CN211219446U - Convenient steel pipe welding equipment for building of adjusting - Google Patents

Convenient steel pipe welding equipment for building of adjusting Download PDF

Info

Publication number
CN211219446U
CN211219446U CN201921745734.7U CN201921745734U CN211219446U CN 211219446 U CN211219446 U CN 211219446U CN 201921745734 U CN201921745734 U CN 201921745734U CN 211219446 U CN211219446 U CN 211219446U
Authority
CN
China
Prior art keywords
bolt
movable block
steel pipe
bottom plate
slide bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921745734.7U
Other languages
Chinese (zh)
Inventor
韩承凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Zhonger Construction Engineering Co ltd
Original Assignee
Hubei Zhonger Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Zhonger Construction Engineering Co ltd filed Critical Hubei Zhonger Construction Engineering Co ltd
Priority to CN201921745734.7U priority Critical patent/CN211219446U/en
Application granted granted Critical
Publication of CN211219446U publication Critical patent/CN211219446U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a convenient steel pipe welding equipment for building that adjusts in building field, including landing leg, first bolt, second bolt, stopper, slide bar, rubber slab, ball, bottom plate, nut, movable block, dovetail block, screw, vertical chute and horizontal spout, bottom plate middle-end department symmetry is equipped with the ball, horizontal spout has been seted up symmetrically on the bottom plate, horizontal spout sliding connection has the movable block, be equipped with the dovetail block on the lateral wall around the movable block, the dovetail block slides in horizontal spout, set up the screw of vertical direction on the movable block, screw threaded connection has the second bolt on the movable block, the upper end is rotated and is connected with the stopper in the second bolt, the stopper lateral wall is fixedly connected with the slide bar, fixedly connected with rubber slab on the outer wall of slide bar, vertical spout has been seted up on the movable block lateral wall, the slide bar slides in vertical spout, another lateral wall of movable block rotates and is linked with first bolt, the utility model discloses simple structure, height and width regulation are convenient, make the fixed effectual of steel pipe.

Description

Convenient steel pipe welding equipment for building of adjusting
Technical Field
The utility model relates to a building field specifically is a convenient steel pipe welding equipment for building of adjusting.
Background
Tubing is the material used to make pipe fittings. Different pipes are used for different pipe fittings, and the quality of the pipes directly determines the quality of the pipe fittings. The pipe is a necessary material for building engineering, and commonly used materials comprise a water supply pipe, a water discharge pipe, a gas pipe, a heating pipe, an electric wire conduit, a rainwater pipe and the like. With the development of science and technology, the pipes used in home decoration also go through the development process of common cast iron pipes → cement pipes → (reinforced concrete pipes, asbestos cement pipes) → (nodular cast iron pipes), galvanized steel pipes → plastic pipes and aluminum-plastic composite pipes.
In the horizontal butt welding technology of round pipes, in view of the fact that construction conditions on site are often simple and crude, factory-used advanced automatic equipment cannot be used, in the process of site construction, the most common method is to directly place two round pipes to be horizontally butted on a flat ground for welding, and the traditional welding method has the operation and operation
The welding process is inconvenient, time and labor are wasted, and the welding quality is affected by overlarge welding deformation and overlarge internal stress of the round pipe during welding. At present, the steel pipe welding frame appears on the construction site, but the steel pipe welding frame is inconvenient to adjust during cutting and has poor adaptability.
For example, chinese patent application number is CN201720469413.3 long steel tube welding frame, including support, backup pad and bolt, the support top is provided with the backup pad, and the spaced apart a plurality of through-holes that are equipped with in the backup pad, the inside nut that is provided with of through-hole is provided with the bolt on the nut, and the bolt encloses into spacing district, the utility model provides an among the prior art inconvenient technical problem of steel pipe welding, but the width can not be adjusted, and the rubber slab is inconvenient during the altitude mixture control simultaneously.
Based on this, the utility model designs a specifically be a convenient steel pipe welding equipment for building of adjusting to solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a convenient steel pipe welding equipment for building of adjusting to although solving and proposing in the above-mentioned background art can play fixed steel pipe, but the width can not be adjusted, the inconvenient problem of rubber slab during altitude mixture control simultaneously.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a convenient steel pipe welding equipment for building of adjusting, includes landing leg, first bolt, second bolt, stopper, slide bar, rubber slab, ball, bottom plate, nut, movable block, dovetail block, screw, perpendicular spout and horizontal spout, bottom plate middle-end department symmetry is equipped with the ball, the symmetry is seted up on the bottom plate
The sliding block is provided with a horizontal sliding groove, the horizontal sliding groove is connected with a movable block in a sliding way, the front side wall and the rear side wall of the movable block are provided with dovetail blocks, the dovetail blocks slide in the horizontal sliding groove, the movable block is provided with a screw hole in the vertical direction, the screw hole on the movable block is in threaded connection with a second bolt, the upper end of the second bolt is rotatably connected with a limiting block, the outer side wall of the limiting block is fixedly connected with a sliding rod,
the outer wall of the sliding rod is fixedly connected with a rubber plate, a vertical sliding groove is formed in the side wall of the movable block, the sliding rod slides in the vertical sliding groove, and the other side wall of the movable block is rotatably connected with a first bolt.
Preferably, the bottom of the bottom plate is symmetrically and fixedly connected with inclined support legs.
Preferably, the material of the ball is steel, and the ball rotates in the limit rod.
Preferably, the horizontal sliding groove is in the same straight line with the ball.
Preferably, the first bolt is in threaded connection with the base plate.
Preferably, the first bolt and the second bolt are both fixedly connected with nuts.
Compared with the prior art, the beneficial effects of the utility model are that: 1. the utility model discloses a first bolt rotates and promotes the movable block and remove for the device is fit for the pipeline of different diameters fixed with the support, the welding of being convenient for.
2. The utility model discloses a second bolt rotates, makes the slide bar slide at the movable block, and adjustable rubber slab is the height on the bottom plate for it is convenient to install altitude mixture control.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a top view of the present invention;
FIG. 3 is a schematic view of the movable block structure of the present invention;
fig. 4 is a schematic view of a second bolt structure of the present invention;
in the drawings, the components represented by the respective reference numerals are listed below:
1. the supporting leg 2, the first bolt 3, the second bolt 4, the limiting block 5, the sliding rod 6, the rubber plate 7, the ball 8, the bottom plate 9, the nut 10, the movable block 101, the dovetail block 102, the screw hole 103, the vertical sliding groove 11 and the horizontal sliding groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, those skilled in the art can obtain the results without creative labor
All other embodiments are within the scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a conveniently-adjusted steel pipe welding device for a building comprises supporting legs 1, first bolts 2, second bolts 3, limiting blocks 4, sliding rods 5, rubber plates 6, balls 7, a bottom plate 8, nuts 9, a movable block 10, dovetail blocks 101, screw holes 102, vertical sliding grooves 103 and horizontal sliding grooves 11, wherein the balls 7 are symmetrically arranged at the middle end of the bottom plate 8, the horizontal sliding grooves 11 are symmetrically formed in the bottom plate 8, the horizontal sliding grooves 11 are slidably connected with the movable block 10, the dovetail blocks 101 are arranged on the front side wall and the rear side wall of the movable block 10, the dovetail blocks 101 slide in the horizontal sliding grooves 11, the movable block 10 is provided with the screw holes 102 in the vertical direction, the screw holes 102 in the movable block 10 are in threaded connection with the second bolts 3, the upper ends of the second bolts 3 are rotatably connected with the limiting blocks 4, and the outer side walls of the, the outer wall of the sliding rod 5 is fixedly connected with a rubber plate 6, the side wall of the movable block 10 is provided with a vertical sliding groove 103, the sliding rod 5 slides in the vertical sliding groove 103, and the other side wall of the movable block 10 is rotatably connected with a first bolt 2.
Wherein, the landing leg 1 of 8 bottom symmetries fixedly connected with slopes of bottom plate, the material of ball 7 are the steel, and ball 7 is at the internal rotation of restriction pole, and horizontal spout 11 and ball 7 are on the same straight line, first bolt 2 and 8 threaded connection of bottom plate, equal fixedly connected with nut 9 on first bolt 2 and the second bolt 3.
One specific application of this embodiment is: the first bolt 2 is rotated according to the diameter of the pipe to be welded, the first bolt 2 rotates on the bottom plate 8 in a threaded mode, and the first bolt 2 is rotatably connected with the movable block 10, so that the movable block 10 is pushed to move leftwards or rightwards by the rotation of the first bolt 2, and the distance between the rubber plates 6 connected with the two sliding rods 5 is suitable for the diameter of the pipe to be welded; meanwhile, the second bolt 3 is rotated, the second bolt 3 is in threaded connection with the movable block 10, the second bolt 3 rotates, and the rubber plate 6 connected with the sliding rod 5 is driven to move downwards or upwards, so that the height of the rubber plate 6 is suitable for the height of a pipe to be welded; put tubular product between the rubber slab 6, rotate first bolt 2 and second bolt 3 respectively and finely tune for the device is fixed tubular product, makes tubular product put the most suitable welded condition.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the present invention disclosed above are intended only to help illustrate the present invention. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, to thereby enable others skilled in the art to best understand the invention for and utilize the invention. The present invention is limited only by the claims and their full scope and equivalents.

Claims (6)

1. The utility model provides a convenient steel pipe welding equipment for building of adjusting, includes landing leg, first bolt, second bolt, stopper, slide bar, rubber slab, ball, bottom plate, nut, movable block, dovetail block, screw, perpendicular spout and horizontal spout, its characterized in that: the utility model discloses a bolt, including bottom plate, horizontal spout, movable block, dovetail block, stopper lateral wall, slide bar, fixedly connected with rubber slab on the outer wall of slide bar, the symmetry of bottom plate middle-end department is equipped with the ball, horizontal spout has been seted up to the symmetry on the bottom plate, horizontal spout sliding connection has the movable block, be equipped with the dovetail block around the movable block on the lateral wall, the dovetail block slides in horizontal spout, set up the screw of vertical direction on the movable block, screw threaded connection has the second bolt on the movable block, the upper end rotates in the second bolt and is connected with the stopper, stopper lateral wall and slide bar fixed connection, fixedly connected with rubber slab on the outer wall of slide bar, vertical spout has been seted up on.
2. The construction steel pipe welding equipment convenient to adjust as claimed in claim 1, wherein: the bottom of the bottom plate is symmetrically and fixedly connected with inclined supporting legs.
3. The construction steel pipe welding equipment convenient to adjust as claimed in claim 1, wherein: the material of ball is steel, and the ball rotates in the restriction pole.
4. The construction steel pipe welding equipment convenient to adjust as claimed in claim 1, wherein: the horizontal sliding groove and the ball are on the same straight line.
5. The construction steel pipe welding equipment convenient to adjust as claimed in claim 1, wherein: the first bolt is in threaded connection with the bottom plate.
6. The construction steel pipe welding equipment convenient to adjust as claimed in claim 1, wherein: and nuts are fixedly connected to the first bolt and the second bolt.
CN201921745734.7U 2019-10-17 2019-10-17 Convenient steel pipe welding equipment for building of adjusting Expired - Fee Related CN211219446U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921745734.7U CN211219446U (en) 2019-10-17 2019-10-17 Convenient steel pipe welding equipment for building of adjusting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921745734.7U CN211219446U (en) 2019-10-17 2019-10-17 Convenient steel pipe welding equipment for building of adjusting

Publications (1)

Publication Number Publication Date
CN211219446U true CN211219446U (en) 2020-08-11

Family

ID=71936350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921745734.7U Expired - Fee Related CN211219446U (en) 2019-10-17 2019-10-17 Convenient steel pipe welding equipment for building of adjusting

Country Status (1)

Country Link
CN (1) CN211219446U (en)

Similar Documents

Publication Publication Date Title
CN110425342B (en) Super high-rise concrete pumping pipe installation structure and installation method thereof
CN211219446U (en) Convenient steel pipe welding equipment for building of adjusting
CN205243006U (en) Side form supports top and holds in palm
CN207064822U (en) Positioning die for installing vertical shaft inner pipeline
CN210623783U (en) Pipeline fixing device is used in municipal administration plumbing construction
CN107504036B (en) Internal support device for casing and construction method thereof
CN206693630U (en) A kind of concreting servicing unit
CN205857710U (en) Air-conditioning formwork support structure
CN205857709U (en) Air-conditioning template length governor motion and air-conditioning formwork support structure
CN211078947U (en) Portable beam slab health preserving device
CN210529616U (en) Water-stop sheet for hydraulic engineering
CN210396042U (en) Portable masonry pointing device
CN219366993U (en) Slope control device for indoor same-layer drain pipe
CN206971809U (en) A kind of civil engineering support
CN211541661U (en) Concrete internal mold supporting device
CN221171111U (en) Adjustable bracket for water discharge open-installation pipeline
CN112901914B (en) Foundation bolt group positioning and fixing device and method
CN211475080U (en) Water supply and drainage pipeline installation positioner
CN111021713A (en) Novel concrete embedded bolt mechanism and use method thereof
CN217461433U (en) Combined steel template circular mold for building concrete
CN212477995U (en) Sewage drainage pipeline concrete pouring pipe stabilizer
CN218028061U (en) Inspection well flowing water tank mounting frame
CN220166979U (en) Pipeline pouring fixing device
CN219834015U (en) Pile pre-buried bolt fixing device
CN219753295U (en) Pipe gallery pouring backplate adjusting bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200811

Termination date: 20211017