedule, which will generate huge economic and social value.

附图说明Description of drawings

图1是本实用新型实施例提供的适用于不良地质的高速铁路制梁台座的主视图;1 is a front view of a high-speed railway beam-making pedestal suitable for poor geology provided by an embodiment of the present utility model;

图2是图1的俯视图;Fig. 2 is the top view of Fig. 1;

图3是图1的左视图;Fig. 3 is the left side view of Fig. 1;

图4是图1中端部蜂窝梁的主视图;Fig. 4 is the front view of the end honeycomb beam in Fig. 1;

图5是图4中端部蜂窝梁的截面图;Fig. 5 is the sectional view of the end honeycomb beam in Fig. 4;

图6是图1中标准段蜂窝梁的主视图;Fig. 6 is the front view of the standard section honeycomb beam in Fig. 1;

图7是图6中标准段蜂窝梁的截面图;Fig. 7 is the sectional view of the standard section honeycomb beam in Fig. 6;

图8是图1中连接件的结构示意图;Fig. 8 is the structural representation of the connector in Fig. 1;

图中:1-端部蜂窝梁;2-标准段蜂窝梁;3-管桩;4-连接件;5-横向连接梁;6-上翼缘板;7-下翼缘板;8-腹板;9-多边形孔洞;10-连接部;11-肋板;12-钢垫板;13-螺栓;14-螺帽。In the figure: 1-end honeycomb beam; 2-standard section honeycomb beam; 3-pipe pile; 4-connector; 5-transverse connecting beam; 6-upper flange plate; 7-lower flange plate; 8-web plate; 9-polygonal hole; 10-connection; 11-rib; 12-steel backing plate; 13-bolt; 14-nut.

具体实施方式Detailed ways

下面结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

如图1-3所示的一种适用于不良地质的高速铁路制梁台座,包括两排以上管桩基础,每排管桩基础包括多个间隔设置的管桩3,每排管桩基础上均架设蜂窝梁组件,多排蜂窝梁组件并列布置、且通过连接件4与管桩3相连;两两相邻的蜂窝梁组件之间通过横向连接梁5相连。其中,所述蜂窝梁组件包括两端的端部蜂窝梁1及中间依次相连的多个标准段蜂窝梁2,所述端部蜂窝梁1与标准段蜂窝梁2的交界处、相邻标准段蜂窝梁2的交界处均设置于管桩3上,所述端部蜂窝梁1与标准段蜂窝梁2的端部均通过连接件4与管桩3固定相连。As shown in Figure 1-3, a high-speed railway beam-making pedestal suitable for poor geology includes more than two rows of pipe pile foundations, each row of pipe pile foundations includes a plurality of pipe piles 3 arranged at intervals, and each row of pipe pile foundations Honeycomb beam assemblies are erected on both sides, and multiple rows of honeycomb beam assemblies are arranged side by side and are connected to the pipe piles 3 through connectors 4 ; two adjacent honeycomb beam assemblies are connected by transverse connecting beams 5 . Wherein, the honeycomb beam assembly includes end honeycomb beams 1 at both ends and a plurality of standard section honeycomb beams 2 connected in sequence in the middle. The junctions of the beams 2 are all set on the pipe piles 3 , and the ends of the end honeycomb beams 1 and the standard section honeycomb beams 2 are fixedly connected to the pipe piles 3 through the connecting piece 4 .

在本实用新型的一个具体实施例中,如图4-7所示,所述端部蜂窝梁1包括上翼缘板6、下翼缘板7和两个腹板8,两个腹板8并列设置于上翼缘板6与下翼缘板7之间,两个腹板8的中部均水平并列设有多边形孔洞9;所述标准段蜂窝梁2为工字型,所述标准段蜂窝梁2包括上翼缘板6、下翼缘板7及设置于上翼缘板6与下翼缘板7之间的腹板8,所述腹板8的中部水平并列设有多边形孔洞9。In a specific embodiment of the present invention, as shown in FIGS. 4-7 , the end honeycomb beam 1 includes an upper flange plate 6 , a lower flange plate 7 and two webs 8 . The two webs 8 Arranged side by side between the upper flange plate 6 and the lower flange plate 7, the middle of the two webs 8 are horizontally juxtaposed with polygonal holes 9; the standard section honeycomb beam 2 is I-shaped, and the standard section honeycomb The beam 2 includes an upper flange plate 6 , a lower flange plate 7 and a web 8 arranged between the upper flange plate 6 and the lower flange plate 7 , and a polygonal hole 9 is arranged horizontally in the middle of the web 8 .

进一步优化上述技术方案,如图4、6所示,所述端部蜂窝梁1与标准段蜂窝梁2的腹板8外侧间隔竖向设有肋板11,相邻两个肋板11之间的腹板8上布设两个多边形孔洞9,所述肋板11设置于腹板8上相邻两个多边形孔洞9之间;所述端部蜂窝梁1端部设置的肋板11与其末端之间预留连接部10,所述横向连接梁5的两端与连接部10及相邻的肋板11配合,即横向连接梁5的两端同时与连接部10及其相邻的肋板连接固定。另外,可在上翼缘板顶部设置调节钢板,调节钢板与上翼缘板通过螺栓连接,通过调节钢板与顶部底模板的配合来调节蜂窝梁组件的反拱度,保证了调试精度,缩短了调试时间。The above technical solution is further optimized. As shown in Figures 4 and 6, the end honeycomb beam 1 and the outer side of the web 8 of the standard section honeycomb beam 2 are vertically provided with rib plates 11, and between two adjacent rib plates 11 Two polygonal holes 9 are arranged on the web 8, and the rib 11 is arranged between the adjacent two polygonal holes 9 on the web 8; the rib 11 provided at the end of the end honeycomb beam 1 and its end A connecting part 10 is reserved between the two ends of the horizontal connecting beam 5, and the two ends of the horizontal connecting beam 5 are matched with the connecting part 10 and the adjacent rib plate 11, that is, the two ends of the horizontal connecting beam 5 are connected with the connecting part 10 and its adjacent rib plate at the same time. fixed. In addition, an adjustment steel plate can be set on the top of the upper flange plate, and the adjustment steel plate and the upper flange plate are connected by bolts. Debug time.

为了保证蜂窝梁组件的整体稳定性,所述端部蜂窝梁1与标准段蜂窝梁2之间及相邻标准段蜂窝梁2间的纵向交界处两侧通过拼接板连接。In order to ensure the overall stability of the honeycomb beam assembly, both sides of the longitudinal junction between the end honeycomb beam 1 and the standard section honeycomb beam 2 and between the adjacent standard section honeycomb beams 2 are connected by splicing plates.

在本实用新型的一个具体实施例中,如图2、3所示,所述横向连接梁5包括两排工字钢,两排工字钢上下并列布置在相邻端部蜂窝梁1之间及相邻标准段蜂窝梁2之间,所述工字钢与端部蜂窝梁1及标准段蜂窝梁2相互垂直。In a specific embodiment of the present invention, as shown in FIGS. 2 and 3 , the transverse connecting beam 5 includes two rows of I-beams, and the two rows of I-beams are arranged side by side between the adjacent end honeycomb beams 1 And between the adjacent standard section honeycomb beams 2, the I-beam is perpendicular to the end honeycomb beams 1 and the standard section honeycomb beams 2.

在本实用新型的一个具体实施例中,所述管桩3为PHC管桩(预应力高强度混凝土管桩),所述PHC管桩为分体式成型,所述PHC管桩包括桩身和用于与连接件相连的桩帽,所述桩身包括下节桩和上节桩,所述下节桩与上节桩的交界处距离地面约1米(上下浮动0.1米);所述下节桩与上节桩间通过垫铁焊接固定;所述桩帽设置于上节桩的桩头顶部。其中,两端采用直径0.4m、桩长20m的PHC管桩基础,中间段采用直径0.4m桩长15m的PHC管桩基础,根据施工进度要求和多方面比较,管桩施工采用静压法施工。In a specific embodiment of the present invention, the pipe pile 3 is a PHC pipe pile (prestressed high-strength concrete pipe pile), the PHC pipe pile is formed in a split type, and the PHC pipe pile includes a pile body and a For the pile cap connected to the connector, the pile body includes a lower section pile and an upper section pile, and the junction of the lower section pile and the upper section pile is about 1 meter away from the ground (floating up and down by 0.1 meters); The pile and the upper section pile are welded and fixed by a pad iron; the pile cap is arranged on the top of the pile head of the upper section pile. Among them, the PHC pipe pile foundation with a diameter of 0.4m and a pile length of 20m is used at both ends, and the PHC pipe pile foundation with a diameter of 0.4m and a pile length of 15m is used in the middle section. According to the construction progress requirements and various comparisons, the pipe pile construction adopts the static pressure method. .

其中,所述桩帽为现浇钢筋混凝土;如图1、8所示,所述连接件4包括钢垫板12、螺栓13和与之配合的螺帽14,所述钢垫板12预埋于桩帽内,所述螺栓13预先贯穿钢垫板12并与之焊接固定,所述螺栓13的外露端贯穿蜂窝梁组件的下翼缘板7与螺帽14螺纹连接。Wherein, the pile cap is cast-in-place reinforced concrete; as shown in Figures 1 and 8 , the connector 4 includes a steel backing plate 12, a bolt 13 and a nut 14 matched therewith, and the steel backing plate 12 is pre-buried In the pile cap, the bolts 13 penetrate the steel backing plate 12 in advance and are fixed by welding, and the exposed ends of the bolts 13 penetrate the lower flange plate 7 of the honeycomb beam assembly and are threadedly connected to the nut 14 .

由于PHC管桩是空心圆柱形先张法预应力钢筋混凝土预制桩,以往多用于沿海地区软土地基工程,但随着现代高速铁路的发展,传统制存梁台座基础的软基处置方式已无法满足使用需求,采用PHC管桩(高强度预应力混凝土管桩)作为制存梁台座基础是近几年一项新的软基处理方式,并且在国内大型铁路项目上广泛应用,施工技术逐步完善。未来桥梁建设应该更注重技术创新,更注重在桥梁工程中贯彻绿色环保理念,更注重桥梁的精细化设计和施工。Since PHC pipe piles are hollow cylindrical pretensioned prestressed reinforced concrete precast piles, they were mostly used in soft soil foundation projects in coastal areas in the past. To meet the needs of use, the use of PHC pipe piles (high-strength prestressed concrete pipe piles) as the foundation for making beams and pedestals is a new soft foundation treatment method in recent years, and is widely used in large-scale domestic railway projects, and the construction technology is gradually improved. . In the future, bridge construction should pay more attention to technological innovation, to implement the concept of green environmental protection in bridge engineering, and to pay more attention to the refined design and construction of bridges.

上述适用于不良地质的高速铁路制梁台座的施工方法,包括以下步骤:The above-mentioned construction method for the high-speed railway beam pedestal suitable for poor geology includes the following steps:

(一)平整场地:满足测量放线和施工要求,根据预制梁场总平面布置图,对管桩3桩位进行施工测量并作出标记,然后进行施工桩位放桩。(1) Leveling the site: To meet the requirements of measurement, lay-out and construction, according to the general layout plan of the prefabricated beam yard, carry out construction measurement and mark the 3 pile positions of the pipe pile, and then carry out the construction pile position.

根据梁场地质的勘察资料,梁场区域内地层自上而下划分为耕土、粉质黏土、细砂、风化泥岩这几个工程地质层,根据制梁台座总平面图上各部分的位置关系,对预设区域进行场地清理,确定桩基位置进行施工测量并作出标记,然后进行施工桩位放桩,桩位偏差不得大于10mm。According to the geological survey data of Liangchang, the strata in the Liangchang area are divided into several engineering geological layers: cultivated soil, silty clay, fine sand and weathered mudstone from top to bottom. Clean up the site in the preset area, determine the position of the pile foundation for construction measurement and make a mark, and then place the pile at the construction pile position. The deviation of the pile position shall not be greater than 10mm.

(二)管桩就位:打桩设备进场,安装调试后移机至桩位处就位,将检测合格的管桩运送至桩位沉桩点;锤击(或静压)沉桩,按设计要求进行接桩、送桩。(2) Pipe piles in place: the piling equipment enters the site, and after installation and debugging, move the machine to the pile position, and transport the qualified pipe piles to the pile driving point; hammer (or static pressure) pile driving, press The design requires pile connection and pile delivery.

具体沉桩步骤如下:The specific pile sinking steps are as follows:

(1)打桩设备进场安装调试后,移至需要施打的位置,启动打桩设备的平台支腿油缸,调整水平;(1) After the piling equipment enters the site for installation and debugging, move it to the position where it needs to be driven, start the platform outrigger cylinder of the piling equipment, and adjust the level;

(2)起吊下节桩,使桩尖垂直对准桩位中心,缓慢放下插入土中,按照先内后外、先中间后两边的原则进行编号,按编号顺序进行压桩,压桩过程中要控制施压速度,详细记录每入土两米时压力表的压力值;(2) Lift the lower section pile so that the tip of the pile is vertically aligned with the center of the pile position, slowly lower it into the soil, number it according to the principle of first inside, then outside, first in the middle and then both sides, and press the pile in the order of numbering. To control the pressure application speed, record the pressure value of the pressure gauge every two meters of soil in detail;

(3)下节桩的桩头距地面一米左右时停止压桩,吊机吊起上节桩,开始对位接桩;接桩时上节桩与下节桩的轴线一致,上下桩节间的缝隙应用铁垫片垫密焊牢,焊接时应采取对称施焊,以减少焊缝变形引起节点弯曲;(3) Stop pressing the pile when the pile head of the lower section pile is about one meter away from the ground, and the crane lifts the upper section pile and starts to align the piles; The gap between them should be tightly welded with iron gaskets, and symmetrical welding should be adopted during welding to reduce the bending of the joints caused by the deformation of the welding seam;

(4)静压沉桩完成后终止压桩,依据成品桩质量验收标准进行桩质量检验。(4) After the static pressure pile driving is completed, the pile pressing shall be terminated, and the pile quality inspection shall be carried out according to the quality acceptance standard of the finished pile.

(三)管桩的桩帽浇注:验桩后浇注钢筋混凝土桩帽,按图纸设计要求将连接件的钢垫板12预埋在桩帽内,并焊接螺栓13的钢垫板12与管桩3的桩头全部焊接在一起;钢垫板为480mm×480mm的钢板,共布置4个直径为20mm的螺栓。(3) Pile cap pouring of pipe piles: pour reinforced concrete pile caps after the pile inspection, pre-embed the steel backing plate 12 of the connector in the pile cap according to the design requirements of the drawings, and weld the steel backing plate 12 of the bolt 13 to the pipe pile The pile heads of 3 are all welded together; the steel backing plate is a 480mm×480mm steel plate, and a total of 4 bolts with a diameter of 20mm are arranged.

(四)安装蜂窝梁组件:待管桩3台座养护完成之后,进行蜂窝梁组件的拼装。按照图纸放置端部蜂窝梁1及多个标准段蜂窝梁2,端部蜂窝梁1及标准段蜂窝梁2的端部均通过连接件4与管桩3连接固定;相邻两排蜂窝梁组件之间通过横向连接梁5连接固定。图2所示的实施例中为三排蜂窝梁组件,纵向每排蜂窝梁组件的长度为端部蜂窝梁+n段标准段蜂窝梁+端部蜂窝梁=4.25m+n*5m+4.25m。(4) Installation of honeycomb beam components: After the maintenance of the three pedestals of the pipe piles is completed, the honeycomb beam components are assembled. Place the end honeycomb beam 1 and a plurality of standard section honeycomb beams 2 according to the drawings, and the ends of the end honeycomb beam 1 and the standard section honeycomb beam 2 are connected and fixed with the pipe pile 3 through the connector 4; the adjacent two rows of honeycomb beam components They are connected and fixed by transverse connecting beams 5. In the embodiment shown in Figure 2, there are three rows of honeycomb beam assemblies, and the length of each longitudinal row of honeycomb beam assemblies is end honeycomb beam + n standard section honeycomb beam + end honeycomb beam=4.25m+n*5m+4.25m .

其中,端部蜂窝梁1及标准段蜂窝梁2与管桩基础通过螺栓13进行连接,端部蜂窝梁1与标准段蜂窝梁2之间、两两相邻的标准段蜂窝梁2之间纵向通过双侧拼接板对接连接,横向连接梁5采用上下两道工字钢进行连接固定,保持稳定。Among them, the end honeycomb beam 1 and the standard section honeycomb beam 2 are connected with the pipe pile foundation by bolts 13, and the longitudinal direction between the end honeycomb beam 1 and the standard section honeycomb beam 2 and between two adjacent standard section honeycomb beams 2 Through the butt connection of double-sided splicing plates, the transverse connecting beam 5 is connected and fixed by two upper and lower I-beams to maintain stability.

本实用新型区别于现有技术的优势在于:The advantages of the utility model different from the prior art are:

(1)工厂预制PHC管桩与相同直径的沉管灌注桩、钻孔灌注桩和人工挖孔桩相比,其承载力设计值高、质量可靠,可广泛应用于淤泥质黏土、季节性冻土、湿陷性黄土等多种不良条件地质,对持力层起伏变化大、包含软弱中间层的地质条件也能很好适用。因此采用PHC管桩代替传统的桩基础,运输吊装方便,接桩快捷,机械化施工程度高,操作简单,易控制施工质量。(1) Compared with the same diameter immersed cast-in-place piles, bored cast-in-place piles and artificial digging piles, the factory prefabricated PHC pipe piles have high bearing capacity design values and reliable quality, and can be widely used in silty clay, seasonal frozen piles, etc. Soil, collapsible loess and other unfavorable geological conditions can also be well applied to the geological conditions with large fluctuations in the bearing layer and including weak intermediate layers. Therefore, the use of PHC pipe piles instead of traditional pile foundations has the advantages of convenient transportation and hoisting, quick pile connection, high degree of mechanized construction, simple operation and easy control of construction quality.

(2)PHC管桩和蜂窝梁组件组装成型的制梁台座,整体性好、结构刚度大,可有效控制基础沉降,确保了制梁台座的生产质量。蜂窝梁组件的重复利用,避免了台座基础拆除工作,从根本上解决了后期场地复耕的技术问题,减少了环境污染,实现了绿色施工。(2) The beam-making pedestal formed by the assembly of the PHC pipe pile and the honeycomb beam assembly has good integrity and high structural rigidity, which can effectively control the foundation settlement and ensure the production quality of the beam-making pedestal. The reuse of honeycomb beam components avoids the dismantling of the pedestal foundation, fundamentally solves the technical problem of site restoration in the later stage, reduces environmental pollution, and realizes green construction.

(3)在蜂窝梁组件的上翼缘板顶部可直接放置调节钢板来调节蜂窝梁组件的反拱度,保证了调试精度,缩短了调试时间。(3) Adjusting steel plates can be directly placed on the top of the upper flange plate of the honeycomb beam assembly to adjust the reverse camber of the honeycomb beam assembly, which ensures the debugging accuracy and shortens the debugging time.

(4)PHC管桩和蜂窝梁组件组装成型的制梁台座,现场不需开挖基坑、不浇筑混凝土、没有养护周期、场地整洁、施工速度快、造价低、工期短,提前竣工投产,将产生巨大的经济效益和社会价值。(4) The beam-making pedestal formed by the assembly of PHC pipe piles and honeycomb beam components does not require excavation of foundation pits, no concrete pouring, no maintenance period, clean site, fast construction speed, low cost, short construction period, and completed and put into production ahead of schedule. It will produce huge economic and social value.

(5)采用PHC管桩和蜂窝梁组件组装成型的制梁台座,在施工前期可不建设混凝土搅拌站,减轻了前期混凝土拌合站建设和生产压力,减少前期大型设备的投入量和人工投入,便于管理。(5) The beam-making pedestal assembled with PHC pipe piles and honeycomb beam components can not build a concrete mixing station in the early stage of construction, which reduces the construction and production pressure of the concrete mixing station in the early stage, and reduces the investment of large-scale equipment and labor in the early stage. Easy to manage.

综上所述,本实用新型提供的制梁台座具有以下优点和积极效果:To sum up, the beam-making pedestal provided by the present utility model has the following advantages and positive effects:

该制梁台座可广泛应用于淤泥质黏土、季节性冻土、湿陷性黄土等多种不良条件地质,对持力层起伏变化大、包含软弱中间层的地质条件也能很好适用;PHC管桩和蜂窝梁组件组装成型的制梁台座,整体性好、结构刚度大,自重小,可有效控制基础沉降,确保了箱梁的生产质量;预制PHC管桩和定制端部蜂窝梁及标准段蜂窝梁,运输吊装方便,接桩快捷,机械化施工程度高,操作简单,施工质量易于控制;蜂窝梁组件的重复利用,避免了台座基础拆除工作,从根本上解决了后期场地复耕的技术问题,减少了环境污染,实现了绿色施工;在蜂窝梁组件的上翼缘板顶部放置调节钢板,可缩短预拱度调试时间;标准段蜂窝梁中间的多边形孔洞,工作人员可以进入箱梁底部,进行操作,方便快捷,而且孔洞尺寸可以根据要求进行定制。另外,在施工前期可不建设混凝土搅拌站,减轻了前期混凝土拌合站建设和生产压力,减少前期大型设备的投入量和人工投入,便于管理;现场不需开挖基坑、不浇筑混凝土、没有养护周期、场地整洁、施工速度快、造价低、工期短,提前竣工投产,将产生巨大的经济效益和社会价值。The beam-making pedestal can be widely used in silt clay, seasonal frozen soil, collapsible loess and other unfavorable geological conditions. The beam-making pedestal assembled from the pipe pile and the honeycomb beam assembly has good integrity, high structural rigidity and low self-weight, which can effectively control the foundation settlement and ensure the production quality of the box beam; prefabricated PHC pipe piles and customized end honeycomb beams and standard The section of honeycomb beam is convenient for transportation and hoisting, quick to connect piles, high degree of mechanized construction, simple operation, and easy to control construction quality; the reuse of honeycomb beam components avoids the dismantling of the pedestal foundation, and fundamentally solves the technology of re-cultivation in the later stage. It reduces environmental pollution and realizes green construction; the adjustment steel plate is placed on the top of the upper flange plate of the honeycomb beam assembly, which can shorten the pre-camber debugging time; the polygonal hole in the middle of the honeycomb beam of the standard section allows the staff to enter the bottom of the box beam , It is convenient and quick to operate, and the hole size can be customized according to requirements. In addition, it is not necessary to build a concrete mixing plant in the early stage of construction, which reduces the construction and production pressure of the concrete mixing plant in the early stage, reduces the input of large-scale equipment and labor in the early stage, and facilitates management; there is no need to excavate foundation pits, pour concrete, and Maintenance cycle, clean site, fast construction speed, low cost, short construction period, and early completion and production will generate huge economic and social value.

在上面的描述中阐述了很多具体细节以便于充分理解本实用新型,但是本实用新型还可以采用其他不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本实用新型内涵的情况下做类似推广,因此本实用新型不受上面公开的具体实施例的限制。In the above description, many specific details are set forth in order to fully understand the present utility model, but the present utility model can also be implemented in other ways different from those described herein, and those skilled in the art can do so without departing from the connotation of the present utility model. Therefore, the present invention is not limited by the specific embodiments disclosed above.

Claims (8)

1. The utility model provides a high-speed railway system beam pedestal suitable for unfavorable geology which characterized in that: the device comprises more than two rows of pipe pile foundations, wherein each row of pipe pile foundations comprises a plurality of pipe piles arranged at intervals, a honeycomb beam assembly is erected on each row of pipe pile foundations, and a plurality of rows of honeycomb beam assemblies are arranged in parallel and connected with the pipe piles through connecting pieces; every two adjacent honeycomb beam assemblies are connected through a plurality of transverse connecting beams arranged at intervals.
2. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 1, wherein: the utility model discloses a tubular pile, including the tip honeycomb roof beam at both ends and the middle a plurality of standard section honeycomb roof beams that link to each other in proper order of honeycomb roof beam subassembly, tip honeycomb roof beam all sets up on the tubular pile with juncture of standard section honeycomb roof beam, juncture of adjacent standard section honeycomb roof beam, tip honeycomb roof beam all links to each other with the tubular pile is fixed through the connecting piece with the tip of standard section honeycomb roof beam.
3. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 2, wherein: the end honeycomb beam comprises an upper flange plate, a lower flange plate and two webs, the two webs are arranged between the upper flange plate and the lower flange plate in parallel, and polygonal holes are horizontally arranged in parallel in the middles of the two webs; the standard section honeycomb beam is I-shaped, the standard section honeycomb beam comprises an upper flange plate, a lower flange plate and a web plate arranged between the upper flange plate and the lower flange plate, and polygonal holes are horizontally arranged in the middle of the web plate in parallel.
4. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 3, wherein: ribbed plates are vertically arranged on the outer sides of the webs of the end honeycomb beam and the standard section honeycomb beam at intervals; and a connecting part is reserved between the rib plate arranged at the end part of the end honeycomb beam and the tail end of the end honeycomb beam, and two ends of the transverse connecting beam are matched with the connecting part and the adjacent rib plate.
5. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 2, wherein: and the two sides of the longitudinal junction between the end honeycomb beam and the standard section honeycomb beam and between the end honeycomb beam and the adjacent standard section honeycomb beam are connected through splice plates.
6. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 2, wherein: the transverse connecting beam comprises two rows of I-shaped steel, the two rows of I-shaped steel are arranged between adjacent end honeycomb beams and between adjacent standard section honeycomb beams in parallel up and down, and the I-shaped steel is perpendicular to the end honeycomb beams and the standard section honeycomb beams.
7. A high speed railway girder fabrication bench adapted for use in unfavorable geology according to any one of claims 1 to 6, wherein: the pipe pile is a PHC pipe pile, the PHC pipe pile is formed in a split mode, the PHC pipe pile comprises a pile body and a pile cap used for being connected with a connecting piece, the pile body comprises a lower pile section and an upper pile section, and the distance between the junction of the lower pile section and the upper pile section and the ground is 1 +/-0.1 m; the lower pile section and the upper pile section are welded and fixed through sizing blocks; the pile cap is arranged at the top of the pile head of the upper section of pile.
8. A high speed railway beam forming pedestal adapted for use in unfavorable geology as set forth in claim 7, wherein: the pile cap is cast-in-place reinforced concrete; the connecting piece includes steel backing plate, bolt and complex nut with it, the steel backing plate is pre-buried in the pile cap, the bolt runs through the steel backing plate in advance and welded fastening with it, the end that exposes of bolt links to each other with the honeycomb roof beam subassembly, and is fixed with nut threaded connection.
CN201921809090.3U 2019-10-25 2019-10-25 High-speed railway beam-making pedestal suitable for unfavorable geology Expired - Fee Related CN211333866U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921809090.3U CN211333866U (en) 2019-10-25 2019-10-25 High-speed railway beam-making pedestal suitable for unfavorable geology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921809090.3U CN211333866U (en) 2019-10-25 2019-10-25 High-speed railway beam-making pedestal suitable for unfavorable geology

Publications (1)

Publication Number Publication Date
CN211333866U true CN211333866U (en) 2020-08-25

Family

ID=72129890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921809090.3U Expired - Fee Related CN211333866U (en) 2019-10-25 2019-10-25 High-speed railway beam-making pedestal suitable for unfavorable geology

Country Status (1)

Country Link
CN (1) CN211333866U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110666953A (en) * 2019-10-25 2020-01-10 石家庄铁道大学 High-speed railway beam-making pedestal suitable for bad geology and its construction method
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110666953A (en) * 2019-10-25 2020-01-10 石家庄铁道大学 High-speed railway beam-making pedestal suitable for bad geology and its construction method
CN115091607A (en) * 2022-07-14 2022-09-23 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal
CN115091607B (en) * 2022-07-14 2024-01-16 华能铜川照金煤电有限公司 Construction method for accurately positioning pre-camber of precast beam pedestal

Similar Documents

Publication Publication Date Title
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN112177857B (en) Prestressed hollow sandwich steel pipe concrete lattice type hybrid tower and production and installation method thereof
CN110055895B (en) Economical and practical steel trestle construction method
CN110344335B (en) Method for constructing steel trestle, initial platform and cofferdam in bridge construction process
CN114411761B (en) Advanced pre-supporting system and method for subway tunnel to be built in new building construction
CN211333866U (en) High-speed railway beam-making pedestal suitable for unfavorable geology
CN112854004A (en) Fish-bellied box girder column type support construction method
CN111622091B (en) Stress test method for prefabricated bridge pier
CN113622316A (en) Steel truss girder multipoint traction type pushing construction system and construction method thereof
CN109653101B (en) Method for erecting trestle for bridge construction
CN108612122B (en) A kind of super large plane size caisson foundation structure and its construction method
CN214459689U (en) Cast-in-place box girder support of weak soil foundation
CN212000648U (en) Prefabricated beam frame facility work machine lateral shifting braced system
CN107227688B (en) Pier hangs bottom technique
CN110666953A (en) High-speed railway beam-making pedestal suitable for bad geology and its construction method
CN114263114A (en) Construction system and construction method of large-section steel box girder
CN209816632U (en) Arch foot structure for special-shaped space arch bridge
CN220433439U (en) Splicing device for splicing wide prefabricated T-beam bridge
CN105421251B (en) Plate-girder jacking supporting mechanism, plate-girder jacking supporting tool
CN111188281A (en) Transverse moving support system for prefabricated beam frame facility working machinery and construction method
CN117488647A (en) Combined beam suitable for upper and lower two-layer steel truss web rods of overhead in urban area and construction method
CN110924312A (en) Construction method of steel trestle
CN211735374U (en) Reinforcement structure of prestressing force tubular pile defect
CN101886370B (en) Steel massive pillar beam for bridge pier
CN116607558A (en) Prefabricated assembled foundation of main transformer equipment of transformer substation and construction method of prefabricated assembled foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200825

CF01 Termination of patent right due to non-payment of annual fee